Request for Design-Build Services Summary
This is a Request for Design-Build Services (RDBS) issued by Miami-Dade County, Florida, through the Miami-Dade Aviation Department (MDAD) for design-build services to expand the Regional Commuter Facility (D60) at Miami International Airport's North Terminal. The project scope includes architectural, engineering, design, construction, and post-design services for a three-level terminal expansion providing seventeen regional jet contact gates, including fifteen new ERJ175-capable gates and reconfiguration of two existing gates to support narrow-body operations. The expansion encompasses hold rooms, concessions, supporting facilities, an upgraded baggage handling system, international corridors, and all necessary infrastructure integration with existing terminal systems. A pre-submittal project briefing is scheduled for September 25, 2026, at 10:00 AM at Miami International Airport, Building 5A. The deadline for submission of questions is October 2, 2026, at 2:00 PM, and the Step 1 qualifications deadline is October 19, 2026, at 2:00 PM. The selection process is two-step: Step 1 evaluates qualifications with the Competitive Selection Committee qualifying no fewer than three responsive and responsible firms to advance to Step 2, which evaluates technical and price proposals. The contract duration is 2,294 calendar days from Notice to Proceed, with beneficial occupancy milestones established for phased project delivery at days 1,050, 1,419, 1,964, and 2,174.
The total estimated project cost is $1,062,134,663, including $71,212,809 in design costs and $855,923,189 in construction costs, plus $92,713,600 in owner contingency fees (10%), $5,128,677 in permitting fees, $15,386,032 for inspections and testing, $5,885,890 for source removal and dewatering, $13,268,841 for art in public places, and $2,615,625 in Inspector General fees. The Price Proposal must include all design and construction services, labor, materials, equipment, utilities, permits, and applicable taxes. Liquidated damages are assessed for failure to achieve beneficial occupancy milestones, ranging from $3,000 to $18,000 per calendar day depending on the milestone. The project is subject to federal funding requirements and Davis-Bacon wage rate compliance. Certain design criteria professionals and prior contract holders are ineligible, including Turner & Townsend Heery LLC, Hill International Inc., HNTB Corporation, BNP Associates Inc., HP Consultants Inc., and GPI Geospatial Inc. The Design-Builder must obtain performance and payment bonds for 100 percent of the total contract amount, maintain comprehensive insurance including professional liability of not less than $20,000,000 per occurrence and $40,000,000 aggregate, and comply with LEED Silver and Envision Silver sustainability certifications minimum.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| LOQ_DB26AV01_Final.doc | DOC document | |
| 09112026_PM_ITB0000005_1_1_0_10142026_Solicitation_Packet.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
RDBS-INFORMS_Rev. 01/20/2026
MIAMI-DADE COUNTY, FLORIDA
REQUEST FOR DESIGN-BUILD SERVICES (RDBS)
MIAMI-DADE AVIATION DEPARTMENT (MDAD)
DESIGN-BUILD SERVICES FOR MIA Cc D-WEST EXTENSION
D60 PHASE 2 (BUILDING EXPANSION & APRON)
STRATEGIC PROCUREMENT DEPARTMENT (SPD) PROJECT NO. DB26AV01
RDBS AVAILABLE FOR DISTRIBUTION:
September 18, 2026
PRE-SUBMITTAL PROJECT BRIEFING TO BE HELD:
(While attendance is not mandatory, interested parties are encouraged to attend. The person responsible for submitting a proposal in INFORMS is strongly encouraged to attend.)
September 25, 2026, at 10:00 AM (local time) Miami International Airport, Building 5A
4200 NW 36 St, Miami, FL 33166 2nd Floor, Conference Room G
DEADLINE FOR RECEIPT OF QUESTIONS:
October 2, 2026, AT 2:00 P.M. (Local Time)
MIAMI-DADE COUNTY CONTACT FOR THIS SOLICITATION:
Jorge Vital, A/E Consultant Selection Coordinator
111 NW 1st Street, Suite 1300, Miami, Florida 33128 Telephone: (305) 375-2103
E-mail: Jorge.Vital@Miamidade.gov
DEADLINE FOR RECEIPT OF STEP 1 PROPOSALS:
October 19, 2026, AT 2:00 P.M. (Local Time)
The County Mayor, Miami-Dade County, pursuant to Chapter 287.055 of Florida Statutes, and Sections 2-8.1 and 2-10.4, and Implementing Orders (“I.O”) 3-34, and 3-39, announces that Miami Dade Aviation Department (MDAD) will require design-build services to expand the existing Regional Commuter Facility (D60) at North Terminal.
Participation Restrictions Pursuant to Florida Statute 287.055, “A design criteria professional who has been selected to prepare the design criteria package is not eligible to render services under a design-build contract executed pursuant to the design criteria package. The Design Criteria Professionals for the Project under Contract No. A18-MDAD-01B, Turner & Townsend Heery, LLC and its subconsultants, Bekka Group, Inc., De Zayas-Bitar Construction Co., EAC Consulting, and Burns Engineering (and their subconsultant Currier and Company, Inc.) are not eligible to render services on this project.
In addition, Hill International, Inc., awarded under SPD Contract A18-MDAD-01A, Capital mailto:Jorge.Vital@Miamidade.gov http://www.flsenate.gov/laws/statutes/2010/287.055 https://www.municode.com/library/fl/miami_-_dade_county/codes/code_of_ordinances?nodeId=PTIIICOOR_CH2AD_ARTIINGE_S2-8.1COPUGE https://www.municode.com/library/fl/miami_-_dade_county/codes/code_of_ordinances?nodeId=PTIIICOOR_CH2AD_ARTIINGE_S2-10.4ACPRARENLAARLASUMASE http://www.miamidade.gov/aopdfdoc/aopdf/pdffiles/IO3-34.pdf https://documents.miamidade.gov/ao-io/IO/IO-03-39.pdf
Improvement Program Specialized Services is precluded from rendering services on this project.
