D.1 Statement of Need.pdf

PDF 255 KB Posted

Attached to
6632--Automated Cytology CPT
Solicitation number
36C24826AP3075
Issued by

About this file

This is a Statement of Need for an Automated Cytology Processing System to be procured by James A. Haley Veterans' Hospital in Tampa, Florida.

The contractor must provide FDA-approved automated cytology processing systems, reagents, and supplies capable of processing monolayer cellular material using liquid-based ThinPrep technology for cytological examination. The contract requires delivery of one Hologic ThinPrep 5000 Processor and one Hologic ThinPrep Genesis with slide printer (or equivalent name brand equipment), both new, with 50% billing at delivery and 50% upon installation completion. The contractor must furnish all reagents and supplies sufficient for a minimum of 30 days of operation, with estimated annual processing volume of 2,000 GYN ThinPrep Pap tests and 7,000 non-gynecological ThinPrep specimens. A detailed kit and supplies list with manufacturer part numbers is specified. The contractor is responsible for complete system installation, on- and off-site training for at least two key operators plus one additional training slot annually, equipment validation with comprehensive assay performance studies (accuracy, linearity, precision, calibration verification, sensitivity, reference range, therapeutic range, and carryover studies per CLSI standards), delivery at no additional charge, and return shipping at contract end. The contractor must provide preventative maintenance per manufacturer specifications within 2 weeks of due dates and full on-site technical support Monday-Friday, 8am-5pm with 3-day response time, plus 24/7 telephone support with 1-hour callback. Emergency supply delivery must be within 24 hours at no cost if supplies are defective or contractor failed routine delivery requirements. Standard acceptable performance is defined as 30 consecutive calendar days without prolonged downtime (>4 hours) more than 3 times or more than 10 instances of any downtime within 30 days; equipment with 10% or greater downtime in one calendar month may be replaced at government request. Data management systems must not interface to VA network but must provide test record storage with instrument identification capabilities. The contractor must comply with extensive VA information security, privacy, and records management requirements including Federal Records Act compliance, Privacy Act provisions, HIPAA standards, background investigations for all personnel with VA system access (National Agency Check with written inquiries at contractor expense), and liquidated damages of $37.50 per affected individual for any data breach involving sensitive personal information.

View the file

Other files

File Type Posted
P03 Single Source Justification MPT to SAT_Redacted.pdf PDF
36C24826P0663_1.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF NEED

TITLE: Automated Cytology Processing System CPT

I. SCOPE:

The Contractor shall provide Food and Drug Administration (FDA) approved automated cytology processing systems, reagents and supplies capable of processing a monolayer of cellular material (Thin-Prep) using liquid-based technology on patient specimens for cytological examination used for diagnosis and treatment of malignancies and disease at the James A. Haley Veterans’ Hospital, Department of Pathology and Laboratory Medicine Service (P&LMS) located at 13,000 Bruce B. Downs Blvd., Tampa, Florida 33612.

All work is to be performed in accordance with the guidelines established by Federal, State, and local ordinances.

FDA and manufacturer's guidelines, with all terms, conditions, provisions, schedules, and specifications provided herein. The Contractor selected is responsible for system installation, maintenance coordination and supply procurement for all equipment.

II. GENERAL REQUIREMENTS:

A. The contractor is required to furnish all of the following:

1. All reagents and supplies, as applicable, necessary to operate the contractor's equipment, including calibration material, reagents, linearity testing material, test control material, disposables, consumables, cleaning solutions, diluent solutions, sheath fluids, and any instrument part required for operating all analyzers and equipment.

ADDITIONAL NOTES:

Contractor shall provide enough reagents sufficient to perform processing for a minimum of 30 days.

Reagent quality must be high enough to satisfy proficiency testing of the College of American Pathologists and the Joint Commission.

Contractor to provide all reagents, calibrators, and controls needed along with technical assistance to perform correlation studies from a single lot at no additional cost for new test methods or changes in test menus. (i.e., Contractor is to provide all manpower and reagents/supplies to do correlation studies).

2. On- and/or Off-site training for end users and key operators.

3. Delivery and installation of equipment at no additional charge as well as return shipping costs at end of contract (removal).

4. All applicable consumables necessary to operate the contractor's equipment based on an estimated annual sample processing volume of 2,000 GYN (ThinPrep Pap Tests) and 7,000 ThinPrep Non- Gynecological specimens.

Kit Description Manufacture Part #

ThinPrep Pap Test Kit – Includes 500 tests and 500 Rovers Combi Brush collection devices per box 70096-007

Laboratory Kit – Includes 500 filters and 500 slides 70137-001

Physician’s Kit - Includes 500 vials and 500 Broom-like collection devices 70136-001

Physician’s Kit - Includes 500 vials and 500 Cytobrush/Plastic Spatula collection devices 70136-002

Physician’s Kit - Includes 500 vials and 500 Rovers Combi Brush collection devices 70136-003

