About this file

This is a Special Notice and Performance Work Statement for a sole-source procurement by the Department of Veterans Affairs for preventive maintenance and repair services on Spectrum Dynamics D-SPECT cardiac imaging equipment at the Michael E. Debakey Medical Center in Houston, Texas.

The VA intends to issue a firm-fixed-price sole-source contract to Spectrum Dynamics Medical Americas, LLC (301 N. Cattlemen Rd., Suite 109, Sarasota, FL 34232) under 41 U.S.C. 253(c)(1) and FAR 6.302-1, citing the vendor as the only responsible source capable of meeting requirements due to unique equipment characteristics. Interested parties may submit capabilities statements by September 8, 2026, at 3:00 PM CST to tiffany.burks@va.gov to demonstrate their ability to provide the required services. The solicitation number is 36C25627Q0011, with the contracting office located at the VA Network Contracting Office, Galleria Financial Center, 5075 Westheimer Road Suite 750, Jackson, MS 39216. All interested parties must be registered in SAM and meet OEM certification requirements for field service engineers.

The contractor shall provide comprehensive maintenance services including all parts, travel, labor, onsite technical support (8:00 AM–9:00 PM Monday–Friday CST excluding federal holidays), quarterly preventive maintenance, full CZT detector module coverage, remote diagnosis and repair, software updates, clinical support, and NIST-traceable calibration. Response time requirements are 30 minutes by phone and 4 hours for onsite response to emergency calls. The contractor must employ OEM-certified field service engineers with minimum two years of experience and shall maintain General Liability and Property Damage Liability insurance of at least $500,000 per occurrence. All replacement parts must be new OEM items; gray market and remanufactured parts are prohibited. The contractor accepts equipment in "as is" condition and is responsible for all travel costs. Service documentation must be submitted within five days of service completion, including detailed Engineering Service Reports signed by both the service technician and authorized VA personnel. The contract does not include costs for damage from fire, accident, vandalism, water, natural disasters, building deficiencies, or power supply fluctuations, nor does it cover service resulting from untrained operator use or failure to operate per specifications.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Special Notice

36C25627Q0011 Special Notice

SUBJECT* Sole Source Spectrum Dynamics Preventive Maintenance & Repair

GENERAL INFORMATION

CONTRACTING OFFICE’S ZIP CODE* 77056

SOLICITATION NUMBER* 36C25627Q0011

RESPONSE DATE/TIME/ZONE 09-08-2026 3pm CENTRAL TIME, CHICAGO, USA

ARCHIVE 7 DAYS AFTER THE RESPONSE DATE

RECOVERY ACT FUNDS N

PRODUCT SERVICE CODE* J065

NAICS CODE* 334517

CONTRACTING OFFICE ADDRESS Department of Veterans Affairs Network Contracting Office Galleria Financial Center 5075 Westheimer Road Suite 750 Jackson MS 39216

POINT OF CONTACT*

Contract Specialist Tiffany Burks tiffany.burks@va.gov 601-362-4471 x56338

ADDITIONAL INFORMATION

AGENCY’S URL https://www.va.gov

URL DESCRIPTION Department of Veterans Affairs

AGENCY CONTACT’S EMAIL ADDRESS tiffany.burks@va.gov

EMAIL DESCRIPTION Special Notice - 36C25626Q0645

Special Notice

36C25627Q0011 Special Notice

DESCRIPTION

NOTICE OF INTENT TO SOLE SOURCE

The Department of Veterans Affairs (VA), Veterans Health Administration, Network Contracting Office (NCO) 16, Houston, Texas 77056, intends to issue a sole-source contract under the authority of 41 U.S.C. 253(c)(1), FAR 6.302-1 (Only One Responsible Source and No Other Supplies or Services Will Satisfy Agency Requirements) to Spectrum Dynamics Medical Americas, LLC, located at 301 N. Cattlemen Rd., Suite 109, Sarasota, FL 34232.

The vendor shall provide all parts and services necessary to repair and provide preventive maintenance Spectrum Dynamics D-SPECT, under NAICS 334517.

This Notice of Intent is not a request for quotations. Due to the unique characteristics required for this repair service, Spectrum Dynamics is the only responsible source capable of meeting the Government’s requirements.

Interested parties may express their interest by submitting a capabilities statement no later than September 8, 2026, at 3:00 PM CST to tiffany.burks@va.gov. When responding, please include “Notice of Intent – “SPECTRUM DYNAMICS” in the email subject line. The capabilities statement must provide clear and unambiguous evidence demonstrating the capability to provide the required services.

