Solicitation No. W912P525BA006
US Army Corps Of Engineers
Nashville District
BLOUNT AVENUE
CHANNEL MODIFICATION
South Mouse Creek Tennessee River Basin Cleveland, Bradley County, Tennessee
Technical Specifications - Ready to Advertise (RTA) Certified Final
July 2025
THIS PAGE INTENTIONALLY LEFT BLANK
FOR DUPLEX PRINTING
Channel Modification Blount Avenue W912P525BA006 RTA Cleveland, TN
PROJECT TABLE OF CONTENTS
DI VI SI ON 01 - GENERAL REQUI REMENTS
01 00 00 GENERAL REQUIREMENTS
01 11 00 SUMMARY OF WORK
01 20 00 PRICE AND PAYMENT PROCEDURES
01 32 01 PROJECT SCHEDULE
01 33 00 SUBMITTAL PROCEDURES
01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS
01 42 00 SOURCES FOR REFERENCE PUBLICATIONS
01 45 00 QUALITY CONTROL
01 45 00.15 RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE (RMS CM)
01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS
01 57 19 TEMPORARY ENVIRONMENTAL CONTROLS
01 78 00 CLOSEOUT SUBMITTALS
01 95 00 FORMS AND ATTACHMENTS
DI VI SI ON 31 - EARTHWORK
31 00 00 EARTHWORK
31 11 00 CLEARING AND GRUBBING
DI VI SI ON 32 - EXTERI OR I MPROVEMENTS
32 92 19 SEEDING
-- End of Project Table of Contents --
PROJECT TABLE OF CONTENTS Page 1
PROJECT TABLE OF CONTENTS Page 2
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 00 00
GENERAL REQUIREMENTS
PART 1 GENERAL
1.1 GENERAL
1.2 REFERENCES
1.3 LOCATION AND ACCESS
1.3.1 Location
1.3.2 Access to Site
1.4 MEETINGS
1.4.1 COORDINATION CONFERENCES
1.4.2 PARTNERING
1.4.3 QUALITY CONTROL MUTUAL UNDERSTANDING MEETING
1.4.4 SAFETY MUTUAL UNDERSTANDING MEETING
1.4.5 SUPERVISOR SAFETY MEETING/WALK
1.4.6 WEEKLY PROGRESS MEETING
1.5 PROJECT SIGNS
1.5.1 General
1.5.2 Materials
1.5.3 Painting
1.5.4 Erection and Maintenance
1.6 Working Hours
1.6.1 Federal Holidays
1.7 Work Outside Regular Hours
1.8 CONTRACTOR'S STAGING AREA
1.9 DAILY CLEANUP AND DISPOSAL
1.10 PROTECTION AND RESTORATION OF EXISTING FACILITIES
1.11 EVALUATION OF CONTRACTOR PERFORMANCE
1.12 VETERANS EMPLOYMENT EMPHASIS FOR U.S. ARMY CORPS OF ENGINEERS
CONTRACTS
1.13 MEASUREMENT AND PAYMENT
PART 2 PRODUCTS (NOT USED)
PART 3 EXECUTION
-- End of Section Table of Contents --
SECTION 01 00 00 Page 1
SECTION 01 00 00 Page 2
SECTION 01 00 00
GENERAL REQUIREMENTS
PART 1 GENERAL
1.1 GENERAL
This section comprises an explanation of the general contract requirements needed to accomplish the work. All work specified herein shall be accomplished in accordance with the procedures prescribed in the specifications and drawings.
1.2 REFERENCES
The publications listed below form a part of this section to the extent referenced. The publications are referred to within the text by the basic designation only.
U.S. ARMY CORPS OF ENGINEERS (USACE)
EP 310-1-6a (2006; 2019 Change 2) Project Operation -- Sign Standards Manual, VOL 1
EP 310-1-6b (2006) Sign Standards Manual, VOL 2, Appendices
1.3 LOCATION AND ACCESS
1.3.1 Location
Cleveland, Tennessee
1.3.2 Access to Site
As specified in the project drawings.
1.4 MEETINGS
1.4.1 COORDINATION CONFERENCES
Routine coordination conferences will be scheduled by the Contracting Officer throughout the life of this project. Coordination conferences will be held to discuss contract administration, Contractor quality control, phasing, scheduling, and other aspects relating to this construction. The Corps of Engineers and the Contractor will be represented at each of these meetings. Coordination conferences will be scheduled to occur when notified by the Contracting Officer.
1.4.2 PARTNERING
In order to most effectively accomplish this contract, the Government urges the contractor to join the Government in establishing a cohesive and professional project management team. Through this "partnering"
SECTION 01 00 00 Page 3 relationship both entities would strive to draw on the strengths of each organization for the ultimate goal of assuring that the project's intended results of finishing on time and within budget are achieved utilizing a risk management approach. This endeavor seeks an environment that nurtures team building, cooperation, and trust between the Government and the Contractor. The partnering relationship would be bilateral in make-up, and participation will be totally voluntary.
1.4.3 QUALITY CONTROL MUTUAL UNDERSTANDING MEETING
After the Preconstruction Conference, before start of construction, and prior to acceptance by the Government of the CQC Plan, meet with the Contracting Officer and discuss the Contractor's quality control system.
Submit the CQC Plan prior to the Mutual Understanding Meeting. During the meeting, a mutual understanding of the system details must be developed, including the forms for recording the CQC operations, definable features of work, 3 phase inspection requirements submittal procedures, control activities, testing, administration of the system for both onsite and offsite work, and the interrelationship of Contractor's Management and control with the Government's Quality Assurance. Minutes of the meeting will be prepared by the Government, signed by both the Contractor and the Contracting Officer and will become a part of the contract file. There may be occasions when subsequent meetings will be called by either party to reconfirm mutual understandings or address deficiencies in the CQC system or procedures which may require corrective action by the Contractor.