Broom-like Collection Devices, 500 per box 70101-001

PreservCyt Solution, 32 oz bottles 0234004

PRESERVCYT 100 PACK VIAL (NON-GYN) ASY-14756

CYTOLYT CUPS, 50 PACK, (US/CAN) 0236004

CYTOLYT CUPS, 50 PACK, US/CAN ASY-15207

CYTOLYT TUBES, 80 PACK, US/CAN ASY-15208

ThinPrep Microscope Slides – 100 slides per box 70372-001

UroCyte Kit 71003-001

FILTER, THINPREP UROCYTE 100 PACK 70472-001

ThinPrep Stain Implementation Kit ASY-14760

UroCyte Collection Kit 70908-001

THINPREP MICROSCOPE SLIDES UROCYTE, 100 PACK 70471-001

UroCyte Software 70987-001

5. Contractor to perform equipment and assay installation including full validation of system hardware and software as well as assay performance studies, as applicable, (assay correlations to existing instrumentation, carryover, linearity, dilution validation, precision, accuracy, reference range studies, and normal range studies).

a. Accuracy studies for each analyte. A minimum of 30 samples, spanning the reportable range, will be run by the present and the new contracted method. Contractors will analyze numbers and provide statistical data to accept the new method. Statistics will consist of at least mean, bias, slope, y-intercept, correlation coefficient, analysis, and meet current standards defined by CLSI.

b. Linearity analysis will be performed on new contracted instrument(s) for each analyte to determine reportable range. A 5-point linearity analysis that adheres to the Beer- Lambert Law should be performed as a minimum.

c. Precision study utilizing normal and abnormal control material will be performed. This should consist of a within run precision study of 10 normal and 10 abnormal controls and a day-to-day precision study of normal controls and abnormal controls for 10 days (may be ran twice a day) for a total of 20 values per level of control.

d. Calibration verification will be performed using samples of known value. These can be calibrators or CAP assayed survey samples, or equivalent.

e. Sensitivity: Sensitivity may be validated concurrently with the linearity verifications.

f. Reference Range: Determine a reference range for each analyte following CLSI guidelines. Samples used for the reference range study shall be representative of the patient population being tested.

Reference range assessment shall be performed for each lab. One of the following protocols should be used:

1) A verification of the manufacturer's suggested reference range may be performed as long as the suggested range is based on a comparable population of test subjects. The manufacturer shall provide specific information defining how the suggested range was determined. A minimum of 20 reference individuals shall be used to verify the manufacturer's range. Any apparent outliers should be discarded and new specimens obtained to provide a statistically valid verification.

2) If the suggested manufacturer's range is not appropriate for the patient population, a reference range shall be established. Establishing a reference shall follow CLSI guidelines. This requires a minimum of 120 reference individuals be used to establish a reference range. The reference interval should be determined using the nonparametric method.

3) If a laboratory is currently using the proposed instrument/reagent system, the "in-use" reference range can be transferred to the "new" system if a method comparison study between the two systems proves to be acceptable. If comparison studies are not acceptable, then an alternate test shall be provided.

g. Therapeutic range validation studies shall be performed by Contractor for applicable analytes, using CLSI guidelines.

h. Carryover studies shall be performed, as applicable, as part of the initial evaluation of the instrument. Contractor will provide interpretation of raw data for each instrument installed and validate no carryover exists within the test platforms.

i. All technical procedures shall be provided by Contractor on diskette in CLSI format, using software compatible with each Laboratory's computer system, for local modification to meet CAP requirements.

6. All shipping costs for reagents, consumables, supplies and equipment (installation and removal at the end of contract) including delivery to the clinical laboratory at all sites. Note: including emergency, overnight delivery as necessary, excluding fault by the government for appropriately managing on-hand inventory.

7. Special handling for emergency orders of supplies: If the supplies are found to be defective and unsuitable for use with the Contractor’s equipment, or the Contractor has failed to comply with the requirements for routine supply delivery, the Contractor is required to deliver the supplies within 24 hours of receipt of a verbal order for emergency delivery. If either circumstance has occurred, the Contractor shall deliver to the Government site in the most expeditious manner possible without additional cost to the Government, the necessary consumables in sufficient quantity as required to allow operation of the Contractor’s equipment for one week (under normal Government test load volume). If additional requests for emergency supply delivery are required by the Government, they shall be honored by the Contractor until the arrival at the laboratory of the monthly standing order/routine supplies delivery with no shipping expenses.

III. EQUIPMENT – SYSTEM TECHNICAL SPECIFICATIONS AND FEATURES:

A. The vendor must provide NAME BRAND OR EQUIVALENT for all of the following equipment:

1. One (1) Hologic® ThinPrep 5000 Processor

2. One (1) Hologic® ThinPrep Genesis with slide printer NOTE: Equipment to be billed as a separate line item: 50% at the time of delivery and 50% at the completion of installation and following the acceptance for use.

B. General System Requirements – Hologic ThinPrep 5000 Processor:

1. All equipment provided must be new.

2. Dimensions (W x D x H): 34´x 26” x 22”

3. Must be a “walk-away” system for up to 45 minutes.

4. Capacity: Up to 20 vials, slides, and filters.

5. Sample Types: ThinPrep Pap, Non-Gyn (PreservCyt Solution), UroCyte samples.

6. Full automation for hands-free operation, automatic vial uncapping, barcode scanning, laser slide etching (for

ID/data), continuous loading/unloading.