Responding as an interested party on www.beta.sam.gov does not constitute adequate or convincing evidence of capabilities. A determination not to compete this requirement based on responses to this notice is solely at the discretion of the Government. Verbal and facsimile responses will not be accepted. All interested parties must be registered in the System for Award Management (SAM) at https://sam.gov/SAM/ to be eligible for any Government contract award. No telephone inquiries will be accepted.

If no viable responses are received by the deadline, NCO 16 intends to proceed with negotiating solely with Spectrum Dynamics, LLC.

The Government anticipates awarding a firm-fixed-price contract. Information received will be used solely to determine whether to conduct a competitive procurement.

End of Document

GENERAL REQUIREMENT

Michael E. Debakey Medical Center is requesting for a contractor to provide preventative maintenance and service on the Spectrum Dynamics D-SPECT Cardiac Systems at the Michael E. Debakey Medical Center located at 2002 Holcombe Blvd, Houston, TX 77030. The services will include but is not limited to:

All parts, travel and labor costs needed for repairs of the equipment Onsite technical support and technical phone support from 8:00am-9:00pm Monday- Friday CST (excluding holidays) and discounted labor at all other times.

Quarterly preventative maintenance checks following the manufacturers guidelines.

Full coverage on CZT detectors modules.

Remote diagnosis and repair if applicable Latest software and patching updates Clinical and Applications Phone support Calibration to NIST traceable calibration standards

The full clinic listing of the equipment can be found in the Equipment Identification Section. The Contractor shall services by manufacturer-authorized service providers of the equipment listed in the Equipment Identification Section.

EQUIPMENT IDENTIFICATION

Manufacturer Model Serial Number Spectrum Dynamics D-SPECT 5177

Spectrum Dynamics D-SPECT 14392

DEFINITIONS/ACRONYMS

A. Biomedical Engineer(ing) - Supervisor or designee.

B. CO - Contracting Officer

C. COR - Contracting Officer's Representative

D. PM - Preventive Maintenance Inspection. Services which are periodic in nature and are required to maintain the equipment in such condition that it may be operated in accordance with its intended design and functional capacity with minimal incidence of malfunction or inoperative conditions.

E. FSE - Field Service Engineer. A person who is authorized by the contractor to perform maintenance (corrective and/or preventive) services on the VAMC premises.

F. ESR - Vendor Engineering Service Report. A documentation of the services rendered for each incidence of work performance under the terms and conditions of the contract.

G. Acceptance Signature - VA employee who is authorized to sign-off on the ESR which indicates that the PM or service has been concluded or is still pending completion, or that the Emergency Repair has been accomplished or is still in a pending status.

H. Authorization Signature - COR's signature; indicates COR accepts work status as stated in ESR.

I. NFPA - National Fire Protection Association.

J. CDRH - Center for Devices and Radiological Health.

K. VAMC - Department of Veterans Affairs Medical Center

L. VAH - Department of Veterans Affairs Hospital

M. OEM - Original Equipment Manufacture

N. NIST - National Institute of Standards and Technology

CONDITION OF EQUIPMENT

The Contractor accepts responsibility for the equipment in "as is" condition. Failure to inspect the equipment prior to contract award will not relieve the Contractor from performance of the requirements of this contract.

SERVICE REQUIREMENTS

HOURS OF COVERAGE

A. Normal hours of coverage are Monday through Friday from 8:00 a.m. to 9:00 p.m. for all maintenance and services, excluding holidays.

B. Any necessary hardware/software update/installations as deemed by the OEM will be scheduled at least three (3) days in advance and shall be performed at no additional charge to the Government (unless it would be detrimental to equipment up-time; to be determined by the COR).

C. Federal Holidays observed by the VAMC are:

- New Years' Day

- Martin Luther King Day

- Presidents' Day

- Memorial Day

- Juneteenth

- Independence Day

- Labor Day

- Columbus Day

- Veterans' Day

- Thanksgiving Day

- Christmas Day

In addition to the days designated as holidays, the Government observes the following days:

- Any other day designated by Federal Statute

- Any other day designated by Executive Order

- Any other day designated by the President’s Proclamation

D. Preventive maintenance will be performed 3 times a year.

UNSCHEDULED MAINTENANCE (Emergency Repair Service/Corrective Maintenance) A. Contractor shall maintain the equipment in accordance with the manufacturer's latest specifications. The Contractor will provide repair service which may consist of calibration, cleaning, oiling, adjusting, replacing parts, and maintaining the equipment, including all intervening calls necessary between regular services and calibrations. All required parts shall be furnished.