1.4.4 SAFETY MUTUAL UNDERSTANDING MEETING
After the Preconstruction Conference, before start of construction, and prior to acceptance by the Government of the Accident Prevention Plan (APP), meet with the Contracting Officer and discuss the Contractor's safety program. Submit the APP prior to the Mutual Understanding Meeting.
During the meeting, a mutual understanding of the safety program details must be developed, including incorporated plans, programs, program management, anticipated AHAs that will be developed and implemented during the performance, additional safety meeting requirements, PPE, mishap reporting, and additional contract requirements considered unique. Minutes of the meeting will be prepared by the Government, signed by both the Contractor and the Contracting Officer and will become a part of the contract file. There may be occasions when subsequent meetings will be called by either party to reconfirm mutual understandings or address deficiencies in the safety program or procedures which can require corrective action by the Contractor.
1.4.5 SUPERVISOR SAFETY MEETING/WALK
A successful safety program has top-down support to include site supervision. Conduct a monthly safety site walk to review ongoing activities, document any issues and correct on the spot if possible.
Conduct meetings/walks at least once a month for all supervisors at the project location. The SSHO, supervisors, foremen, or CDSOs along with appropriate Government personnel will attend. The Contractor will document meeting minutes to include the date, persons in attendance, subjects discussed, and names of individual(s) who conducted the meeting.
Any concerns identified during the safety meeting/walk will be followed up on in the following week and discussed at the weekly progress meeting until corrected. Maintain documentation on-site and furnish copies to the Contracting Officer on request. Notify the Contracting Officer of all scheduled meetings 7 calendar days in advance. Please reference 01 35 26
SECTION 01 00 00 Page 4 specifications for additional requirements.
1.4.6 WEEKLY PROGRESS MEETING
After receiving notice-to-proceed, the Contractor shall establish a schedule for weekly progress meetings. The purpose of the weekly progress meeting is for the Contractor to: 1) Communicate information relevant to the current status of the project's progress; 2) Communicate risks which may impact near term progress; 3) Identify upcoming activities and necessary actions which precede those activities; 4) Relay relevant personnel information; Go over status of pending modifications, pay requests, RFI's, submittals, deficiencies, and other administrative matters. This list is not all inclusive and should be expanded as deemed appropriate by the Contracting Officer and the Contractor.
The Contractor shall host the weekly progress meeting on the same day of the week for the duration of the project. The day of the week and time of the meeting shall be approved by the Contracting Officer. The meeting shall be held on-site in a location that provides adequate seating for the Contractor's attendees and the Government's attendees.
The Contractor is responsible for preparing the agenda for the weekly progress meeting. The agenda must be updated as the project progresses so that it remains relevant to the status of the project. The Contractor shall provide the agenda to the Contracting Officer on a weekly basis at least 4 hours prior to the start of the meeting.
The Contractor is responsible for recording meeting minutes at every weekly progress meeting. The meeting minutes shall be provided via e-mail to the Government for review no more than 24 hours after completion of the meeting. The Government may respond with corrections to the meeting minutes, and the Contractor shall provide a final copy no more than 24 hours after receiving Government comments or concurrence. Final meeting minutes will be attached to the QC daily report corresponding to the day the meeting takes place.
1.5 PROJECT SIGNS
1.5.1 General
Furnish and erect, within 15 days after issuance of the Notice to Proceed, a PROJECT IDENTIFICATION SIGN and a SAFETY PERFORMANCE SIGN at the location directed by the Contracting Officer. Letter signs on one side only and conform to EP 310-1-6a (Section 16), EP 310-1-6b , and to the details and colors shown on the sketches attached at the end of Section 01 95 00 FORMS AND ATTACHMENTS. Name the project as follows:
Cleveland Flood Risk Management: Blount Avenue Channel Modification
1.5.2 Materials
Construct the sign with a face sheet of 3/4 inch exterior grade plywood mounted on a substantial framework of treated 4-inch by 4-inch material.
Screws shall be commercial quality and of sizes shown.
1.5.3 Painting
Apply one prime coat and two finish coats of exterior oil paint to signs and post before lettering. Apply letters and trim to one side only using
SECTION 01 00 00 Page 5 one coat of enamel of color, style, and size shown.
1.5.4 Erection and Maintenance
Erect signs at the locations designated by the Contracting Officer. Signs shall be plumb and backfill of post holes shall be well tamped to properly support the signs throughout the life of the contract. Maintain signs in good condition until completion of the contract. Remove signs from the site upon final acceptance of the contract work.
1.6 Working Hours
Regular working hours must consist of an 8 1/2 hour period established by the Contracting Officer, between 7 a.m. and 3:30 p.m., Monday through Friday, and 7 a.m. to 3:30 p.m. on Saturday , excluding Government holidays.
1.6.1 Federal Holidays
Do not schedule work on Federal holidays
Refer to OPM Website for Federal holidays listed by calendar year https://www.opm.gov/policy-data-oversight/pay-leave/federal-holidays .
1.7 Work Outside Regular Hours
Work outside regular working hours requires Contracting Officer approval.
Make application 15 calendar days prior to such work to allow arrangements to be made by the Government for inspecting the work in progress, giving the specific dates, hours, location, type of work to be performed, contract number and project title. Based on the justification provided, the Contracting Officer may approve work outside regular hours. During periods of darkness, the different parts of the work must be lighted in a manner approved by the Contracting Officer.
1.8 CONTRACTOR'S STAGING AREA
The Contractor will be assigned an area within or near the project site for use as a staging area. Proposed staging area is annotated in the drawings. The building of structures, the erection of tents or other forms of protection will be permitted only at such places as the Government shall approve, and the sanitary conditions of the grounds in or about such structures shall at all times be maintained in a satisfactory manner. Temporary Contractor facilities provided during Construction shall be removed prior to final acceptance from the Government. As a minimum the area shall be left looking "broom clean" and at least as clean as before the structure placement.
