This is a StormTrap Installation Guide providing general guidelines for the installation of StormTrap stormwater management systems, which are modular precast concrete structures designed for retention, detention, infiltration, and rainwater harvesting applications. The guide covers the installation of two primary system configurations: SingleTrap (internal heights ranging from 1'-1" to 5'-8") and DoubleTrap (internal heights ranging from 2'-2" to 11'-4"), both constructed of reinforced, high-strength precast concrete with HS-20 loading capacity and minimum 6" cover. The systems can be installed on stone aggregate bases to facilitate infiltration or on concrete pads or footings for contained applications. Installation standards reference ASTM C891-90, and all specifications on engineer-approved drawings take precedence over this guide. The guide emphasizes that the installing contractor is responsible for full compliance with project-specific installation specifications and that engineer drawings take precedence over StormTrap drawings in case of discrepancies.

The installation guide details the equipment, site preparation, foundation types, delivery logistics, lifting procedures, and backfill requirements necessary for proper system installation. Key installation steps include establishing the specified foundation, applying joint tape and wrap, placing modules according to approved shipping layouts, connecting pipes and manholes, and completing backfill operations with compaction to 95% standard proctor density. Perimeter backfill should use clean, crushed, angular aggregate (AASHTO M43 No. 5), while material placed over the system must not exceed 120 pcf density. The guide emphasizes the importance of a preconstruction meeting with StormTrap prior to delivery to coordinate shipping sequences, installation procedures, and site logistics. All modules must be handled using cast-in lifting anchors and approved lifting clutches, with exterior joints sealed using 8" wide self-adhering joint wrap. The document includes installation examples for SingleTrap systems on concrete pad foundations and stone foundations, as well as DoubleTrap systems on stone foundations.

View the file

Other files

File Type Posted
A - Project Drawings_Notice.pdf PDF
B-Specifications.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STORMTRAP

INSTALLATION

GUIDE

This guide shall serve as a general guideline for the installation of the StormTrap® system. Each project is unique and may require additional considerations by the installing contractor. All specifications on the approved shop drawings and project drawings shall take precedence over this guide. The installing contractor is responsible for full compliance with project installation specifications.

The StormTrap system is available in two configurations to provide conventional retention, detention, infiltration to groundwater, rainwater harvesting or treatment solutions. The SingleTrap and the DoubleTrap systems provide design solutions to meet volume requirements.

This guide refers to the installation of the SingleTrap and DoubleTrap systems.

Designed to exceed HS-20 loading with minimum of 6’’ cover.

Made of reinforced, high-strength precast concrete available in internal heights that range from 1’-1’’ to 5’-8”.

Placement on a stone base allows for large infiltrative surface area for water to discharge back into the soil. Projects not conducive to infiltration can be placed on a concrete pad.

Designed to exceed HS-20 loading with minimum of 6’’ cover.

Made of reinforced, high-strength precast concrete available in internal heights that range from 2’-2’’ to 11’-4’’.

A flexible design that can allow for stormwater infiltration or remain a completely contained system.

Facilitates quick installation and the smallest overall footprint.

SINGLETRAP® DOUBLETRAP®

June, 2018

INSTALLATION STANDARDS

1. StormTrap shall be installed in accordance with ATSM C891-90, standard practice for installation of underground precast concrete utility structures.

2. Specifications on the engineer’s drawings shall take precedence. If a discrepancy arises between the engineer drawings and StormTrap drawings, contact StormTrap immediately for clarification.

INSTALLATION GUIDE

MODULE DETAILS

1. StormTrap modules are customizable from 1’-1” to 11’-4” in height. Modules are either 8’-5” wide by 15’-4” long (i.e., Type I or II) or 6’-7.5” wide by 15’-4” long (i.e., Type III or IV) with the exception of “special” pieces which are shortened in length.

2. There are a number of different StormTrap modules available and their use and placement will depend on design requirements and site layout. The approved StormTrap drawings will show the layout of the units along with their designated unit types.