Subconsultants of the Prime firm awarded under contract A18-MDAD-01A may compete to participate in this project, as a Prime or Subconsultant, since this project will not be managed by their respective team under SPD Contract No. A18-MDAD-01A.
The Prime awarded the Bond Engineering Consulting Services PSA under ISD Project No. E20-
MDAD-01, HNTB Corporation and its subconsultants Ambro, Inc, Goal Associates, Inc, Glass Land Acquisition Service Specialist, Brady Infrared Inspections, Inc., Butterfly Consulting, LLC, DAAB ConTech, G. Navarrete Consulting, Inc., INDRA USA, Inc., Intertek PSI Solutions, JD Solve IT (and their subconsultant SharperSaw, LLC), Pre LLC d.b.a. Pangiam, TGA Consulting, LLC, and ABC Imaging will not be eligible to render services on the design build contract awarded under this solicitation.
The Prime awarded the Baggage Handling System (BHS) design services under Contract No.
E24AV02B, BNP Associates Inc., will not be eligible to render services in the design build contract awarded under this solicitation.
The Prime awarded the Equitable Distribution Program Professional Services Agreement (PSA) under Contract No. EDP-AV-T180B, HP Consultants, Inc. will not be eligible to render services in the design build contract awarded under this solicitation.
The Prime awarded the PSA under Contract No. E20-MDAD-03, GPI Geospatial, Inc. and its subconsultant, Bello and Bello Land Surveying Corp., will not be eligible to render services in the design build contract awarded under this solicitation.
The selection process for this design build solicitation is a two-step process, Step 1 – Evaluation of Qualifications and Step 2 – Evaluation of Technical and Price Proposal.
▪ Step 1 is the evaluation of a design-build team’s qualifications based on the teams’ completed submittal. The Competitive Selection Committee will attempt to qualify no fewer than three (3) responsive and responsible firms and by majority vote will determine the maximum number of responsive and responsible firms to advance to Step 2 (the “Advancing Firms”).
▪ Step 2 is the evaluation of competitive Technical and Price Proposals from those Advancing Firms who choose to offer a responsive and responsible proposal.
For ease of reference, this document has been divided into three distinct Divisions corresponding to its applicability. Please refer to each of these Divisions for information related to applicable submittal deadlines.
Division 1 – General Requirements and Scope of Services – The provisions of Division 1 are applicable to both Step 1 and Step 2, unless otherwise indicated in the text or otherwise precluded by the context.
Division 2 – Step 1 - Evaluation of Qualifications – The provisions of Division 2 are applicable to Step 1 – Evaluation of Qualifications, unless otherwise indicated in the text or otherwise precluded by the context.
Division 3 – Step 2 - Evaluation of Technical and Price Proposal – The provisions of Division 3 are applicable to Step 2 – Evaluation of Technical and Price Proposal, unless otherwise indicated in the text or otherwise precluded by the context. The design criteria package for the project, which is an integral part of this solicitation, constitutes Volume 2 of this RDBS.
For the purpose of preparing and submitting a Technical and Price Proposal, the following shall be the order of precedence:
1. Addenda to the RDBS
2. Design Criteria Package (DCP)
3. Request for Design-Build Services
4. Referenced Codes and Standards
5. Sample Design-Build Services Agreement
It is the policy of Miami-Dade County that all elected and appointed County officials and County employees shall adhere to the Public Service Honor Code (Honor Code). The Honor Code consists of minimum standards regarding the responsibilities of all public servants in the County.
Violation of any of the mandatory standards may result in enforcement action. (See I.O. 7-7)
Pursuant to Florida Statutes Section 287.05701, Proposers are hereby notified that the County will not request documentation of, or consider, the social, ideological or political interests of a Proposer when determining if a Proposer is a responsible vendor nor will the County give preference to a Proposer based on the Proposer’s social, ideological or political interests.
Therefore, nothing in this RDBS shall in any way be utilized to request documentation relating to or authorizing consideration of a Proposer's social, political, or ideological interests when determining if the Proposer is a responsible vendor or give a preference to a Proposer based on the Proposer's social, political, or ideological interests.
The following project specific documents may be requested from the A/E Consultant Selection Coordinator denoted above as they become available: Selection Committee Appointment Memoranda, Pre-Submittal Project Briefing Attendance List, List of Respondents, Schedule of Presentations as applicable, and Evaluation Meeting Tabulation Sheets showing final rankings.
PURSUANT TO REVISIONS TO MIAMI-DADE COUNTY IMPLEMENTING ORDER 3-
39, THE EVALUATION CRITERIA, TIE BREAKING PROCEDURES, AND SUBMITTAL
REQUIREMENTS AMONGST OTHERS HAVE CHANGED.