7. Interface with Intuitive touchscreen and real-time status.

8. Methodology: efficiently transfers cells from a liquid sample onto a filter, then creates a uniform layer on a glass slide, and automatically places it into a fixative, all while maintaining sample integrity and providing data tracking.

9. An electronic operator’s manual shall be furnished with each instrument installed.

C. General System Requirements – Hologic® ThinPrep Genesis with Slide Printer:

1. All equipment provided must be new.

2. Dimensions (W x D x H): 19ʺ x 14ʺ x 23ʺ

3. Automation to include uncapping/recapping vials, sample aliquoting, tube/slide printing.

4. Sample Types: Gynecological (Pap), Non-Gyn (urine, body fluid, etc.), and UroCyte samples

5. closed-cap dispersion for safety

6. An electronic operator’s manual shall be furnished with each instrument installed.

7. Slide Printing: Laser prints slides with barcodes (1D/2D DataMatrix, QR) and sample IDs, linking to LIS

8. Barcode Support: Reads Code 128, I2 of 5, Code 39, DataMatrix, QR codes

IV. SYSTEM DATA MANAGEMENT HARDWARE / SOFTWARE

A. System shall NOT interface instruments to the VA network.

B. The system shall have a capability for data management with test record storage, including instrument identification used for testing.

C. Shall include all software, software licenses, and hardware (e.g., operating systems, printers, printer drivers, monitors, UPS, etc.) required for complete system operations. Result, calibration and quality control reports must be available to be printed.

V. PREVENTATIVE MAINTENANCE:

A. The contractor shall provide maintenance, at their expense (travel, labor and parts), to keep the equipment in good operating condition and subject to security regulations. The government shall provide the contractor access to the equipment to perform maintenance services.

B. The preventive maintenance shall be of a frequency that conforms to the manufacturer's operation and maintenance instructions for the supported equipment. Preventative maintenance tasks must be completed within 2 weeks of the due date, based on the date of the previously completed task.

VI. SERVICE AND SUPPORT

A. Contractor shall provide full service on-site technical support, Monday – Friday, excluding federal holidays, 8am- 5pm, for all equipment to keep the equipment in good operating condition and subject to security regulations.

Response time within 3 days from date of call.

B. Telephone technical support shall be available 24 hours/day, 7 days/week with follow up on all calls within one hour of initial call. Following determination that service is required, technical on-site support must be provided within 24 hours.

C. The contractor will provide all parts and labor needed to repair the malfunction.

D. Travel, per diem and other expenses associated with the repair will be borne by the contractor.

E. The contractor shall furnish a comprehensive malfunction incident report to the installation upon completion of each maintenance call. The report shall include, at a minimum, the following: (a) date and time of notification (b) date and time of arrival (c) serial number type and model numbers(s) of equipment (d) time spent for repair, (e) description of malfunction and (f) proof of repair. Parts (e) and (f) shall be written verification of quality control of the sample run.

F. During the contract period, should the repair record of any laboratory equipment reflect a downtime of 10% or more of the normal working days in one calendar month, a determination will be made by the contracting officer representative (COR) of the government to request a replacement the initial laboratory equipment with new equipment.

G. Credit for Prolonged and/or Frequent Equipment Malfunction/Downtime: If a piece of equipment remains inoperative (unable to process patient specimens, perform patient testing, and/or report a valid test result) due to a malfunction through no fault or negligence of the government for a total of 48 hours consecutive hours or more, the contractor shall be assessed damages at the rate of 1/30 of the preceding average three month CPRR billings times the total number of days certified as downtime for each incident. The downtime shall start from the time the user makes a bona fide attempt to contact the contractor's designated representative (technical support hotline) until the equipment is returned to good operating order.

H. Computer Patient Data Handling: No hardware, containing any VA patient information is to be removed from either location, without the approval and removal of data by the VA Information Technology Department. Failure to comply with this VA requirement may result in prosecution.

I. Failure Mean Time Disclosure: The contractor will state the failure mean time (between failure and mean time to repair) for each piece of equipment offered. In addition, the Contractor will help establish normal ranges. The Contractor will provide emergency backup equipment. Only instruments which are FDA approved will be considered and shall be operational and interface with VA laboratory computer systems and upgrades. This shall be a "tum-key" system.

J. Operator Procedure Manuals: Operator and Service manuals along with CLSI procedures shall be furnished for each instrument model supplied.

VII. DELIVERY, PERFORMANCE, INSPECTION AND ACCEPTANCE:

A. General:

1. The Contractor is responsible for performing all inspections and tests necessary to substantiate that the equipment, supplies and services furnished under the contract conform to contract requirements. The VA has the right to test all services ordered under the contract at all times and places throughout the term of the contract Government testing and inspection will not unduly delay any Contractor work being performed nor will it create a defect in services covered by this contract.

2. The VA reserves the right to thoroughly inspect and investigate the contractor and manufacturer business reputations and other qualifications, and to reject any bid, irrespective of price, that shall be administratively determined lacking in any of the essentials necessary to assure acceptable standards of performance.