B. The CO, COR or designee has the authority to approve/request a service call from the Contractor.

C. Response Time: - Contractor's FSE must respond to the COR or his/her designee within thirty (30) minutes after receipt of telephoned notification twenty-four (24) hours per day. If the problem cannot be corrected by phone, the FSE will commence work (on-site physical response) within four (4) hours after receipt of second notification. Contractor shall proceed progressively to completion without undue delay. Corrective work shall be completed within forty-eight (48) hours from onsite arrival unless otherwise approved by the COR in writing.

D. Any charges for parts, services, labor, travel, manuals, tools, installation, firmware or software required to successfully complete unscheduled maintenance are included within this contract unless specifically stated in writing otherwise and approved by the COR in writing. Parts and services not included within this contract are parts that are needed due to the failure of MEDVAMC to operate the system in accordance with the Specifications and the system use by untrained operators. Parts and services needed due to system damage from fire, accident, vandalism, water, smoke, lightning, natural disasters, building structural deficiency or power supply and/or heating, ventilation, or air conditioning fluctuation are also not included within this contract.

E. Contractor shall provide mandatory safety and performance-related updates to covered equipment and software. The contractor shall provide all operational software updates to the equipment hardware and operating system software that materially affects the performance of the equipment as deemed necessary by the OEM, without additional charge to the government. These enhancements to the equipment shall be delivered to the government site and installed by the contractor within 30 days of their issuance or date of first commercial availability.

F. The Contractor must have the ability to concurrently address multiple emergency calls and unscheduled maintenance on different equipment.

SCHEDULED MAINTENANCE

A. The Contractor shall perform quarterly PM service to ensure that equipment listed in the schedule performs in accordance with Section 3, Conformance Standards. Preventive maintenance inspections shall be scheduled at least three (3) days in advance with the Contracting Officer Representative (COR). The PM must be done in accordance with the latest OEM maintenance procedures and protocols. (An outline of the PM procedures and schedule shall be provided to the COR).

The Contractor shall provide and utilize procedures and checklists with worksheet originals indicating work performed and actual values obtained (as applicable). This documentation shall be provided to the COR at the completion of the PM. The contractor shall provide written description of Preventive Maintenance Inspections (PMI). This description shall include an itemized list of the procedures performed, including electrical safety. PM services shall include, but are not limited to, the following:

1) Cleaning of equipment.

2) Reviewing operating system software diagnostics to ensure that the system is operating in accordance with Section 3, Conformance Standards or the manufacturer's specifications.

3) Calibrating and lubricating the equipment.

4) Performing remedial maintenance of non-emergent nature.

5) Testing and replacing faulty and worn parts and/or parts likely to become faulty, fail or become worn.

6) Inspecting and replacing where indicated, electrical wiring and cables for wear and fraying.

7) Inspecting, and replacing where indicated, worn or damaged mechanical components which may include, but is not limited to: patient restraints and support devices, cables and mounting hardware, chains, belts, bearings and tracks, interlocks, clutches, motors, keyboards, and patient couches for mechanical integrity, safety, and performance.

8) Returning the equipment to the operating condition defined in "Conformance Standards" Section.

9) Providing documentation of services performed.

10) Inspecting and calibrating the hard copy image device.

B. PM services shall be performed in accordance with, and during the hours defined in the "Hours of Coverage" section and the preventive maintenance schedule established herein. All exceptions to the PM schedule shall be arranged and approved in advance with the COR.

C. Any charges for parts, services, labor, travel, manuals, tools, installation, firmware or software required to successfully complete scheduled PM are included within this contract, and its agreed upon price, unless specifically stated in writing otherwise and approved by the COR.

PARTS & TRAVEL

Gray market items are Original Equipment Manufacturers (OEM) goods sold through unauthorized channels in direct competition with authorized distributors. This procurement is for new OEM medical supplies, medical equipment and/or service for maintenance of medical equipment (i.e. replacement parts) for VA Medical Centers. No re-manufactures or gray market items will be acceptable.

The delivery of gray market items to the VA in the fulfillment of an order/award constitutes a breach of contract. Accordingly, the VA reserves the right to enforce any of its contractual remedies. This includes termination of the contract or, solely at the VA’s election, allowing the Contractor to replace, at no cost to the Government, any remanufactured or gray market item(s) delivered to a VA facility upon discovery of such items.

