CTSI Materials RFP_ADDENDUM 1_11.12.2025.pdf

PDF 87 KB Posted

Attached to
RFP MATERIALS PROCUREMENT FOR FIBER OPTIC NETWORK
Solicitation number
S-X21600-00014970
Issued by
Jackson County, Oregon

About this file

This is an addendum to a Request for Proposals issued by the Confederated Tribes of Siletz Indians (CTSI) for materials procurement to support fiber optic network deployment in Oregon. The addendum, issued November 12, 2025, extends the original proposal submission deadline from November 14, 2025, to November 21, 2025, at 4:00 p.m. PST due to requests from interested bidders. The procurement seeks qualified vendors to supply fiber optic network materials including fiber optic cables with strand counts ranging from 1 to 288, multi-port service terminals, aerial fiber storage equipment, support strands, guy wires, anchors, and associated hardware for a broadband infrastructure deployment project targeting Jackson County. All other terms, conditions, and requirements of the original RFP remain unchanged, and proposers are required to acknowledge receipt of Addendum 1 in their cover letters.

The addendum clarifies that detailed OSP fiber material specifications are located in Appendix B of the original RFP, addressing bidder inquiries regarding vague RUS materials references. Proposals must include unit pricing, delivery schedules, logistics plans, and evidence of compliance with industry standards including Telcordia Generic Requirements and International Telecommunication Union specifications. The evaluation process utilizes a 100-point scoring system allocating 35 points to cost competitiveness, 30 points for delivery schedule, 15 points for specifications compliance, 5 points for support and value-added services, and 15 points for Indian preference. The procurement includes specific set-aside provisions and compliance requirements, particularly emphasizing Indian preference and adherence to "Build America, Buy America" provisions, with materials required to meet stringent performance criteria including specific attenuation rates, operational temperature ranges, and a guaranteed 20-year life expectancy when installed according to manufacturer specifications.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Confederated Tribes of Siletz Indians PO Box 549, Siletz, OR 97380

(541) 444-2532 (800) 922-1399 Fax: (541) 444-2307

RFP: MATERIALS PROCUREMENT FOR FIBER OPTIC

NETWORk DEPLOYMENT

ADDENDUM 1

DATE: November 12, 2025

NOTE: PROPOSER SHALL ACKNOWLEDGE RECEIPT OF

ADDENDUM 1 IN THE COVER LETTER OF THE PROPOSAL.

Part 1. Answers to the Questions received by November 7th, 2025.

Question: The RUS materials are fairly vague when we look them up, can you give us more precise OSP fiber material?

Answer: The required material specifications are located in Appendix B of the RFP.

Part 2. Revisions Due Date to the RFP

Due to request from interested bidders, the Confederated Tribes of Siletz Indians is extending the submission deadline the Materials Procurement for Fiber Optic Network.

The original due date of November 14th, 2025 by 4pm PST has been extended by one (1) week. Proposals are now due by November 21, 2025 by 4pm PST.

All other terms, conditions, and requirements of the RFP remain unchanged.

File details come from the government source that posted it. Updated .