1.9 DAILY CLEANUP AND DISPOSAL
Work areas shall be kept reasonably neat on a daily basis. Debris resulting from the work, such as empty paint cans, packing cases, scrap lumber, oil and grease spills, and other debris shall be collected, removed, and disposed of off-site at least once per week. Government trash cans, dump boxes and other containers shall not be used. Liquid waste shall not be disposed of in existing drains.
SECTION 01 00 00 Page 6
1.10 PROTECTION AND RESTORATION OF EXISTING FACILITIES
Existing facilities shall be protected whether or not shown on the drawings. Upon completion of the work, existing facilities, not included as a portion of the work, shall be left in a condition equal to the original condition prior to the contract. Costs for repair and restoration of any facilities shall be considered to be incidental to and included in the contract price.
1.11 EVALUATION OF CONTRACTOR PERFORMANCE
The Contractor's performance will be evaluated in accordance with FAR Part
42.15 in the areas of quality, schedule, cost control, management, utilization of small businesses, and regulatory compliance at minimum.
The evaluation will include a written narrative and rating of either exceptional, very good, satisfactory, marginal, or unsatisfactory for each. The format for the evaluation is attached at the end of Section
01 95 00 FORMS AND ATTACHMENTS.
The Contractor's review of the evaluation shall be completed electronically at the CPARS, http://www.cpars.gov . This website also includes guidance and the user's manual.
Upon contract award, the Contractor shall provide the Contracting Officer with the name and e-mail address of the Contractor's Representative to be registered into the system. Following initial completion by the Government, the Contractor will have sixty (60) calendar days to review, comment, and return the evaluation.
1.12 VETERANS EMPLOYMENT EMPHASIS FOR U.S. ARMY CORPS OF ENGINEERS
CONTRACTS
In addition to complying with the requirements outlined in FAR Part 22.13 EQUAL OPPORTUNITY FOR VETERANS, FAR Clause 52.222-35 EQUAL OPPORTUNITY FOR VETERANS, FAR Clause 52.222-37 EMPLOYMENT REPORTS ON VETERANS, DFARS
222.13 SPECIAL DISABLED AND VIETNAM ERA VETERANS, and Department of Labor regulations, U.S. Army Corps of Engineers (USACE) contractors and subcontractors at all tiers are encouraged to promote the training and employment of U.S. veterans while performing under a USACE contract.
While no set-aside, evaluation preference, or incentive applies to the solicitation or performance under the resultant contract, USACE contractors are encouraged to seek out highly qualified veterans to perform services under this contract. The following resources are available to assist USACE contractors in their outreach efforts:
a. Veterans’ Employment and Training Service (VETS):
http://www.dol.gov/vets/
b. Federal Veteran Employment Information: www.fedshirevets.gov
c. Veterans Opportunity to Work (VOW) Program: http://benefits.va.gov/vow/
d. Hiring Our Heroes: www.uschamberfoundation.org/hiring-our-heroes
1.13 MEASUREMENT AND PAYMENT
No separate payment will be made for the work covered under this section.
The costs thereof shall be included in the item to which the work pertains.
SECTION 01 00 00 Page 7
PART 2 PRODUCTS (NOT USED)
PART 3 EXECUTION
-- End of Section --
SECTION 01 00 00 Page 8
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 11 00
SUMMARY OF WORK
PART 1 GENERAL
1.1 REFERENCES
1.2 SUBMITTALS
1.3 WORK COVERED BY CONTRACT DOCUMENTS
1.3.1 Project Description
1.3.2 Location
1.4 EXISTING WORK
1.5 LOCATION OF UNDERGROUND UTILITIES
1.5.1 Notification Prior to Excavation
1.6 AVAILABILITY AND USE OF UTILITY SERVICES
1.6.1 Contractor Responsibilities
1.6.2 Alterations to Utilities
1.6.3 Interruptions of Utilities
PART 2 PRODUCTS
PART 3 EXECUTION
3.1 SEQUENCE OF WORK
3.1.1 General
3.2 CONTRACTOR SURVEYS
3.2.1 Pre and Post Construction Surveys
3.2.2 Survey Standards
3.2.3 Survey Firm Acceptance
3.2.4 Survey Control and Datum
3.2.5 Positioning System
3.2.6 Survey Data
3.2.6.1 Survey Data
3.2.7 Progress Payment Surveys
SECTION 01 11 00 Page 1
SECTION 01 11 00 Page 2
SECTION 01 11 00
SUMMARY OF WORK
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this section to the extent referenced. The publications are referred to within the text by the basic designation only.
U.S. ARMY CORPS OF ENGINEERS (USACE)
EM 385-1-1 (2024) Safety -- Safety and Occupational Health (SOH) Requirements
EM 1110-1-1000 (2015) Photogrammetric and LiDAR Mapping
EM 1110-1-1002 (2012) Survey Markers and Monumentations
EM 1110-1-1003 (2011) NAVSTAR Global Positioning System Surveying
EM 1110-1-1004 (2002) Engineering and Design - Geodetic and Control Surveying
EM 1110-1-1005 (2007) Control and Topographic Surveying
EM 1110-1-2909 (2012) Engineering and Design -- Geospatial Data and Systems
ERDC/ITL TR-19-6 (2019) A/E/C Graphics Standard, Release 2.1
1.2 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Survey Firm Acceptance; G
SD-07 Certificates
Progress Payment Surveys; G
SD-11 Closeout Submittals
Pre And Post Construction Surveys; G
SECTION 01 11 00 Page 3
1.3 WORK COVERED BY CONTRACT DOCUMENTS
1.3.1 Project Description
This section comprises an explanation of the general contract requirements associated with channel excavation along South Mouse Creek. The scope of services for the items described is in the bidding schedule. This section is not intended to be all encompassing in the descriptions. All work specified herein shall be accomplished in accordance with the procedures prescribed in the specifications and contract drawings. The Contractor shall bid each type of work under the applicable bid item. Compensation for any item of work described in the contract documents, but not listed in the bid schedule shall be included in the price for the item of work to which it is made subsidiary.
