D.2 - SOW Attachment A - Environmental Review and Compliance Seminar for Natural Gas Facilities.pdf
PDF 21 MB Posted
- Attached to
- Natural Gas Industry Seminars Support Services for the U. S. Federal Energy Regulatory Commission (FERC)
- Solicitation number
- 89603025Q0018
About this file
This document is a comprehensive seminar agenda and training materials for FERC's Environmental Review and Compliance for Natural Gas Facilities seminar, scheduled for September 24-26, 2024 in Fort Lauderdale, Florida. The seminar covers detailed aspects of FERC's environmental review process, including regulatory pathways, National Environmental Policy Act (NEPA) requirements, pre-filing procedures, resource reporting, agency coordination, and compliance protocols for natural gas infrastructure projects. Key course instructors include FERC staff and ERM environmental professionals who will provide in-depth insights into topics such as project planning, environmental assessments, stakeholder engagement, and regulatory compliance.
The training agenda comprehensively addresses critical elements of natural gas facility environmental review, including sections on project development, NEPA documentation, resource reporting (covering areas like cultural resources, land use, air quality, reliability, and safety), and post-approval processes. The seminar is designed to guide participants through the complex regulatory landscape of natural gas facility development, emphasizing FERC's environmental review procedures, consultation requirements with federal and state agencies, and the detailed documentation needed for project approvals. The materials provide a thorough overview of the regulatory expectations, procedural nuances, and environmental compliance strategies for natural gas infrastructure projects.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Navigating the Process
FERC’s Environmental Review and Compliance for Natural Gas Facilities
Fort Lauderdale, Florida September 24-26, 2024
Program Overview
Course Instructors FERC Staff
Public Outreach
David Hanobic
Outreach Coordinator
(202) 502-8312
David.Hanobic@ferc.gov
Environmental Review
David Swearingen
Branch Chief
David.Swearingen@ferc.gov
Construction Compliance
Gertrude Fernandez-Johnson
Branch Chief
(202) 502-6692
Gertrude.Fernandez.Johnson@ferc.gov
Course Instructors FERC Staff
Kareem Monib
Chemical Engineer & Environmental Project Manager
Kareem.Monib@ferc.gov
Hosanna Loreaux
Environmental Biologist
(202) 502-8670
Hosanna.Loreaux@ferc.gov
Construction Compliance
Keith Rodgers
Project Manager
(202) 502-6839
Keith.Rodgers@ferc.gov mailto:Hosanna.Loreaux@ferc.gov
Ariana Johnson
(503) 705-5116
Ariana.Johnson@erm.com
Course Instructors ERM Staff
Jennifer Lee
(503) 833-2966
Jennifer.Lee@erm.com
Environmental ReviewFacilitator/Environmental
Compliance
Tim Drake
(612) 840-9160
Tim.Drake@erm.com
Justin Casey
(850) 525-3755 justin.casey@erm.com
Environmental Review/
Environmental
Compliance
Environmental Review/
Environmental Compliance
Stephanie Pesek
(702) 340-2260
Stephanie.Pesek@erm.com
Safety Rules
Emergency alert system
Exits
Meeting location
Safety moment
Introduction to FERC
The FERC Environmental Review Process
• NGA Section 7/3: New Construction, Abandonment, and Import/Export Projects
• Section 2.55: Exclusion Projects
• Section 157: Blanket Certificate Projects
Developing Robust Resource Reports
Construction
• Traditional Construction
• Specialized Construction
Post-Construction
Course Agenda
Plan Ahead
Map Legend
Participate with an open mind
Ask questions
Observe break times
“Disconnect”
Turn off cell phones and other media devices
Keep side discussions to a minimum
Timeframes
Reference
Don’t Forget
Best
Management Practices
Closer Look
Questions
During this seminar you may email or text the instructors with questions:
David Hanobic: David.Hanobic@ferc.gov or 570-660-0456
Tim Drake: Tim.Drake@erm.com
Introduction to FERC and the Natural Gas Program
Organization
Independent federal regulatory agency
• Decisions subject to review by federal courts
• FERC implements a statute passed by Congress—the Natural Gas Act
The “Commission”
• Commissioners are nominated by the President and confirmed by the Senate
• Chairman is nominated by the President
• Only three commissioners can be from the same political party
Natural Gas Act
NGA Section 7 (Siting and Construction)
• Interstate pipelines
• Interstate storage
• Interstate LNG peakshaving facilities (and compliance)
NGA Section 3 Pipeline (Siting and Construction)
• Presidential Permits for border crossing facilities
NGA Section 3 LNG (Siting, Construction, and Compliance)
• LNG Import/Export Terminals
NGA Section 3 Pipeline or LNG (Commodity)
• U.S. Department of Energy – Public Interest Determination
FERC’s Natural Gas Program
Evaluate applications for facilities to import, export, transport, store, or exchange natural gas
Authorize siting, construction, and operation
Abandonment of facilities
Environment is just “one piece” of the Commission’s decision on a project
• Consideration of Public Convenience and Necessity (Section
7) or Public Interest (Section 3)
• Regulation of rates and tariffs
• Consider engineering/flows
Regulatory Path
Section 3 Exportation/Importation
15 USC §717b
Section 7(b) Abandonment
15 USC §717f (b)
Section 7(c) New Construction
15 USC §717f (c)
§2.55 Exclusions
18 CFR § 2.55
§157 Blanket Certificates
18 CFR § 157, Subpart F
Natural Gas Act FERC Regulations
The FERC Environmental Review Process
FERC & NEPA
Categorical Exclusion
Actions that will not have a significant effect on human environment
Actions that are procedural, administrative, compliance, or clarifying rules
Environmental Assessment
Pipeline and compression projects
LNG Facilities
Aids determination whether to prepare an Environmental Impact
Statement
Actions that do not pose significant impacts
Environmental Impact Statement
Major greenfield pipeline projects
New LNG Facilities
Projects with significant effects on human environment or where the effects are highly controversial
CEQ NEPA regulations - 40 CFR 1500-1508
FERC’s NEPA regulations - 18 CFR 380
The National Environmental Policy Act of 1969
EPAct 2005 – amended the Natural Gas Act
Planning a Project
Project
Development and Planning
Project Concept
Project Planning
Filing Type – Traditional or Pre-filing
Project Concept/Planning
Determine project purpose and need
Identify a base project
• Pipeline alignment
• Aboveground facility locations
• Interconnects
Begin public outreach efforts
Identify and contact agencies
• Potential resource issues
• Applicable permits
Develop project execution plans and schedules (e.g., plan field surveys)
Filing Types - Pre-Filing and Traditional
Pre-Filing Traditional
Applicability Required for LNG projects
Recommended if proposing an applicant-prepared EA or for complex and/or high degree of public interest projects
Used for smaller, less complex and lesser degree of public interest projects
FERC Involvement
Starts…
Before an Application is filed Once an Application is filed
Outreach Provides opportunity for FERC to receive early identification of stakeholders’ concerns and coordinate on resolution
Pre-Application stakeholder outreach is the responsibility of the Applicant
Ex-Parte Applicable No Often Yes
Pre-Filing Process
Pre-Filing Authorization
Stakeholder Outreach
NEPA Scoping
Resource Reports 1 - 13
18 CFR §157.21
Initial Consultation with FERC
Introduce project to FERC
Discuss environmental and non-environmental topics
Discuss status of ongoing activities (e.g., public outreach)
Determine regulatory path and NEPA document options
Submit drafts
• Pre-Filing Request Letter
• RFP for third-party contractors to prepare NEPA document
What is a 3rd Party Contractor?