REMAINDER OF PAGE INTENTIONALLY LEFT BLANK
http://www.miamidade.gov/aopdfdoc/aopdf/pdffiles/IO7-7.pdf https://www.flsenate.gov/Laws/Statutes/2023/0287.05701
TABLE OF CONTENTS
VOLUME I
DIVISION 1 - GENERAL REQUIREMENTS AND SCOPE OF SERVICES…………………………6
DIVISION 2 - STEP 1 - EVALUATION OF QUALIFICATIONS …………………………...…………..37
1.1 1.2 1.3 1.4 1.5 1.6
1.7 1.8 1.9
1.10 1.11 1.12 1.13 1.14
1.15 1.16
1.17 1.18 1.19 1.20 1.21 1.22 1.23
Definitions Notice of Electronic Bidding Scope of Services Project Terms Q&A/Additional Information/Addenda Listing of Subconsultants/Subcontractors Via the County’s Web-Based Business Management Workforce System (BMWS) Insurance Requirements Payment and Performance Bond Teaming Restrictions Contract Measures Applicable Legislation Cone of Silence Intentionally Omitted Intentionally Omitted
Confidential Information Monthly Reporting when Subcontractors or Sub-consultants are Utilized Costs Incurred by Design-Builder Organizational Conflicts of Interest (OCI) Sustainable Building/Infrastructure Program Vendor Registration Public Entity Crimes Lobbyist Contingency Fees Collusion
1.24 1.25
1.26 1.27 1.28 1.29 1.30 1.31
1.32
1.33
1.34 1.35 1.36
1.37 1.38
1.39 1.40 1.41
Office of the Inspector General Postponement/Cancellation/Right to Waive Minor Irregularities Submittal of Information Contract Award Written Objections and Rights of Protest Energy Efficient Building Tax Credit Scrutinized Companies Subcontractors – Race, Gender and Ethnic Makeup of Owners and Employees Access Statement for Notices of Public Meetings and Departmental Publications Communications and Submittal of Additional Information Sea Level Rise Team Composition Public Records and Contracts for Services Performed on Behalf of Miami- Dade County Intentionally Omitted Reporting of Subconsultants/ Subcontractors Payment Via the County’s Web-Based System Business Management Workforce System
(BMWS)
Buy American Iron and Steel Products E-verify Requirement Draft Design Build Contract
2.1 2.2
2.3
Experience and Qualifications Pre-Qualification Requirements for A/E Design Team Design-Builder’s Licensing Requirements and A/E Technical Certification Requirements
2.4 2.5 2.6
Step 1 Format and Contents Step 1 Submittal Requirements Step 1 Evaluation Process
DIVISION 3 - STEP 2 – EVALUATION OF TECHNICAL AND PRICE PROPOSAL ……………46
ATTACHMENTS:
Exhibit “A” Miami-Dade County Forms:
Design-Build Letter of Qualifications (LOQ) Form Design-Build Experience & Qualification/ Preference/ Reference Form Form 9 – Fair Subcontracting Practices
Exhibit “B” Affidavits Required at Time of Proposal:
Design-Builder’s Affidavit
Certification of Compliance with Buy American Iron and Steel Products Procurement Program Certification of Offeror/Bidder Regarding Tax Delinquency and Felony Convictions
Exhibit “C” Other forms for federally funded projects:
Federal Requirements Title IV Solicitation Notice Certification of Offer/Bidder Regarding Debarment Certification of Lower Tier Contractors Regarding Debarment Disadvantaged Business Enterprise Federal Fair Labor Standards Act Certification Regarding Lobbying Trade Restriction Certification FAA Buy American Preference Certification Regarding Domestic Preferences For Procurements
APPLICABLE TO STEP 2 ONLY:
Exhibit “D” Surety Bid Bond Form Exhibit “E” Surety Performance and Payment Bonds Exhibit “F” Price Proposal Forms Exhibit “G” Draft Contract
VOLUME II
Design Criteria Package (To be provided/made available to Short-Listed firms)
3.1 3.2 3.3 3.4 3.5 3.6 3.7 3.8
Design Criteria Package Availability Addenda Bid Bond Step 2 Schedule Intentionally Omitted Intentionally Omitted Intentionally Omitted Intentionally Omitted
3.9 3.10 3.11 3.12
3.13
3.14
Step 2 Format and Contents Step 2 Selection Criteria Step 2 Evaluation/Selection Process County Responses At Meetings Are Non- Binding Recommendation to the County Mayor or County Mayor’s Designee to Initiate Negotiations Negotiations
DIVISION 1
GENERAL REQUIREMENTS AND SCOPE OF SERVICES
1.1 DEFINITIONS
The following definitions, as well as additional terms necessary for understanding the provisions of this solicitation are defined in Implementing Order 3-39, which may be obtained at http://www.miamidade.gov/procurement/architectural-engineering-legislation.asp, or from the Clerk of the Board.
a) A/E: Architectural and engineering.
b) A/E Consultant Selection Coordinator: The person designated by the County as the primary contact for this solicitation, whose name appears on the cover of this RDBS. Synonymous with the term “Contracting Officer”
c) Advancing Firms: Design-Builders selected by the Competitive Selection Committee to advance to Step 2 based upon the evaluation of the firms’ submittal pursuant to Step 1.
d) BCC: Board of County Commissioners.
e) BMWS: Business Management & Workforce System: Shall refer to the County’s web-based system used to report all Miami-Dade County A/E, Design-Build and Construction contracts awarded and payments to Prime(s) and Subconsultants/Subcontractors.
f) COB: Clerk of the Board.
g) County: Shall refer to Miami-Dade County, Florida.
h) CSC: Competitive Selection Committee as defined in Section 2-10.4 (5) of the County Code (the “Code”), shall be the committee appointed by the County Mayor or County Mayor’s designee to evaluate qualifications and performance of the firm’s requesting consideration for the specific project and select the most qualified firm (s) to perform the services.
i) Contract: Design-Build Contract; synonymous with the term “Agreement”.
j) Days: unless otherwise expressly stated, all references to days shall be to calendar days.
k) Design-Build Contract: A single contract for the design and construction of a public construction project.
l) Design-Builder: The legal person (including individuals, firms or entities) contractually responsible for delivering the project design and construction, and includes any person authorized by law to enter into the contract and perform the services requested in this solicitation. As used in this solicitation the term is synonymous with the words “Submitter”, “Design-Builder”, “Consultant”, “Contractor” and “Respondent”.
m) Design Criteria Professional: An individual or a firm who holds a current certificate of registration under Chapter 481 of Florida Statutes, to practice architecture or landscape architecture or a firm who holds a current certificate as a registered engineer under Chapter 471 of Florida Statutes, to practice engineering and who is employed by or under contract http://www.miamidade.gov/procurement/architectural-engineering-legislation.asp to the agency for the provision of professional architectural services, or engineering services in connection with the preparation of the design criteria package.
n) INFORMS: Integrated Financial Resources Management System: shall refer to the technology utilized to track budget, procurement (including soliciting and receiving bids through the Strategic Sourcing module), as well as human resources, and financial operations for the County.
o) Non-Responsive: A Design-Builder who in the County’s sole discretion, has not complied with all of the material requirements outlined in the solicitation, as applicable, and may not be considered for contract award.
p) Owner: Miami-Dade County, a political subdivision of the State of Florida.
q) Pre-Qualification Certification: An annual certification process required of all firms providing architectural, engineering, landscape architectural, land surveying and mapping professional services pursuant to Miami-Dade County professional services agreements.
