Cost Breakdown.pdf
PDF 145 KB Posted
- Solicitation number
- 36C26124R0009-0005
About this file
The provided document is a Cost Breakdown for a Nurse Call System project at the Department of Veterans Affairs' Menlo Park Healthcare System. The Cost Breakdown details the divisional costs for various construction-related activities, including General Requirements, Demolition, Electrical Work, and Communications Systems. The total project bid amount is provided, broken down into Subtotal, Overhead, and Profit.
The related federal contract opportunity is a solicitation (Solicitation Number: 36C26124R0009-0005) for construction services to replace the existing Nurse Call System at Buildings 331 and 360 at the Menlo Park Healthcare System. The solicitation is set aside for Service-Disabled Veteran-Owned Small Businesses (SDVOSBs). Key details include a site visit on December 13, 2023, RFI due date of December 18, 2023, and proposal due date of January 8, 2024. The solicitation has been cancelled effective March 27, 2024, as stated in the amendment.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 000000 Specs Merged NEW.pdf | ||
| Wage Determination San Mateo.pdf | ||
| ICRA MPD Nurse Call Replacement_ complete.pdf | ||
| 36C26124R0009.pdf | ||
| S02 - RFI FORM.docx | DOCX document | |
| NURSE CALL_MERGED SET.pdf | ||
| PER VHA DIRECTIVE 7715 EMR.docx | DOCX document | |
| 36C26124R0009 0005.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DIVISIONAL COST BREAK-OUT
Menlo Park Nurse Call System
CLIN 0001
Provide complete Divisional Cost Break-Out for complete project. If necessary, add additional lines for each Division applicable to this project.
REF DESCRIPTION TOTAL
01 01 15 List of Drawing Sheets $ 01 00 00 General Requirements $
01 32 16.15 Project Schedules (Small Projects – Design/Bid/Build
01 33 23 Shop Drawings, Product Data, and Samples $ 01 35 26 Safety Requirements 01 57 19 Temporary Environmental Controls 01 74 19 Construction Waste Management 02 41 00 Demolition 09 91 00 Painting 26 05 11 Requirements for Electrical Installations 26 05 19 Low-Voltage Electrical Power Conductors and
Cables
26 05 26 Grounding and Bonding for Electrical Systems 26 05 33 Raceway and Boxes for Electrical Systems 27 05 11 Requirements for Communications Installations 27 05 26 Grounding and Bonding for Communications
Systems
27 05 33 Raceways and Boxes for Communications Systems
27 08 00 Commissioning of Communications Systems 27 10 00 Control, Communication and Signal Wiring 27 52 23 Nurse Call and Code Blue Systems
OTHER
OTHER $
SUB TOTAL:
OVERHEAD
PROFIT
TOTAL PROJECT BID AMOUNT:
DIVISIONAL COST BREAK-OUT
File details come from the government source that posted it. Updated .