Request for Quotation Summary
This is a combined synopsis and Request for Quotation (RFQ) issued by the U.S. Department of State for preventive maintenance services on a photovoltaic (solar panel) system at the American Embassy in Nouakchott, Mauritania. The solicitation number is 19MR6026Q0005, with offers due June 19, 2026 at 18:00 GMT. The contract is a firm fixed price agreement, payable entirely in ouguiya (local currency), covering a base year plus four optional one-year periods. Award will be made to the lowest priced, technically acceptable offeror under FAR 12 (commercial items acquisition procedures).
The contractor must provide monthly full maintenance services and monthly technical check reports for photovoltaic equipment, including 681 solar panels (Suniva OPT 270-watt units), nine SMA inverters (both 15.3KW and 20.4KW models), nine combiner boxes, and associated DC disconnect systems. Required services include visual inspections, panel cleaning, infrared testing, inverter maintenance, fuse replacement, grounding verification, and DC system testing per IEC62446-12016 standards and manufacturer recommendations. The contractor shall supply all materials, tools, testing equipment, and trained technicians; provide safety equipment and protective measures; maintain on-site parts inventory; prepare post-trip reports within 14 days; and dispose of hazardous materials properly. Contractor personnel require security clearance for CAA/PCC areas, prior authorization, and identity cards issued by the Government. The contract excludes equipment repairs and hardware replacements unless caused by contractor negligence; repairs require separate purchase orders. Insurance requirements include public liability coverage and workers' compensation per local law. All contractors must register in SAM and comply with FAR telecommunications equipment restrictions. The Government retains the option to obtain spare parts from alternative sources.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
United States Department of State
General Services Section
Nouakchott, Mauritania
1. Public Notice
Classification Code: D3010 – Photovoltaic System (SOLAR PANELS PLANT
SYSTEM)
NAICS Code : 561210 FACILITIES SUPPORT SERVICES
The U.S. American Embassy in Nouakchott, Mauritania seeks services of a qualified and specialized contractor to perform preventive maintenance services for the photovoltaic system. The related service description is provided as an attachment to this notice. This contract will cover a base year and four option years.
Please note that this is a combined synopsis/solicitation for a service, prepared in accordance with the format FAR 12, as supplemented with additional information included in this notice.
This announcement constitutes the only solicitation; offers are being requested, and a written solicitation will not be issued.
The solicitation number is 19MR6026Q0005 and is issued as a Request for Quotation.
Offers are due on June 19 ,2026 at 18:00 GMT.
Contract Clause, in addendum to FAR 52.212-1, Instructions to Offerors-
Commercial Items, FAR 52.212-2, Evaluation—Commercial Products and
Commercial Services, FAR 52.212-3, Offeror Representations and
Certifications—Commercial Products and Commercial Service, FAR 52.212-4, Contract Terms and Conditions—Commercial Products and Commercial Services, FAR 52.212-5, Contract Terms and Conditions Required to Implement Statutes or
Executive Orders—Commercial Products and Commercial Services, apply to this acquisition. Award will be made to the lowest priced, technically acceptable offeror.
52.203-10, Price or Fee Adjustment for Illegal or Improper Activity applies to this solicitation.
The following DOSAR provisions/clauses will also apply: 652.206-70, Competition Advocacy/Ombudsman; 652.214-71, Authorization to Perform;
652.225-70, Arab League Boycott of Israel; 652.225-71, Section 8(a) of the
Export Administration Act of 1979, as Amended; 652.242-70, Contracting
Officer’s Representative; and 652.243-70, Notices. All offerors must include a completed copy of FAR 52.212-3, Offeror Representations and Certifications -
Commercial Items with their offer.
All responsible sources may submit an offer that shall be considered. If there are any questions regarding, please contact
NouakchottGSOSolicitations@state.gov.
All contractors have to be registered in the SAM (System for Award
Management) Database https://www.sam.gov prior to contract award pursuant to FAR provision 52.204-mailto:NouakchottGSOSolicitations@state.gov https://www.sam.gov/
7. Therefore, prospective offerors are encouraged to register prior to the submittal of quotations/proposals.
The guidelines for registration in SAM are also available at:
https://www.statebuy.state.gov/pd/Pages/AdditionalVendorReg.aspx
Furthermore, with the recent FAR update, it is now a mandatory requirement for the Government to inquire if contractors are using or will be using, in government contracting, covered telecommunications equipment produced by Huawei, ZTE, Hikvision, Dahua, and Hytera, or their subsidiaries or affiliates. Consequently, vendors are required to update their SAM registration with that information. Potential offerors are advised to take special attention to clauses FAR 52.204-24, FAR 52.204-25 and FAR 52.204-26 while completing their registration in SAM.
The preferable means of contact for this request for quotation is via electronic mail to the Contracting Officer at:
NouakchottGSOSolicitations@state.gov .
You will need to check this website periodically for updates.
Thank you in advance for your interest in cooperation with the US Government.
https://www.statebuy.state.gov/pd/Pages/AdditionalVendorReg.aspx mailto:NouakchottGSOSolicitations@state.gov%20.