A contractor that works for FERC, paid for by the application, but subject to the same rules as FERC staff (e.g., ex parte).
Refer to FERC’s guidance document “Guidelines for Applicant-
Prepared Draft Environmental Assessments”
Pre-Filing Participation Request Letter
• Request participation in the Pre-Filing process
• Reason for requesting Pre-Filing
• Acknowledgment that a complete Application and Environmental Report will be provided
Request Basics
• Project description, maps, and drawings
• Zoning & availability of property (LNG)
• Work completed to date
Project Details
Project Schedule
Key Milestone Activities Anticipated Schedule Time Period
Submit Request to Initiate Pre-
Filing Review Process March 13, 2015 180 days from Pre-Filing to
Application File Certificate Application September 2015
Commencement of Construction September 2016 2 months from FERC Order to
Construction Start
Pipeline In-Service January 2017 5 months from Construction
Start to In-Service
For illustration purposes only. Examples can be found on eLibrary.
Status of Work To Date
Land
•Tax and title records searches
•Landowner contacts
•Survey permissions
Public Outreach
•Community contacts
•Governmental contacts
•Open houses
•Other communications
Engineering
•Civil survey plans
•Routing
•Facility design
Environmental
•Agency contacts
•Environmental analyses
•Plans for biological, cultural, and paleo surveys
FERC’s “Suggested Best Practices for Industry
Outreach Programs to Stakeholders”
• Applicable authorizations or consultations
• Willingness to participate in Pre-Filing
• Proposed Application submittal and authorization schedule
Agency Involvement
• Interested parties and stakeholders contacted
• Public outreach plan description
Public Outreach
• Letter of Intent and Preliminary WSA Certification
• DOE authorization
LNG
Specific Items
Pre-Filing Request Letter - Proposals
Applicant-Prepared Draft EA or EIS
Third-Party Contractors (3PC)
Refer to FERC’s guidance document “Handbook for Using Third-Party
Contractors to Prepare Environmental Documents”
Develop Request for
Proposal (RFP)
FERC reviews draft PF request letter and RFP
Update RFP and circulate to consultants
Receives proposals
File PF request letter and ALL proposals to
FERC
FERC completes conflict of interest review and selects 3PC
Pre-Filing Approval Letter
Conveys acceptance into pre-filing process
Issuance of docket number at PF filing opens the public record
Third-party NEPA document consultant selected or acknowledgement of the applicant’s intention to file applicant-prepared draft EA or
EIS
• FERC staff can still request third-party contractor if needed
Pre-Filing Clock
The clock starts when the PF approval letter is issued
Identify locations for open houses and agency meetings
Execute contract for third-party NEPA contractor and inform stakeholders about the project
Minimum time to File
WSA (LNG only) and
FERC Application
Submit updated mailing list and file draft Resource Report 1 and summary of alternatives considered
*Calendar Days
P
F
A
P
R
O
V
A
L
* 180 Days
* 30 Days
* 14 Days
* 7 Days
Mailing Lists
Mailing address information provided for:
• Landowners (§157.6(d)(2)), other interested stakeholders, agencies, elected officials, tribes, non-governmental organizations, libraries, newspapers, and other local media outlets
Mailing lists provided to FERC staff in specified
• Excel format
Open Houses
Open to the public
Sponsored and hosted by the applicant
Informal setting
FERC or the third-party NEPA document contractor will attend
General discussions are not part of the public record
FERC site review possible
Number and locations of open houses are project specific
Notice of Scoping
Issuance of Notice of Scoping starts scoping period (prefiling or application)
Announces close of scoping period
Announces public session dates and locations (if held)
Requests agencies to indicate if they will act as cooperating agencies
Identifies stakeholders/ mailing list
What is Scoping? – Process for identifying those issues that need to be considered in the NEPA document
Scoping Sessions
Purpose is to solicit comments on the proposed project
Sponsored and hosted by FERC
Included as part of public record
• Public scoping session transcripts
Cooperating and Participating Agencies
During Pre-Filing, all agencies can participate the same because there is no ex parte (communication limits)
Cooperating Agency
• Has NEPA responsibility or expertise
• Post-Application ex parte doesn’t apply
• Advanced review of draft NEPA document
Participating Agency
• Post-Application provide comments on the record during the proceeding
• Non-party agency can discuss project with FERC, but FERC must disclose
Interagency Coordination Meetings
Applicant provides a project status update
FERC identifies agency roles and responsibilities for NEPA review
Agencies identify issues and concerns
Agency Roles and Responsibilities
FERC
Lead federal agency responsible for complying with NEPA
Establishes and maintains schedule for federal authorizations
Coordinates all federal authorizations and agency comments
Compiles agency actions and decisions into a consolidated record
Other Federal Agencies
Participate in Pre-Filing process as specified in Interagency MOU (2002)
Coordinate with FERC and other agencies to:
• identify and resolve issues early in the process;
• coordinate schedules;
• share data; and
• coordinate requests for additional information.