Pre-qualification certification is the consolidation of the various certification processes into one streamlined process and includes, but may not be limited to, technical certification, affirmative action plan verification, vendor registration and execution of the basic Miami- Dade County affidavits, as applicable. The pre-qualification certification program is administered by the Strategic Procurement Department (SPD) re-Qualification approval is granted to firms who have received approval from SPD on all the required certification processes outlined above.
r) RDBS: Request for Design Build Services.
s) Responsible: A Design-Builder who the County affirmatively determines has the ability, capacity and skill to perform under the terms of the contract; does not have an unsatisfactory record of past performance in County contracting; including abiding by applicable ordinances, resolutions, and other policies of the County; and has a satisfactory record of integrity and business ethics.
t) Responsive: A Design-Builder who in the County’s sole discretion, has complied with all of the requirements outlined in the solicitation, as applicable.
u) Strategic Procurement Department (SPD): The County Department that manages all Procurement of goods and services for the County and its agencies and instrumentalities including the acquisition of goods, services, professional services, design-build projects and similar projects on a County-wide basis and who is charged with the administration of the processes and programs set forth in certain procurement related Administrative and Implementing Orders.
v) Step 1 Submittal Deadline: The deadline for submittal of the qualifications package by interested Design-Builders. The Step 1 submittal deadline appears on the cover of this
RDBS.
w) Step 2 Submittal Deadline: The deadline for submittal for technical and price proposal by
Advancing Firms. The Step 2 submittal deadline for this project appears in Division 3, Section 3.4, Step 2 Schedule.
x) Sub-consultant: Any and all persons, firms or entities, which will be engaged by the Design- Builder to provide services under this solicitation.
y) Technical Certification: Comprehensive review by the County Technical Certification
Committee affirming a firm’s eligibility to provide professional services to the County in various technical categories.
z) Work: Professional services, all labor, materials, tools, equipment, services, methods, procedures, etc., necessary or convenient to be provided by the Design/Builder to fulfill all duties and obligations imposed by the Contract Documents, which can be reasonably assumed as necessary to fulfill the intent of the Contract Documents to provide a complete, fully functional and satisfactory project.
1.2 NOTICE OF ELECTRONIC BIDDING
This RDBS is being solicited electronically through the INFORMS Strategic Sourcing module platform. Electronic bids are to be submitted through a secure mailbox at INFORMS (https://supplier.miamidade.gov) until the date and time indicated in this Solicitation document. It is the sole responsibility of the Proposer to ensure their proposal reaches INFORMS before the Solicitation closing date and time. There is no cost to the Proposer to submit a proposal in response to a Miami-Dade County solicitation via INFORMS. Electronic proposal submissions require the uploading of electronic attachments and Proposers must CONFIRM their proposal (acknowledge) in order for the proposal to be received by the County through INFORMS. The submission of attachments containing embedded documents or proprietary file extensions is prohibited. All proposals received and time stamped through the County’s INFORMS system, prior to the proposal submittal deadline shall be accepted as timely submitted. If you submit your Proposal and subsequently an Addendum is issued, failure to resubmit the Proposal by clicking on the “Submit Bid” button, after acknowledging Addenda or making any edits to your Proposal in INFORMS, will result in your Proposal not being received by the County. The circumstances surrounding all proposals received and time stamped after the proposal submittal deadline will be evaluated by the procuring department in consultation with the County Attorney’s Office to determine whether the proposal will be accepted as timely. Proposals will be opened promptly at the time and date specified. The responsibility for submitting a proposal on or before the stated time and date is solely and strictly the responsibility of the Proposer. The County will in no way be responsible for delays caused by technical difficulty or caused by any other occurrence.
All expenses involved with the preparation and submission of proposals to the County, or any work performed in connection therewith, shall be borne by the Proposer(s). No exceptions. For information concerning technical specifications please utilize the question/answer feature provided by INFORMS at https://supplier.miamidade.com within the solicitation. If there are any questions regarding INFORMS, please contact INFORMS Support at 305-375-5773 or email: ISD-VSS@miamidade.gov.
No part of your proposal can be submitted via HARDCOPY, EMAIL, OR FAX, unless otherwise expressly directed by the solicitation documents.
1.3 SCOPE OF SERVICES
The Miami-Dade Aviation Department (MDAD) intends to establish a Design-Build Services contract to provide Architectural, Engineering, Design, Construction, Post-Design Services and Commissioning for the MIA Cc D-West Extension D60 Ph 2 (Building Expansion & Apron) at the North Terminal. The existing Regional Commuter airline has outgrown the existing (D60) facility.
The concourse needs to be expanded to meet current industry demands, and anticipated airport/airline growth, and provide better experience for the traveling public. The proposed three-https://supplier.miamidade.gov/ https://supplier.miamidade.com/ mailto:ISD-VSS@miamidade.gov level expansion will provide seventeen (17) Regional Jet (RJ) contact gates, including fifteen (15) new RJ (ERJ175) capable gates, and the reconfiguring two (2) existing gates D53 and D55 to support narrow-body operations. Twelve (12) of the seventeen (17) contact gates are sized to accommodate Airplane Design Group III ADG III (A321) narrow-body aircraft. The expansion will provide new hold rooms, concessions, and supporting facilities, along with an upgraded baggage handling system and international corridors and accessways that will integrate with the existing North Terminal baggage systems and Federal Inspection Services (FIS) facilities. The scope encompasses all necessary phasing and Maintenance of Traffic (MOT) measures required to maintain active airline and airport operations during demolition and construction activities.