The Contractor is required to commence work within ten (10) days of the issuance of the Notice to Proceed, unless otherwise directed by the Contracting Officer. All work shall be completed as specified, detailed and/or in strict accordance with all terms, conditions, general, specific and technical provisions, contained herein or incorporated by reference.
Incorporation by reference shall include any and all mandatory provisions required by the Federal Acquisition Regulation (FAR) whether it is referenced or not referenced, current at time of award.
The Blount Avenue Channel Improvement project generally consist of approximately 1,400 linear feet channel modification along the left bank of South Mouse Creek, which includes but may not be limited to, channel excavation, hauling, grading, stripping, hydroseeding, planting, clearing and grubbing, and riprap placement around existing sewer manhole.
1.3.2 Location
The work is located along the left bank of South Mouse Creek from Smith Drive SW to approximately 1,400 feet down stream in Cleveland, TN, approximately as indicated. The exact location will be shown by the Contracting Officer and on the Contract Drawings.
1.4 EXISTING WORK
In addition to FAR 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements:
a. Remove or alter existing work in such a manner as to prevent injury or damage to any portions of the existing work which remain.
b. Repair or replace portions of existing work which have been altered during construction operations to match existing or adjoining work, as approved by the Contracting Officer. At the completion of operations, existing work must be in a condition equal to or better than that which existed before new work started.
1.5 LOCATION OF UNDERGROUND UTILITIES
Obtain digging permits prior to start of excavation, and comply with requirements for locating and marking underground utilities. Contact local utility locating service a minimum of 72 hours, excluding weekends and holidays, prior to excavating, to mark utilities, and within sufficient time required if work occurs on a Monday or after a Holiday.
SECTION 01 11 00 Page 4
Verify existing utility locations indicated on contract drawings, within area of work.
1.5.1 Notification Prior to Excavation
Notify the Contracting Officer at least 48 hours prior to starting excavation work.
1.6 AVAILABILITY AND USE OF UTILITY SERVICES
1.6.1 Contractor Responsibilities
a. The Contractor shall be responsible for the availability of utilities for use on the project. Unless otherwise provided in the contract, the amount of each utility service consumed shall be charged to and paid for by the Contractor. The Contractor shall carefully conserve any utilities furnished without charge.
b. The Contractor, at its expense and in a workmanlike manner satisfactory to the Contracting Officer, shall install and maintain all necessary temporary connections and distribution lines, and all meters required to measure the amount of each utility used for the purpose of determining charges. Before final acceptance of the work by the Government, the Contractor shall remove all the temporary connections, distribution lines, meters, and associated paraphernalia.
1.6.2 Alterations to Utilities
a. Where changes and relocations of utility lines are noted to be performed by others, the Contractor shall give the Contracting Officer at least ten (10) days written notice in advance of the time that the change or relocation is required. In the event that, after the expiration of ten
(10) days after the receipt of such notice by the Contracting Officer, such utility lines have not been changed or relocated and delay is occasioned to the completion of the work under contract, the Contractor will be entitled to a time extension equal to the period of time lost by the Contractor after the expiration of said ten (10) day period. Any modification to existing or relocated lines required as a result of the Contractor's method of operation shall be made wholly at the Contractor's expense and no additional time will be allowed for delays incurred by such modifications.
b. Separate payment will not be made for alterations or relocations of utilities.
1.6.3 Interruptions of Utilities
a. No utility services shall be interrupted by the Contractor to make connections, to relocate, or for any purpose without approval of the Contracting Officer.
b. Request for Permission to shut down services shall be submitted in writing to the Contracting Officer not less than seventeen (17) days prior to date of proposed interruption. The request shall give the following information:
(1) Nature of Utility (Gas, L.P. or H.P., Water, etc.)
SECTION 01 11 00 Page 5
(2) Size of line and location of shutoff.
(3) Buildings and services affected.
(4) Hours and date of shutoff.
(5) Estimated length of time services will be interrupted.
c. Services shall not be shutoff until receipt of approval of the proposed hours and date from the Contracting Officer.
d. Shutoffs which will cause interruption of Government work operations as determined by the Contracting Officer shall be accomplished during regular non-work hours or on non-work days of the Using Agency.
e. Operation of valves on water mains will be by Government personnel.
Where shutoff of water lines interrupts service to fire hydrants or fire sprinkler systems, the Contractor shall arrange his operations and have sufficient material and personnel available to complete the work without undue delay or to restore service without delay in event of emergency.
PART 2 PRODUCTS
Not used.
PART 3 EXECUTION
3.1 SEQUENCE OF WORK
3.1.1 General
After receipt of Notice to Proceed (NTP), the Contractor shall initiate coordination meetings with the Contracting Officer and representatives.
Submission requirements affecting utilities and initial surveys as covered under this section shall be given to the Government for review and acceptance. The Contractor shall perform all preparatory work associated with the disposal area and channel prior to performing excavation. The Contractor may begin construction on portions of the work for which the Government has reviewed the final submission and has determined satisfactory for purposes of beginning construction. The Contracting Officer will notify the Contractor when the design is cleared for construction. The Government will not grant any time extension for any design re-submittal required when, in the opinion of the Contracting Officer, initial submission failed to meet the minimum quality requirements as set forth in the Contract.
If the Government allows the Contractor to proceed with limited construction based on pending minor revisions to the reviewed Final Design submission, no payment will be made for any in-place construction related to the pending revisions until they are completed, resubmitted and are satisfactory to the Government.
3.2 CONTRACTOR SURVEYS
3.2.1 Pre and Post Construction Surveys
The preconstruction survey will be performed after clearing and grubbing is completed and prior to any stripping, excavation or construction activities.