STATEMENT OF WORK FOR
PREVENTIVE MAINTENANCE SERVICE CONTRACT
D3010 – Photovoltaic System
United States Embassy
In Nouakchott, Mauritania
Monday, May 4, 2026
TABLE OF CONTENTS
Section Page
1. DESCRIPTION
2. PRICING
3. NOTICE TO PROCEED
4. EQUIPMENT AND PERFORMANCE REQUIREMENTS
5. HOURS OF PERFORMANCE
6. ACCESS TO GOVERNMENT BUILDINGS AND STANDARDS OF CONDUCT
7. SCHEDULED PREVENTIVE MAINTENANCE
8. PERSONNEL, TOOLS, CONSUMABLE MATERIALS AND SUPPLIES
9. SOFTWARE, LICENSES AND PASSWORDS
10. DELIVERABLES
11. INSURANCE REQUIREMENTS
12. LOCAL LAW REGISTRATION
13. QUALITY ASSURANCE PLAN (QAP)
14. TRANSITIONS/CONTACTS
15. SUBMISSION OF INVOICES
Attachments:
Exhibit A – Statement of Work
1. DESCRIPTION
The American Embassy in Nouakchott requires preventive maintenance services for the photovoltaic system. These services shall result in all systems being serviced under this agreement being in good operational condition when activated. If this work is to be performed on systems accessing the PCC/CAA areas of the building. Please see section 6.2.3 for security requirements.
1.1. Type of Contract
This is a firm fixed price contract payable entirely in ouguiya. Prices for all Contract Line-Item
Numbers (CLIN) shall include proper disposal of toxic substances as per Item 8.4 where applicable. No additional sums will be payable for any escalation in the cost of materials, equipment or labor, or because of the contractor's failure to properly estimate or accurately predict the cost or difficulty of achieving the results required. The contract price will not be adjusted due to fluctuations in currency exchange rates.
1.2. Period of Performance
The contract will be for a period of one-year, with a maximum of four one-year optional periods of performance and will be expected to commence no later than the date on NTP.
2. PRICING
The rates below include all costs associated with providing preventive maintenance services in accordance with the attached scope of work, and the manufacturer’s warranty including materials, labor, insurance (see FAR 52.228-4 and 52.228-5), overhead, profit and GST (if applicable).
2.1. Base Year. The Contractor shall provide the services shown below for the base period of the contract and continuing for a period of 12 months.
2.2. Option Year 1. The Contractor shall provide the services shown below for Option Year 1 of the contract, and continuing for a period of 12 months.)
CLIN Description
Quantity of
Equipment
Type of services No. of service
Unit price
/ service
Total per year ($)
Photovoltaic Systems
Monthly full maintenanc e
Tech. check reports & Permits Monthly 12
Total Base Year
2.3. Option Year 2. The Contractor shall provide the services shown below for Option Year 2 of the contract, and continuing for a period of 12 months.
2.4. Option Year 3. The Contractor shall provide the services shown below for Option Year 3 of the contract, and continuing for a period of 12 months
CLIN Description
Quantity of
Equipment
Type of services
No. of servic e
Unit price
/ service
Total per year ($) e
Tech. check reports
& Permits
Total Option Year 1
Quantity of
Equipment
Type of services No. of service
Unit price
/ service
Total per year ($) maintenance
Tech. check reports
Total Option Year 2
Quantity of
Equipment
Type of services No. of service
Unit price
/ service
Total per year ($) e
Tech. check reports
2.5. Option Year 4. The Contractor shall provide the services shown below for Option Year 4 of the contract, and continuing for a period of 12 months
2.6. Total for all years: Base Year $
Option Year 1 $
Option Year 2 $
Option Year 3 $
Option Year 4 $
TOTAL $
2.7 Repair option. Repairs are NOT included under this agreement (see 7.1.3) and are to be done outside this contract. However, the Government desires current labor rates in the event that there is an issue discovered during the preventive maintenance of the specified equipment. Please provide your current labor rates in the Repair Option fields below. As stated in 7.1.3 any necessary repairs or parts will be submitted for approval and then billed against a separate PO.
The Contractor is not approved to do any additional work without specific authorization from the
Contracting Officer.
Repair Labor Rates
Base Year $/hr
Option Year 1 $/hr
Total Option Year 3
Quantity of
Equipment
Type of services No. of service
Unit price / service ($)
Total per year ($) e
Tech. check reports
Total Option Year 4
Option Year 2 $/hr
Option Year 3 $/hr
Option Year 4 $/hr
3. NOTICE TO PROCEED
After Contract award and submission of acceptable insurance certificates and copies of all applicable licenses and permits, the Contracting Officer will issue a Notice to Proceed. The
Notice to Proceed will establish a date (a minimum of ten (10) days from date of Contract award unless the Contractor agrees to an earlier date) on which performance shall start.
4. EQUIPMENT AND PERFORMANCE REQUIREMENTS
4.1. The American Embassy in Nouakchott requires the Contractor to maintain the following equipment in a safe, reliable and efficient operating condition. Please see equipment list included in Exhibit A for a more detailed description.
1. Solar panels, combiner boxes, panels, central mini-computer and inverters, Sunniva –
SMA – Solar BOS, Sunny TRIPOWER, 20000TL-US-10, 25000 W, Warehouse – Utility
Building and Parking areas.
4.2. The Contractor shall provide all necessary managerial, administrative and direct labor personnel, as well as all transportation, equipment, tools, supplies and materials required to perform inspection, maintenance, and component replacement as required to maintain the systems in accordance with this work statement. Under this Contract the Contractor shall provide:
• The services of trained and qualified technicians to inspect, adjust, and perform scheduled preventive maintenance.