3. Request for upgrades or replacement hardware/software, due to workload increase, excessive instrumentation failures will be evaluated as needed or at least annually with communication to the Contractor for modification of the contract. A high incidence of such problems with any equipment/analyzer or assay within the test menu supplied may indicate probable non-compliance with the terms of this contract and will entitle the government to its replacement with other analyzer(s) that can produce the required criteria of this contract satisfactorily

a. “Downtime” is defined as any time the equipment is not available for patient testing due to malfunction, unacceptable quality control, software system errors, or hardware failures. This includes time used for end-user troubleshooting, conversations with technical support or on-site engineer repair/support.

Downtime for each incident shall start from the time the government makes a bona fine attempt to contact the contractor's designated representative at the prearranged contact point until the system or machine(s) is returned to the government in proper operating condition.

b. Standard acceptable performance for the life of the contract is defined as a period of 30 consecutive calendar days by operating in conformation with the contractor's technical specification without prolonged downtime (>4 hours) per instance more than 3 times within 30 days or more than 10 instances of downtime (of any length of time) within 30 days. In the event the equipment or an assay does not meet the standard acceptable performance for 30 consecutive days, the government will notify the contractor of the ongoing unacceptable performance, and the performance will be monitored for an addition 90 consecutive days. If after 120 calendar days from the initial date of unacceptability, the vendor does not resolve the performance concerns to meet the government’s expectations, the government, through the contracting officer, may request a replacement of the equipment / assay or terminate the order upon mutual agreement.

c. Removal of the existing instrument by the Contractor shall be performed within 30 days following the acceptance of replacement equipment without additional charge to the government.

d. Enhancements to the contractor's equipment shall be delivered to the government site and installed by the contractor within 60 days of their issuance or date of first commercial availability.

e. The Contractor shall provide all upgrades to the equipment hardware and operating system software without additional charge to the government as necessary to ensure compliance with vendor and VA specifications.

4. Returned goods: The VA is responsible for inspecting all products shipped here under and will give the contractor written notice of rejection within thirty (30) calendar days following receipt or installation by the contractor.

5. Government's Responsibility: The trained user will perform routine operation maintenance and cleaning as required in the manufacturer's operation and maintenance instructions. The user shall maintain appropriate daily records to satisfy the requirements of this paragraph.

B. Equipment:

1. The contractor is required to provide new state-of the art equipment. Previously used or discontinued models are not acceptable.

2. Site Preparation: Site preparation specifications shall be furnished in writing by the contractor as a part of the equipment proposal. These specifications shall be in such detail as to ensure that the equipment to be installed shall operate efficiently and conform to the manufacturer's claimed specifications.

3. Space Requirements, System Specifications, etc.:

a. System specifications shall all be disclosed in the proposed space with limited adjustments. These specifications shall be in such detail as to ensure that the equipment to be installed shall operate efficiently and conform to manufacturer’s claimed specifications. Crossover from current to new instrumentation shall be performed timely with no interruption in patient care laboratory services.

b. The government shall prepare the site at its own expense and in accordance with the specifications furnished by the contractor.

c. Any alterations or modifications in site preparation which are attributable to incomplete or erroneous specifications provided by the contractor which involve additional expense to the government, shall be made at the expense of the contractor.

4. Acceptance will normally be consummated upon delivery and, when applicable, following installation and completion of personnel training.

5. The VA reserves the right to request a ninety (90) day test and evaluation of all pieces of equipment prior to placing a delivery order under the contract. If the test and evaluation is not successful as determined by the CO and COR, the VA will not be required to continue with placing a delivery order under this contract, and no default or penalty will accrue.

6. The contractor shall be responsible for installation, which consists of in-house delivery, positioning and mounting of all equipment listed on the delivery order and connections of all equipment and interconnecting wiring and cabling if applicable. Upon receipt of notice to proceed with installation, it shall be the contractor's responsibility to inform the Contracting Officer of any problems which may be anticipated in connection with installation, or which will affect optimum performance once installation is completed. If progress of the installation is interrupted through no fault of the contractor, the continuous installation referenced in the preceding paragraphs may be terminated until such time as the cause of delay has been eliminated and then shall be resumed within 24 hours after the contractor has been notified that work may again proceed.

7. Upon completion of installation the equipment will be turned over to the hospital for use. Final acceptance of the equipment and installation will be based upon an inspection and test to be performed within ten (10) calendar days from date of installation. If equipment passes inspection or if acceptance inspection is not conducted within ten (10) calendar days from installation, the Government shall accept installation with guaranteed date commencing ten calendar days after installation.

8. The contractor will provide all operational upgrades to the equipment’s hardware and operating system software that materially affects the performance of the equipment, without additional charge to the government. These enhancements to the contractor's equipment shall be delivered to the government site and installed by the contractor within 60 days of their issuance or date of first commercial availability.

9. Ownership of Equipment shall remain with the contractor. All equipment accessories (hardware and software) furnished by the contractor shall accompany the equipment when returned to the contractor. The contractor, upon expiration of order(s) at termination and/or replacement of equipment, will remove the equipment. The contractor will disconnect the equipment and will be responsible for all packing and shipping required to remove the equipment within ten business days. The hard drive will remain within the VA.

C. Reagents / Supplies / Consumables:

1. The VA shall require the delivery of reagents for all services required under this contract. The contractor shall deliver reagents, shipping cost included, as needed (including emergency over-night delivery orders) from CALL orders within 24 hours.