SECTION 01 11 00 Page 6
3.2.2 Survey Standards
Prepare digital survey material in accordance with the applicable technical references specified. The Contracting Officer may issue additional instructions during the performance of the work. Notify the Contracting Officer of any missing criteria needed for the survey work.
EM 385-1-1 (2014) Safety and Health Requirements Manual EM 1110-1-1000 (2015) Photogrammetric and LiDAR Mapping EM 1110-1-1002 (2012) Survey Markers and Monumentations EM 1110-1-1003 (2011) NAVSTAR Global Positioning System Surveying EM 1110-1-1004 (2002) Engineering and Design - Geodetic and Control Surveying EM 1110-1-1005 (2007) Control and Topographic Surveying EM 1110-1-2909 (2012) Geospatial Data and Systems ERDC/ITL TR-19-6 (August 2019) A/E/C CAD Standard Release 6.1 ERDC/ITL TR-19-6 (August 2019) A/E/C Graphics Standard Release 2.1
3.2.3 Survey Firm Acceptance
All surveys must be performed by a survey firm, independent of the Contractor. The firm must have a minimum of three years of qualifying experience in topographic surveys, boundary surveys, and construction staking. The firm must have a current Tennessee Land Surveyor's license.
3.2.4 Survey Control and Datum
a. Perform all surveys using the Corps of Engineers control network as indicated. All survey and mapping work must be in the datum, projection and units of the control indicated or as otherwise directed.
b. Replace or relocate survey control points that have been disturbed or destroyed. Coordinate with the Contracting Officer and County Surveyor's office based on the original survey control and submitting field notes showing the character of the new points and methods of establishment or re-establishment. The Contractor must make no changes without prior written approval from the Contracting Officer.
c. Notify the Contracting Officer in writing, 7 days in advance of movement or removal of any monument, bench mark or right-of-way marker.
3.2.5 Positioning System
Perform Surveys using proven, modern electronic surveying equipment such as RTK GPS, automated Total Station or similar system with positional accuracy equal to or exceeding the requirements of EM 1110-1-1003 and EM 1110-1-1005 . Antiquated equipment and/or emerging technology must not be used unless otherwise approved.
3.2.6 Survey Data
3.2.6.1 Survey Data
a. Each survey submittal must consist of three sets of the applicable files on DVD or external hard drives, if necessary, and include the following:
(1) Openroads Designer DGN (3D) file with contours generated from
SECTION 01 11 00 Page 7 the terrain models. All Openroads Designer files must include the proper Geographic Coordinate System and working unit's settings.
Each digital file must immediately reference to other digital files and be correctly oriented. Submit each DGN file with layers at a minimum showing: point ID Descriptions, Codes, breaklines, and contours and TIN. The DGN must be processed and ready for surface to surface comparisons. CADD files must use the settings for layer, color, and other properties found in ERDC/ITL TR-09-2.
(2) ASCII mass points file with a data header. The first header line must be preceded by an asterisk, which indicates a comment line.
All DVD's, hard drives, points files and drawing files (DGN files) must be labeled with a header or title block showing, at a minimum, the following project information:
(1) Project: (____)
(2) Date: (____)
(3) Surveyor: Name of firm and licensed surveyor
(4) Area: (____)
(5) Survey Type: topographic, construction staking, boundary, other
(6) Survey Method: RTK, total station, digital levels, other
(7) Unit of measure: US Survey Feet
(8) Vertical Datum: (____)
(9) Horizontal Datum: (____)
(10) Projection: (____)
(11) Control used: (____)
(12) Data Format: use northing, easting, elevation, point description
c. Use a Data Processing System to map the survey data and calculate quantities. The software must be capable of digital terrain modeling and must produce, at a minimum, topographic survey sheets, cross section profiles, 3-dimensional area profiles, and quantity volume calculations using end area method having cross sections cut along the control line at intervals of 25 feet and at every change in grade and/or bearing.
d. Unless otherwise directed, the accuracy of all quantity surveys submitted for progress payment must be at a minimum of one foot contour intervals.
3.2.7 Progress Payment Surveys
Progress payments will be based upon quantities from the Contractor's surveys. Provide full coverage of the entire area for which progress payment is requested. Survey data which does not conform to the specifications will not be considered for payment.
SECTION 01 11 00 Page 8
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 20 00
PRICE AND PAYMENT PROCEDURES
PART 1 GENERAL
1.1 SUBMITTALS
1.2 CONTRACTOR'S INVOICE AND CONTRACT PERFORMANCE STATEMENT
1.2.1 Submission of Invoices
1.2.2 Final Invoice
1.3 PAYMENT ITEMS
1.3.1 Mobilization and Demobilization
1.3.1.1 Payment
1.3.1.2 Unit of Measure
1.3.2 Clearing,Grubbing And Miscellaneous Demolition
1.3.2.1 Payment
1.3.2.2 Unit of Measure
1.3.3 Excavation
1.3.3.1 Payment
1.3.3.2 Measurement
1.3.3.3 Unit of Measure
1.3.4 Seeding and Planting
1.3.4.1 Payment
1.3.4.2 Unit of Measure
1.3.5 Disposal Area Closure
1.3.5.1 Payment
1.3.5.2 Unit of Measure
PART 2 PRODUCTS
PART 3 EXECUTION
SECTION 01 20 00 Page 1
SECTION 01 20 00 Page 2
SECTION 01 20 00
PRICE AND PAYMENT PROCEDURES
PART 1 GENERAL
1.1 SUBMITTALS
Government approval is required for submittals with a "G" or "S" classification. Submittals not having a "G" or "S" classification are for information only. When used, a code following the "G" classification identifies the office that will review the submittal for the Government.
Submit the following in accordance with Section 01 33 00 SUBMITTAL
PROCEDURES:
1.2 CONTRACTOR'S INVOICE AND CONTRACT PERFORMANCE STATEMENT
1.2.1 Submission of Invoices
Submit monthly invoices and supporting forms for work performed within one week after the month billed. Submit a written copy (pencil copy) five calendar days prior to the end of the month.