The Contractor shall furnish and replace parts in accordance with the manufacturer's specifications. The Contractor has ready access to all parts, including unique and/or high mortality replacement parts. All parts supplied shall be compatible with existing equipment. The contract shall include all parts [except -if applicable - those parts specifically listed as being EXCLUDED]. The contractor shall use new original equipment manufacturer (OEM) parts. All parts shall be of current manufacture and have complete versatility with the presently installed equipment. All parts shall perform identically to the original equipment specifications. Rebuilt parts, used parts or those removed from other equipment, shall not be installed without specific approval by the CO or the COR. (The Contractor shall also list any excluded parts under the service contract).

Travel for any and all service and preventative maintenance covered within this contract shall be covered by the Contractor and shall not be reimbursed by the CO, VAMC, COR or any of its and/or their associates, employees or descendants under any conditions or circumstances.

TEST EQUIPMENT

Should the COR request it, prior to commencement of work on this contract, the Contractor shall provide the VAMC with a copy of the current calibration certification of all test equipment which is to be used by the Contractor on VAMC's equipment. This certification shall also be provided on a periodic basis when requested by the VAMC. Test equipment calibration shall be traceable to the NIST national standard.

CONTACT INFORMATION

Upon contract award, the Contractor must provide valid and reliable contact information for service, preventative maintenance, emergency and technical assistance requests.

REPORTING REQUIREMENTS

The Contractor shall be required to report to Biomedical Engineering to log in. This check in is mandatory. When the service is completed, the FSE shall document services rendered on a legible ESR(s). The FSE shall be required to log out with Biomedical Engineering and submit the ESR(s) to the COR. ALL ESRs shall be submitted to the equipment user for an "acceptance signature" and to the COR for an "authorization signature" unless otherwise stated by the COR. If the COR is unavailable, a signed, authorized copy of the ESR will be sent to the Contractor after the work can be reviewed (if requested or noted on the ESR).

VA Biomedical Contact Persons:

Location (Building/Room Number):

Telephone Number & Extension(s):

DOCUMENTATION/REPORTS

Contractor ‘s repairman shall complete a full service report, in writing, after each service call (emergency or scheduled) and submit either a hard copy or an electronic version of this report to the COR within 5 days after the service day.

The documentation shall include detailed descriptions of the scheduled and unscheduled maintenance (i.e., Emergency repairs) procedures performed, including replaced parts and prices (for outside normal working hour services) required to maintain the equipment in accordance with the "Conformance Standards" section or the manufacturer's specifications. Such documentation shall meet the guidelines as set forth in the Conformance Standards section. The electronic engineering service report (ESR) will consist of a separate PM report for the item(s) covered under the "specific" contract. Grouping different equipment from different contracts on "one" ESR is prohibited. In addition, each ESR must, at a minimum, document the following data legibly and in complete detail:

A. Name of contractor and contract number.

B. Name of FSE who performed services.

C. Contractor service ESR number/log number.

D. Date, time (starting and ending), equipment downtime and hours on-site for service call.

E. VA purchase order numbers covering the call if outside normal working hours.

F. Description of problem reported by COR.

G. Identification of equipment to be serviced:

1) Inventory ID number,

2) Manufacturer's name,

3) Device name,

4) Model number,

5) Serial number,

6) Any other manufacturer's identification numbers.

H. Itemized Description of Service Performed (including, if applicable, Costs associated with after normal working hour services) including:

1) Labor and Travel,

2) Parts (with part numbers),

3) Materials and Circuit Location of problem/corrective action.

I. Total Cost to be billed (if applicable - i.e., part(s) not covered or service rendered after normal hours of coverage).

J. Signatures:

1) FSE performing services described.

2) Authorized VA Employee who witnessed service described.

NOTE: - Any additional charges claimed must be approved by the COR before service is completed!

REMOVAL OF EQUIPMENT

Should a piece of equipment require repair at the Contractor ‘s plant, the Contractor shall coordinate with the COR the removal of equipment. Government property cannot be removed from the station without a signed Property Pass. This Property Pass may be obtained from Acquisition & Material Management Service, Personal Property Section, 4A-320 after removal is authorized by the COR. The Contractor may not remove equipment from Government site for minor repairs only. The Contractor shall be responsible for damage or loss of equipment while in the Contractor ‘s charge.