4.3. Performance Standards
The photovoltaic system shall be clean and in good operating condition upon completion of the service. The preventive maintenance service shall result in the parts of the system serviced being in a condition to operate efficiently and effectively.
5. HOURS OF PERFORMANCE
5.1. The Contractor shall maintain work schedules. The schedules shall take into consideration the hours that the staff can effectively perform their services without placing a burden on the security personnel of the Post. The Contractor shall deliver standard services between the hours of 8:00AM and 4:30 PM Monday through Friday. No work shall be performed on US
Government and local holidays. Below is a list of the holidays.
Date Holiday US/Local
Jan 01 New Year's Day Am
Jan 16 Birthday of Martin Luther King, Jr. Am
6. ACCESS TO GOVERNMENT BUILDINGS AND STANDARDS OF CONDUCT
6.1 General. The Contractor shall designate a representative who shall supervise the
Contractor’s technicians and be the Contractor’s liaison with the American Embassy Nouakchott.
The Contractor’s employees shall be on-site only for contractual duties and not for any other business or purpose. Contractor employees will be given access to the equipment and equipment areas and will be escorted by Embassy personnel.
6.2 Personnel Security. The Government reserves the right to deny access to U.S.-owned and
U.S.-operated facilities to any individual. The Contractor shall provide the names, biographic data and police clearance on all Contractor personnel who to be used on this Contract prior to their utilization. Submission of information shall be made within 30 days of award of contract.
No technician will be allowed on site without prior authorization. Note: this may include cleared personnel if advance notice of visit is not given at least one week before the scheduled visit.
6.2.1 Vehicles. Contractor vehicles will not be permitted inside the embassy compound without prior approval. If vehicle access is necessary, submit contractor vehicle information (Make, Model, License Plate #) along with a written justification as to why access is necessary. This shall be submitted to the Facility Manager at least one (1) week prior to the visit.
6.2.2 Government shall issue identity cards to Contractor personnel, after they are approved.
Contractor personnel shall display identity card(s) on the uniform at all times while providing services under this contract. These identity cards are the property of the US Government. The
Contractor is responsible for their return at the end of the contract, when an employee leaves
Contractor service, or at the request of the Government. The Government reserves the right to deny access to U.S.-owned and U.S.-operated facilities to any individual.
Government shall issue identity cards to Contractor personnel, after they are approved.
Contractor personnel shall display identity card(s) on the uniform at all times while providing services under this contract. These identity cards are the property of the US Government. The
Contractor is responsible for their return at the end of the contract, when an employee leaves
Contractor service, or at the request of the Government. The Government reserves the right to deny access to U.S.-owned and U.S.-operated facilities to any individual.
6. 3 Security Clearances. All Work locations under this contractor that are designated as non-
CAA areas may be performed by un-cleared American or local workers. However, all work done in CAA and PCC areas shall be performed by cleared American Construction personnel as
Feb 18 President's Day Am
May 27 Memorial Day Am
Jul 04 Independence Day Am
Sep 02 Labor Day Am
Oct 14 Columbus Day Am
Nov 11 Veterans Day Am
Nov 28 Thanksgiving Day Am
Dec 25 Christmas Am needed to complete the services. The Contractor shall work closely with the COR, the Post
Facility Manager (FM) or the General Services Officer (GSO).
6.4 Standards of Conduct
6.4.1 General. The Contractor shall maintain satisfactory standards of employee competency, conduct, cleanliness, appearance, and integrity and shall be responsible for taking such disciplinary action with respect to employees as may be necessary. Each Contractor employee shall adhere to standards of conduct that reflect credit on themselves, their employer, and the
United States Government. The Government reserves the right to direct the Contractor to remove an employee from the worksite for failure to comply with the standards of conduct. The
Contractor shall immediately replace such an employee to maintain continuity of services at no additional cost to the Government.
6.4.3 Neglect of Duties. Neglect of duties is unacceptable. This includes sleeping while on duty, unreasonable delays or failures to carry out assigned tasks, conducting personal affairs during duty hours and refusing to render assistance or cooperate in upholding the integrity of the worksite security.
6.4.4 Disorderly Conduct. The Contractor shall not condone disorderly conduct, use of abusive or offensive language, quarreling, and intimidation by words, actions, or fighting. Also included is participation in disruptive activities that interfere with normal and efficient Government operations.
6.4.5 Intoxicants and Narcotics. The Contractor shall not allow its employees while on duty to possess, sell, consume, or be under the influence of intoxicants, drugs or substances which produce similar effects.
6.4.6 Criminal Actions. Contractor employees may be subject to criminal actions as allowed by law in certain circumstances. These circumstances include but are not limited to the following actions: falsification or unlawful concealment, removal, mutilation, or destruction of any official documents or records or concealment of material facts by willful omission from official documents or records; unauthorized use of Government property, theft, vandalism, or immoral conduct; unethical or improper use of official authority or credentials; security violations;
organizing or participating in gambling in any form; and misuse of weapons.
6.4.7 Key Control. The Contractor will not be issued any keys. The keys will be checked out by a “Cleared American” escort on the day of service requirements.
6.4.8 Notice to the Government of Labor Disputes. The Contractor shall inform the COR of any actual or potential labor dispute that is delaying or threatening to delay the timely performance of this contract.
7. SCHEDULED PREVENTIVE MAINTENANCE
7.1. General
7.1.1. The Contractor shall perform preventive maintenance as outlined in Exhibit A -
STATEMENT OF WORK. The objective of scheduled preventive maintenance is to eliminate system malfunction, breakdown and deterioration when units are activated/running.
7.1.2. The Contractor shall inventory, supply and replace expendable parts (eg, filters, belts, hoses, gaskets) that have become worn due to wear and tear. The Contractor shall maintain a supply of expendable and common parts on site so that these are readily available for normal maintenance to include: hoses, belts, oil, chemicals, coolant, filters (Air, Fuel, Oil), grease, sealant, thermostat, fuses; in addition to the appropriate tools, testing equipment, safety shoes and apparel for technicians, personal protective equipment (hands, hearing, eye protection), MSDS, cleaning material and oil spill containment kits. The contractor shall inventory the supply after each visit and order replacement supplies and have them delivered on site. Maintenance materials shall be unused and are to be industry standard and intended for the task to be performed. Parts shall be OEM approved. Refrigerants shall meet the AHRI Standard 700-2015 or most recent AHRI Standards.
7.1.3. Refrigerants, parts and maintenance materials delivered to the post are to be new and unused. Reclaimed refrigerants are not to be delivered to posts. Reclaimed refrigerants within post compounds are to be retained and stored and may be used if not contaminated. Refrigerants shall be stored in containers clearly indicating the refrigerant type.
7.1.4. Exclusion. This contract does NOT include repair of equipment and replacement of hardware (e.g. bearings, pistons, piston rings, crankshaft, gears.) Hardware replacements will be separately priced out by the Contractor for the Government’s approval and acceptance.
The Government has the option to accept or reject the Contractor’s quote for parts and reserves the right to obtain similar spare parts from other competitive sources. If required by the
Government, the Contractor shall utilize Government-purchased spare parts, if awarded the work. Such repairs/replacements will be accomplished by a separate purchase order. However, this exclusion does not apply if the repair is to correct damage caused by Contractor negligence.
7.1.5. Replacement/repair of any electronic or electrical parts shall be approved by the COR prior to installation of the part. If the Contractor proceeds to replace any electronic or electrical parts without COR approval, the Contractor shall de-install the parts at no cost to the
Government.
7.1.6. Stocking of recommended repair parts is at the discretion of the Facility Manager and is dependent upon the nearest location of the Equipment manufacturer, distributor or dealer. A recommended spare parts list shall be obtained by the contractor from the manufacturer or distributor and provided to the Facility Manager to procure.
7.1.7. Parts/materials/tools procurement and delivery for the CAA/PCC areas shall be at the discretion of the Regional Security Officer (RSO).
7.2 Checklist Approval
The Contractor shall submit to the COR a schedule and description of preventive maintenance tasks which the Contractor plans to perform. The Contractor shall prepare this schedule and task description in a checklist format for the COR’s approval prior to contract work commencement.
7.2.1. The Contractor shall provide trained technicians to perform the service at frequencies stated in Exhibit A and on the equipment called out in this SOW. The technician shall sign off on every item of the checklist and leave a copy of this signed checklist with the COR or the
COR's designate after each maintenance visit.
7.2.2. It is the responsibility of the Contractor to perform all manufacturers’ recommended preventive maintenance including preventive maintenance recommended by the manufacturers’ technical manuals for the respective equipment.
7.2.3 Additionally, the maintenance contractor shall obtain and keep at the post O&M binders provided by the manufacturers. These binders shall be placed in a location accessible to post personnel to review as needed.
8. PERSONNEL, TOOLS, CONSUMABLE MATERIALS AND SUPPLIES
The Contractor shall provide trained technicians with the appropriate tools and testing equipment for scheduled maintenance, safety inspection, and safety testing as required by this Contract.
The Contractor shall provide all of the necessary materials and supplies to maintain, service, inspect and test all the systems to be maintained.
8.1 Contractor furnished materials include but are not limited to appropriate tools, testing equipment, safety shoes and apparel for technicians, hands, hearing and eye protection, MSDS, cleaning material and oil spill containment kit. Expendable/consumable items (e.g. hoses, belts, oil, chemicals, coolant, filters (Air, Fuel, Oil), generator starting batteries, grease, sealant, thermostat, fuse), shall be maintained in the onsite inventory. See 7.1.2.
8.2 Repairs are not included in this contract. See 7.1.3. Exclusions.
8.3 Disposal of used oil, fuel, battery and other toxic substances. The Contractor is responsible for proper disposal of toxic/hazardous substances. All material shall be disposed of according to
Government and Local law. After proper disposal the contractor must show proof of authorized disposal of these toxic/hazardous substances.
9. SOFTWARE, LICENSES AND PASSWORDS
Copies of any and all software and licenses needed to control or to adjust the communications module shall be given to the post upon completion of the work.
10. DELIVERABLES
Provide a typewritten report to Post Facilities Manager containing following:
a) System information (make, model, all devices types)
b) Pass/Fail of each feature and type of component tested. If a device fails, note device type, address and location within Post
c) Any comments on system (or device) condition pertaining to service life and dependability.
d) Full printout of test from system printer
The Contractor shall provide a post-trip report in English or French (whenever possible) no later than fourteen (14) days after the service visit. Invoices shall not be reviewed or processed until the post-trip report has been received.
The following items shall be delivered under this contract:
Description QTY Delivery Date Deliver to
Names, biographic data, police clearance on Contractor personnel (#6.2)
1 30 days after contract award COR
Certificate of Insurance (#11.2) 1 30 days after contract award CO
PM Checklist signed by Contractor’s employee (#7.2.1)
1 After completion of each maintenance service
COR
Invoice (#15) 1 After completion of each maintenance service
COR
11. INSURANCE REQUIREMENTS
11.1 Personal Injury, Property Loss or Damage (Liability). The Contractor assumes absolute responsibility and liability for any and all personal injuries or death and property damage or losses suffered due to negligence of the Contractor’s personnel in the performance of this Contract
The Contractor’s assumption of absolute liability is independent of any insurance policies.
11.2 Insurance. The Contractor, at its own expense, shall provide and maintain during the entire period of performance of this Contract, whatever insurance is legally necessary. The Contractor shall carry the following minimum insurance:
Public Liability Insurance
Property damage: $ Cumulative: $
Workers’ Compensation and Employer’s Liability
11.3 Worker's Compensation Insurance. The Contractor agrees to provide all employees with worker's compensation benefits as required under local laws (see FAR 52.228-4 “Worker’s Compensation and War-Hazard Insurance Overseas”).
12. LOCAL LAW REGISTRATION
If the local law or decree requires that one or both parties to the contract register the contract with the designated authorities to insure compliance with this law or decree, the entire burden of this registration shall rest upon the Contractor. Any local or other taxes which may be assessed against the Contract shall be payable by the Contractor without Government reimbursement.
13. QUALITY ASSURANCE PLAN (QAP).
13.1 Plan. This plan is designed to provide an effective surveillance method to promote effective Contractor performance. The QAP provides a method for the Contracting Officer's
Representative (COR) to monitor Contractor performance, advise the Contractor of unsatisfactory performance, and notify the Contracting Officer of continued unsatisfactory performance. The Contractor, not the Government, is responsible for management and quality control to meet the terms of the Contract. The role of the Government is to conduct quality assurance to ensure that Contract standards are achieved.
Performance Objective SOW Para Performance Threshold
Services.
Performs all services set forth in the
Statement of Work (SOW)
1 thru 12 &
Exhibit A
All required services are performed and no more than one
(1) customer complaint is received per month
13.2 Surveillance. The COR will receive and document all complaints from Government personnel regarding the services provided. If appropriate, the COR will send the complaints to the Contractor for corrective action.
13.3 Standard. The performance standard is that the Government receives no more than one (1) customer complaint per month. The COR shall notify the Contracting Officer of the complaints so that the Contracting Officer may take appropriate action to enforce the inspection clause (FAR
52.212-4, Contract Terms and Conditions-Commercial Items), if any of the services exceed the standard.
13.4. Procedures.
13.4.1 If any Government personnel observe unacceptable services, either incomplete work or required services not being performed, they will immediately contact the COR.
13.4.2 The COR will complete appropriate documentation to record the complaint.
13.4.3 If the COR determines the complaint is invalid, the COR will advise the complainant.
The COR will retain the annotated copy of the written complaint for his/her files.
13.4.4 If the COR determines the complaint is valid, the COR will inform the Contractor and give the Contractor additional time to correct the defect, if additional time is available. The COR shall determine how much time is reasonable.
13.4.5 The COR shall, as a minimum, orally notify the Contractor of any valid complaints.
13.4.6 If the Contractor disagrees with the complaint after investigation of the site and challenges the validity of the complaint, the Contractor shall notify the COR. The COR will review the matter to determine the validity of the complaint.
13.4.7 The COR will consider complaints as resolved unless notified otherwise by the complainant.
13.4.8. Repeat customer complaints are not permitted for any services. If a repeat customer complaint is received for the same deficiency during the service period, the COR will contact the
Contracting Officer for appropriate action under the Inspection clause.
14. TRANSITIONS/CONTACTS
Within 30 days after contract award, the Contracting Officer may ask the contractor to develop a plan for preparing the contractor to assume all responsibilities for preventive maintenance services. The plan shall establish the projected period for completion of all clearances of contractor personnel, and the projected start date for performance of all services required under this contract. The plan shall assign priority to the selection of all supervisors to be used under the contract.
14.1 On site contact. The following are the designated contact personnel between the US
Embassy and the Contractor
COR
Jason Kuhn-Facility Manager
Kuhnjd@state.gov
The Post Control Officer (PCO) will be the contractor’s point of contact at the U.S. Embassy, Nouakchott. All questions concerning coordination of service activities while at post shall be directed to the Post Control Officer, with weekly reporting to the COR:
PCO
Koffi Komlagan -Post Control Officer (PCO)
Komlagank@state.gov
15. SUBMISSION OF INVOICES
The Contractor shall submit an invoice after each preventive maintenance service has been performed. Invoices must be accompanied by a signed copy of the Maintenance Checklist for the work performed including parts replacement and break down calls, if any. No invoice for preventive maintenance services will be considered for payment unless accompanied by the relevant documentation.
The Contractor should expect payment 30 days after completion of service or 30 days after receipt of invoice at the Embassy payment office, whichever is later. Invoices shall be sent to:
US Embassy Nouakchott
Route Nouadhibou – Carrefour Al Quds
Nouakchott, Mauritania mailto:Kuhnjd@state.gov
Exhibit A - - STATEMENT OF WORK
D3010 - Photovoltaic System
[NOTE: Notes are included throughout to help post make informed decisions on what is needed for post specific circumstances and help to understand the intent. Notes should be deleted from final version of Exhibit A Statement of Work]
[NOTE: Coordinate the requirements of Exhibit A with the base contract requirements, particularly those sections dealing with pricing, scheduled preventive maintenance, deliverables and quality]
I. GENERAL INFORMATION:
The United States Embassy in Nouakchott requires professional services and contractor cost proposals to perform preventive maintenance services of the facility’s photovoltaic systems.
II. PROJECT REQUIREMENTS:
The Contractor shall perform preventive maintenance as described in this STATEMENT OF WORK.
The objective of scheduled preventive maintenance is to eliminate system malfunction, breakdown and optimal photovoltaic system performance.
DESCRIPTION OF EQUIPMENT *:
2. Suniva OPT 270-Watt Mono Solar Panel
-270-WATT SUNIVA OPTIMUS SERIES
-(234) Photovoltaic Solar Panels NORTH Parking
-(447) Photovoltaic Solar Panels SOUTH Parking
3. SUNNY TRIPOWER 15000TL-US / 20000TL-US
SMA INVERTER SUNNY TRIPOWER 15000TL-US
-(1) 15.3KW DC INVERTER
SMA INVERTER SUNNY TRIPOWER 20000TL-US
_ (8) 20.4KW DC INVERTER
DISCONNECT COMBINER BOXES (SMA CONNETION)
_ (9) Total
DC FUSED DISCONNECTS 3P-60A
_ (18) Total
III. GENERAL REQUIREMENTS:
The contractor shall provide the labor and materials required to carry out all preventive maintenance as outlined in this SOW. Embassy staff have service manuals for photovoltaic system on-site. The contractor shall confirm on-site manuals are complete and current and provide the Contracting Officer’s
Representative (COR) a listing of any missing or out of date manuals. The following items should be in the service manual: plans, elevations, sections and mounting details; details of the equipment assemblies;
diagrams for power, signal and control wiring; utility connection and inverter type. The technician shall sign off on every task specified in the Statement of Work and will provide a typewritten copy of their report to the COR or the COR's designate within five business days of each maintenance visit.
IV. SCOPE OF WORK – PHOTOVOLTAIC SYSTEM OPERATIONS AND PREVENTIVE
MAINTENANCE
The contractor shall provide all materials, supervision, labor, tools, and equipment to perform preventive maintenance. All personnel working in the vicinity shall wear and /or use appropriate safety protection while work is performed. Any questions or injuries shall be brought to the attention of the Post COR and
Occupation Safety and Health Officer (POSHO). The Contractor will provide an SDS to the COR immediately upon delivery of each chemical to be used by Contractor personnel on-site. The
SDS copies will be provided to the COR for approval.
The systems and components to be maintained include Manufactured photovoltaic unit, Photovoltaic module framing, photovoltaic array construction, Inverters, system overcurrent protections, mounting structures, connection to utility, as well as control and monitoring systems. The attached equipment list provides details.
1. The contractor shall provide the COR with a list of necessary parts and materials.
2. Preventive maintenance parts shall be provided at the expense of the U.S. Govt.
a. Inverter that meet or exceed manufacturer’s specifications shall be used.
b. Fuses that meet or exceed manufacturer’s specifications shall be used.
c. Photovoltaic panels that meet or exceed manufacturer’s specifications shall be used
d. Conductors that meet or exceed manufacturer’s specifications shall be used
3. The contractor shall provide emergency assistance for photovoltaic failure, priced at an hourly rate, within 24 hours of being contacted by the COR.
4. The Government [will / will not] provide monitoring data to contractor so the failing part can be order and in his procession prior to responding. [NOTE: If Post has monitoring, they shall provide all data to the maintenance contractor]
If any discrepancies are found with the photovoltaic systems that are not covered under this scope of work, the contractor shall provide the following:
1. Detailed report noting the discrepancy found.
2. Bill of Materials (BOM) to include component name, quantity, part #, and price for any repair material required and material lead time.
3. Price quote for repair labor.
SAFETY & SPECIAL INSTRUCTIONS:
1. Use appropriate personal protective equipment (PPE) when performing work
2. Check all work areas, tools, and equipment to ensure unsafe conditions are eliminated or guarded against.
3. Follow site safety procedures.
4. Schedule maintenance with operating personnel and affected offices (security).
5. Follow approved lockout/tag out procedures.
6. Lockout and disconnect the main power and DC power connection before tightening the main supply lugs in order to avoid the hazard of electrical shock, which could result in serious personal injury or death.
7. Review and follow the manufacturer’s instructions.
8. Record results in the equipment history log.
9. Remove lockout/tag out in accordance with appropriate procedures.
10. Report all incidents and near miss incidents to COR and assist as requested in the investigation and corrective action.
At a minimum, the following work shall be completed:
Notes:
• Contractor shall submit to the COR for review, work sheet/checklist that will be used for performing maintenance service.
• A discrepancy report shall be submitted to the COR immediately upon discovery of any condition that could result in equipment failure or not preforming per design output and corrective measure to bring the system back to designed optimization.
• Performance test and output of the system shall be submitted to the COR within 30 days from date of service.
Maintenance Interval Schedule
[NOTES FOR POST:
• This is a basic generic list. Manufacturer’s recommendations should be followed and supersede recommendations in this list. Note: contractor should make confirm these before finalizing contract.
• The manufacturer’s maintenance schedules can be taken directly from equipment operations and maintenance manual and used in place of the list below.
• Before each consecutive interval is performed, all maintenance from the previous intervals must be performed.
• Photovoltaic module framing, photovoltaic array construction, Inverters, system overcurrent protections, mounting structures, connection to utility, as well as control and monitoring systems and are an essential component of the Diplomatic Facility’s Electrical Supply System.
• The contract does not replace the need for inspections. There may be items pertinent to the operation of the system which are not included in this SOW.]
The purpose of this Statement of Work is to ensure the entire photovoltaic systems for this facility are maintained according to manufacturer’s recommendations to ensure the readiness and proper operation of the system. All maintenance requirements are callout in IEC62446-12016 (Photovoltaic (PV) systems – requirement for testing, documentation and maintenance).
A. Annual Schedule
1. Conduct visual inspection of photovoltaic system.
• Check for evidence damage to photovoltaic panels.
• Inspect wiring harness for wear and damage.
• Inspect supports damage and stability.
• Inspect system for corrosion.
• Inspect inverters and replace if needed.
• Fuses – Inspect and adjust/replace if needed.
• Check photovoltaic system to ensure that vegetation is removed or controlled under and over photovoltaic.
2. Panel inspection and cleaning:
• Check each connection for voltage and current output
• Soiling and resulting cleaning regimen depend on local sources of dirt. (agricultural dust, construction dust, pollen, bird population, diesel soot, industrial sources, snow, sand and lack of rain). Area climate may result in a more often cleaning this will be determined by the monitoring system and the drop off of production of the overall system.
• Infrared all panels for hot spots on the panel which results in a panel failure
• Infrared all cable connections.
• Check disconnects for DC system.
• Test grounding on each panel it should be close to zero
• Two tests methods are possible (short circuit test or operational test) and both will provide information on the correct functions of the PV panels
3. DC disconnect cleaning and inspection
• Replace input filters on disconnection system
• Inspect fans for proper operations and damage
• Replace output filters on disconnection system.
• Test output DC system for quick release and break of connection
• Test GFCI system and insure that the system is protected space.
• Polarity of all DC cables shall be verified using suitable test apparatus
4. Inverters.
• Inverter preventive maintenance for each inverter per manufacturers operating guideline
• Clean inverter cabinet air vents
• Clean and change inverter air filter, if present, per manufacturer requirements
• Clean and remove dust from inverter heat sinks per manufacturer requirements
• Check torque marks and re-tightening appropriate wiring connection to design specification torque force per manufacture requirements.
• The potential for the system inverter to produce a DC back-feed into PV array circuits shall also be verified. It should also be verified that any back-feed current is lower than the module maximum fuse rating and the string cable ampere rating.
• There some mains to the inverter on the AC side that have to be isolated
• The inverter operational parameters operation as programmed and designed.
• All DC junction boxes (PV generator and PV array boxes) carry a warning label indicating that active parts inside of boxes are fed form the PV array and may still be energized after isolation from the PV inverter and public supply.
• Inverter type
▪ AC Module: no Dc test or inspection work required
▪ Micro inverter: testing of DC circuits is required; inspection of DC works is required.
▪ Module integrated electronics: Where possible a standard test regime to be followed, manufacturer to be consulted to determine any restrictions to tests, manufacturers to be consulted on pass/fail criteria for tests.
• Once polarity is confirmed, cables shall be checked to ensure they are correctly identified and correctly connected into system inverter.
Table 1 Equipment List:
Level 1 Level
Level 3 Space Name Element
Equipment
ID
Model
Serial
Number Manufacturer
Created
Date
In-
Service
Date
D
Services D30
D3010
Energy
Supply
UTL SWGR
RM U101
CNTLR, PV
SYSTEM 1
CNTLR, PV
SYSTEM 1
K0182
SMA CLUSTER
CONTROLLER
N/A
SMA SOLAR
TECHNOLOGY
6/30/2016 6/30/2017
D
Services D30
D3010
Energy
Supply
UTL SWGR
RM U101
PV
INVERTER
UTL-01
PV
INVERTER
UTL-01
K0184 STP20000TL-US-10 2E+08
SMA SOLAR
TECHNOLOGY
6/30/2016 6/30/2017
D
Services D30
D3010
Energy
Supply
UTL SWGR
RM U101
PV
INVERTER
UTL-02
PV
INVERTER
UTL-02
K1740 STP20000TL-US-10 2E+08
SMA SOLAR
TECHNOLOGY
6/30/2016 6/30/2017
D
Services D30
D3010
Energy
Supply
UTL SWGR
RM U101
PV
INVERTER
UTL-03
PV
INVERTER
UTL-03
K0183 STP20000TL-US-10 2E+08
SMA SOLAR
TECHNOLOGY
6/30/2016 6/30/2017
D
Services D30
D3010
Energy
Supply
SITE
NORTH
PKG
CANOPY
PV SUB
ARRAY N-
PKG-A
PV SUB
ARRAY N-
PKG-A
K3005 OPT275-60-4-100 N/A SUNIVA 6/30/2016 6/30/2017
D
Services D30
D3010
Energy
Supply
SITE
NORTH
PKG
CANOPY
PV SUB
ARRAY N-
PKG-B
PV SUB
ARRAY N-
PKG-B
K3006 OPT275-60-4-100 N/A SUNIVA 6/30/2016 6/30/2017
D
Services D30
D3010
Energy
Supply
SITE
NORTH
PKG
CANOPY
PV SUB
ARRAY N-
PKG-C
PV SUB
ARRAY N-
PKG-C
K3007 OPT275-60-4-100 N/A SUNIVA 6/30/2016 6/30/2017
D
Services D30
D3010
Energy
Supply
WHE
SOLAR
INV W205
CNTLR, PV
SYSTEM 2
CNTLR, PV
SYSTEM 2
K3009
SMA CLUSTER
CONTROLLER
N/A
SMA SOLAR
TECHNOLOGY
6/30/2016 6/30/2017
D
Services D30
D3010
Energy
Supply
NOB 1ST
FL FMS
COMPUTER,
PV SYS
COMPUTER,
PV SYS
K1739 PRECISION T1700 NSN DELL CORPORATION 6/30/2016 6/30/2017
D
Services D30
D3010
Energy
Supply
WHE
SOLAR
INV W205
PV
INVERTER
WHE-01
PV
INVERTER
WHE-01
K1741 STP20000TL-US-10 2E+08
SMA SOLAR
TECHNOLOGY
6/30/2016 6/30/2017
D
Services D30
D3010
Energy
Supply
WHE
SOLAR
INV W205
PV
INVERTER
WHE-02
PV
INVERTER
WHE-02
K1743 STP20000TL-US-10 2E+08
SMA SOLAR
TECHNOLOGY
6/30/2016 6/30/2017
D
Services D30
D3010
Energy
Supply
WHE
SOLAR
INV W205
PV
INVERTER
WHE-03
PV
INVERTER
WHE-03
K1745 STP20000TL-US-10 2E+08
SMA SOLAR
TECHNOLOGY
6/30/2016 6/30/2017
D
Services D30
D3010
Energy
Supply
WHE
SOLAR
INV W205
PV
INVERTER
WHE-04
PV
INVERTER
WHE-04
K1746 STP20000TL-US-10 2E+08
SMA SOLAR
TECHNOLOGY
6/30/2016 6/30/2017
D
Services D30
D3010
Energy
Supply
WHE
SOLAR
INV W205
PV
INVERTER
WHE-05
PV
INVERTER
WHE-05
K1747 STP20000TL-US-10 2E+08
SMA SOLAR
TECHNOLOGY
6/30/2016 6/30/2017
D
Services D30
D3010
Energy
Supply
WHE
SOLAR
INV W205
PV
INVERTER
WHE-06
PV
INVERTER
WHE-06
K1748 STP15000TL-US-10 2E+08
SMA SOLAR
TECHNOLOGY
6/30/2016 6/30/2017
D
Services D30
D3010
Energy
Supply
SITE
SOUTH
PKG
CANOPY
PV SUB
ARRAY S-
PKG-A
PV SUB
ARRAY S-
PKG-A
K3004 OPT275-60-4-100 N/A SUNIVA 6/30/2016 6/30/2017
D
Services D30
D3010
Energy
Supply
SITE
SOUTH
PKG
CANOPY
PV SUB
ARRAY S-
PKG-B
PV SUB
ARRAY S-
PKG-B
K3003 OPT275-60-4-100 N/A SUNIVA 6/30/2016 6/30/2017
D
Services D30
D3010
Energy
Supply
SITE
SOUTH
PKG
CANOPY
PV SUB
ARRAY S-
PKG-C
PV SUB
ARRAY S-
PKG-C
K3002 OPT275-60-4-100 N/A SUNIVA 6/30/2016 6/30/2017
D
Services D30
D3010
Energy
Supply
SITE
SOUTH
PKG
CANOPY
PV SUB
ARRAY S-
PKG-D
PV SUB
ARRAY S-
PKG-D
K3001 OPT275-60-4-100 N/A SUNIVA 6/30/2016 6/30/2017
D
Services D30
D3010
Energy
Supply
SITE
SOUTH
PKG
CANOPY
PV SUB
ARRAY S-
PKG-E
PV SUB
ARRAY S-
PKG-E
K3000 OPT275-60-4-100 N/A SUNIVA 6/30/2016 6/30/2017
D
Services D30
D3010
Energy
Supply
SITE
SOUTH
PKG
CANOPY
PV SUB
ARRAY S-
PKG-F1
PV SUB
ARRAY S-
PKG-F1
K1750 OPT275-60-4-100 N/A SUNIVA 6/30/2016 6/30/2017
D
Services D30
D3010
Energy
Supply
SITE
SOUTH
PKG
CANOPY
PV SUB
ARRAY S-
PKG-F2
PV SUB
ARRAY S-
PKG-F2
K3008 OPT275-60-4-100 N/A SUNIVA 6/30/2016 6/30/2017
END OF STATEMENT OF WORK