The Work of the project as defined in the Contract Documents includes, but is not limited to:
Design Requirements:
• Architectural Design
• Civil Engineering (site, utilities, drainage, and pavement design)
• Structural Engineering
• Mechanical, Electrical, and Plumbing (MEP) Engineering
• Fire Protection Engineering
• Vertical Transportation Systems (elevators, escalators, moving walkways)
• Lighting and Acoustical Design
• Landscape Architecture
• Baggage Handling Systems (BHS)
• Passenger Boarding Bridges (as applicable)
• Wayfinding and Signage (static and digital)
• Information Technology (IT) and Communications Infrastructure
• Public Address / Paging Systems
• Security Systems (access control, CCTV, and coordination with TSA requirements)
• Audio/Visual Systems
• Building Management / Automation Systems (BMS/BAS)
• Integration of Art in Public Places program
• Design to achieve LEED Silver Certification (minimum)
• Design to achieve Envision Silver Certification (minimum)
• Energy modeling and sustainability analysis
• Resiliency measures (including flood mitigation and climate adaptation)
• Topographic, boundary, and utility surveying
• Subsurface utility engineering (SUE)
• Geotechnical investigations and reporting
• Environmental assessments and studies
• Existing facility assessments and documentation
• Environmental and building permits
• Coordination with regulatory agencies (FAA, TSA, local AHJs, etc.)
• Compliance with applicable codes and standards (IBC, NFPA, ADA, etc.)
• Threshold inspections and special inspections
• Project Management
• Construction Management
• Cost estimating, cost control, and value engineering
• Project scheduling (baseline, updates, recovery schedules)
• Quality Assurance / Quality Control (QA/QC)
• Risk management and mitigation planning
Construction Services Requirements:
• Construction of all terminal and apron expansion and supporting infrastructure
• Utility relocations, upgrades, and new installations
• Structural, architectural, and systems installation
• Airfield & apron marking improvements
• Drainage and stormwater management systems
• Hydrant fueling systems
• Development and implementation of detailed phasing plans
• Maintenance of airport operations throughout construction
• Construction logistics, staging, and traffic management
• Temporary facilities and enabling works
• Design submittals at all phases
• Shop drawings and product submittals
• Record documents and as-built drawings
• Operations and Maintenance (O&M) manuals
• Systems start-up, testing, and commissioning
• Integrated systems testing (IST), including BHS, security, and IT systems
• Training for Owner’s operations and maintenance personnel
• Operational readiness and airport transfer (ORAT) support
• Final inspections and approvals
• Punchlist completion
• Warranty documentation and support
• Project closeout documentation
Notable components of the scope of work are the following:
• Ramp Level: This level will house the new baggage handling system (BHS) makeup units serving the new D60 gate, replacing the existing Early Baggage Storage Building (EBS) operation and expanding BHS capacity to support American Airlines’ future growth. It will also include facilities for international passenger bus operations connected to a sterile corridor, a concessions injection point, airline operations support areas, and MEP support spaces.
• Second Level: Designed for passenger services, this level will feature hold rooms, sterile corridors, restrooms, and approximately 30,800 square feet of concession space. Vertical circulation cores will provide access to the third- level sterile corridors.
• The third level is planned to support international operations. It will include sterile corridors, restrooms, MEP support areas, and a 25,000-square-foot shell space.
1.4 PROJECT TERMS
The duration for the proposed design-build contract is two thousand two hundred ninety-four (2,294) calendar days. The total compensation for the Design-Build Contract is estimated at One Billion, Sixty-Two Million, One Hundred Thirty-Four Thousand, Six Hundred Sixty-Three Dollars ($1,062,134,663.00) inclusive of contingencies and allowances, which includes the following:
$ 71,212,809 Estimated design cost $ 855,923,189 Estimated construction cost
$ 92,713,600 Owner Contingency fees (10%) $ 5,128,677 Permitting Fees (Dedicated Allowance) $ 15,386,032 Inspections and Testing (Dedicated Allowance) $ 5,885,890 Source Removal & Dewatering (Dedicated Allowance) $ 13,268,841 Art in Public Places (Excluding Apron & Demolition) $ 2,615,625 IG Fee
The County reserves the right to negotiate or reject any and all proposal(s), if the price exceeds the estimated project cost. The Price Proposal Form is to include all design and construction services, labor, materials, equipment, tools, utilities, permit fees, approvals, authorizations, certificates, including applicable taxes and all facilities necessary for the completion of the Work, as applicable.
LIQUIDATED DAMAGES
Timely completion of the Beneficial Occupancy Milestones is critical to maintaining continuous airport operations, aircraft gate capacity, airline operations, passenger service, concession operations, airport revenues, and Project implementation.
The parties further acknowledge that the actual damages resulting from the Design/Builder’s failure to timely achieve the Beneficial Occupancy Milestones are impracticable and extremely difficult to determine with precision. Accordingly, the parties agree that the following amounts represent a reasonable estimate of the damages that the Owner will incur and shall be assessed as Liquidated Damages and not as a penalty.
Beneficial Occupancy
Beneficial Occupancy shall include, as applicable, completion, testing, commissioning, inspection, regulatory approvals, and Owner acceptance of all facilities, systems, infrastructure, equipment, documentation, and operational support necessary to place the applicable phase into operational and revenue service, including, but not limited to:
• Aircraft gates, aircraft parking positions, apron improvements, taxilanes, aircraft servicing systems, fueling systems, passenger boarding bridges, gate equipment, and associated airside infrastructure;
• Passenger hold rooms, concourses, circulation areas, vertical circulation, passenger processing areas, public spaces, concessions, tenant spaces, airline operational support facilities, public amenities, restrooms, and all occupiable areas designated for use during the applicable phase;
• Baggage handling systems and associated equipment;
• Mechanical, electrical, plumbing, fire protection, life safety, communications, information technology, security, access control, building automation, utilities, lighting, signage, roadway improvements, pedestrian facilities, landscaping, and all supporting infrastructure;
• Completion of all inspections, certifications, regulatory approvals, operational testing, commissioning, staff training, turnover documentation, and all other requirements necessary for the Owner to safely occupy, use, and operate the applicable phase; and
• Any additional Work required by the Contract Documents to support continuous airport operations and place the applicable phase into operational and revenue service.