Pre-Filing Scoping Clock
Within 14 days of the end of the scoping comment period, respond to issues raised during scoping to fullest extent possible
Within 60 days of the end of the scoping comment period, file draft
Resource Reports 1-12
The clock starts when NEPA scoping period has concludedS
C
O
P
I
N
G
E
N
D
*Calendar Days
* 14 Days
* 60 Days
Be prepared for comment tracking and obtaining transcripts
Draft Resource Reports
General Project Description
Water Use and Quality
Fish, Wildlife, & Vegetation
Socioeconomics
Cultural Resources
Geological Resources
Soils
Refer to FERC’s guidance document “Guidance Manual for Environmental Report Preparation”
Land Use, Recreation &
Aesthetics
Air Quality & Noise
Alternatives
PCB Contamination
Reliability & Safety
Engineering & Design
Materials (LNG)
General Resource Report Requirements
Existing conditions
Direct, indirect, and cumulative impacts
• Construction
• Operation
• Abandonment
Proposed mitigation measures
• Applicant-committed
• Agency-recommended
Applicable agency correspondence
Reference list
FERC may require a revised set of draft resource reports if the first drafts are not complete which can have significant schedule impacts
18 CFR §380.12(c)
Resource Report Recommendations
Divide agency correspondence by appropriate resource report, agency, and in chronological order, not a single mass tab filed under RR1
• Assists PM and FERC staff to review only their respective agency correspondence in order
• Use electronic bookmarks
Use cross references to other resource reports instead of repeating information
• Avoids inconsistencies and simplifies updates
Provide redacted versions of Privileged and Confidential or Critical Energy Infrastructure Information
Information Types ri vi le ge d Not released to the public
Affected landowners
Cultural resource data & reports
Proprietary information
Detailed designs
Can be obtained from applicant or by signing
FERC NDA
Submit less detailed drawings for NEPA document
Unrestricted distribution
Published on FERC’s e-Library website
Included in NEPA document
C
EI
I
Controlled Unclassified Information (CUI)
Public
FERC Comments/Data Request
FERC will issue comments on draft RRs during Pre-Filing
• FERC comments on RR1 and alternatives incorporated into filing5 of complete set of draft RRs
• FERC may request written response (but not typical)
• FERC may request comments to be incorporated into next round of draft RRs, if a second draft of a RR is requested in PF
• Typically comments are addressed in application, when filed
Once an application is filed, FERC will issue a data request for missing, incomplete, or inconsistent information
• The applicant will respond to each question
Application Review
Application Filing
Post Application
18 CFR §157, Subpart A
Applicant will
• Submit requests for other federal authorizations before or concurrent with FERC Application
• Include Exhibit H (LNG) or Exhibit J (pipelines) in FERC Application
• Authorization needed and issuing agency
• Submittal date and anticipated approval date
• Justification for requests not yet submitted and anticipated submittal date
Other Federal Authorizations
Application Clock
The clock starts when the CP docket number is issued
~Business Days * Calendar Days
C
D
O
C
K
E
T
Place copies of Application in libraries/publicly accessible central locations in each county throughout project area
FERC issues Notice of Application in Federal Register
Publish Notice twice in a general circulation newspaper in each county
File updated landowner list
Mail landowner notification packets to mailing list (within 3 days of issuance of Notice)
* 30 Days
~ 7-10 Days
~ 3 Days
~ 3 Days
* 14 Days
Direct Mailing List
Other Stakeholders/ Interested Parties
Residences within 50’ of construction work areas
Jurisdictional and permitting agencies
Local and state officials
Tribes
As identified by FERC staff
Affected Landowners
Crossed
Abutting existing ROWs or where there is a house within 50’ of an adjacent property
Properties within 0.5 mile of a new compressor station
Affected by surface disturbance within an existing gas storage field boundary
18 CFR §157.6.(d)
Notice of Application
CP docket number assigned
Announces submittal of Application
Describes process for becoming involved in the FERC’s review of the project
Notifies landowners of project timing
Announces time period for intervention
What is an Intervenor?
https://www.ferc.gov/resources/guides/how-to/intervene.asp https://eur01.safelinks.protection.outlook.com/?url=https%3A%2F%2Fwww.ferc.gov%2Fresources%2Fguides%2Fhow-to%2Fintervene.asp&data=02%7C01%7CLisa.DiNicolantonio%40erm.com%7Cd068ca19c1114885e50008d70546d9ee%7Cf2fe6bd39c4a485bae69e18820a88130%7C0%7C0%7C636983674176092824&sdata=qSHasXGGBSTFmtcdcHGLDQRXt457wl%2FVoMFV9zj1q4Y%3D&reserved=0 https://eur01.safelinks.protection.outlook.com/?url=https%3A%2F%2Fwww.ferc.gov%2Fresources%2Fguides%2Fhow-to%2Fintervene.asp&data=02%7C01%7CLisa.DiNicolantonio%40erm.com%7Cd068ca19c1114885e50008d70546d9ee%7Cf2fe6bd39c4a485bae69e18820a88130%7C0%7C0%7C636983674176092824&sdata=qSHasXGGBSTFmtcdcHGLDQRXt457wl%2FVoMFV9zj1q4Y%3D&reserved=0
Ex Parte
Once application is filed, communication must be:
• in a public manner (no private meetings or calls)
• “on the record” (part of decisional file / equal opportunity)
Assures fairness and transparency in the development of the record that FERC will use for its decision
Certain exemptions, but they need to be disclosed
Procedural matters are not ex parte
Common Prohibited Communication Exemptions:
• from non-party elected official
• with non-party Federal, state, local or tribal official
• related to NEPA documentation, and prior to FEIS/EA
• communication with non-party landowner
Notice of Intent to Prepare an EIS
Requests comments on the scope of issues, including potential alternatives and impacts, and any relevant information, studies, or analyses of any kind concerning impacts affecting the quality of the human environment.
