11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NUMBER IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

16C. DATE SIGNED

Previous edition unusable STANDARD FORM 30 (REV. 11/2016) Prescribed by GSA FAR (48 CFR) 53.243

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE PAGE OF PAGES

2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)

6. ISSUED BY CODE 7. ADMINISTERED BY (If other than Item 6) CODE

8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X) 9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NUMBE

10B. DATED (SEE ITEM 13)

CODE FACILITY CODE

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

Section C - Description/Specifications/Statement of Work

Miscellaneous text in this section has been modified to:

PERFORMANCE WORK STATEMENT (PWS)

NAVAL OCEANOGRAPHIC OFFICE

(NAVOCEANO)

OCEAN FLOOR MAPPING WITH LONG-ENDURANCE UNMANNED SYSTEMS

June 3, 2026

1.0 BACKGROUND:

The Naval Oceanographic Office (NAVOCEANO) collects, processes, and databases a wide variety of high resolution, ocean floor mapping data.

While a primary purpose is to support Safety of Navigation (SoN) for Fleet operations, the data are also utilized in a variety of other products that provide improved situation awareness for the Fleet.

The US Navy has a need globally for additional ocean floor mapping data in many ocean regions but does not possess the capacity to collect this information in a timely manner using the current portfolio of survey platforms. This request aims to enhance mission effectiveness by shifting tasks traditionally performed by government-owned, manned platforms, to obtain services that incorporate contractor-owned long-endurance Unmanned Surface Vehicles (USV).

2.0 OBJECTIVE:

The objective is to enhance operational efficiency and personnel safety by employing a Contractor-provided autonomous maritime solution for hydrographic data collection. The Contractor shall use a USV, equipped with a multibeam sonar system to gather and manage a minimum of 2000 linear nautical miles of International Hydrographic Organization (IHO) Order 1a compliant survey data per month. This data must be protected with end-to-end encryption. The system must also provide a remote interface over the Non-classified Internet Protocol Router Network (NIPRNET) for real-time monitoring and interaction by NAVOCEANO Subject Matter Experts (SMEs)

3.0 SCOPE:

The Contractor shall provide a comprehensive, contractor-owned, contractor-operated, government augmented (COCOGA) service using long-endurance USV to perform high-resolution ocean floor mapping. The primary goal is to increase the volume of quality hydrographic information in diverse and remote maritime environments, reduce operational risk to personnel, and enhance overall mission effectiveness. The contractor must have current capability and experience to conduct long-endurance USV survey operations in all mission profiles described in section 3.1:

3.1 Mission profiles

3.1.1 Bathymetric Survey (200m to full ocean depth)

3.1.2 Seamount Survey (vessel draft to ~4000m)

3.2 Operating Model: Contractor Owned, Contractor Operated, Government Augmented

N0018926RL0210001

(COCOGA)

3.2.1 The contractor provides all equipment required for the execution of mission requirements.

3.2.2 The contractor provides preventative and emergent maintenance for all equipment required for the execution of mission requirements.

3.2.3 The contractor is responsible for all coordination associated with survey operations.

3.2.4 The contractor is responsible for planning and executing all logistical, regulatory, and operational coordination required for the successful completion of survey operations. These responsibilities include, but are not limited to:

3.2.4.1 Arranging for all port services, pier support, customs, and resupply.

3.2.4.2 Ensuring compliance with all applicable international maritime law, flag state regulations, and local authorities.

3.2.4.3 Deconflicting survey plans with other maritime traffic.

3.2.4.4 Serving as the primary liaison with all third-party entities necessary to conduct survey operations.

3.2.5 The contractor is responsible for all safe mobilization, integration, mission planning and daily operations.

3.2.6 The contractor is responsible for processing the resultant data to meet mission requirements and delivering said data in a timely manner.

3.2.7 Government Augmented tasks may include government participation during planning and execution phases.

3.2.8 Government Augmented tasks may include government performing all data processing.

3.2.9 The specific roles and responsibilities, including the extent of Government augmentation for any given mission, will be defined and mutually agreed upon during the Preliminary Mission Review (PMR) and documented in the Plan of Action (POA).

The briefing materials for this review shall be delivered in accordance with CDRL A003.

4.0 PERIOD OF PERFORMANCE:

The period of performance associated with this PWS shall be for a 24-month ordering period.

5.0 PLACE OF PERFORMANCE:

5.1 Geographic Location (OPAREA)

The primary Operational Area (OPAREA) encompasses the international waters of the Indian Ocean and Pacific Ocean Basins, well beyond U.S.

territorial boundaries. Operations may occur across diverse maritime environments, ranging from high-latitude regions to equatorial waters. The Contractor must ensure all deployed assets are configured to operate in the varying sea states, thermal gradients, and atmospheric conditions characteristic of these oceanic basins. Specific mission locations will be identified by the Government at the Task Order level.

5.2 Remote Service Delivery

While physical data collection occurs at sea, the performance of the service (mission management, piloting, and data delivery) is conducted remotely.

The Government shall access all mission outputs via a secure online platform provided by the Contractor, maintaining near-real-time capability for mission monitoring and data transmission throughout the performance period.