3. All unit heights and weights will be shown on the approved StormTrap drawings or shipping layout drawings.

4. Some modules will contain openings to allow for inlet or outlet pipes and maintenance access points. These inlets and outlets may be placed at varying inverts and positions around the perimeter of the structure. StormTrap will work with the project engineer and contractor to determine the best location for these openings to accommodate incoming and outgoing pipes, inlets, and access points.

5. Depending on the overall size, each StormTrap system is designed with either 2’ or 3’ diameter openings throughout the system in the roof at specified locations.

1. StormTrap modules shall be installed according to shop drawings approved by the installing contractor and project engineer. The shop drawings shall indicate size and location of roof openings, weir walls, and inlet/outlet pipe openings as well as specific required sub-base and backfill requirements.

2. StormTrap will provide a set of approval drawings for the contractor to confirm pipe locations and sizes prior to production.

DESIGN (APPROVAL DRAWINGS)

INSTALLATION GUIDE

DESIGN (APPROVAL DRAWINGS) 1

The following is representative of the StormTrap approval drawings.

MODULE DETAILS - STANDARD TYPES 2

MODULE DETAILS - STANDARD TYPES

1. Establish the specified foundation found on StormTrap drawing;

2. Apply joint tape (when applicable - SingleTrap on pad/footing or DoubleTrap systems);

3. Place modules according to agreed upon shipping/installation layout (as determined in preconstruction meeting);

4. Apply joint wrap to vertical joints and top of the system in both directions;

5. Connect pipes/manholes when applicable;

6. Backfill.

It is the responsibility of the installing contractor to ensure that the equipment used to set/install the system is adequate. StormTrap will provide the necessary information regarding weight and size of the pieces in order for the contractor to make an informed decision. It is the contractor’s responsibility to ensure any/all machines used on/around the StormTrap system shall not exceed the max allowable design loading (refer to backfill procedure for appropriate use of machines overtop of the system).

The following list of equipment is suggested for a safe and efficient installation:

- Tape measure

- Chalk line/masonry string

- Stanley knife

- Broom

- Swivel for chains

- Concrete rake

- 20# Propane tank with weed burner (winter installs)

- Four lifting clutches (supplied by StormTrap)

- Joint tape and joint wrap (supplied by StormTrap)

SITE PREPARATIONS

In addition to the overall system dimensions, the sub-base of the system will extend beyond the dimensions of the StormTrap system. Refer to the approved StormTrap drawings for sub-base requirements and system dimensions.

Consideration should also be taken to allow space to apply the joint wrap properly to the exterior vertical joints of the system. As well as any specified waterproofing or geoweb material as directed by StormTrap drawings, engineer of record, or others.

INSTALLATION GUIDE

INSTALLATION STANDARDS 3

Installation in 6 steps

Excavation

Construction Equipment Requirements

- A can of marking spray

- Pinch/crowbar

- Level – 4’

- Two ladder

- Safety harness for working at height

- Total station

- Four-way chains or cables (not to exceed 6’ to 8’ when using an excavator)

FOUNDATION TYPES

Aggregate (Stone)

1. StormTrap modules shall be placed on a bed of clean, crushed, angular stone as detailed in the approved drawings. Both the aggregate and geogrid (if required) shall be installed within a minimum

2’-0” overhang beyond the limits of the StormTrap system (refer to StormTrap approval drawings for depth of subgrade and specifications).

2. For systems requiring infiltration, refer to the civil engineer’s drawings for specifications pertaining to the subgrade.

3. Sub-base preparation can vary from project to project. See approved StormTrap drawings for requirements.

4. Refer to the approved StormTrap drawings for the required minimum soil pressure. Soil strengths to be verified in the field by others.

5. Systems utilizing a stone base must be protected from all traffic until the final grade is completed over the system. Check the approved drawings for allowable loads.

6. Geoweb with concrete “splash pads” shall be installed at all pipe penetrations of a SingleTrap system to prevent undermining of stone (see StormTrap drawings for specifications).

