Coyote. Cinch. Hook Ruin Pit C and S SOW.pdf

PDF 133 KB Posted

Attached to
127EAX22R0016-RFI Sources Sought/Request For Information (RFI) Crush & Stockpile
Solicitation number
127EAX22R0016-RFI
Issued by

About this file

This document includes a statement of work and request for information for an aggregate crushing and stockpiling project. The statement of work outlines requirements for mobilization, clearing and grubbing, drilling, blasting, sampling, testing, surveying, crushing, and stockpiling of aggregate materials in accordance with provided plans and specifications. It lists required submittals and notification timelines before beginning any work. The request for information seeks capability statements from interested vendors by May 2, 2022 to inform potential set-aside opportunities for small businesses. It describes requirements for simultaneous aggregate crushing at multiple locations in north-central Arizona to create road base materials. Responses should include company size standards and experience on similar aggregate production contracts. No pricing information should be included in capability statements.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK/ SPECIFICATIONS

C.1 – STATEMENT OF WORK

Coyote, Cinch Hook, Ruin Pit Crush and Stockpile Project: This project will include mobilization, clearing and grubbing, drilling, blasting, sampling and testing, stockpile surveying for quality control and crushing and stockpiling of an aggregate material in accordance with the plans and specifications.

Payment for contract work will be made only for and under those pay items included in the Schedule of Items. All other work and materials will be considered as incidental to and included in the payment for items shown.

SUBMITTAL/NOTIFICATION TIMELINES per FP-14 Specs

Required Submittal/Notification

Deadline for Receipt by the Government

Applicable Specification

Work Schedule At Pre-Work Meeting 151 - Mobilization

Hazardous Spill Plan Before beginning any work 107 – Legal Relations & Responsibility to the Public

Contractor Quality Control Plan

Before beginning any work 153.02 Contractor Quality Control Plan

Equipment Mobilization Notification

1 week prior to moving equipment onto Coconino National Forest

151 - Mobilization

Traffic Control Plan 14-days prior to prework conference

156-Public Traffic

Aggregate Gradation*** During aggregate production FSSS 703 Plan of Operations 14-days prior to prework conference.

FSSS 314

Blasting Plan 14-days prior to drilling and blasting operations

205 – Rock Blasting; FSSS 205

*** Items to be tested:

1. Gradation (AASHTO T 11)

2. Gradation (AASHTO T 27)

3. Liquid Limit (AASHTO T 89)

4. Plastic Limit (AASHTO T 90)

5. LA Abrasion (AASHTO T 96)

6. Sodium Sulfate Soundness (AASHTO T 104)

7. Durability (AASHTO T 210)

8. Fractured Faces (ASTM D 5821)

9. Specific Gravity and Absorption of Course Aggregate