1.2.2 Final Invoice
a. A final invoice must be accompanied by the Contractor's Final Release.
If the Contractor is incorporated, the Final Release must contain the corporate seal. An officer of the corporation must sign and the corporate secretary must certify the Final Release.
b. Final invoices not accompanied by the Contractor's Final Release will be considered incomplete and will be returned to the Contractor.
1.3 PAYMENT ITEMS
Payment items for the work of this Contract for which Contract job payments and Contract unit price payments will be made are listed in the BIDDING SCHEDULE and described below. All costs for items of work, which are not specifically mentioned to be included in a particular job or unit price payment item, are included in the listed job item most closely associated with the work involved. The job price and payment made for each item listed constitutes full compensation for furnishing all plant, labor, materials, and equipment, and performing any associated Contractor quality control, environmental protection, meeting safety requirements, tests and reports, and for performing all work required for which separate payment is not otherwise provided.
1.3.1 Mobilization and Demobilization
1.3.1.1 Payment
Payment will be made for costs associated with mobilization and demobilization, as defined in Special Contract Clause DFARS 252.236-7004 PAYMENT FOR MOBILIZATION AND DEMOBILIZATION. Sixty percent of the CLIN must be allocated to mobilization and forty percent of the CLIN must be
SECTION 01 20 00 Page 3 allocated to demobilization.
Payment will be also be made for Performance and Payment Bonds that are required as part of this contract in accordance with Contract Clause 52.232-5 PAYMENTS UNDER FIXED-PRICE CONSTRUCTION CONTRACTS. Payment for the premiums for performance and payment bonds will be made at the contract price per Job for "Performance and Payment Bonds."
1.3.1.2 Unit of Measure
Unit of measure: job.
1.3.2 Clearing,Grubbing And Miscellaneous Demolition
1.3.2.1 Payment
Payment will be made for costs associated with operations necessary for clearing, grubbing and miscellaneous demolition. Payment will be made for clearing and grubbing of trees and vegetation, maintaining the cleared and grubbed areas, removal of all obstructions as required to perform the work including, but not limited to, preparation of a clearing and grubbing plan. Payment also includes filling of holes and depressions associated with clearing and grubbing, offsite disposal of all cleared, grubbed and removed items, disposal fees, installation and removal of temporary chain link fence, placement of class A-3 riprap and other items indicated, complete.
1.3.2.2 Unit of Measure
Unit of measure: job.
1.3.3 Excavation
1.3.3.1 Payment
Payment will be made for excavating to the lines and grades indicated, including stockpiling, grading, shaping, hauling, stripping of top soil, water control, unwatering, and offsite disposal of material, complete. No additional payment will be made for quantity variations due to bulking, moisture content or subsidence of the in-place material to be excavated.
The Contractor will not receive any compensation for excavation work outside of the lines and grades indicated, unless otherwise directed.
1.3.3.2 Measurement
The total quantity of excavated material for which payment will be made will be the theoretical quantity between the ground surface as determined by a preconstruction survey and the grade and slope of the theoretical cross sections indicated. No allowance will be made for overdepth excavation or for the removal of any material outside the required slope lines unless authorized.
1.3.3.3 Unit of Measure
Unit of measure: cubic yard.
SECTION 01 20 00 Page 4
1.3.4 Seeding and Planting
1.3.4.1 Payment
Payment will cover all costs associated with seeding, planting, mulching, incorporating, protecting, and maintaining at the primary project site.
This price shall constitute full compensation for furnishing all plants, labor, equipment, materials, and performing all operations necessary for placing and maintaining seed, mulch, and plants including acquisition and incorporation of topsoil and erosion control blankets or other items as specified in Section 32 92 19 - SEEDING. No payment for seeding, planting, and mulching will be made until acceptance by the Contracting Officer or his/her representative. Payment will be made for costs associated with satisfactory performance of seeding.
1.3.4.2 Unit of Measure
Unit of measure: job.
1.3.5 Disposal Area Closure
1.3.5.1 Payment
Payment will be made for costs associated with disposal area closure, including grading, shaping, stockpiling, stripping of top soil, water control, seeding, mulching, incorporation of top soil, erosion control measures and preparation of a disposal area closure plan, complete and accepted.
1.3.5.2 Unit of Measure
Unit of measure: job.