Summarizes the Proposed Project, Purpose and Need, and Expected Impacts
Serves as the Schedule for Environmental Review
List of federal permits
May announce scoping sessions if not already conducted
Can be issued within the NOI for an EIS
Issued separately for EA level projects
Can be amended for various reasons:
• if information not provided
• project changes/amendments
Notice of Schedule for
EA Process – FERC Issued Notices
If Pre-Filing Is Used
During Pre-Filing
Notice of Scoping
After Application Filed
Notice of Application
Notice of Schedule for the Preparation of an EA
• Starts CEQ 1-year timeline
• 90-day federal agency action/decision target date
If Pre-Filing Is NOT Used
All Notices after Application Filed
Notice of Application
Notice of Scoping
Notice of Schedule for the Preparation of an EA
• Starts CEQ 1-year timeline
• 90-day federal agency action/decision target date
EIS Process – FERC Issued Notices
If Pre-Filing Is Used
During Pre-Filing Notice of Scoping
After Application Filed Notice of Application
Notice of Intent to Prepare an EIS/Notice of Schedule
If Pre-Filing Is NOT Used
All Notices after Application Filed
Notice of Application
Notice of Intent to Prepare and EIS/Notice of Scoping/ Notice of Schedule
NOI (includes NOS)
NOI is the start of the NEPA process
Opens a comment period
States month and year Draft EIS is anticipated to be issued
States issuance date of Final EIS
Starts CEQ 2-year timeline
States 90-day federal agency action/decision target date
NEPA Review Process
EA
Draft EIS
Final EIS
18 CFR §380
From Resource Reports to NEPA Document
Resource reports filed with application are reviewed and then used as the basis for the EA/EIS
Staff will ask “data requests” for missing information
FERC conducts independent analysis and draws conclusions about impact based on proposal
Staff often has environmental recommendations (bolded in NEPA doc)
Environmental Assessment
There is no draft EA
30 day comment period
Company should respond to substantive comments received on an EA
FERC will address comments within the Order
Order is official Finding of No Significant Impact
Draft EIS
If Pre-Filing is used - FERC staff and its third-party contractor begins work prior to the Application submittal
After Application Filing - Once all necessary information has been received, FERC estimates it will take four months to issue the Draft EIS
Addresses comments received in response to NOI/scoping
Notice of Availability of Draft EIS
Provides FERC Staff’s conclusion on the potential environmental impact of the project
Announces public comment sessions
Issuance of EPA’s subsequent Notice of Availability begins 45-day comment period
Draft EIS Comment Sessions
Sponsored and hosted by FERC
Meeting transcripts included as part of public record
Similar format to scoping sessions
Discussion with FERC staff limited to process
Applicants typically do not participate
Final EIS
FERC estimates 4 months from issuance of Draft EIS to issuance of Final EIS (assuming “prior to close of comment period recommendations” have been addressed)
Addresses comments received on Draft EIS
Final EIS is FERC’s final environmental document
FERC and EPA will issue Notices of Availability in Federal Register
Knowledge Check 1
Using our proposed Project with the variables described below, should pre-filing or traditional filing be used:
1. The Project involves constructing all facilities seen on the map.
2. The Project only involves looping the lateral. There are no homes near the lateral and the route is 90% agricultural, with the exception of the crossing of the Yarrat State Forest, but it would be crossed using a drill.
3. The Project involves looping the entire mainline and building the compressor station near Moto. The mainline crosses the Moto business district and might prevent access to some businesses.
4. The LNG terminal is existing, and the Oceanview Pipeline Company wants to add another liquefaction train.
5. The Project only entails installation of the meter stations and additional compression through software upgrades.
Post-NEPA Document Process
Decision Order
Post-Certificate
18 CFR §380
The Commission Decision/Order
FERC staff works to help address public comments
Commissioners vote on project and issue an Order:
• Notational
• Commission Meeting
Order identifies intervenors (if not done before)
Order summarizes project description, open season results, proposed rates, tariffs, capacity, environmental impacts and alternatives evaluated
Order identifies Conditions
Order indicates timeframe applicant has to complete project
Section 7(h) of the Natural Gas Act conveys right of federal eminent domain is identified in Order
Applicant “accepts” Certificate within 30 days
Order Conditions
Standard Conditions
• Commitment and acknowledgement statements
• “Construction” alignment sheets
• Implementation plan
• Post Construction Requirements
• Status Reports
Other Common Conditions
• FERC’s approval required to begin service
• Environmental complaint resolution program
• Documentation of applicable federal authorizations
Knowledge Check 2
As a third-party contractor working for FERC, would you: (Yes or No)
1. Go to eLibrary to look for templates of current FERC notices you are being asked to prepare?
2. Make edits to FERC staff’s edits that change the document’s content and meaning?
3. Call the applicant to discuss issues during the NEPA review?
4. Provide a schedule to the applicant that is not public for budgeting?
5. Do something that is out of scope but requested by FERC?
6. Follow the FERC Style Guide for writing?
Countdown to Construction
Order 871
Implementation Plan
Notice to Proceed
Modifies 6/2020 rule prohibiting construction until FERC acts on rehearing requests
Construction prohibited until:
• A qualifying rehearing request is no longer pending; or
• 90 days after the date that a rehearing request is denied by operation of law
Limited to cases where rehearing request raises issues reflecting opposition to project construction, operation, or need.
Section 7(c) Orders stayed during rehearing pd. and pending
Commission resolution of any timely requests for rehearing filed by landowners
• Subject to the same 90-day time limitation or a showing by the pipeline developer that the stay should be lifted.
Order 871B – RM20-15-001
Order 871
Commission issues an NGA section 7 or 3 Authorization;
It will not authorize construction during the 30-day rehearing period , when intervenors can request rehearing
Order 871 no longer applies
FERC can authorize construction
If no qualifying rehearing request filed
If a qualifying rehearing request filed
Continued next slide
Within 30 days, issues a merits order denying rehearing
871 no longer applies
FERC can authorize construction
Within 31 days, issues a notice stating it will not issue a further merits order
Rehearing is deemed denied
871 no longer applies
FERC can authorize construction
Within 31 days, issues a notice or an order stating it will issue a further merits order
871 applies
For no more than 90 days after rehearing may be deemed denied, FERC cannot authorize construction
Issues an order granting rehearing and revoking the
Authorization Order
871 no longer applies but revocation means construction cannot be authorized.