2. The contractor will assure that all supplies provided/ordered for use on their equipment will be of the quality necessary to produce a quality result. The reagent quality must be high enough to satisfy proficiency testing standards of the College of American Pathologists (CAP) and The Joint Commission.

3. In the event that the supplies, to include consumables, are found to be defective and unsuitable for use with the contractor's equipment or the contractor has failed to comply with the requirements herein, the contractor is required to deliver the supplies within 24 hours of receipt of the verbal order for priority delivery from the government activity. This will be done at no cost to the government and in sufficient quantity as required to allow operation of the contractor's equipment for one week (under normal government test load volume).

4. The Contractor is required to provide a continuously stocked inventory of reagents, calibrators, troubleshooting controls, required consumable supplies including all routinely replaced parts, disposables and any other materials required to properly perform tests on the equipment. Unexpected changes in methodology or technology will be at the expense of the Contractor. Alert and Notification of all technical advisory recalls and, or alerts, prior to or simultaneously with field alerts should be forwarded to Laboratory Supervisor and the Laboratory Manager. On or about the first day of each month, the contractor will ensure that each site is furnished with sufficient consumable supplies to produce a volume of tests for that month. Separate deliveries of products will be shipped to each testing site, as applicable. Failure to reserve adequate inventory will result in default.

5. In the event that the supplies / consumables are found to be defective and unsuitable for use with the contractor's equipment or the contractor has failed to comply with the requirements herein, the contractor is required to deliver the supplies within 24 hours of receipt of the verbal order from the government activity, if verbal order is received by 1 pm EST time. This will be done at no cost to the government, in sufficient quantity as required to allow operation of the contractor's equipment for one week (under normal government test load volume). The Contractor shall reimburse each facility for any costs/supplies related to tests performed by another Contractor or sent to a referral laboratory when reagents were not available due to product issues or instrumentation failure.

6. Items Included: The Contractor shall provide all routine and specialty items required to operate and maintain the equipment analyzer in optimal condition, such as but not limited to, standards, controls, calibrators, chemical test strips, printers, consumable equipment parts, and required replacement parts for maintenance or service. Any items excluded by the Contractor but required for operation of the system at any time, shall be delineated in their technical proposal. The cost of the any excluded items shall be disclosed in the price proposal.

7. If additional requests for emergency supply delivery are required by the government, the contractor shall honor them until the arrival of the monthly standing order and routine supplies are delivered.

8. All deliveries (routine and emergent) of reagents, supplies, consumables must be delivered directly to the laboratory at the expense of the contractor.

VIII. TRAINING

A. The contractor, without additional charge to the government, shall provide training on- and/or off-site for at least two (2) key operating personnel per instrument module installed and all automation system components at the time of installation of the contractor's equipment. The contractor will also supply one (1) additional key operator training slots per year throughout the life of the contract.

B. The contractor shall provide supplemental operating training to (2) two government personnel, without additional charge to the government, upon installation of an upgrade in equipment hardware or operating system software connected with the operation of an instrument already furnished.

C. Contractor shall provide, install, and train users on the data management system with either on- or off-site training. Additional training will be provided for 2 additional operators throughout the life of the contract.

D. Training of Operating Personnel: The contractor shall provide the services of a qualified technical person, at the time of equipment installation and at such time designated by Contracting Officer (CO) or Contracting Officer's Representative (COR) to on-site orientation and training to designated personnel in: operation and care of equipment; techniques and procedures recommended by manufacturer to achieve maximum dependable, efficient, and economical utilization of equipment. This training shall include actual demonstration and operation of the equipment including any adjustments or other actions which may be undertaken by operating personnel in the event of failure of equipment, provided that such adjustment or action will in no way jeopardize the Government's rights under contract guarantee clause. This training shall include at least (2) two-day on-site training sessions, all day, upon installation and acceptance of equipment and later, for refresher training.

IX. REGULATORY REQUIREMENTS: If the product(s) included in this solicitation are considered medical devices by the US

Food and Drug Administration, the manufacturer shall be in compliance with the Food, Drug and Cosmetic Act, as amended, and regulations promulgated there under.

X. TECHNICAL INDUSTRY STANDARDS: The contractor certifies that all applicable equipment offered under this contract shall conform to all common industry standards.

XI. MANUFACTURED PRODUCTS: Materials furnished shall be the current productions of manufacturers regularly engaged in manufacture of such items. Approval by Contracting Officer is required of deviation from products and manufacturers as shown in the schedule of items. Shelf-life of all consumables shall be at least ONE YEAR from shipping date unless FDA requires different expiration date.

XII. REFERENCE SPECIFICATIONS AND PUBLICATIONS: Where an item is required to conform to certain requirements, conformance shall be evidenced by seal, label, stamp, or approval listing from such agency, or by a certified test report from an independent testing laboratory acceptable to the Government, that the item has been tested and conforms to requirements of referenced agency.

XIII. RECALLS: If at any time during the term of the contract, the FDA or the Contractor, or subcontractor initiates an item recall or FDA withdraws its approval to manufacture an item, the contractor will issue a notice to indicate the complete item description and identification of the recall with necessary instructions for return for credit or replacement.