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
Not Used
SECTION 01 20 00 Page 5
SECTION 01 20 00 Page 6
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 32 01.00 10
PROJECT SCHEDULE
PART 1 GENERAL
1.1 REFERENCES
1.2 SUBMITTALS
1.3 PROJECT SCHEDULER QUALIFICATIONS
PART 2 PRODUCTS
2.1 SOFTWARE
2.1.1 Government Default Software
2.1.2 Contractor Software
PART 3 EXECUTION
3.1 GENERAL REQUIREMENTS
3.1.1 Scheduling Expectations Kickoff Meeting(SEKO)
3.2 BASIS FOR PAYMENT AND COST LOADING
3.2.1 Activity Cost Loading
3.2.2 Withholdings / Payment Rejection
3.3 PROJECT SCHEDULE DETAILED REQUIREMENTS
3.3.1 File Naming Convention
3.3.2 Level of Detail Required
3.3.3 Activity Durations
3.3.4 Design and Permit Activities
3.3.5 Submittals, Fabrication, andProcurement Activities
3.3.6 Closeout Activities
3.3.7 Government Activities
3.3.8 Standard Activity Coding Dictionary
3.3.8.1 Workers Per Day (WRKP)
3.3.8.2 Responsible Party Coding (RESP)
3.3.8.3 Area of Work Coding (AREA)
3.3.8.4 Modification Number (MODF)
3.3.8.5 Bid Item Coding (BIDI)
3.3.8.6 Phase of Work Coding (PHAS)
3.3.8.7 Category of Work Coding (CATW)
3.3.8.8 Feature of Work Coding (FOW)
3.3.9 Contract Milestones and Constraints
3.3.9.1 Project Start Date Milestone and Constraint
3.3.9.2 End Project Finish Milestone and Constraint
3.3.9.3 Interim Completion Dates and Constraints
3.3.9.3.1 Start Phase
3.3.9.3.2 End Phase
3.3.10 Adverse Weather
3.3.11 Calendars
3.3.12 Open Ended Logic
3.3.13 Default Progress Data Disallowed
SECTION 01 32 01 Page 1
3.3.14 Out-of-Sequence Progress
3.3.15 Added and Deleted Activities
3.3.16 Original Durations
3.3.17 Leads, Lags, and Start to Finish Relationships
3.3.18 Retained Logic
3.3.19 Percent Complete
3.3.20 Remaining Duration
3.3.21 Cost Loading of Closeout Activities
3.3.21.1 As-Built Drawings
3.3.21.2 O & M Manuals
3.3.22 Early Completion Schedule and the Right to Finish Early
3.4 PROJECT SCHEDULE SUBMISSIONS
3.4.1 Preliminary Project Schedule Submission
3.4.2 Initial Project Schedule Submission
3.4.2.1 Design Package Schedule Submission
3.4.3 Periodic Schedule Updates
3.4.4 Re-Baseline for Exercised Options
3.5 SUBMISSION REQUIREMENTS
3.5.1 Electronic Scheduling Data
3.5.2 Narrative Report
3.5.3 Schedule Reports
3.5.3.1 Activity Report
3.5.3.2 Logic Report
3.5.3.3 Total Float Report
3.5.3.4 Earnings Report by CLIN
3.5.3.5 Scheduling and Leveling Report
3.5.4 Network Diagram
3.5.4.1 Continuous Flow
3.5.4.2 Project Milestone Dates
3.5.4.3 Critical Path
3.5.4.4 Grouping and Sorting
3.5.4.5 Cash Flow / Schedule Variance Control (SVC) Diagram
3.6 SCHEDULE EXPECTATIONS KICKOFF MEETING (SEKO)
3.7 PERIODIC SCHEDULE UPDATE
3.7.1 Periodic Schedule Update Meetings
3.7.2 Update Submission Following Progress Meeting
3.8 WEEKLY PROGRESS MEETINGS
3.9 REQUESTS FOR TIME EXTENSIONS
3.9.1 Justification of Delay
3.9.2 Changes That Do Not Cause Delay
3.9.3 Time Impact Analysis (Prospective Analysis)
3.9.4 Forensic Schedule Analysis (Retrospective Analysis)
3.9.5 Fragmentary Network (Fragnet)
3.9.6 Time Extension
3.9.7 Impact to Early Completion Schedule
3.10 FAILURE TO ACHIEVE PROGRESS
3.10.1 Artificially Improving Progress
3.10.2 Failure to Perform
3.10.3 Recovery Schedule
3.11 OWNERSHIP OF FLOAT
3.12 TRANSFER OF SCHEDULE DATA INTO RESIDENT MANAGEMENT SYSTEM
3.13 PRIMAVERA P6 MANDATORY REQUIREMENTS
SECTION 01 32 01 Page 2
SECTION 01 32 01.00 10
PROJECT SCHEDULE
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
AACE INTERNATIONAL (AACE)
AACE 29R-03 (2011) Forensic Schedule Analysis
AACE 52R-06 (2006) Time Impact Analysis - As Applied in Construction
AACE 84R-13 (2015) Planning and Accounting for Adverse Weather
AMERICAN SOCIETY OF CIVIL ENGINEERS (ASCE)
ASCE 67-17 (2017) Schedule Delay Analysis
U.S. ARMY CORPS OF ENGINEERS (USACE)
ER 1-1-11 (2017) Administration -- Project Schedules
1.2 SUBMITTALS
Government approval is required for submittals with a "G"classification.
Submittals not having a "G" classification are for information only. When used, a code following the "G" classification identifies the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Project Scheduler Qualifications; G
Preliminary Project Schedule; G
Initial Project Schedule; G
Periodic Schedule Update; G
1.3 PROJECT SCHEDULER QUALIFICATIONS
Designate an authorized representative to be responsible for the preparation of the schedule and all required updating and production of reports. The Designated Project Scheduler must have prepared and maintained at least three previous construction schedules for projects of similar size and complexity to this contract, using Primavera P6.
Representative must have a comprehensive knowledge of CPM scheduling
SECTION 01 32 01 Page 3 principles and application.
PART 2 PRODUCTS
2.1 SOFTWARE
The scheduling software utilized to produce and update the schedules required herein must be capable of meeting all requirements of this specification.
2.1.1 Government Default Software
The Government intends to use Primavera P6 version 22.12
2.1.2 Contractor Software
Scheduling software used by the contractor must be able to meet the requirements of this specification and be compatible with the software used by the Government; Primavera P6 version 22.12
PART 3 EXECUTION
3.1 GENERAL REQUIREMENTS
Prepare for approval a project schedule, as specified herein. Show in the schedule the proposed sequence to perform the work and dates contemplated for starting and completing all schedule activities. The scheduling of the entire project is required. The scheduling of design and construction is the responsibility of the Contractor. Contractor management personnel must actively participate in its development. Designers, Subcontractors, and suppliers working on the project must also contribute in developing and maintaining an accurate Project Schedule. Provide a schedule that is a forward planning as well as a project monitoring tool. Use the Critical Path Method (CPM) of network calculation to generate all Project Schedules. Prepare each Project Schedule using the Precedence Diagram Method (PDM).
3.1.1 Scheduling Expectations Kickoff Meeting(SEKO)
In conjunction with the post award conference or pre construction conference the Government and the Contractor will hold a separate and distinct Scheduling Expectations Kickoff Meeting(SEKO). The intent of this meeting is for the Government to review with the contractor the requirements of the scheduling specification, communicate the Government’s expectations regarding schedule development and management, and answer any questions the Contractor may have regarding the schedule requirements.