Physical completion of construction alone shall not constitute Beneficial Occupancy.
Beneficial Occupancy shall be achieved only upon the Owner's written determination that the applicable phase satisfies the requirements of the Contract Documents and may be safely occupied, used, and operated for its intended purpose.
Milestone 1 – Early Works
Milestone 1 consists of the completion of the Early Works identified in the Contract Documents, including the Project Phasing Plans. Milestone 1 is established solely as a contractual prerequisite to the commencement of Milestone 2 – Phase 1 Beneficial Occupancy Work.
The Design-Builder shall complete Milestone 1 and obtain the Owner's written determination that the Early Works have been completed in accordance with the Contract Documents before commencing any Work associated with Milestone 2.
Milestone 1 is not a Beneficial Occupancy Milestone and is not subject to Liquidated Damages.
However, the Design-Builder shall not commence Work associated with Milestone 2 until Milestone 1 has been completed and accepted by the Owner.
Failure to timely complete Milestone 1 shall not relieve the Design-Builder of its obligation to achieve Milestones 2 through 5 within the Contract Time. Any delay in completing Milestone 1 that results in the late achievement of Milestones 2 through 5 shall be subject to the applicable Liquidated Damages provisions for those milestones
Milestone 2 – Phase 1 Beneficial Occupancy
The Design/Builder shall achieve Beneficial Occupancy of Phase 1 and place the Phase 1 facilities into service no later than 1,050 calendar days following the Notice to Proceed (NTP).
Phase 1 Beneficial Occupancy shall include the operational availability of seven (7) new contact gates, together with all associated passenger processing areas, hold rooms, concessions, tenant spaces, airline operational support facilities, public amenities, apron improvements, passenger boarding bridges, baggage handling systems, building systems, utilities, life safety systems, roadway and pedestrian improvements, and all other facilities, systems, and infrastructure necessary for the Owner to safely occupy, use, and operate the Phase 1 facilities for their intended purpose.
Failure to achieve Milestone 2 by day 1,050 shall result in Liquidated Damages in the amount of Eleven Thousand Dollars ($11,000.00) for each calendar day the milestone remains incomplete.
Milestone 3 – Phase 2 Beneficial Occupancy The Design/Builder shall achieve Beneficial Occupancy of Phase 2 and place the Phase 2 facilities into service no later than 1,419 calendar days following the Notice to Proceed (NTP).
Phase 2 Beneficial Occupancy shall include the operational availability of three (3) new contact gates, together with all associated passenger processing areas, hold rooms, concessions, tenant spaces, airline operational support facilities, public amenities, apron improvements, passenger boarding bridges, baggage handling systems, building systems, utilities, life safety systems, roadway and pedestrian improvements, and all other facilities, systems, and infrastructure necessary for the Owner to safely occupy, use, and operate the Phase 2 facilities for their intended purpose.
Failure to achieve Milestone 3 by day 1,419 shall result in Liquidated Damages in the amount of Three Thousand Dollars ($3,000.00) for each calendar day the milestone remains incomplete.
Milestone 4 – Phase 3 Beneficial Occupancy
The Design/Builder shall achieve Beneficial Occupancy of Phase 3 and place the Phase 3 facilities into service no later than 1,964 calendar days following the Notice to Proceed (NTP).
Phase 3 Beneficial Occupancy shall include the operational availability of four (4) new contact gates, together with all associated passenger processing areas, hold rooms, concessions, tenant spaces, airline operational support facilities, public amenities, apron improvements, passenger boarding bridges, baggage handling systems, building systems, utilities, life safety systems, roadway and pedestrian improvements, and all other facilities, systems, and infrastructure necessary for the Owner to safely occupy, use, and operate the Phase 3 facilities for their intended purpose.
Failure to achieve Milestone 4 by day 1,964 shall result in Liquidated Damages in the amount of Eleven Thousand Dollars ($11,000.00) for each calendar day the milestone remains incomplete.
Milestone 5 – Final Beneficial Occupancy and Substantial Completion
The Design/Builder shall achieve Final Beneficial Occupancy and Substantial Completion of the Project no later than day 2,174 following the Notice to Proceed (NTP).
Final Beneficial Occupancy shall include the operational availability of the remaining three (3) new contact gates, together with completion of all remaining Work necessary for the Owner to fully occupy, use, operate, and place the entire D60 Facility into operational and revenue service.
This milestone shall include, but not be limited to:
• All remaining passenger processing areas;
• Concessions and tenant spaces;
• Airline operational support facilities;
• Public circulation areas and amenities;
• Apron improvements;
• Passenger boarding bridges;
• Building systems and utilities;
• Roadway, pedestrian, landscaping, and site improvements;
• Final commissioning and integrated systems testing;
• Regulatory inspections and approvals;
• Staff training and operational turnover;
• Final closeout documentation; and
• All other Work required by the Contract Documents to achieve Substantial Completion and place the entire D60 Facility into operational and revenue service.
Failure to achieve Milestone 5 by day 2,174 shall result in Liquidated Damages in the amount of Eighteen Thousand Dollars ($18,000.00) for each calendar day the milestone remains incomplete.
Concurrent Assessment of Liquidated Damages
Liquidated Damages shall be assessed independently for each Beneficial Occupancy Milestone.
If the Design/Builder fails to achieve a Beneficial Occupancy Milestone by the required milestone completion date, Liquidated Damages shall commence on the first calendar day following the applicable milestone completion date and shall continue until the Owner determines, in writing, that the applicable Beneficial Occupancy Milestone has been achieved.