Further proceedings are governed by order revoking Authorization
If a qualifying rehearing request is filed, the
Commission has four options
Continued from previous slide
Implementation Plan
Typically submitted within 60 days of acceptance of Certificate
Identifies how all environmental conditions will be satisfied
Includes applicant-committed plans, reports, documents, and clearances
Provides opportunity for changes
Describes how environmental requirements will be communicated
• Incentives/penalties
Notice to Proceed (NTP) Request
Applicant must submit a NTP request to begin construction
Do not request authorization to construct unless:
• All applicable permits and authorizations have been obtained
• All pre-construction requirements have been fulfilled
If the entire project is not ready to go to construction, a partial NTP can be submitted for discrete spreads, segments, or facilities
• Must be able to demonstrate independent utility from the rest of the Project
Show how construction will access requested areas without traversing unauthorized areas
NTP Request for Discrete Facilities
If requesting authorization for only part of the project
Identify which spreads, facilities, etc. you want authorized
• Describe locations and mileposts
• Include all necessary work areas in the request
• Access roads
• Contractor yards
• ATWS or staging areas
NTP Request Letter
Identify what relevant information is attached
Describe when other information necessary to issue the NTP was filed
Allow time for the FERC’s review
NTP Authorization Letter
Says what is approved for construction
Indicates what is not being granted
Knowledge Check 3
The project has been approved by the Commission. The applicant has filed its Implementation Plan and requested a Notice to Proceed with Construction. What would FERC do in the following situations (grant or deny)?
1. The applicant has all of its federal permits.
2. Section 106 is complete for the LNG terminal, but not the associated pipelines.
3. The lateral is partially in a different state. All permits are in hand for the mainline, but the lateral still lacks a permit.
a) The lateral and mainline are dependent on each other for operating the system and delivering gas to the LNG terminal.
b) The mainline has independent utility and could function on its own without the lateral project.
c) The Company is only missing a local township building permit on the lateral.
2.55 and Blanket Certificate Projects
2.55 and Blanket Certificate Projects
Pre-filing (if utilized) (PF Docket)
Required for LNG, Voluntary for pipelines
Certificate Filing (CP Docket)
Environmental Assessment or Impact Statement produced
2.55 Projects
2.55 a
Auxiliary
Facilities
2.55 b
Replacements
Blanket
Certificate
Projects
Automatic
Authorization Prior Notices
Certificated
Facilities
Pre-Certificate
Section 2.55 – Auxiliary Installations and Replacements
Subject to the FERC’s NGA jurisdiction
No new Certificate authority required
Company must comply with environmental restrictions of the original Certificate and other applicable federal laws and landowner agreements
• FERC staff may conduct compliance inspections
Operations/Maintenance activities that result in facility replacement, or the addition of auxiliary facilities may become 2.55 projects
2.55(a) Installations
On Certificated or proposed transmission pipeline systems
Auxiliary or appurtenant facility
Installed to obtain more efficient or economical operation
2.55(a)(3) allows abandonment & replacement of 2.55 auxiliary facilities, if there is no impact on customers
Typical 2.55 Auxiliary Installations
Valves and drips
Pig launchers/receivers
Yard and station piping
Buildings
Gas cleaning, cooling, and dehydration equipment
Water pumping, treatment, and cooling equipment
Electrical and communication systems
Residual refining equipment
Cathodic protection equipment
2.55(b) Replacements
On a Certificated transmission pipeline system
Replaces existing facility that is or soon will become physically deteriorated or obsolete
Substantially equivalent in designed delivery capacity
2.55(b) replacement facilities and 2.55 (a) facilities that do not meet
2.55(a)(3) requirements may be abandoned under 157.216 of the blanket certificate regulations
All activities must occur within
Certificated rights-of-way and previously used workspaces
Guidelines where the original work area is unknown
Construction ROW width based on pipe diameter
• <75 feet for >12” diameter
• <50 feet for <12” diameter
Reasonable extra workspace at feature crossings
(e.g., roads, railroads, streams) depending on site-specific conditions
Work Area for 2.55 Projects
18 CFR §2 Appendix A
Landowner Notification Requirements for
2.55 Projects
Landowners are those that are directly affected
Notification required at least 5 days before work is performed except in cases of:
• Emergency
• Where no soil is disturbed
• Landowner has waived requirement
• Work would occur within fence line of company facility
FERC Notification Requirements for 2.55(a) Projects
Is the 2.55(a) work on an existing facility?
Yes
Is the 2.55(a) work on a Certificated facility not yet in service?
No
Is the 2.55(a) work on a proposed Section
7 facility pending before FERC?
No FERC advance notification required
Yes
No Notify FERC 30 days in advance of work, include description of auxiliary facilities and location
Include notification in the FERC
Section 7 application
Yes
No 2.55(a) not applicable
FERC Notification Requirements for 2.55(b) Projects
Budget should include materials, planning, & construction
Cost limits on Table 1 in §157.208(d) are adjusted annually
Project budget meets first tier cost limit on Table 1 in §157.208(d)
Emergency project requiring immediate replacement, regardless of cost
No advance notification required if
Project is not an emergency & budget exceeds first tier cost limit
30-day advance notification required if
Information Required for 2.55(b) FERC Notification
Brief description of the replacement facilities, including estimated costs
Current USGS 7.5 minute topographic map
Description of procedures for erosion control, wetland & waterbody crossings, and revegetation & maintenance
Photos may be helpful
18 CFR §2.55(b)(3)
FERC Reporting Requirements
No Reports Required No Reports Required
• During or at the completion of construction
Must be reported in annual report by May 1 except for where:
• Notification given in advance
• Aboveground facilities that do not involve ground disturbance or compression
Annual report must include the same project information as is required for advanced notification projects
2.55(b) Replacements2.55(a) Installations
Knowledge Check 4
Oceanview Pipeline Company is planning to install a new groundbed on a cathodic protect unit on its existing mainline.
All excavation and installation activities will take place within the permanent pipeline right-of-way.