3.2 BASIS FOR PAYMENT AND COST LOADING
The schedule is the basis for determining contract earnings during each update period and therefore the amount of each progress payment. The aggregate value of all activities coded to a contract CLIN must equal the value of the CLIN. Match the progress payment "Pay Period Thru" date in RMS to the schedule data date.
3.2.1 Activity Cost Loading
Activity cost loading must be reasonable and without front-end loading.
Activities with a negative cost loading is not allowed. Provide
SECTION 01 32 01 Page 4 additional documentation to demonstrate reasonableness if requested by the Contracting Officer.
3.2.2 Withholdings / Payment Rejection
Failure to meet the requirements of this specification may result in the disapproval of the preliminary, initial, or periodic schedule updates and subsequent rejection of payment requests until compliance is met.
In the event that the Contracting Officer directs schedule revisions and those revisions have not been included in subsequent Project Schedule revisions or updates, the Contracting Officer may withhold 10 percent of pay request amount from each payment period until such revisions to the project schedule have been made.
3.3 PROJECT SCHEDULE DETAILED REQUIREMENTS
3.3.1 File Naming Convention
All contractual scheduling documents shall be submitted with a three part naming structure comprised of: 1. Contract ID Number, 2. Schedule Type and
3. Version.
The Contract ID Number shall align with the official contract documents and numbering structure. A truncated version of this number may be appropriate.
The Schedule Type shall be one of the following options:
"1PREL" for Preliminary Schedules "2INIT" for Initial Schedules "3MPCT" for schedules that model potential delays "4RBAS" for Re-baseline Schedules "5UP##" for Periodic Schedule Updates "6RCVR" for Recovery Schedules "7COMPL" for Completion Schedules
The version # shall be used to identify subsequent updates.
An Example naming structure: A123456-2INIT-V02; This file would be submitted as the 2nd version of the Initial Schedule for contract A123456
3.3.2 Level of Detail Required
Develop the Project Schedule to the appropriate level of detail to address major milestones and to allow for satisfactory project planning and execution. Failure to develop the Project Schedule to an appropriate level of detail will result in its disapproval. The Contracting Officer will consider, but is not limited to, the following characteristics and requirements to determine appropriate level of detail:
3.3.3 Activity Durations
Reasonable activity durations are those that allow the progress of ongoing activities to be accurately determined between update periods.
The unit of measurement for durations in "days". Non-procurement activities Original Durations (OD) are not to exceed 30 calendar days.
SECTION 01 32 01 Page 5
3.3.4 Design and Permit Activities
Include design and permit activities with the necessary conferences and follow-up actions and design package submission dates. Include the design schedule in the project schedule, showing the sequence of events involved in carrying out the project design tasks within the specific contract period. Provide a detailed level of scheduling sufficient to identify all major design tasks, including those that control the flow of work. Also include review and correction periods associated with each item.
3.3.5 Submittals, Fabrication, andProcurement Activities
Include in the schedule activities associated with critical submittals and their approvals, procurement, fabrication, and delivery of long lead materials, equipment, fabricated assemblies, and supplies. Long lead procurement activities are those with an anticipated procurement sequence of over 90 calendar days.
3.3.6 Closeout Activities
Include activities associated with the closeout of the project that take place after the contractor is substantially complete. The contractor shall maintain at least 45 days of time, post substantial completion, to account for all closeout related activities. These activities may include, but are not limited to: Final Punchlist Corrections, Final Walk Through, and Acceptance, Preparation and Submission of O&M Manuals and As-Builts.
3.3.7 Government Activities
Show Government and other agency activities that could impact schedule progress. These activities include, but are not limited to approvals, acceptance, design reviews, environmental permit approvals by State regulators, inspections, utility tie-in, Government Furnished Equipment (GFE) and Notice to Proceed (NTP) for phasing requirements.
3.3.8 Standard Activity Coding Dictionary
Use the activity coding structure defined in the Standard Data Exchange Format (SDEF) in ER 1-1-11 . This exact structure is mandatory. Develop and assign all Activity Codes to activities as detailed herein.
The SDEF format is as follows:
Field Activity Code Length Description
1 WRKP 3 Workers per day
2 RESP 4 Responsible party
3 AREA 4 Area of work
4 MODF 6 Modification Number
5 BIDI 6 Bid Item (CLIN)
6 PHAS 2 Phase of work
SECTION 01 32 01 Page 6
Field Activity Code Length Description
7 CATW 1 Category of work
8 FOW 20 Feature of work*
*Some systems require that FEATURE OF WORK values be placed in several activity code fields. The notation shown is for Primavera P6. Refer to the specific software guidelines with respect to the FEATURE OF WORK field requirements.
3.3.8.1 Workers Per Day (WRKP)
Assign Workers per day codingfor all field construction or direct work activities. Workers per day is based on the average number of workers expected each day to perform a task for the duration of that activity.
Activity durations should be based on, in part, the number of workers assigned to that task.
3.3.8.2 Responsible Party Coding (RESP)
Assign responsibility coding for all activities to the Prime Contractor, Subcontractor(s) or Government agency(ies) responsible for performing the activity.
a. Activities coded with a Government Responsibility code include, but are not limited to: Government approvals, Government design reviews, environmental permit approvals by State regulators, Government Furnished Property/Equipment (GFP) and Notice to Proceed (NTP) for phasing requirements.
b. Activities cannot have more than one Responsibility Code. Examples of acceptable activity code values are: DOR (for the designer of record);
ELEC (for the electrical subcontractor); MECH (for the mechanical subcontractor); and GOVT (for USACE).
3.3.8.3 Area of Work Coding (AREA)
Assign Work Area coding to activities based upon the work area in which the activity occurs. Define work areas based on resource constraints or space constraints that would preclude a resource, such as a particular trade or craft work crew from working…