REPORTING REQUIRED SERVICES BEYOND THE CONTRACT SCOPE

The Contractor shall immediately, but no later than 24 (twenty-four) consecutive hours after discovery, notify the CO and COR (in writing) of the existence or the development of any defects in, or repairs required, to the scheduled equipment which the Contractor considers he/she is not responsible for under the terms of the contract. The Contractor shall furnish the CO and COR with a written estimate of the cost to make necessary repairs.

ADMINISTRATIVE REQUIREMENTS

COMPETENCY OF PERSONNEL SERVICING EQUIPMENT

A. Each respondent must have an established business, with an office and full-time staff. The staff includes a "fully qualified" FSE and a "fully qualified" FSE who will serve as the backup.

B. "Fully Qualified" is based upon training and on experience in the field. For training, the FSE(s) has successfully completed a formalized training program, for the equipment and is OEM Certified. For field experience, the FSE(s) has a minimum of two years of experience (except for equipment newly on the market) with respect to scheduled and unscheduled preventive and remedial maintenance, on the listed equipment in the Equipment Identification Section.

C. The FSEs shall be authorized by the OEM to perform the maintenance services. All work shall be performed by "Fully Qualified", OEM Certified competent FSEs. The Contractor shall provide written assurance of the competency of their personnel and a list of credentials of approved FSEs for each make and model the Contractor services at the VAMC prior to award. The COR may authenticate the training requirements, request locations, training certificates or credentials, and technician location from the Contractor at any time for any personnel who are servicing or installing any equipment. The CO and/or COR specifically reserve the right to reject any of the Contractor's personnel and refuse them permission to work on the VAMC equipment if evidence is not provided when requested.

D. If subcontractor(s) are used, they must be approved by the COR; the Contractor shall submit any proposed change in subcontractor(s) to the CO for approval/disapproval.

The VAMC, CO, COR or any of its and/or their associates, employees or descendants under any conditions or circumstances shall not be held responsible for any safety incident or any injury or any inconvenience experienced by the Contractor, their associates, or subcontractors while performing the services, labor, travel, software upgrades or maintenance included within this contract to the extent applicable by federal, local and state law with federal law taking precedence.

INSURANCE

A. Worker compensation and employer's liability: - Contractors are required to comply with applicable Federal and State Worker Compensation and occupational disease statutes.

B. General Liability: - Contractors are required to have Bodily Injury Liability Insurance coverage written on the comprehensive form of policy of at least $500,000 per occurrence.

C. Property Damage Liability: - Contractors are required to have Property Damage Liability insurance coverage of at least $500,000.

ADDITIONAL CHARGES & PAYMENT

There will be no additional charge for time spent at the site (during, or after the normal hours of coverage) awaiting the arrival of additional FSE and/or delivery of parts.

In any case, the VA shall be explicitly notified in advance that additional charges will be incurred, prior to beginning such work. In such instances that the VA agrees the work is not within the scope of the contract, and the VA desires the Contractor to perform service, a separate purchase order will be issued to the Contractor for the work. Any service required which the Contractor believes to be in excess of the contract provisions and require additional payment (e.g., work beyond normal work hours) shall not be performed without prior authorization from the BIOMED COR, who will arrange a separate purchase order to pay for the additional service if desired by the VA.

The Government shall not be responsible for incidental charges including, but not limited to, parking, tolls, mileage, phone, etc., on straight time or overtime work.

All invoices shall be submitted in arrears, properly prepared in accordance with FAR 52.212-4, contain sufficient details, and match with the service tickets for the work rendered.

A. Invoices

Invoices shall be properly prepared and sent electronically to the VA Financial Services Center for payment processing via their electronic e-Invoice system. Invoices shall be sent in arrears at the beginning of the first month of each quarter following the quarter in which the services were rendered and billed for. At a minimum, all invoices shall include the following details:

Ø Contract No.

Ø Purchase Order No. Correct purchase order number which will be issued by the Contracting Officer after the contract is awarded. Invoices without correct purchase order number shall be rejected and returned to the Contractor.

Ø Item(s) covered (to include serial #'s) Ø Description of the services rendered Ø Billing period in which the services were rendered Ø Invoice number and date

Payments will be made in accordance with the prompt payment act out of the Government annual appropriated funds obligated in a purchase order which will be issued after the contract is awarded.

GOVERNMENT PARTY TO EXECUTE AND MODIFY THE CONTRACT

After the contract has been in force for a period of time, it may be necessary to change and/or modify the operations to provide better service. Pursuant to FAR 43.102, no government personnel other than the Contracting Officer can execute contract modifications on behalf of the government.