1. Can Oceanview complete this installation under 2.55(a)?
2. Is landowner notification required? If so, how many days in advance of the work?
3. Does Oceanview need to provide advanced notification to FERC before installing the cathodic protection system?
4. Is Oceanview responsible for providing an annual report?
Bonus Question: What would happen if Oceanview wanted to install the cathodic protection system perpendicular to the right-of-way?
Knowledge Check 5
Blue = Property line for land that Oceanview Pipeline Company owns
Red = Fence line of compressor station Oceanview Pipeline
Company operates
Knowledge Check 5
1. Can Oceanview replace compressor units within the red fence line under 2.55? If so, using 2.55(a) or 2.55(b)?
2. Can Oceanview use workspace within their blue property line, but outside of the red fence line to perform the replacement activity?
3. Does Oceanview need to provide advanced notification to FERC and/or landowners before replacing the compressors?
4. Is Oceanview responsible for providing an annual report?
Oceanview Pipeline Company plans to replace 2 obsolete compressor units at this station with 2 new, more efficient units.
The existing units are 15,600 horsepower each. The new units are 15,800 horsepower each. The estimated cost is $26M.
Knowledge Check 6
Knowledge Check 6
Oceanview Pipeline Company needs to replace pipe at the yellow star on its existing pipeline. Oceanview has access to its pipeline from the green arrow for the nearest public road crossing. A landowner has offered direct access to the anomaly dig site from his private driveway (blue arrow) to avoid traveling down the right-of-way and disturbing multiple other landowners.
Can Oceanview use the landowner’s blue access road under 2.55(b)?
Section 157, Subpart F – Blanket Certificate Projects
Certain “pre-approved” activities do not require an individual Certificate
A FERC environmental review will be conducted
Project must comply with
• Other applicable federal and state laws
• FERC Plan and Procedures (75-foot ROW)
• Construction time limit of one year if ground disturbance
Blanket Certificates are typically requested in conjunction with 7(c) filings for major projects or systems
Types of Blanket Projects
Does not require additional FERC approval
Subject to first tier cost limits
No formal public protest process
Automatic
Must request approval to use authorization
Subject to second tier cost limits
Project noticed in Federal Register and subject to public protest
Prior Notice
Cost limits on Table 1 in §157.208(d) are adjusted annually
18 CFR §157
Authorizations
Automatic Prior Notice
Cost
Limits
Apply
Requires
Env. Report
.208 Misc. Rearrangement Yes Yes Yes Yes
.209 Temporary Compression Yes No Yes No
.210 Mainline Facilities No Yes Yes Yes
.211 Delivery Points Yes Yes No No
.212 Synthetic/LNG Facilities No Yes Yes Yes
.213 Storage Field Facilities Yes Yes Yes Yes
.214 Increase Storage
Capacity
No Yes No No
.215 Storage Testing/Develop. Yes No Yes* No
.216 Abandonment Yes Yes Yes Yes
.217 Change in Rate Schedule Yes No No No
.218 Customer Name Change Yes No No No
Types of Projects * See Table II limits
Limitations
Projects are not eligible to use blanket authorization if they will:
Affect cultural resources
Adversely affect federally listed species or designated critical habitat
Exceed compressor station noise limits
55 dBA Ldn at NSAs
Exceed cost limits
Be within 0.5 mile of a nuclear plant
Significantly impact sensitive environmental resources
Projects involving nighttime drilling should attempt to meet the 55 dBA noise limit at existing NSAs
Blanket Project Landowner Notification Requirements
Prior Notice
• Within 3 business days following issuance of docket number or during easement negotiations, whichever is earlier
Affected landowners defined in 18 CFR 157.6 and include more than just owners of directly affected properties
Automatic
• 45 days prior to construction or during easement negotiations, whichever is earlier
The notification period for automatic authorizations can be waived by the affected landowner or in cases where emergency activities are required to restore service
FERC Notification Requirements
Automatic
• No advanced notification required
Prior Notice
• Submit request for authorization at least 60 days prior to construction
Company information
Docket number(s)
Statement of compliance
Form of Notice for Federal Register
Required activity-specific information
Environmental clearances
Prior Notice – Content of Environmental Report
Description of facilities
Maps of facilities & sensitive resources
Concise assessment of conditions/impacts
Mitigation to avoid significant impacts
Document compliance with ESA, NHPA, CZMA
How compressor station will comply with SIPs per CAA
How HDDs will meet goal of 55 dBA at NSAs
FERC Reporting Requirements
No reports required during construction
File annual report by May 1
Automatic Submit weekly EI reports during construction
File annual report by May 1
Prior Notice
Content of FERC Annual Report
Actual costs (AA and PN)
Construction and in-service dates (AA)
Required activity-specific info. (AA)
Written & photo documentation of restoration progress representative of all habitats and land uses crossed
(AA)
Issues and corrective actions (AA)
Compressor station noise surveys (AA)
Required content of the annual reports can be found in 18 CFR §157.207 & 157.208(e)
Knowledge Check 7
Oceanview Pipeline Company is an existing interstate pipeline company that plans to build a pipeline that is 6 miles long and would cost $10 million.
1. The U.S. Fish and Wildlife Service determined that the Project is “not likely to adversely affect” any federally listed species, and the State Historic Preservation Office indicated it would have “no adverse effect” on cultural resources. Can Oceanview use the Blanket Program?
2. This is a loop of the mainline with no significant impacts.
Which Blanket Program process can Oceanview use:
Automatic Authorization or Prior Notice?
3. This is a lateral off of the mainline with no significant impacts. Which Blanket Program process can Oceanview use: Automatic Authorization or Prior Notice?
Knowledge Check 8
Oceanview Pipeline Company is an existing interstate pipeline company that plans to install 10 miles of pipeline at an estimated cost of $39.1 million. Oceanview submits a Prior Notice Request to FERC and receives no protests over the 60-day protest period.
1. Can Oceanview begin construction?
2. During construction, the contractor needs more workspace for a waterbody crossing. The landowner has agreed to the extra workspace. Can Oceanview begin using the extra workspace?