XIV. RECORDS MANAGEMENT OBLIGATIONS

a) Applicability: This clause applies to all Contractors whose employees create, work with, or otherwise handle

Federal records, as defined in Section B, regardless of the medium in which the record exists.

b) Definitions:

1) “Federal record” as defined in 44 U.S.C. § 3301, includes all recorded information, regardless of form or characteristics, made or received by a Federal agency under Federal law or in connection with the transaction of public business and preserved or appropriate for preservation by that agency or its legitimate successor as evidence of the organization, functions, policies, decisions, procedures, operations, or other activities of the United States Government or because of the informational value of data in them.

2) The term Federal record:

includes James A. Haley Veterans’ Hospital Network records.

does not include personal materials.

applies to records created, received, or maintained by Contractors pursuant to their James A. Haley network contract.

may include deliverables and documentation associated with deliverables.

c) Requirements:

1) Contractor shall comply with all applicable records management laws and regulations, as well as National

Archives and Records Administration (NARA) records policies, including but not limited to the Federal Records Act (44 U.S.C. chs. 21, 29, 31, 33), NARA regulations at 36 CFR Chapter XII Subchapter B, and those policies associated with the safeguarding of records covered by the Privacy Act of 1974 (5 U.S.C. 552a). These policies include the preservation of all records, regardless of form or characteristics, mode of transmission, or state of completion.

2) In accordance with 36 CFR 1222.32, all data created for Government use and delivered to, or falling under the legal control of, the Government are Federal records subject to the provisions of 44 U.S.C. chapters 21, 29, 31, and 33, the Freedom of Information Act (FOIA) (5 U.S.C. 552), as amended, and the Privacy Act of 1974 (5 U.S.C. 552a), as amended and must be managed and scheduled for disposition only as permitted by statute or regulation.

3) In accordance with 36 CFR 1222.32, Contractor shall maintain all records created for Government use or created in the course of performing the contract and/or delivered to, or under the legal control of the Government and must be managed in accordance with Federal law. Electronic records and associated metadata must be accompanied by sufficient technical documentation to permit understanding and use of the records and data.

4) James A. Haley Veterans’ Hospital Network and its contractors are responsible for preventing the alienation or unauthorized destruction of records, including all forms of mutilation. Records may not be removed from the legal custody of James A. Haley Veterans’ Hospital Network or destroyed except for in accordance with the provisions of the agency records schedules and with the written concurrence of the Head of the Contracting Activity. Willful and unlawful destruction, damage or alienation of Federal records is subject to the fines and penalties imposed by 18 U.S.C. 2701. In the event of any unlawful or accidental removal, defacing, alteration, or destruction of records, Contractor must report to James A. Haley Veterans’ Hospital Network. The agency must report promptly to NARA in accordance with 36 CFR 1230.

5) The Contractor shall immediately notify the appropriate Contracting Officer upon discovery of any inadvertent or unauthorized disclosures of information, data, documentary materials, records or equipment. Disclosure of non-public information is limited to authorized personnel with a need-to-know as described in the contract.

The Contractor shall ensure that the appropriate personnel, administrative, technical, and physical safeguards are established to ensure the security and confidentiality of this information, data, documentary material, records and/or equipment is properly protected. The Contractor shall not remove material from Government facilities or systems, or facilities or systems operated or maintained on the Government’s behalf, without the express written permission of the Head of the Contracting Activity. When information, data, documentary material, records and/or equipment is no longer required, it shall be returned to James A. Haley Veterans’ Hospital Network control or the Contractor must hold it until otherwise directed. Items returned to the Government shall be hand carried, mailed, emailed, or securely electronically transmitted to the Contracting Officer or address prescribed in the contract. Destruction of records is EXPRESSLY PROHIBITED unless in accordance with Paragraph (4).

6) The Contractor is required to obtain the Contracting Officer's approval prior to engaging in any contractual relationship (sub-contractor) in support of this contract requiring the disclosure of information, documentary material and/or records generated under, or relating to, contracts. The Contractor (and any sub-contractor) is required to abide by Government and James A. Haley Veterans’ Hospital Network guidance for protecting sensitive, proprietary information, classified, and controlled unclassified information.

7) The Contractor shall only use Government IT equipment for purposes specifically tied to or authorized by the contract and in accordance with James A. Haley Veterans’ Hospital Network policy.

8) The Contractor shall not create or maintain any records containing any non-public James A. Haley Veterans’ Hospital Network information that are not specifically tied to or authorized by the contract.

9) The Contractor shall not retain, use, sell, or disseminate copies of any deliverable that contains information covered by the Privacy Act of 1974 or that which is generally protected from public disclosure by an exemption to the Freedom of Information Act.

10) The James A. Haley Veterans’ Hospital Network owns the rights to all data and records produced as part of this contract. All deliverables under the contract are the property of the U.S. Government for which James A. Haley Veterans’ Hospital Network shall have unlimited rights to use, dispose of, or disclose such data contained therein as it determines to be in the public interest. Any Contractor rights in the data or deliverables must be identified as required by FAR 52.227-11 through FAR 52.227-20.

11) Training. All Contractor employees assigned to this contract who create, work with, or otherwise handle records are required to take [Agency]-provided records management training. The Contractor is responsible for confirming training has been completed according to agency policies, including initial training and any annual or refresher training.

[Note: To the extent an agency requires contractors to complete records management training, the agency must provide the training to the contractor.]

d) Flowdown of requirements to subcontractors:

1) The Contractor shall incorporate the substance of this clause, its terms and requirements including this paragraph, in all subcontracts under this [contract vehicle], and require written subcontractor acknowledgment of same.

2) Violation by a subcontractor of any provision set forth in this clause will be attributed to the Contractor.

XV. VA INFORMATION AND INFORMATION SYSTEM SECURITY/PRIVACY LANGUAGE

a) Access To Va Information and VA Information Systems:

1) Contractors, contractor personnel, subcontractors, and subcontractor personnel shall be subject to the same Federal laws, regulations, standards, and VA Directives and Handbooks as VA and VA personnel regarding information and information system security.

2) A contractor/subcontractor shall request logical (technical) or physical access to VA information and VA information systems for their employees, subcontractors, and affiliates only to the extent necessary to perform the services specified in the contract, agreement, or task order.

3) All contractors, subcontractors, and third-party servicers and associates working with VA information are subject to the same investigative requirements as those of VA appointees or employees who have access to the same types of information. The level and process of background security investigations for contractors must be in accordance with VA Directive and Handbook 0710, Personnel Suitability and Security Program. The Office for Operations, Security, and Preparedness is responsible for these policies and procedures.

4) The contractor or subcontractor must notify the Contracting Officer immediately when an employee working on a VA system or with access to VA information is reassigned or leaves the contractor or subcontractor’s employ. The Contracting Officer must also be notified immediately by the contractor or subcontractor prior to an unfriendly termination.

5) Contractor Personnel Security Requirements:

All contractor employees who require access to the Department of Veterans Affairs’ computer systems shall be the subject of a background investigation and must receive a favorable adjudication from the VA Office of Security and Law Enforcement prior to contract performance. This requirement is applicable to all subcontractor personnel requiring the same access. If the investigation is not completed prior to the start date of the contract the contractor will be responsible for the actions of those individuals that provide or perform work for the VA.

Position Sensitivity – The position sensitivity has been designated as ( low ) risk.

Background Investigation – The level of background investigation commensurate with the required level of access is National Agency Check (NACI) with written inquiries.

Contractor Responsibilities:

The contractor shall bear the expense of obtaining background investigations. If the investigation is conducted by the Office of Personnel Management (OPM), the contractor shall reimburse the VA within 30 days.The web site which provides information on the cost of the security investigation is:

www.opm.gov\extra\investigate – Select Federal Investigations Notices (FIN 01-01) The contractor shall prescreen all personnel requiring access to the computer systems to ensure they maintain a U.S. citizenship and are able to read, write, speak, and understand the English language.

The contractor will provide to the Contracting Officer prior to award the following: (1) List of names of contract personnel. (2) Social security numbers of contractor personnel. (3) Home address of contractor personnel or the contractor address. The Contracting Officer will submit the above information to the Office of Security and Law Enforcement, Washington, D.C. The Office of Security and Law Enforcement will provide the necessary investigative forms (these forms are indicated in paragraph 3.d. below) to the contractor’s personnel, coordinate the background investigations with OPM and notify the Contracting Officer and contractor of the results of the investigation.

The contractor shall submit or have their employees submit the following required forms to the VA Office of Security and Law Enforcement within 30 days of receipt:

Standard From 85P, Questionnaire for Public Trust Positions Standard Form 85P-S, Supplemental Questionnaire for Selected Positions FD 258, U.S. Department of Justice Fingerprint Applicant Chart VA Form 0710, Authority for Release of Information Form

Optional Form 306, Declaration for Federal Employment Optional Form 612, Optional Application for Federal Employment

The contractor, when notified of an unfavorable determination by the Government, shall withdraw the employee from consideration from working under the contract.

Failure to comply with the contractor personnel security requirements may result in termination of the contract for default.

b) VA Information Custodial Language:

1) Information made available to the contractor or subcontractor by VA for the performance or administration of this contract or information developed by the contractor/subcontractor in performance or administration of the contract shall be used only for those purposes and shall not be used in any other way without the prior written agreement of the VA. This clause expressly limits the contractor/subcontractor's rights to use data as described in Rights in Data - General, FAR 52.227-14(d) (1).

2) VA information should not be co-mingled, if possible, with any other data on the contractors/subcontractor’s information systems or media storage systems in order to ensure VA requirements related to data protection and media sanitization can be met. If co-mingling must be allowed to meet the requirements of the business need, the contractor must ensure that VA’s information is returned to the VA or destroyed in accordance with VA’s sanitization requirements. VA reserves the right to conduct on site inspections of contractor and subcontractor IT resources to ensure data security controls, separation of data and job duties, and destruction/media sanitization procedures are in compliance with VA directive requirements.

3) Prior to termination or completion of this contract, contractor/subcontractor must not destroy information received from VA, or gathered/created by the contractor in the course of performing this contract without prior written approval by the VA. Any data destruction done on behalf of VA by a contractor/subcontractor must be done in accordance with National Archives and Records Administration (NARA) requirements as outlined in VA Directive 6300, Records and Information Management and its Handbook 6300.1 Records Management Procedures, applicable VA Records Control Schedules, and VA Handbook 6500.1, Electronic Media Sanitization. Self-certification by the contractor that the data destruction requirements above have been met must be sent to the VA Contracting Officer within 30 days of termination of the contract.

