Cost Schedule.xlsx
XLSX spreadsheet 16 KB Posted
- Solicitation number
- 24VS-S2579
- Issued by
- Washoe County, Virginia City CDP, Nevada
About this file
This document is a Cost Schedule for an RFP (Request for Proposal) issued by the Department of Veterans Services/Northern Nevada State Veterans Home for an Outside Visitation Area project. The RFP schedule outlines key milestones and deadlines, including the RFP preparation start on 11/6/23, advertisement on 11/14/23, a site walk on 11/21/23, questions due on 11/27/23, answers due on 11/30/23, proposal submission on 12/13/23, evaluation on 12/19/23, award letter issuance on 12/19/23, negotiations on 12/22/23, contract signatures by 1/7/24, and the Board of Examiners (BOE) deadline of 1/9/24, with the BOE meeting scheduled for 2/13/24. The project start date is set for 3/4/24, with a construction duration of 114 days, resulting in a completion date of 6/26/24.
The Cost Schedule provides a detailed breakdown of the line items for the project, including insurance and bonds, general conditions, general requirements, overhead and profit, mobilization, demolition, grading, concrete work, landscaping, electrical, and demobilization. Contractors must provide unit or lump sum pricing for these categories, and the pricing will become the basis for the payment schedule. Contractors must demonstrate their ability to provide accurate site and task-specific accounting and detailed task-specific invoicing documentation.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Mandatory Site Visit Form~1.doc | DOC document | |
| Construction drawings.pdf | ||
| Reference Questionnaire 2023-04-13.docx | DOCX document | |
| 24VS-S2579 RFP~2.pdf | ||
| Proposed Staff Resume 2023-04-13.docx | DOCX document | |
| Quote Instructions.pdf | ||
| Standard Form Contract ~1.pdf | ||
| Terms and Conditions for Goods 2023-04-14.pdf | ||
| Letter of Intent - Garden Shop Nursery Landscaping.docx | DOCX document | |
| Insurance Schedule - RFP 24VS-S2579 - RFP.pdf | ||
| Terms and Conditions for Services 2023-04-13.pdf | ||
| Attachments for Signatures 2023-04-13.pdf |
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
RFP Schedule
| Outdoor Visitation Schedule | |||
| Veterans Art Garden | |||
| Activity / Milestones | Duration | Day | Comments |
| RFP prep start | 11/6/23 | ||
| Advertisement | 8 | 11/14/23 | |
| Site Walk | 7 | 11/21/23 | |
| Questions Due | 6 | 11/27/23 | |
| Answers Due | 3 | 11/30/23 | |
| Submission | 13 | 12/13/23 | |
| Evaluation | 6 | 12/19/23 | |
| Award Letter | 0 | 12/19/23 | |
| Negotiations | 3 | 12/22/23 | |
| Contract Signatures | 16 | 1/7/24 | |
| BOE Deadline | 2 | 1/9/24 | Hard Date to meet BOE Mtg. |
| BOE (2nd Tues.) | 35 | 2/13/24 | Hard Date to work back from |
| Start of Construction | 20 | 3/4/24 | |
| Construction | 114 | 6/26/24 |
Cost Schedule
| COST SCHEDULE |
| RFP 24VS-S2579 |
| NNSVH - OUTDOOR VISITATION |
| Vendor Name: |
Contractors must provide unit or Lump Sum pricing of the catagories listed below that represent all costs required by the contract for a complete and finished project. The Contractor shall be properly licensed and provide appropriately experienced, trained, and accredited personnel with current credentials/certifications as well as supplies, materials, tools and equipment necessary to complete the job. The pricing per activity shall become the basis for the payment schedule. Payment for the General Conditions, General Requirements, Overhead, and Profit shall be invoiced as a percentage equal to the percentage that all other catogories are complete. Contractor shall account for all incidental and miscellaneous costs in the catagories that most closely matches the nature of the costs. Costs for all activities may be negotiated in advance via a Task Order proposal by the contractor and approved by the Division. A schedule of values for completion of the work activities will be required along with supporting documentation for all costs that are invoiced to the Division. Contractors proposing for the contract must demonstrate their ability to provide accurate site and task-specific accounting and detailed task specific invoicing documentation. A sample invoice and supporting documentation shall be provided as part of the Proposal.
Labor Rates: Hourly labor rates shall comply with the more stringent of the current Nevada Prevailing Wage Rates or the Davis Bacon Wage Rates.
| Reference | Description | Unit or Lump Sum $ | Quantity | Extended Price |
| Insurance and bonds | ||||
| GC's, Gen req., Overhead and Profit | ||||
| Mobilization | ||||
| Demolition | ||||
| Rough grading | ||||
| Finish grading | ||||
| Aggregate base | ||||
| Concrete formwork | ||||
| Concrete placement and finishing | ||||
| Sidewalk drain covers | ||||
| Catch basins and drain pipes | ||||
| Lanscape and irrigation lines | ||||
| Steel posts | ||||
| Rock mulch | ||||
| Electrical | ||||
| Demobilization | ||||
| Total Proposed Lump Sum Amount | $ |