3. While preparing the Annual Report to FERC, Oceanview learns that the actual cost of the Project was $40.1 million. Should Oceanview cap the amount reported in the annual report to the Prior Notice limit of $39.7 million?
Knowledge Check 9
Oceanview Pipeline Company plans to replace 1 mile of exposed pipeline at a waterbody crossing for an estimated cost of $3 million. Oceanview plans to use the Automatic Authorization program. During project planning, Oceanview determines it needs an extra temporary workspace within 50 feet of the waterbody to facilitate the pipeline removal and replacement. Can Oceanview proceed to use the space under the Automatic Authorization Program?
Developing Robust Resource Reports
The FERC Environmental Review Process
2.55 and Blanket Certificate Projects
Developing Robust Resource Reports
Resource Reports
Form the heart of the environmental application
Minimum filing requirements vs complete resource reports
Public, CEII, Privileged
Most Common Overall Data Requests
Consistency:
• acreage numbers, including clear definition of temporary vs. permanent
• construction methods and committed mitigation measures
Address:
• comments within the resource reports
• commitment to implement agency-recommended measures (if not, why not)
Lack of source information
Conclusions not supported by data
Revisiting Our Project
Project Schedule
General and Special Construction and
Restoration Methods
Purpose and Need
Mapping
Permits and
Authorizations
Description of Proposed Facilities
Non-jurisdictional
Facilities
18 CFR §380.12(c)
RR 1: General Project Description
Identify in a table:
• the location, milepost range, length, and diameter of each pipeline segment
• the location, milepost of each aboveground facility including amount of new or additional compression
If the scope of project shrinks or expands, explain the necessary facility modifications
Clearly and consistently state the purpose and need for the project
Provide sufficient specificity to define the potential range of alternatives
Proposed Facilities and Project Purpose and Need
Overview of Land Acreages
Facility County Land Affected During
Construction (acres)
Land Affected During
Operation (acres)
Pipeline Rights-of-Way a
Line 3A Williams 714.2 374.8
Line 3B McKenzie 185.1 123.5
Additional Temporary Workspace
Line 3A Williams 79.1 0.0
Line 3B McKenzie 10.1 0.0
Access Roads
Temporary access roads Multiple 54.9 0.0
Permanent access roads Williams 3.7 3.7
Aboveground Facilities b
3A Compressor Station Williams 12.0 10.9
Block Valves Multiple 0.0 0.0
Pig Launcher/receivers Multiple 0.0 0.0
Total 1,059.1 512.9 a Based on a 100-foot-wide construction right-of-way and a 50-foot-wide permanent.
b Block valves and pig launcher/receivers will be constructed entirely within the permanent pipeline rights -of-way.
Construction Methods
Describe the typical construction sequence
Provide sufficient detail for each activity to describe what is being proposed
Describe each proposed special construction method. For example:
• wetland & waterbody crossings
• road and rail crossings
• residential construction
Include cross references for methods described in more detail in other resource reports
Revised versions issued May 2013 (Docket No. AD12-2-000)
Baseline mitigation measures for construction and maintenance activities at jurisdictional facilities
Any proposed modifications from the Plan and Procedures must be fully described and justified
FERC’S Plan and Procedures
Upland Erosion Control, Revegetation and Maintenance Plan
Wetland and Waterbody Construction and Mitigation Procedures
See http://www.ferc.gov/industries/gas/enviro/guidelines.asp. Also referred to at
18 CFR 380.12(i)(5), 380.12(d)(2), and 18 CFR 157.206(b)(3)(iv).
http://www.ferc.gov/industries/gas/enviro/guidelines.asp
Project Schedule and Timing
Provide a schedule for each proposed facility
Indicate year(s) and months of construction
Include additional schedule details where appropriate (e.g., the dates of proposed in-street construction)
Update the schedule if the project plans change
Provide the days of the week and specific hours each day of construction by activity and note those that may occur outside that time
• Discuss if work is proposed over the weekends
• Generally, activities should be limited to daylight hours (exceptions such as hydrostatic testing, time-limited stream crossings, completion of tie-ins, required equipment maintenance, etc.)
List applicable permits and permitting agencies
Indicate the status of each permit
Periodically update the table during the FERC’s review
Permits and Authorizations
Permit & Consultation Summary Table
Agency Permits and
Consultations
Anticipated
Permit Submittal
Date
Anticipated
Permit Receipt
Date
FEDERAL
Federal Energy Regulatory
Commission (FERC) o Office of Energy
Projects (“OEP”)
Required Permit:
o Certificate of
Public
Convenience and Necessity o National
Environmental
Policy Act
(NEPA) –
Environmental
Impact
Statement
Review o Pipeline abandonment under Section
7(b) of the
Natural Gas Act
Ini tiate Pre-Filing
– Feb. 20, 2015
File Formal
FERC
Application –
Sept., 2015
Receive FERC certificate –
November 2016
U.S. Army Corps of Engineers
(USACE)
o New England
District –
Regulatory Div ision o New York District –
Regulatory Div ision
Required Permit:
o Section 10
Rivers and
Harbors Act o Section 404
Clean Water
Act (CWA)
Sept. 2015 Jan. 2017
Reminder: All federal authorizations should be filed at the time of the FERC application, or discussed why it was not
Include facilities in the cumulative impact discussion
Non-Jurisdictional Facilities
Describe each facility and provide map(s)
Provide correspondence with other agencies (ESA and Section 106)
Identify federal permits required and who has regulatory authority
Topographic maps
Photo-based alignment sheets
Right-of-way configuration & cross section drawings
Plot/site plan
Mapping
Topographic Map
Minimum Scale: 1:24,000/1:25,000 covering 0.5-mile-wide corridor
Key Elements: all project facilities, work areas, and access roads; mileposts
Photo-Based Alignment Sheet
Minimum Scale: 1:6,000 covering 0.5-mile-wide corridor
Key Elements: all project facilities, work areas, and access roads; temporary and permanent ROW; mileposts; survey corridor; resources and features crossed; property boundaries; tract numbers
Recommend clear identification of wetlands and waterbodies using color coding
ROW Configuration & Cross-Section Drawing
Minimum Scale: none
Typical Drawings: temporary and permanent ROW configurations;
collocation, overlap, and offsets; road, railroad, utility, waterbody, and wetland crossings
For illustration purposes only.