If more than one Beneficial Occupancy Milestone remains incomplete after its required completion date, Liquidated Damages shall accrue concurrently for each overdue milestone.
For example, if Milestone 2 has not achieved Beneficial Occupancy by day 1,419, Liquidated Damages for both Milestone 2 and Milestone 3 shall accrue concurrently until Milestone 2 is achieved. Likewise, if Milestone 3 remains incomplete after day 1,964, Liquidated Damages for both Milestone 3 and Milestone 4 shall accrue concurrently. If Milestone 4 remains incomplete after day 2,174, Liquidated Damages for both Milestone 4 and Milestone 5 shall accrue concurrently.
The assessment or cessation of Liquidated Damages for one milestone shall not relieve the Design/Builder of its obligation to timely achieve any subsequent milestone, nor shall it suspend the assessment of Liquidated Damages applicable to any other incomplete milestone.
Liquidated Damages for a Beneficial Occupancy Milestone shall cease only upon the Owner's written determination that the applicable Beneficial Occupancy Milestone has been achieved.
The Liquidated Indirect Cost rate for which the Design/Builder shall be compensated for each day of Compensable Excusable Delay shall be $13,000.00 per Calendar Day.
1.5 Q&A/ADDITIONAL INFORMATION/ADDENDA
Requests for additional information or clarifications must be made in writing and submitted using the question/answer feature provided by INFORMS at https://supplier.miamidade.gov. Subject requests must be submitted no later than the deadline for receipt of questions specified on the Cover of this RDBS.
The County will issue responses to inquiries and any other corrections or amendments it deems necessary in the form of written addenda. Proposers should not rely on any representations, statements or explanations other than those made in this RDBS or in any written addenda to this RDBS. Where there appears to be conflict between the RDBS and any addenda, the last addendum issued shall prevail. It is the proposer’s responsibility to assure receipt of all addenda.
Proposers are required to acknowledge the number of addenda received, on the Acknowledgement of Addenda Form, as part of their proposal.
Proposers who obtain copies of this RDBS from sources other than through INFORMS risk the potential of not receiving project addenda. Such proposers are solely responsible for those risks.
1.6 LISTING OF SUBCONSULTANTS/SUBCONTRACTORS VIA THE COUNTY’S WEB-
BASED SYSTEM BUSINESS MANAGEMENT WORKFORCE SYSTEM (BMWS)
The Design-Builder firm is responsible for reporting via the BMWS all subconsultant/subcontractor’s agreements entered into listing award amounts or percentage for each Miami-Dade County project. For additional information regarding online BMWS registration, manage County contracts, and to track compliance with SBE program measures, please contact Small Business Development, at (305) 375-3111 or via email at SBDmail@miamidade.gov.
1.7 INSURANCE REQUIREMENTS
1) The Design/Builder shall maintain the insurance set forth in the Contract Documents throughout the performance of this Contract until the Work has been completed by the Design/Builder and accepted by the County.
https://supplier.miamidade.gov/ mailto:SBDmail@miamidade.gov
A. Within fifteen (15) days from the date of Notice of Award of this Contract and prior to commencement of Work, (with the exception of the Builders Risk Insurance), the Design/Builder shall obtain all insurance required under this Section. All insurance shall be maintained until the Work has been completed and accepted by the County. The Design/Builder shall furnish to the County:
1. Worker’s Compensation & Employer Liability, as required by Chapter 440, Florida Statutes with Statutory Limits, and Employer’s Liability Insurance with limit of no less than $1,000,000.00 per accident for bodily injury or disease.
2. Automobile Liability Insurance, covering all owned, non-owned, hired or operated vehicles used in connection with this project.
3. Commercial General Liability, insurance, written on an occurrence basis and including Contractual Liability, Broad Form Property Damage, Products and Completed Operations, Independent Contractors, and all hazards customarily insured under a standard ISO Commercial General Liability policy for construction operations. Coverage shall include, without limitation, liabilities arising from excavation, trenching, grading, demolition, blasting, shoring, underpinning, structural activities, Explosion, Collapse, Underground Property Damage (XCU), and all other construction-related operations associated with the Project. Coverage shall be maintained without exclusions inconsistent with the scope of the Work.
4. Professional Liability Insurance (Design-Builder). The Design/Builder shall maintain project-specific professional liability insurance with limits of not less than $20,000,000 per occurrence or claim and $40,000,000 in the policy aggregate. Coverage shall apply to professional services performed in connection with the Project, including services provided by the Design-Builder, design professionals, architects, engineers, consultants, subconsultants, contractors, and any other party providing design, engineering, construction administration, consulting, or other professional services for which the Design- Builder is responsible. Coverage shall include claims arising from negligent acts, errors, omissions, or breaches of professional duty in the performance of such professional services, whether performed directly by the Design-Builder or by any lower-tier design professional or consultant retained for the Project. If coverage is written on a claims-made basis, the policy retroactive date shall precede the commencement of any professional services related to the Project and shall not be advanced without the prior written consent of the County and Miami-Dade Aviation Department. The Design/Builder shall maintain continuous professional liability coverage during the term of the Project and for an extended reporting period that matches or exceeds the applicable statute of repose in Florida for construction projects, which is currently seven (7) years, or such longer period as may be required by the Contract Documents. Coverage shall be maintained without exclusions or limitations that would materially restrict coverage for the scope of professional services required for the Project.
The Design/Builder shall be responsible for all deductibles, self-insured retentions, uninsured losses, and any amounts within applicable policy retentions. Prior to commencement of professional services and upon renewal, replacement, or material change of coverage, the Design-Builder shall provide certificates of insurance and, upon request, copies of applicable policy endorsements or declarations evidencing compliance with this requirement.
5. Contractors Pollution Liability applicable to the work being performed with limits no less than $5,000,000 per claim or occurrence and $10,000,000 aggregate per policy period of one year.