Concrete Pad

1. StormTrap modules shall be placed on a level smooth or broomed finished concrete pad (as shown in the approved StormTrap drawings) with a 1’-0” overhang on all sides that shall be poured in place by the installing contractor.

2. Unless otherwise specified, the concrete pad shall have a minimum compressive strength of 4,000 psi

(refer to approval drawings).

3. The perimeter horizontal joint of the StormTrap modules shall be sealed to the foundation with preformed mastic joint sealer according to ASTM C891-90, 8.8 and 8.12.

4. Refer to the approved StormTrap drawings for specific requirements regarding subgrade preparation.

Concrete Footing

1. StormTrap modules shall be placed on a level concrete footing (as shown in the approved StormTrap drawings) with the specified overhang on all sides that shall be poured in place by the installing contractor.

2. Unless otherwise specified, the concrete footing shall have a minimum compressive strength of 4,000 psi (refer to approval drawings).

3. The perimeter horizontal joint of the StormTrap modules shall be sealed to the foundation with preformed mastic joint sealer according to ASTM C891-90, 8.8 and 8.12.

STORMTRAP SYSTEMS ON DIFFERENT FOUNDATIONS

SINGLETRAP 5’-8’’ SYSTEM ON STONE BASE

SINGLETRAP 5’-8’’ SYSTEM ON CONCRETE PAD

DOUBLETRAP 11’-4’’ SYSTEM ON STONE BASE

DELIVERY

Preconstruction Meeting

Prior to delivery, the installing contractor is responsible for arranging a preconstruction meeting with

StormTrap. It is recommended that all involved parties participate in the meeting. It is also recommended that the preconstruction meeting is completed prior to preparation of the sub-base. Any installation questions/ concerns, as well as shipping logistics/sequencing should be discussed and determined at this time.

The shipping plan/drawing will help to alleviate the double handling of modules; saving time and effort, making for more efficient use of the crane/excavator, and reducing site congestion. The shipping plan/ drawing will be coordinated with StormTrap and approved by the contractor prior to commencing the delivery of modules to site.

StormTrap will coordinate the delivery with the installing contractor and determine the number of trucks requested by the customer. Delivery does not have to be consecutive days, however; loads need to be complete and fully loaded and coincide with the design parameters pertaining to the total number of loads quoted for the project.

Each unit will be appropriately labeled with a unit type as designated on the StormTrap drawings. Example:

Type 1, 2, 3, 4, etc.

The most efficient installation typically is to sequence the order of delivery with the order in which the pieces are being installed. Pieces picked right off the truck and placed directly into place is typically the most efficient installation.

Instances may occur where a unit may be out of sequence to avoid partial loads.

A StormTrap representative can be available on-site to help coordinate the delivery of the units and answer questions. It is the installing contractor’s responsibility to ensure the system has been installed according to the specifications for the project.

SAMPLE SHIPPING LAYOUT FOR DOUBLETRAP SAMPLE SHIPPING LAYOUT FOR SINGLETRAP

DELIVERY

Lifting and Inspection

Before removing any units from the delivery truck, the contractor is responsible for inspecting and verifying that the units have arrived in an undamaged state. Once the product has been removed from the mode of transport, any damage/defects will be the responsibility of the installing contractor.

All the precast units are supplied with cast-in lifting anchors to enable safe handling. To prevent stress and possible concrete cracking, all units must be handled using the cast-in lifting anchors and associated lifting clutches. Installers should use approved lifting equipment only. It is the installing contractor’s responsibility to ensure the lifting clutches, and 4-way cables are available on site. The lifting points of anchors are clearly shown on the StormTrap drawings.

Wherever possible, all modular components should be lifted from the delivery truck and set directly onto the prepared foundation. In most applications, each module will take approximately 5-10 minutes to unload and set into position. Times could vary depending on methods of installation (i.e., crane vs. excavator) and site restraints.

If temporary storage of the modules is required on site, they should be placed carefully on level, even ground, free of rocks and uniformly supported across the entire leg surface by using dunnage/ timbers.

Modules should not be stacked on top of each other unless otherwise approved by StormTrap.

BACKFILL PROCEDURE

After the system is installed, backfill should be placed around the StormTrap units, deposited on both sides at the same time and to approximately the same elevation. At no time shall the fill behind one sidewall be more than 2’-0” higher than the fill on the opposite side. Backfill shall be compacted to 95% standard proctor density or otherwise specified by the engineer. Care shall be taken to prevent any wedging action against the structure, and all slopes bounding or within the area to be backfilled must be stepped or serrated to prevent wedge action. Care shall also be taken as not to disrupt the joint wrap from the joint during the backfill process. Recommended perimeter backfill material shall be clean, crushed, angular No. 5 (AASHTO

M43) aggregate (3/4 inch angular stone).

Backfill material overtop of the StormTrap system can consist of a variety of materials including, but not limited to, stone or soil. The backfill material placed overtop of the StormTrap system shall not exceed a 120 pcf material density.

Compaction – when compaction is completed overtop the StormTrap system; vibratory action shall be disengaged at all times. Equipment above the system shall not exceed the loading requirements shown in the approved StormTrap drawings.

After the required minimum amount of cover is placed overtop of the system, the standard designed loads can be utilized over the system.

EXAMPLE 1 - SINGLETRAP ON CONCRETE PAD FOUNDATION

INSTALLATION EXAMPLES4

1. Sweep the concrete slab/footings clean of dirt and debris. (For a concrete pad only)

2. Begin placement of joint tape on slab approximately 2.5” inside the perimeter line marking. (For a concrete pad only)

3. Secure the first module utilizing the four lifting anchors precast into the units. Take care not to strike the modules together when unloading and lowering them. Be aware of pinch hazard at all times and do not walk or work under suspended loads.

4. When lowering the first module into position, pause 2” above the concrete slab, and then gradually lower it into position once it is aligned with the perimeter markings.

Ensure the unit is square and the bottom of the module is on the foundation before lifters are removed.

5. Align the next module with the edge markings and position it adjacent to the previously installed unit. Be sure to minimize the gap to no more than 3/4” between units. Use a pinch or crowbar to assist with the finer adjustment of the modules.

At no point shall dragging or pushing of the modules be a permitted method of adjusting the modules to a finer tolerance. If the space exceeds 3/4”, the modules shall be reset with appropriate adjustment made to line and grade to bring the space into specification.

EXAMPLE 1 - SINGLETRAP ON CONCRETE PAD FOUNDATION

6. Continue to install the modules in the order shown on the shipping plan as agreed upon in the pre-construction meeting.

Note: During the installation, check the overall dimensions of the system periodically to make sure the system is being installed within the constraints of the design. Adjust the laying gap when necessary to recover any discrepancies.

7. All exterior joints between adjacent StormTrap modules shall be sealed with 8” wide self-adhering joint wrap provided by StormTrap.

The exterior joint wrap shall be installed according to the following installation instructions: Broom the outside surface at the point where the joint wrap is to be applied.

A release paper protects the adhesive side of the joint wrap. Place the adhesive wrap

(adhesive side down) around the structure, removing the release paper as you go.

Press the joint wrap firmly against the

StormTrap module surface when applying.

8. End panels will be used to cap off ends of units with rebar 6’ bars.

EXAMPLE 2 - SINGLETRAP ON STONE FOUNDATION

1. Ensure minimum soil bearing pressure is met, then prepare sub-base as specified in

StormTrap approved drawings. Grade and level elevation as specified per engineer drawings.

2. The concrete splash pad and geoweb shall be installed prior to installation of the StormTrap modules. Geoweb infill material shall be 3/4” aggregate.

Concrete splash pad shall be installed within the geoweb and is required at all pipe entry locations.

Geoweb edge shall be installed 1’ beyond the outer perimeter of the StormTrap system. The geoweb longitudinal dimension (25’) shall be installed parallel to the StormTrap legs. The concrete splash pad and geoweb shall be centered at the pipe penetration. Refer to splash pad layout for concrete splash pad dimensions.

3. Secure the first module utilizing the four lifting anchors precast into the units. Take care not to strike the modules together when you are unloading and lowering them. Be aware of pinch hazard at all times and do not walk or work under suspended loads.

4. When lowering the first module into position, pause 2” above the stone base, and then gradually lower it into position once it is aligned with the perimeter markings. Ensure the unit is square and the bottom of the module is on the foundation before lifters are removed.

5. Align the next module with the edge markings and position it adjacent to the previously installed unit. Be sure to minimize the gap to no more than 3/4” between units. Use a pinch or crowbar to assist with the finer adjustment of the modules.

EXAMPLE 2 - SINGLETRAP ON STONE FOUNDATION

. At no point shall dragging or pushing of the modules be a permitted method of adjusting the modules to a finer tolerance. If the space exceeds 3/4”, the modules shall be reset with appropriate adjustment made to line and grade to bring the space into specification.

6. Continue to install the modules in the order shown on the shipping plan as agreed upon in the pre-construction meeting.

Note: During the installation, check the overall dimensions of the system periodically to make sure the system is being installed within the constraints of the design. Adjust the laying gap when necessary to recover any discrepancies.

7. All exterior joints between adjacent

StormTrap modules shall be sealed with

8” wide self-adhering joint wrap provided by StormTrap. The exterior joint wrap shall be installed according to the following installation instructions: Broom the outside surface at the point where the joint wrap is to be applied. A release paper protects the adhesive side of the joint wrap.

Place the adhesive wrap (adhesive side down) around the structure, removing the release paper as you go. Press the joint wrap firmly against the StormTrap module surface when applying.

8. End panels will be used to cap off ends of units with rebar 6’ bars.

EXAMPLE 3 - DOUBLETRAP ON STONE FOUNDATION

1. Grade and level elevation per engineer drawings.

2. Secure the first module utilizing the four lifting anchors precast into the units. Take care not to strike the modules together when you are unloading and lowering them. Be aware of pinch hazard at all times and do not walk or work under suspended loads.

3. When lowering the first module into position, pause 2” above the stone base, and then gradually lower it into position once it is aligned with the perimeter markings. Ensure the unit is square and the bottom of the module is on the foundation before lifters are removed.

4. Align the next module with the edge markings and position it adjacent to the previously installed unit. Be sure to minimize the gap to no more than 3/4” between units.

Use a pinch or crowbar to assist with the finer adjustment of the modules. At no point shall dragging or pushing of the modules be a permitted method of adjusting the modules to a finer tolerance. If the space exceeds 3/4”, the modules shall be reset with appropriate adjustment made to line and grade to bring the space into specification.

5. Continue to install the modules in the order shown on the shipping plan as agreed upon in the pre-construction meeting.

Note: During the installation, check the overall dimensions of the system periodically to make sure the system is being installed within the constraints of the design. Adjust the laying gap when necessary to recover any discrepancies.

EXAMPLE 3 - DOUBLETRAP ON STONE FOUNDATION

DoubleTrap

6. All exterior joints between adjacent

StormTrap modules shall be sealed with 8” wide self-adhering joint wrap provided by StormTrap. The exterior joint wrap shall be installed according to the following installation instructions:

Broom the outside surface at the point where the joint wrap is to be applied. A release paper protects the adhesive side of the joint wrap.

Place the adhesive wrap (adhesive side down) around the structure, removing the release paper as you go. Press the joint wrap firmly against the StormTrap module surface when applying.

7. End panels will be used to cap off ends of units with rebar 6’ bars.

SingleTrap

Stormwater Detention VCBMP System Northwestern University

Stormwater Treatment System - Sand Filter US Bank Stadium

Stormwater Infiltration System CVS Pharmacy

Rainwater Havesting System Wescott Park

PHONE877 867 6872
WEBstormtrap.com

Play Play Play Play

WATCH TIME-LAPSE VIDEOS OF STORMTRAP INSTALLATIONS