Examples can be found on eLibrary.
Facility/County Mileposts Length
(mi.)
Existing ROW
Relationship of
Proposed
Pipeline to
Existing ROW
Overlap of
Proposed ROW with Existing
ROW (ft.)
30-inch pipeline
Calumet County 0.0 – 6.5 6.5 ATC Power Line West 50
6.5 – 8.9 2.4 None N/A N/A
8.9 – 12.3 3.4 ATC Power Line North 50
12.3 – 16.0 3.7 ANR Pipeline West 25
16.0 – 18.2 2.2 ANR Pipeline East 25
20-inch pipeline
Brown County 0.0 – 3.3 3.3 None N/A N/A
3.3 – 3.5 0.2 South Overland
Road
East 0
Total Collocated 16.0 (73.7%)
Right-of-Way Orientation and Overlap
For illustration purposes only. Examples can be found on eLibrary.
Additional Options May Include:
Insert additional line items for greenfield segments to avoid gaps in mileposts
Insert additional column identifying applicable ROW configuration drawing
Plot Plan/Site Plan
Minimum Scale: 1:3,600
Key Elements: non-linear construction areas, temporary and permanent disturbance, access roads, mileposts, associated non-jurisdictional facilities, fence line, facility configuration (avoid labeling sensitive components such as control room)
For illustration purposes only.
Examples can be
Additional Considerations
Additional Information Stakeholder Outreach
• Description of outreach activities conducted and summary of open houses
Cumulative Impacts
• Stand-alone analysis or addressed by resource in each resource report
• Evaluates the past, present, and future development and the potential for additive or synergistic effects
• The area of potential cumulative impact varies depending on the resource
Common Omissions
Inconsistent or inappropriate purpose and need
Location and overlap relative to other rights-of-way
Inadequate maps and discussion of non-jurisdictional facilities
Updated mailing list and status table of permits
Inadequate description of special construction methods/timing
Inconsistent accounting of acreages
Knowledge Check 10
What would FERC ask if Oceanview Pipeline Company presented the following statements in Resource Report 1?
1. The Project’s purpose is to provide energy to Florida.
2. We plan to only use standard construction techniques.
3. The Project’s impacts are minor and would not be detectable;
therefore, we are not evaluating cumulative impacts.
4. We’re planning on having the Project in-service by 2027.
5. We’re planning daytime construction (7am to 10 pm).
6. We used a different scale for our alignment sheets.
7. We do not plan to apply for any local permits.
8. We haven’t applied for our federal permits because the U.S. Army
Corps of Engineers asked us to hold off filing for six months.
9. We cross some federal land.
RR 10: Alternatives
S it e lt e rn a ti ve sR o u te e rn a ti ve s
N o
-A c ti o n e rn a ti ve
Consequences
Environmental impacts avoided
S ys te m e rn a ti ve s New pipeline system
Existing pipeline system(s)
Alternative configurations
Additional compression
Existing system interconnections
Major route alternatives
Route variations or deviations
Landowner and stakeholder requests
Major aboveground facility sites
18 CFR §380.12(l)
Route Alternative Map
Minimum scale: none
Key Elements: proposed route and facility locations, alternate route and facility locations
For illustration purposes only. Examples can be
Routing Factors
Length and acres of construction and operation impact
Collocation vs. greenfield
Quantity and quality of affected wetlands & waterbodies
Land uses (e.g., forest land, developed land, etc.)
Nearby residences and other structures
Environmental Justice communities
In-street construction
Public lands
Soils/geological concerns
T&E and cultural resource considerations
Constructability and other engineering factors
Siting Factors
Property size
Availability of land
Acres of construction and operation impact
Land uses (e.g., forest land, developed land, etc.)
Quantity and quality of affected wetlands & waterbodies
Noise and proximity of NSAs and densely populated areas
EJ communities
Soils/geological concerns
Air quality issues
Visibility and visual resources
T&E and cultural resource considerations
Access road length and street access
Constructability, slope, and other engineering factors
Comparison Item Unit Proposed Route Alt. 1 Route Alt. 2
Facility Requirements
Pipeline Length miles 172 206 218
Greenfield Construction miles 2.5 17.4 23.1
Compression hp 41,200 36,700 36,100
Land Requirements
Construction acres 2,080 2,508 2,651
Operation acres 1,255 1,510 1,590
Environmental Considerations
Waterbodies no. 125 132 158
Wetlands acres 8.9 20.9 21.8
Public Lands no. 0 2 1
Forested Areas acres 14.3 15.6 15.6
Developed Land
Structures within 100’ acres no.
20.6
19.2
21.3
Typical Route Alternatives Comparison Table
Alternatives Analysis
Common Omissions
Inconsistent scope relative to purpose & need statement
Insufficient documentation of initial siting evaluations and discussion of alternatives adopted during pre-filing
Inadequate evaluation of system alternatives
Table omissions/inconsistencies
Inadequate maps (labeling & MPs)
Inadequate scope of analysis (e.g., failure to address alternatives identified by stakeholders)
Appropriate comparison of routes
Impact Analysis
Reasoning for alternative (i.e., what is it trying to avoid or minimize?)
Description of alternatives
Written & tabular comparison to proposed action
Discussion and conclusions
Knowledge Check 11
A landowner recommended the red alternative to the Oceanview Pipeline Expansion Project during scoping, but has not allowed access to their property. The landowner indicates the alternative would avoid sensitive areas around the Milinga Reservoir.
What would FERC expect in the following situations?
1. Oceanview dismisses the alternative without an analysis because they have already completed surveys.
2. Oceanview has provided a table with its survey data, comparing it to the desktop data available for the alternate route.
3. Oceanview’s analysis concludes an alternative is better.
4. Oceanview shows an analysis that compares the alternative from different starting and ending points as compared to the proposed route, showing the alternative to have much greater impact.
RR 2: Water Use and Quality
18 CFR §380.12(d)
Wetlands
Federal jurisdiction
Temporary vs.
Permanent Impacts
Mitigation
Modifications from FERC Procedures
Aquifers
Wellhead protection…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .