These are technical specifications for the Townsend Dwelling Crawlspace Improvements project, detailing comprehensive requirements for renovating a crawlspace. The specifications cover multiple critical aspects of crawlspace rehabilitation, including clean-up/disposal, insulation, vapor retarder installation, and mechanical ventilation. Key technical requirements include:
Specific installation specifications mandate R-15 to R-19 insulation for various components (vent closures, stem walls, rim boards), a Class 1 vapor retarder covering exposed earth, and mechanical ventilation delivering 1 cubic foot per minute of conditioned air per 50 square feet of crawl space floor area. The contractor is responsible for design and construction to create a conditioned crawl space, with all methods and materials subject to Contracting Officer's Representative (COR) approval. Disposal requirements stipulate removing existing materials like siding, trim, fascia, and insulation, with strict instructions to dispose of waste at the contractor's expense in compliance with local, state, and federal regulations.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 1240LU25Q0020.pdf | ||
| CAD_Townsend_Dwelling_100CD_12.10.24.pdf | ||
| Wage Determination MT20250016 01-03-2025.pdf | ||
| Sections B-M.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
C.2 SPECIFICATIONS
SECTION 01 74 00 – CLEAN UP AND DISPOSAL
PART 1 – GENERAL
1.01 CLEAN UP
A. Remove and dispose of all loose materials and debris from the crawlspace. See drawings for photos.
B. The contractor shall keep the work site free from accumulation of waste materials and rubbish resulting from the work. Clean areas daily as required to maintain a safe working site.
C. Before final acceptance of the project by the Government, the contractor shall remove from the site all excess material, waste, and rubbish resulting from this work.
1.02 DISPOSAL
A. Disposal includes, but is not limited to, the following; all existing siding, trim, fascia, soffits, gable vents, fiberglass insulation from west bay exterior walls, and electrical meter base cabinet.
B. Waste and excess material:
a. Material that is either waste or in excess of the needs of the contractor shall be disposed of at the contractor’s expense in accordance with all local, state and federal regulations at an approved offsite location.
b. Burning of waste or excess material on site is not permitted.
END OF SECTION 01 74 00
Townsend Dwelling Crawlspace Improvements SPECIFICATIONS December 10, 2024
SECTION 07 21 13 – INSULATION – VENT CLOSURES
1.01 SUMMARY
A. Work includes the fabrication of insulated vent closures for each of the existing crawl space vent openings. Vent closures shall be removable and provide a thermal value of R- 15.
PART 2 – PRODUCTS
2.01 GENERAL
A. Cover: Exterior facing cover of vent closures shall be decay resistant.
B. Insulation: Insulation shall be closed cell foam with a final thermal value of R-15.
PART 3 – EXECUTION
3.01 INSTALLATION
A. General: Comply with the International Residential Code and manufacturer’s written installation instructions applicable to products and applications indicated unless more stringent requirements apply.
END OF SECTION 07 21 13
SECTION 07 21 16 – INSULATION – STEM WALL
1.01 SUMMARY
A. Work includes the installation of continuous insulation over concrete stem walls inside the crawl space.
PART 2 – PRODUCTS
2.01 THERMAL INSULATION
A. Thermal Resistance Value (R-Value):
a. R-15 for continuous insulation
b. R-19 for cavity insulation on the inside of the wall
PART 3 – EXECUTION
3.01 INSTALLATION
A. Crawl space wall insulation shall be permanently fastened to the wall and shall extend downward from the floor to the finished grade elevation and then vertically or horizontally for not less than an additional 24 inches.
B. General: Comply with the International Residential Code and manufacturer’s written
END OF SECTION 07 21 16
SECTION 07 21 29 – INSULATION – RIM BOARDS
1.01 SUMMARY
A. Work includes the application of closed cell polyurethan foam insulation on all rim boards from inside the crawl space.
PART 2 – PRODUCTS
2.01 POLYURETHANE FOAM
A. Thermal Resistance Value (R-Value)
a. R-19 B. Properties:
a. Closed Cell, spray polyurethane foam, 2 pounds per cubic foot density.
PART 3 – EXECUTION
3.01 INSTALLATION
A. Rim joists shall be insulated so that the insulation maintains permanent contact with the exterior rim board.
B. The junctions of the rim board to the sill plate and the rim board to the subfloor shall be air sealed.
C. Finished foam thickness shall provide a minimum thermal value of R-19.
D. General: Comply with the International Residential Code and manufacturer’s written
END OF SECTION 07 21 29
SECTION 07 26 00 – VAPOR RETARDER
1.01 SUMMARY
A. Work includes the preparation of the existing crawl space floor to receive a new vapor retarder. Install new Class 1 vapor retarder over entire crawl space floor.
PART 2 – PRODUCTS
2.01 VAPOR RETARDER
A. Type: Class 1
PART 3 – EXECUTION
3.01 INSTALLATION
A. All exposed earth in the crawl space shall be covered with a continuous Class 1 vapor retarder.
B. Joints of the vapor retarder shall overlap by 6 inches and be sealed or taped. The edges of the vapor retarder shall extend not less than 6 inches up the stem walls and shall be attached to the stem walls.
C. General: Comply with the International Residential Code and manufacturer’s written
END OF SECTION 07 26 00
SECTION 23 33 00 - MECHANICAL VENTILATION
1.01 SUMMARY
A. Work includes the re-attachment of the HVAC ductwork where necessary and the installation of grilles in the ductwork to create a mechanically ventilated crawl space.
B. Contractor is responsible for the design and construction necessary to create a conditioned crawl space.
PART 2 – PRODUCTS
2.01 MISCELLANEOUS
A. General: Contractor is responsible for all materials and products necessary to complete this work. Methods and materials used to ventilate crawl space shall be approved by the COR prior to implementation.
PART 3 – EXECUTION
3.01 INSTALLATION
A. Conditioned air supply to the crawl space shall be sized to deliver at a rate equal to 1 cubic foot per minute for each 50 square feet of crawl space floor area, including an air pathway to the common area.
B. General: Comply with the International Residential Code and manufacturer’s written
END OF SECTION 23 33 00