END OF SERVICE PERIOD

No service shall be performed under this agreement after the contract expiration date without written authority or direction from the Contracting Officer.

Contractor guarantees all equipment covered in this contract shall be in optimum working condition at the contract expiration date provided that the Contractor is notified of any deficiencies at least one (1) day before the contract expiration date to the COR. Any changes, updates or retrofits made on any component or system shall be reported to the COR for annotation on station equipment manuals and records. For any service call made during normal working hours, the Contractor‘s repairman shall report their arrival and departure to the COR.

INFORMATION TECHNOLOGY SECURITY REQUIREMENTS

PRIVACY/SECURITY

The Contractor will need to access VA systems to perform software upgrades, preventative maintenance and maintenance repairs.

The Contractor will have electronic connectivity to the devices. The Contractor will have access to patient databases with PHI present when troubleshooting equipment issues.

Any electronic or magnetic data storage devices such as hard drives, etc. shall be turned into the ISO.

Electronic or magnetic data storage devices are not to be removed from VA property.

REMOTE SUPPORT

The contractor shall have proper access and control to remotely monitor all equipment listed in the "Equipment Identification and Coverage" Section. This includes background checks and Information Security Officer approval as required by Directive 6500. The contractor must demonstrate active security clearance before award.

MOBILE MEDIA SCANNING

The Contractor will identify if removable media (i.e. USB or DVD/CD Device) is required to perform his/her duties. Personally owned USB thumb drive utilization is prohibited. Non-VA support personnel must furnish their own FIPS140-2 certified USB thumb drives, and only with the permission of a designated VA supervisor. All USB drives must be scanned with an antivirus program running current virus definitions by the local VA staff, prior to connection to any VA device. COR or designee will ensure the removable media is scanned with anti-virus software running current virus definitions prior to connection to any medical device system. The computer system for scanning removable media is located in the Biomedical Engineering shop, Building 100, Room BA200.

Records Management The following standard items relate to records generated in executing the contract and should be included in a typical Electronic Information Systems (EIS) procurement contract:

1. Citations to pertinent laws, codes and regulations such as 44 U.S.C chapters 21, 29, 31 and 33;

Freedom of Information Act (5 U.S.C. 552); Privacy Act (5 U.S.C. 552a); 36 CFR Part 1222 and Part 1228.

2. Contractor shall treat all deliverables under the contract as the property of the U.S. Government for which the Government Agency shall have unlimited rights to use, dispose of, or disclose such data contained therein as it determines to be in the public interest.

3. Contractor shall not create or maintain any records that are not specifically tied to or authorized by the contract using Government IT equipment and/or Government records.

4. Contractor shall not retain, use, sell, or disseminate copies of any deliverable that contains information covered by the Privacy Act of 1974 or that which is generally protected by the Freedom of Information Act.

5. Contractor shall not create or maintain any records containing any Government Agency records that are not specifically tied to or authorized by the contract.

6. The Government Agency owns the rights to all data/records produced as part of this contract.

7. The Government Agency owns the rights to all electronic information (electronic data, electronic information systems, electronic databases, etc.) and all supporting documentation created as part of this contract. Contractor must deliver sufficient technical documentation with all data deliverables to permit the agency to use the data.

8. Contractor agrees to comply with Federal and Agency records management policies, including those policies associated with the safeguarding of records covered by the Privacy Act of 1974.

These policies include the preservation of all records created or received regardless of format [paper, electronic, etc.] or mode of transmission [e-mail, fax, etc.] or state of completion [draft, final, etc.].

9. No disposition of documents will be allowed without the prior written consent of the Contracting Officer. The Agency and its contractors are responsible for preventing the alienation or unauthorized destruction of records, including all forms of mutilation. Willful and unlawful destruction, damage or alienation of Federal records is subject to the fines and penalties imposed by 18 U.S.C. 2701. Records may not be removed from the legal custody of the Agency or destroyed without regard to the provisions of the agency records schedules.

10. Contractor is required to obtain the Contracting Officer's approval prior to engaging in any contractual relationship (sub-contractor) in support of this contract requiring the disclosure of information, documentary material and/or records generated under, or relating to, this contract. The Contractor (and any sub-contractor) is required to abide by Government and Agency guidance for protecting sensitive and proprietary information.

Source: The National Archives Records Administration (NARA). http://www.archives.gov/records-mgmt/handbook/records-mgmt-language.html

End of Performance Work Statement

File details come from the government source that posted it. Updated .