4) The contractor/subcontractor must receive, gather, store, back up, maintain, use, disclose and dispose of VA information only in compliance with the terms of the contract and applicable Federal and VA information confidentiality and security laws, regulations and policies. If Federal or VA information confidentiality and security laws, regulations and policies become applicable to the VA information or information systems after execution of the contract, or if NIST issues or updates applicable FIPS or Special Publications (SP) after execution of this contract, the parties agree to negotiate in good faith to implement the information confidentiality and security laws, regulations and policies in this contract.

5) The contractor/subcontractor shall not make copies of VA information except as authorized and necessary to perform the terms of the agreement or to preserve electronic information stored on contractor/subcontractor electronic storage media for restoration in case any electronic equipment or data used by the contractor/subcontractor needs to be restored to an operating state. If copies are made for restoration purposes, after the restoration is complete, the copies must be appropriately destroyed.

6) If VA determines that the contractor has violated any of the information confidentiality, privacy, and security provisions of the contract, it shall be sufficient grounds for VA to withhold payment to the contractor or third party or terminate the contract for default or terminate for cause under Federal Acquisition Regulation (FAR) part 12.

7) If a VHA contract is terminated for cause, the associated BAA must also be terminated and appropriate actions taken in accordance with VHA Handbook 1600.1, Business Associate Agreements. Absent an agreement to use or disclose protected health information, there is no business associate relationship.

8) The contractor/subcontractor must store, transport, or transmit VA sensitive information in an encrypted form, using VA-approved encryption tools that are, at a minimum, FIPS 140-2 validated.

9) The contractor/subcontractor’s firewall and Web services security controls, if applicable, shall meet or exceed VA’s minimum requirements. VA Configuration Guidelines are available upon request.

10) Except for uses and disclosures of VA information authorized by this contract for performance of the contract, the contractor/subcontractor may use and disclose VA information only in two other situations: (i) in response to a qualifying order of a court of competent jurisdiction, or (ii) with VA’s prior written approval.

The contractor/subcontractor must refer all requests for, demands for production of, or inquiries about, VA information and information systems to the VA contracting officer for response.

11) Notwithstanding the provision above, the contractor/subcontractor shall not release VA records protected by Title 38 U.S.C. 5705, confidentiality of medical quality assurance records and/or Title 38 U.S.C. 7332, confidentiality of certain health records pertaining to drug addiction, sickle cell anemia, alcoholism or alcohol abuse, or infection with human immunodeficiency virus. If the contractor/subcontractor is in receipt of a court order or other requests for the above mentioned information, that contractor/subcontractor shall immediately refer such court orders or other requests to the VA contracting officer for response.

12) For service that involves the storage, generating, transmitting, or exchanging of VA sensitive information but does not require C&A or an MOU-ISA for system interconnection, the contractor/subcontractor must complete a Contractor Security Control Assessment (CSCA) on a yearly basis and provide it to the COR.

c) Security Incident Investigation:

1) The term “security incident” means an event that has, or could have, resulted in unauthorized access to, loss or damage to VA assets, or sensitive information, or an action that breaches VA security procedures. The contractor/subcontractor shall immediately notify the COR and simultaneously, the designated ISO and Privacy Officer for the contract of any known or suspected security/privacy incidents, or any unauthorized disclosure of sensitive information, including that contained in system(s) to which the contractor/subcontractor has access.

2) To the extent known by the contractor/subcontractor, the contractor/subcontractor’s notice to VA shall identify the information involved, the circumstances surrounding the incident (including to whom, how, when, and where the VA information or assets were placed at risk or compromised), and any other information that the contractor/subcontractor considers relevant.

3) With respect to unsecured protected health information, the business associate is deemed to have discovered a data breach when the business associate knew or should have known of a breach of such information. Upon discovery, the business associate must notify the covered entity of the breach. Notifications need to be made in accordance with the executed business associate agreement.

4) In instances of theft or break-in or other criminal activity, the contractor/subcontractor must concurrently report the incident to the appropriate law enforcement entity (or entities) of jurisdiction, including the VA OIG and Security and Law Enforcement. The contractor, its employees, and its subcontractors and their employees shall cooperate with VA and any law enforcement authority responsible for the investigation and prosecution of any possible criminal law violation(s) associated with any incident. The contractor/subcontractor shall cooperate with VA in any civil litigation to recover VA information, obtain monetary or other compensation from a third party for damages arising from any incident, or obtain injunctive relief against any third party arising from, or related to, the incident.

d) Liquidated Damages for Data Breach:

1) Consistent with the requirements of 38 U.S.C. §5725, a contract may require access to sensitive personal information. If so, the contractor is liable to VA for liquidated damages in the event of a data breach or privacy incident involving any SPI the contractor/subcontractor processes or maintains under this contract. However, it is the policy of the VA to forego collection of liquidated damages in the event the contractor provides payment of actual damages in an amount determined to be adequate by the agency.

2) The contractor/subcontractor shall provide notice to VA of a “security incident”…