5.3 Areas of Interest (AOI) & Duration

For each task mission, the Government will designate specific Areas of Interest (AOIs), estimated to encompass approximately 100 nm. The specific geographic coordinates and Mission Start Dates will be mutually agreed upon under separate cover. The performance period for each individual survey task mission is estimated to be no less than 25 days.

6.0 TASKS REQUIREMENTS:

The Contractor shall provide the Naval Oceanographic Office (NAVOCEANO) with collection of high quality, accurate, and timely data by use of USVs to support various functions, provide greater agility, effectiveness, and efficiency in meeting the demands of fast-changing and complex environments. The Contractor shall provide NAVOCEANO proof of the ability to collect within the parameters of the effort referenced herein. The Contractor is responsible for providing all means to fulfill this requirement.

6.1 Survey Administration:

6.1.1 The Contractor shall only provide NAVOCEANO access to comprehensive data repository that includes real-time and historical maritime data collected by USVs during period of performance.

6.1.1.1 Government supplied information and the information developed under this performance work statement will be Unclassified.

6.1.1.2 All information, products delivered, or services performed may not be disclosed by any means unless stated in this document. The Contractor shall protect the information with administrative controls and protect from public or other unauthorized disclosure. This includes protection from unauthorized disclosure in compliance with all applicable executive orders, statutes, and regulations.

6.1.2 To ensure compliance, all data collection methods and survey planning will be consistent with accepted commercial hydrographic surveying practices. Furthermore, the collection of bathymetric data is required to meet the specific criteria for Order 1a (uncertainty, feature search, and coverage) as outlined in IHO Special Publication 44, Edition 6.2.0.

6.1.3 Data collection methods and survey plan shall be provided to NAVOCEANO Subject Matter Expert (SME) at Preliminary Mission Review (PMR). Contractor shall provide planned procedures to minimize positional errors. COR will document agreed upon Plan of Action (POA) and provide to all parties within 5 business days of meeting.

6.1.4 Contractor shall provide a Report of Survey (ROS) generated at the completion of the mission survey. The Report of Survey shall be delivered in accordance with CDRL A005. The ROS shall include basic information on deliverables, including the following: survey dates, asset identifiers, equipment models and identifiers, datum information, system configuration, offset, and calibration / patch test information, linear nautical miles (LNM), and of transit, and all other relevant metadata.

6.1.6 The Contractor shall prepare the USV with the necessary sensors to perform the designated mission profile collection within 60 days after task order award and prove successfully tested capability prior to their survey start date as assigned by the SME at kickoff survey planning meeting.

6.1.7 The Contractor shall provide a Vessel Test and Configuration Report including geometric survey of sensor offsets, collection and, when applicable, processing of angular offsets, and equipment manufacturer, model, and serial number information within 72 Hours after testing completion for every survey operation. The Vessel Test & Configuration Report shall be delivered in accordance with CDRL A008.

6.1.8 The Contractor shall provide its own supporting shore facilities, office space, pier support and supporting vessels necessary for its own operations and include all associated costs in the total task order price.

6.2 Survey Data Collection:

6.2.1 The vessel shall be capable of safely conducting deep ocean surveys for a minimum duration of 25 consecutive days, excluding any necessary transit time required. The data must be evaluated near real time (NRT) to ensure accuracy and relevance. The configuration of specific survey hardware aboard the USV shall be reviewed and approved by NAVOCEANO during pre-testing period following contract award and before survey execution. This is initially documented within operational plan during PMR. Any changes to the initial operational plan shall be communicated to the Contracting Officer and COR immediately and documented in Vessel Test and Configuration Report. No changes to the task order shall be made without prior authorization from the Contracting Officer. The Vessel Test & Configuration Report shall be delivered in accordance with CDRL A008.

6.2.2 The collection system shall consist of integrated hull mounted multibeam sonar system , defined as a deep-water multibeam echosounder capable of achieving IHO Order 1a bathymetric uncertainty standards across the full specified depth range (per Section 3.1)., vessel position and attitude system, global satellite-based augmentation system (GSBAS) capable of providing real-time horizontal and vertical accuracies at sub-decimeter level, sea surface sound speed sensor co-located near the face of the multibeam transducer, as well as supporting oceanographic sensors to map sound velocity profile at depth. The collection system shall be operational such that resultant bathymetric depth uncertainties are compliant with IHO Order 1a standards.

6.2.3 Bathymetric coverage density shall support the generation of Bathymetric Attributed Grids (BAG). At least 95% of all grid nodes must be able to populate at a min. 5 valid soundings.

6.2.4 The contractor shall take immediate action to correct any surveyequipment issues. When immediate correction cannot be achieved, the contractor shall promptly notify the Government and submit a remedy plan within one business day.

6.2.5 Vessel capability should be in compliance with Coast Guard regulations for Unmanned Vessels underway.

6.2.6 Contractor should identify and document interference sources to optimize best practical data collection as per established requirements.

6.2.7 Under any business structure if a vessel requires emergency service, the Government will not incur additional charges for the associated downtime. This includes scenarios such as transit to port, service days in port, and transit days back to the operational area (OPAREA). The Contractor shall provide a remedy plan to the Government immediately to ensure the situation does not result in mission delay.

6.2.8 In the event of unforeseen weather conditions or uncontrollable incidents, the Contractor may be granted an extension of survey days at no additional cost to the Government, provided the Contractor submits written notification the Contracting Officer (CO) and the COR within one business day. The CO will issue a written response to both Contractor and COR indicating whether the extension is granted.

6.3 Data Quality:

The Contractor's performance will be measured by their ability to deliver a minimum of 2000 linear nautical miles of IHO compliant bathymetric data per month that has been verified by the Government. This metric confirms that the monthly mileage target is met with high-quality data collection and applies to all data gathered throughout the entire mission profile. This plan shall be delivered in accordance with CDRL A006.

6.3.1 The Contractor shall implement quality control measures to ensure data integrity by meeting the specified IHO collection standards. The Contractor shall submit a Quality Control Plan to the NAVOCEANO Mission Team for approval no later than 30 days after task order award and when change occurs. This plan shall be delivered in accordance with

CDRL A001.

6.3.1.1 The Contractor shall utilize standard processes based on industry best practices wherever applicable

6.3.1.2 The Contractor shall provide services in a format that is compatible with NAVOCEANO survey requirements as specified in Section 6.1 through 6.3.

6.4 Timeliness:

The Contractor shall ensure that system remains in compliance and available to NAVOCEANO within specified timeframes of the Deliverables Schedule.

6.5 Customer Support:

The Contractor shall provide responsive and knowledgeable customer support to address any issues or questions related to data access and usage. The Contractor shall offer customer support to assist with secure online platform, data access, and usage 24 hours a day/7-days a week. The online platform must be consistently maintained and deliver high reliability, with minimal downtime in line with commercial-grade standards.

6.6 Project Management:

The Contractor shall assign a Project Manager (PM) to act as the single primary interface with NAVOCEANO SME. The PM specifically has the responsibility of engaging with NAVOCEANO on all matters pertaining to this Performance Work Statement (PWS) for Survey Administration efforts as described above. The Contractor shall designate this person and an alternate in writing to the contracting officer and NAVOCEANO Mission Team within 10 days of contract execution. The Project manager or alternate shall have full authority to act for the Contractor on all contract matters relating to daily operation of this contract. In the event of a change, NAVOCEANO Mission Team should be notified within 48 hours.

6.7 Task Order Management (Task Order Awardee Only):

6.7.1 The Contractor shall provide a Point of Contact (POC) who shall be responsible for invoices, quarterly review meetings, and any administrative actions in regard to the contract. The Contractor shall designate this person and an alternate in writing to the contracting officer within 10 days of task order execution. Acting as a single point of contact for the Government, the POC or alternate shall have full authority to act for the Contractor on all contract matters relating to daily administration of this contract.

6.7.2 The Contractor shall sponsor Quarterly Project Review (QPR) to monitor task order performance and discuss any issues that the Contractor and/or NAVOCEANO are experiencing with the project referenced herein with the NAVOCEANO Mission Team. The briefing materials for this review shall be delivered in accordance with CDRL A004.

NAVOCEANO will schedule this review; submit a suggested agenda to the Contractor who shall be responsible for all briefing slides and materials.

6.7.3 The Contractor shall support other NAVOCEANO briefings and meetings as applicable by providing feedback and documentation/numbers/metrics concerning any efforts. NAVOCEANO will provide written request in a timely manner if this occurs.

6.8 Data Security (Unclassified)

6.8.1 The Contractor shall ensure the proper functionality of the solution by providing all necessary software, including any third-party dependencies required for operation during PMR.

6.8.2 Contractor must ensure all included software is compatible with existing systems. The Software Inventory Document shall be delivered in accordance with CDRL A008.

6.8.3 The Contractor shall safeguard data at rest and data in transit by implementing appropriate controls to reduce risk of unauthorized access.

6.8.4 The Contractor's information systems utilized to receive, process, store, or transmit Controlled Unclassified Information (CUI) under this contract shall achieve and maintain a Cybersecurity Maturity Model Certification (CMMC) Level 2 (Third-Party Assessed). The Contractor shall deliver its comprehensive CMMC Level 2 compliance evidence package and certification tracking documentation in accordance with CDRL A002.

6.9 Base Level Data Types and Format Constraints

The service must be capable of delivering the following data types in the specified formats:

6.9.1 Raw Sensor Data:

6.9.1.1 Multibeam Bathymetry (seafloor backscatter and water column backscatter) in its raw sensor format (e.g., Kongsberg .kmall or equivalent).

6.9.1.2 Sub-bottom profile data in its raw sensor format

6.9.1.3 Ancillary sensor data (sound speed, GNSS observables, motion/attitude) in its raw format.

6.9.2 Processed Data and Products

6.9.2.1 A complete CARIS Project folder containing all processed data, cleaning logs, and supporting files.

6.9.2.2 Final hydrographic surfaces, delivered as both Bathymetric Attributed Grids (BAG) and CARIS Surface (CSAR) files.

6.9.2.3 Sub-bottom profile data in Society of Exploration Geophysicists Y (SEGY) data format

6.9.2.4 Logs and Metadata:

6.9.2.4.1 Report of Survey (ROS) in PDF format.

6.9.2.4.2 Daily collection and watchstander logs.

6.9.2.4.3 Sound Velocity Profile (SVP) data logs.

6.9.2.4.4 Vessel configuration report detailing sensor offsets and equipment.

6.9.2.4.5 A summary file detailing the count of all multibeam files collected.

6.9.3 Data Repository Updates:

The Contractor shall maintain and update the data repository regularly to ensure accuracy, relevance, and integrity of stored information.

6.10 Cyber Incident Reporting:

Upon discovery of a cyber incident involving any data collection, the performer shall take immediate steps to mitigate any further loss or compromise. The performer shall notify NAVOCEANO immediately. The performer shall preserve and protect images of all known affected information systems and all relevant monitoring/packet capture data for at least 90 days from reporting the cyber incident to enable NAVOCEANO to assess the cyber incident. The performer agrees to rapidly implement security measures as recommended by NAVOCEANO and to provide to NAVOCEANO any additionally requested information to help the Parties resolve the cyber incident and to prevent future cyber incidents.

6.11 Software Inventory & Documentation (Task Order Awardee Only):

The Contractor shall deliver a comprehensive Software Inventory Document (or Software Bill of Materials) detailing all software and third-party components integrated into the final data deliverables and data processing solutions provided to the Government.

This requirement is strictly limited to the data delivery and processing architecture and does not apply to the internal operating software, firmware, or proprietary command-and-control systems utilized by the Unmanned Surface Vehicle (USV) during autonomous operations. The Software Inventory Document shall be delivered in accordance with CDRL A008.

6.11.1 Update & Reporting Requirements:

The Contractor shall update the Software Inventory Document upon request and provide periodic reports in the following instances:

Major software upgrades.

Identification of a software issue.

Occurrence of an incident affecting software integrity.

6.11.2 Security & Compliance:

If the software is subject to cybersecurity or regulatory standards, the Contractor shall provide documentation verifying compliance, including security patching and vulnerability management measures.

7.0 PERSONNEL QUALIFICATIONS:

7.1 All Contractor personnel conducting work associated with this effort shall have, at a minimum, the combination of education and experience required to qualify for the Office of Personnel Management (OPM) General Schedule Qualifications Standard, is a study in physical science, engineering, or mathematics that included 24 semester hours in physical science and/or related engineering science such as mechanics, dynamics, properties of materials, and electronics; or, a combination of education and experience equivalent to one of the majors forementioned that included at least 24 semester hours in physical science and/or related engineering science, plus appropriate experience or additional education.

7.2 All Contractor personnel associated with this contract shall be U.S. citizens and must possess, or be able to obtain, a valid Department of Defense (DoD) Common Access Card (CAC) requiring a baseline Public Trust fitness determination.

8.0 SECURITY REQUIREMENT:

The overall classification of this contract is Unclassified. Contractor does not require access to classification information in the performance of this contract. All contract personnel shall comply with the directives and policies established in 2 CFR Part 117 "National Industrial Security Program Operating Manual", DoD Instruction 5200.48 (Controlled Unclassified Information) and SECNAVINST 5510.36B "Department of the Navy (DoN) Information Security Program." The Contractor does not require access to U.S. Government Information Technology (IT) systems.

The scope of the contract will be limited to Unclassified.

All information, products delivered, or services performed may not be disclosed by any means without prior approval of the authorized SME /TCOR. All collected data within the specified areas are restricted to Department of Defense and U.S DOD Contractors only identified to this contract.

Contractor shall protect DoD sensitive unclassified data regardless of the location or ownership of the transport media, including, but not limited to Contractor owned/leased mobile computing devices and removable storage media. Contractor shall comply with all current information assurance and information security policies, procedures, and statutes applicable to DoD information technology, including the July 3, 2007 DoD CIO Policy Memorandum on Encryption of Sensitive Unclassified Data at Rest on Mobile Computing Devices and Removable Storage Media.

The Contractor shall mark the data, products, reports, and transfer media properly.

9.0 POST AWARD CONFERENCE REQUIREMENT: (Task Order Awardees)

9.1 A NAVOCEANO survey planning Kickoff Meeting will be held by the NAVOCEANO Mission Team within two weeks of contract award. Contractor representatives are required to attend this meeting to discuss, identify, and document survey logistics and planning. Participation from the NAVOCEANO Mission Team, including the Contract Officer Representative (COR) and/or Technical Point of Contact (TPOC), is required for survey planning and data collection for each Area of Interest (AOI). The Contractor shall be available for all necessary meetings and teleconferences to address production and technical issues, coordinated with the

NAVOCEANO Mission Team. NAVOCEANO Subject Matter Experts (SMEs) will also be available for teleconferences to discuss production and technical issues and will provide guidance and coordination during platform deployment as needed.

9.1.1 The Contractor must provide all required training, certifications, and proof of Public Trust Eligibility / Common Access Card (CAC) Vetting Approval to NAVOCEANO prior to Kickoff Meeting.

9.1.2 Data Storage Infrastructure documentation with technical details and physical locations shall be provided by Contractor within 15 days of task order execution and 15 days prior to any change occurrence.

9.2 The Contractor shall host a Preliminary Mission Review (PMR) no later than 15 days prior to initiation of a respective mission, so as to troubleshoot and mitigate risk, ensuring the probability that a respective mission will result in operational success.

The Contractor shall assess the feasibility of surveying in the Operating Area (OPAREA) and present those findings and/or recommendations during the PMR. The documents and briefing materials for this review shall be delivered in accordance with

CDRL A003.

9.3 The Contractor shall attend any post award conference convened by the contracting activity. The contracting officer and the Contracting Officers Representative (COR) may meet periodically with the Contractor to review the Contractor's performance. At these meetings, the contracting officer will apprise the Contractor of how the Government views the Contractor's performance and the Contractor will apprise the Government of problems experiencing, if any. The Government or the Contractor, as applicable, shall take appropriate action to resolve outstanding issues. These meetings shall be at no additional cost to the Government.

10.0 TRAVEL:

All meetings will be conducted virtually with NAVOCEANO personnel. Government-funded travel is not authorized under this contract.

11.0 DATA DELIVERABLES : Provided per mission, submitted with the Report of Survey (ROS).This shall be delivered in accordance with CDRL A007.

11.1 Survey Data Deliverables:

11.1.1 Multibeam sonar in raw proprietary sensor formats, to include bathymetry, seafloor backscatter and water column backscatter

11.1.2 Sub-Bottom Profile data in raw sensor format

11.1.3 Oceanographic profile data in raw sensor format

11.1.4 Global Navigation Satellite System (GNSS) data in raw format

11.1.5 Vessel motion / attitude data in raw proprietary format

11.1.6 Collection / watchstander logs

11.1.7 Report of Survey (includes mission impacts from equipment maintenance, weather or any other outside influence, how they calculated uncertainty, vessel offsets, calibration data, etc...)

11.2 Processed Data Deliverables

11.2.1 Processed multibeam data (bathymetry, seafloor backscatter and water column backscatter)

11.2.2 Sub-bottom profile data in SEGY data format

11.2.3 Oceanographic profile data in processed format

11.2.4 GNSS data in *.rnx (RINEX Format)

11.2.5 Final Production Surface (Grid) in a *.CSAR and *.BAG processed format

11.2.6 Data Processing Logs

11.2.7 Detailed list of production software utilized, to include software versions.

12.0 GOVERNMENT FURNISHED EQUIPMENT (GFE) AND GOVERNMENT PROVIDED FACILITIES:

12.1 No GFE will be provided by NAVOCEANO under this contract. Government furnished resources provided at time of task order include the following:

12.1.1 Survey planning resources

12.1.2 Survey technical specifications

12.1.3 Survey documentation templates

12.1.4 Designated NAVOCEANO Mission Team to provide requirement familiarization and to participate in project efforts as REMOTE Mission system operator during Government Augmented operations

12.1.5 Identification of NAVOCEANO SME, TPOC, and COR.

13.0 PRIVACY ACT COMPLIANCE

Contractor may be in contact with data subject to the Privacy Act (Title 5 of the U.S. Code, Section 552.a).

Reports and data will be identified and safeguarded accordingly. Agency procedures shall be followed. The Contractor shall ensure that Contractor employees assigned to this task are briefed annually on properly identifying and handling privacy act data/information.

14.0 DATA RIGHTS AND OWNERSHIP

14.1 Government Rights: The U.S. Government (NAVOCEANO) shall have Unlimited Rights to all data collected, generated, or processed under this service. This includes, but is not limited to, raw sensor data, intermediate processed data, final data products, and all associated metadata.

14.2 Prohibition on Release: The contractor is strictly prohibited from releasing, sharing, publishing, or otherwise distributing any data acquired or generated during this service to any third party. All data is for the exclusive use of NAVOCEANO.

14.3 The Government intends to retain unlimited rights to all custom software, scripts, documentation, and data products specifically produced or generated for the Government under this PWS to deliver the required data deliverables. The Government's unlimited rights do not extend to the Contractor's pre-existing, proprietary Unmanned Surface Vehicle (USV) operating software, firmware, or commercial off-the-shelf (COTS) applications.

15.0 GENERAL/ADMINISTRATIVE MATTERS:

15.1 Identification Requirement:

All Contractor personnel performing under this statement of work shall identify themselves as a Contractor employee to avoid creating any impression that they are Government officials. Such identification shall be made in all meetings attended, when answering Government telephones, in all e-mails, and when working in other situations where their Contractor status is not obvious to third parties. They must also ensure that all documents or reports produced by Contractors are suitably marked as Contractor products or that Contractor participation is appropriately disclosed.

15.2 Statement of Non-Personal Service:

The Contractor employees performing services under this contract will be controlled, directed, and supervised at all times by management personnel of the Contractor. Contractor management shall ensure that employees properly comply with the performance work standards outlined in the PWS.

Contractor employees shall perform their duties independently, under the supervision of, an appointed Government official. The tasks, duties, and responsibilities set forth in this contract shall not be interpreted or implemented in any manner that results in Contractor employees creating or modifying Federal policy, obligating the appropriated funds of the United States Government, overseeing the work of Federal employees, providing direct personal services to

Federal employees, or otherwise violating the prohibitions set forth in Parts 7.5 and 37.1 of the

Federal Acquisition Regulation (FAR) The Government shall control access to thehttps://www.acquisition.gov/browse/index/far.

facilities and shall perform the inspection and acceptance of completed work.

16.0 Service Contract Reporting (SCR) (NMCARS 5237.102-90)

Services Contract Reporting (SCR) requirements apply to this contract. The contractor shall report required SCR data fields using the SCR section of the System for Award Management (SAM) at following web address: https://sam.gov/SAM/.

https://www.acquisition.gov/browse/index/far https://www.acquisition.gov/browse/index/far https://www.acquisition.gov/browse/index/far https://sam.gov/SAM/ https://sam.gov/SAM/

Section I - Contract Clauses

Additional Information/Notes

The following clauses were added:

DFARS Clauses Incorporated by Full Text

252.204-7021 Contractor Compliance with the Cybersecurity Maturity Model Certification Level Requirements.

(Nov 2025)

CONTRACTOR COMPLIANCE WITH THE CYBERSECURITY MATURITY MODEL CERTIFICATION LEVEL REQUIREMENTS (NOV 2025)

(a) . As used in this clause- Definitions

"Controlled unclassified information" means information the Government creates or possesses, or information an entity creates or possesses for or on behalf of the Government, that a law, regulation, or Governmentwide policy requires or permits an agency to handle using safeguarding or dissemination controls (32 CFR 2002.4(h)).

"Current" means-

(1) With regard to Conditional Cybersecurity Maturity Model Certification (CMMC) Status-

(i) Not older than 180 days for Conditional Level 2 (Self) assessments and Conditional Level 2 (certified third-party assessment organization (C3PAO)) assessments, with-

(A) No changes in compliance with the requirements at 32 CFR part 170 since the Conditional CMMC Status date (see 32 CFR

170.16 and 170.17); and

(B) A corresponding affirmation of continuous compliance by an affirming official (see 32 CFR 170.4); and

(ii) Not older than 180 days for Conditional Level 3 (Defense Industrial Base Cybersecurity Assessment Center (DIBCAC)) assessments, with-

(A) No changes in compliance with the requirements at 32 CFR part 170 since the Conditional CMMC Status date (see 32 CFR 170.18); and

(B) A corresponding affirmation of continuous compliance by an affirming official;

(2) With regard to Final CMMC Status-

(i) Not older than 1 year for Final Level 1 (Self), with-

(A) No changes in compliance with the requirements at 32 CFR part 170 since the Final CMMC Status date (see 32 CFR 170.15); and

(B) A corresponding affirmation of continuous compliance, not older than 1 year, by an affirming official;

(ii) Not older than 3 years for Final Level 2 (Self) assessments and Final Level 2 (C3PAO) assessments, with-

(A) No changes in compliance with the requirements at 32 CFR part 170 since the Final CMMC Status date (see 32 CFR 170.16 and 170.17); and

(B) A corresponding affirmation of continuous compliance, not older than 1 year, by an affirming official; and

(iii) Not older than 3 years for Final Level 3 (DIBCAC) assessments, with-

(A) No changes in compliance with the requirements at 32 CFR part 170 since the Final CMMC Status date (see 32 CFR 170.18); and

(B) A corresponding affirmation of continuous compliance, not older than 1 year, by an affirming official; and

(3) With regard to affirmation of continuous compliance (32 CFR 170.22), not older than 1 year with no changes in compliance with the requirements at 32 CFR part 170.

"Cybersecurity Maturity Model Certification (CMMC) status" means the result of meeting or exceeding the minimum required score for the corresponding assessment. The potential statuses are as follows:

(1) Final Level 1 (Self).

(2) Conditional Level 2 (Self).

(3) Final Level 2 (Self).

(4) Conditional Level 2 (C3PAO).

(5) Final Level 2 (C3PAO).

(6) Conditional Level 3 (DIBCAC).

(7) Final Level 3 (DIBCAC).

"Cybersecurity Maturity Model Certification unique identifier (CMMC UID)" means 10 alpha-numeric characters assigned to each CMMC assessment and reflected in the Supplier Performance Risk System (SPRS) for each contractor information system.

"Federal contract information (FCI)" means information, not intended for public release, that is provided by or generated for the Government under a contract to develop or deliver a product or service to the Government. It does not include information provided by the Government to the public, such as on public websites, or simple transactional information, such as information necessary to process payments.

"Plan of action and milestones" means a document that identifies tasks to be accomplished. It details resources required to accomplish the elements of the plan, any milestones in meeting the tasks, and scheduled completion dates for the milestones, as defined in National Institute of Standards and Technology Special Publication 800-115 (32 CFR 170.21).

(b) . The Cybersecurity Maturity Model Certification (CMMC) is a framework for assessing a contractor's compliance with Framework applicable information security protections (see 32 CFR part 170).

(c) . The CMMC assessments will not duplicate efforts from any other comparable DoD assessment, except for rare circumstances Duplication when a reassessment may be necessary, for example, when there are indications of issues with cybersecurity and/or compliance with CMMC requirements.

(d) . The Contractor shall- Requirements

(1)(i) Have and maintain for the duration of the contract a current CMMC status at the following CMMC level, or higher: ____ for all information Contracting Officer insert: CMMC Level 1 (Self); CMMC Level 2 (Self); CMMC Level 2 (C3PAO); or CMMC Level 3 (DIBCAC) systems used in performance of the contract, task order, or delivery order that process, store, or transmit FCI or CUI; and

(ii) Consult 32 CFR 170.23 related to the flowdown of the CMMC requirements, and flow down the correct CMMC level to subcontracts and other contractual instruments;

(2) Only process, store, or transmit FCI or CUI on contractor information systems that have a CMMC status at the CMMC level required in paragraph (d)(1) of this clause, or higher;

(3) Complete on an annual basis, and maintain as current, an affirmation, by the affirming official (see 32 CFR 170.4), of continuous compliance with the requirements associated with the CMMC level required in paragraph (d)(1) of this clause in the Supplier Performance Risk System (SPRS) ( ) for each CMMC UID applicable to each of the contractor information systems that process, store, or transmit FCI https://piee.eb.mil or CUI and that are used in performance of the contract;

(4) Ensure all subcontractors and suppliers complete prior to subcontract award, and maintain on an annual basis, an affirmation, by the affirming official (see 32 CFR 170.4), of continuous compliance with the requirements associated with the CMMC level required for the subcontract or other contractual instrument for each of the subcontractor information systems that process, store, or transmit FCI or CUI and that are used in performance of the subcontract; and

(5) If the Contractor has a CMMC Status of Conditional, successfully close out a valid plan of action and milestones (32 CFR 170.21) to achieve a CMMC Status of Final.

(e) . The Contractor shall- Reporting

(1) Submit to the Contracting Officer-

(i) The CMMC UID(s) issued by SPRS for contractor information systems that will process, store, or transmit FCI or CUI during performance of the contract; and

(ii) Any changes in the CMMC UIDs generated in SPRS throughout the life of the contract, task order, or delivery order, if applicable;

(2) Enter into SPRS the results of a current self-assessment for each CMMC UID, not covered by a C3PAO assessment or DIBCAC assessment, applicable to each of the contractor information systems that process, store, or transmit FCI or CUI and that are used in performance of the contract; and

(3) Complete in SPRS on an annual basis and maintain as current an affirmation of continuous compliance by the affirming official (see 32 CFR 170.4) for each self-assessment, C3PAO assessment, or DIBCAC assessment required under the contract in SPRS.

(f) . The Contractor shall- Subcontracts

(1) Insert the substance of this clause, including this paragraph (f) and excluding paragraph (e)(1), in subcontracts and other contractual instruments, including those for the acquisition of commercial products or commercial services, excluding commercially available off-the-shelf items, if the subcontract or other contractual instrument will contain a requirement to process, store, or transmit FCI or CUI; and

(2) Prior to awarding a subcontract or other contractual instrument, ensure that the subcontractor has a current CMMC certificate or current CMMC status at the CMMC level that is appropriate for the information that is being flowed down to the subcontractor based on the requirements at 32 CFR 170.23.

(End of clause)

Section L - Instructions, Conditions, & Notices to Offerors or Quoters

Miscellaneous text in this section has been modified to:

Solicitation Addendum to FAR 52.212-1

In addition to FAR 52.212-1, "Instructions to Offerors - Commercial Products and Commercial Services," and any other instructions contained elsewhere in this solicitation, the following information is provided. Offerors are required to meet all solicitation requirements, including all terms and conditions of the RFP, representation and certifications, and technical requirements, in addition to those identified as evaluation factors. Failure to meet a requirement may result in a proposal being ineligible for award. Offerors shall clearly identify any exceptions to the solicitation terms and conditions and provide complete accompanying rationale.

The Government intends to award a Firm-Fixed-Price (FFP), multiple-award Indefinite Delivery, Indefinite Quantity (IDIQ) contract as a result of this solicitation in accordance with FAR Part 12, Part 15 and Subpart 16.5. Awards will be made to offerors whose proposals are determined technically acceptable and qualified under the selection criteria set forth in this solicitation. To be determined a qualifying offeror, the offeror must meet the technical capability evaluation and meet the responsibility requirements of FAR 9.104. The Government intends to evaluate proposals and award a contract based on initial proposals. Therefore, the offeror's initial proposal should contain the offeror's best terms from a technical and past performance standpoint. The Government intends to award without discussions.

QUESTIONS:

Offerors may submit questions regarding clarification of the solicitation requirements directly to the Contract Specialist and Contracting Officer at borui.z.tang.civ@us.navy.mil and joseph.p.caltagirone3.civ@us.navy.mil, respectively. It is requested that all questions be received no later than 10:00 AM, as time may not permit responses to 5 June 2026 questions received after that date to be prepared and issued prior to the receipt of proposals.

INSTRUCTIONS FOR SUBMISSIONS OF PROPOSALS:

mailto:borui.z.tang.civ@us.navy.mil mailto:joseph.p.caltagirone3.civ@us.navy.mil

(1) Proposals shall be submitted to Borui Tang and Joseph Caltagirone electronically no later than the due date of the solicitation via e-mail borui.z.tang.civ@us.navy.mil and joseph.p.caltagirone3.civ@us.navy.mil. Offerors shall comply with the detailed instructions for the format and content of the proposals contained herein; proposals that do not comply may be considered unacceptable and may render the proposal ineligible for award.

Offerors are strongly encouraged to confirm their proposal was received PRIOR to the closing date and time. It is the responsibility of the offerors to ensure that the Contracting Office has received their entire proposal, with all attachments, PRIOR to the solicitation closing date and time. Only the documents received prior to the solicitation closing date and time will be evaluated.

Offerors should include the following information in the Subject Line of their electronic submission

Proposal - N0018926RL021 - (Name of Offeror) - Email (#) of (#)

(2) All submissions and attachments shall be in Microsoft Office Word or PDF. Submissions are page limited to the maximum number of pages as defined below. These page limitations are inclusive of the executive summary and any charts, diagrams, and/or other graphics. Graphics (including tables) in the proposal may use Times New Roman font with 8-point size type or larger. Each "page" is defined as one sheet, 8 1/2 " x 11", with at least one inch margins on all sides, using Times New Roman font with a point size of 12 or greater. Lines shall, at a minimum, be selected as single-spaced in Microsoft Word with Microsoft Word Normal character spacing. Pages shall be consecutively numbered. The offeror is permitted to submit no more than one page for each of the following, which will not be included in the page count: a cover sheet, list of tables, list of figures, list of acronyms, compliance matrix, and table of contents.

Pages submitted in excess of the page limitations described within will not be evaluated.

GENERAL:

mailto:joseph.p.caltagirone3.civ@us.navy.mil

Proposals shall include the following legend on each page:

Source Selection Information - FAR 2.101 and FAR 3.104

PROPOSAL CONTENT:

The proposal should contain the following items in addition to other information required by this solicitation:

The cover page should indicate the following:

- Title of the proposal

- Proposal Category (Factor)

- Request for Proposal Number

- Name and Address of Offeror, CAGE Code, SAM Unique Entity ID, and applicable Tax I.D. Number (TIN)

- Point of Contact name, telephone number, and email address

- Proposal valid for 180 days after solicitation closing

The proposal shall also include completed solicitation documents and additional supporting documentation described below:

- A complete and signed SF1449 (Solicitation/Contract/Order for Commercial Products and Commercial Services) and executed copy of Amendments, if applicable, completed by the offeror;

- Unless completed in the System for Award Management, the offeror shall complete the solicitation's representations, certifications and other statements of offerors.

*** This submission is not page limited, but is strictly limited to the solicitation documentation***

The Non-price Proposals shall be prepared in two (2) separate factors :

- Factor I: Technical Approach

- Factor II: Past Performance

Table of Contents: The table of contents should provide sufficient detail as to allow the important elements to be easily located.

(3) Requirements for Style: Each offeror shall submit a proposal that clearly and concisely describes and defines the contractor's response to the requirements contained in the RFP. Unnecessary elaboration or other presentations beyond that sufficient to present a complete and effective proposal are not desired and may be construed as an indication of the offeror's lack of understanding of technical consciousness. The proposal shall contain all the pertinent information in sufficient detail in the one area of the proposal where it contributes most critically to the discussion of the same information. When necessary, the offeror shall refer to the initial discussion and identify its location within the submitted proposal.

(4) Proposal Page Limitations

Title Page Limit*

Factor I: Technical Approach 10 Pages

Factor II: Past Performance 12 Pages

Pages submitted in excess of the page limitations described above will not be evaluated.

* Page limits represent the maximum pages the Government will evaluate and are not construed as de facto standards for the amount of material expected in the proposal.

Factor I - Technical Approach

The offeror shall submit a technical proposal that demonstrates a comprehensive understanding of, and the capability to provide the required services identified in the Performance Work Statement (PWS).

To be considered for award, the Offeror must explicitly demonstrate compliance with the following core seven (7) requirements:

The Offeror must demonstrate its specific capabilities to manage and deploy unmanned ocean survey vehicles. This must include a description of the offeror's owned or leased fleet, technical support infrastructure, and the specific autonomy or sensor suites used to meet the Performance Work Statement (PWS).

The Offeror must demonstrate that its Unmanned Surface Vehicle (USV) is capable of safely conducting deep ocean surveys for a minimum duration of 25 days. The narrative must show that the vehicle is configured to operate in the varying sea states, thermal gradients, and atmospheric conditions characteristic of these oceanic basins.

The Offeror must demonstrate it can provide a full Contractor-Owned, Contractor-Operated (COCOGA) service model. The narrative must confirm that the contractor provides all equipment required for the mission.