6. Umbrella / Excess Liability Insurance. The Design/Builder shall maintain Umbrella Liability and/or Excess Liability insurance written on a follow-form basis providing coverage in excess of the Commercial General Liability, Automobile Liability, and Employer's Liability policies required under this Agreement. Such coverage shall apply on a per occurrence basis and shall be at least as broad as the underlying insurances. The Umbrella and/or Excess Liability coverage, together with the underlying Commercial General Liability and Automobile Liability insurance, shall provide combined total limits of not less than Fifty Million Dollars ($50,000,000) per occurrence and One Hundred Million Dollars ($100,000,000) in the aggregate for each respective policy.
Coverage shall be maintained without exclusions that would materially restrict coverage for the operations, hazards, or liabilities associated with the Project, including completed operations exposures. The Umbrella and/or Excess Liability policy shall drop down in the event of exhaustion of applicable aggregate limits of the underlying insurance policies where coverage has been exhausted. The products and completed operations coverage shall remain in force for the entire statute of repose period in the State of Florida. (currently seven years). Miami-Dade County and Miami Dade Aviation Department to be listed as additional insureds.
7. Builders Risk (coverage to be bound at the earlier of commencement of construction or delivery of materials to the project site or laydown yard)
i) Option I Design/Builder agrees to provide, in a policy acceptable to the Miami-Dade County and Miami Dade Aviation Department, "all risk" builder's risk insurance for each of the three phases of the project on all construction, additions, modifications, machinery, and equipment. Miami Dade County shall be a named insured under all builder’s risk policies.
The policy(ies) shall be issued on a Completed Value form.
The amount of the insurance shall be no less than the full construction values for each respective phase of the project, as amended from time to time, plus any values associated with existing building structure(s) impacted by the project as may be specified by the MDAD project team.
Coverage Sub-limits of $40,000,000 for the losses attributable to named windstorm and $20,000,000 for losses attributable to flood will be permitted for each phase of the project. The coverage shall not be subject to any restriction with respect to occupancy or use by the Miami- Dade Aviation Department and shall remain in full effect until all parties concur that the respective project Phase has reached Beneficial Occupancy.
The maximum deductible for losses from perils other than named windstorm or flood shall be $250,000 per occurrence and $500,000 per occurrence for losses associated with water damage other than flood.
The maximum deductible per occurrence for named windstorm and flood shall be 5% of the values at risk at the time of loss. Design-Builder shall be responsible for all losses within the deductibles for losses other than those associated with named windstorm and/or flood losses.
Deductibles associated with losses caused by the perils of named windstorm and/or flood shall be the sole responsibility of Maimi Dade County and/or Miami- Dade Aviation Department. Prior to mobilization, Design Builder shall provide evidence of coverage in compliance with all provisions of this section to Miami-Dade County and Miami-Dade Conty Aviation department.
Option II Miami Dade County/Miami Dade Aviation Department shall procure "all risk"/ “special form” builder's risk insurance for each of the three phases of the project on all construction, additions, modifications, machinery, and equipment. The policy shall be issued on a Completed Value form.
The amount of the insurance shall be no less than the full construction values for each respective phase of the project, as amended from time to time, plus any values associated with existing building structure(s) impacted by the project as specified by the MDAD project team.
Coverage Sub-limits of $40,000,000 for the losses attributable to named windstorm and $20,000,000 for losses attributable to flood will be permitted for each phase of the project. The coverage shall not be subject to any restrictions with respect to occupancy or use by the Miami-Dade Aviation Department and shall remain in full effect until all parties concur that the respective project Phase has reached Beneficial Occupancy.
The maximum deductible for losses from perils other than named windstorm or flood shall be $250,000 per occurrence and $500,000 per occurrence for losses associated with water damage other than flood.
The maximum deductible per occurrence for named windstorm and flood shall be 5% of the values at risk at the time of loss. Design-Builder shall be responsible for all losses within the deductibles for losses other than those associated with named windstorm and/or flood losses.
Deductibles associated with losses caused by the perils of named windstorm or flood shall be the sole responsibility of Maimi Dade County and/or Miami-Dade Aviation Department.
The builder's risk coverage will be maintained by the County, and the Design-Builder shall be a named insured on all builder’s risk policies.
Prior to mobilization, Miami Dade County and/or Miami Dade County Aviation department shall provide evidence of coverage in compliance with all provisions of this section to Design Builder.
For claims related to this project, builder’s risk insurance coverage shall be primary and non-contributory coverage.
The Miami Dade County/Miami Dade Aviation Department and Design/Builders waive all rights against (1) each other and any of their subcontractors, sub-subcontractors, agents and employees, each of the other, and (2) the Architect, Architect's consultants, separate contractors, if any, and any of their subcontractors for damages caused by fire or other causes of loss to the extent covered by builders risk insurance obtained pursuant this section or other property insurance applicable to the Work, except such rights as they have to proceeds of such insurance held by the insured as fiduciary. The Miami Dade Aviation Department or Design/Builder, as appropriate, shall require of the Architect, Architect's consultants, separate contractors and the subcontractors, of any of them, and to the extent required a notice of cancellation endorsement assuring that the Miami Dade Aviation Department shall receive not less than 30 days advance written notice of cancellation. All endorsements shall be properly completed and signed by an authorized representative of the insurer providing the coverage and shall indicate the policy number.
County reserves the right to determine, in its sole discretion, whether the County shall purchase and maintain the builder’s risk insurance with coverage in compliance with the above-described specifications or whether the Design/Builder will provide the Builder’s Risk insurance for the price indicated by the Design/Builder on the SPD FORM 6, PROPOSAL PRICE. In the event the County elects to purchase this coverage, the project award amount shall be adjusted to deduct the full amount indicated by the Design/Builder on SPD FORM 6, PROPOSAL PRICE for this coverage.
The County…