This document is a Corrective and Preventative Maintenance Checklist for Ceiling Mounted and Portable Patient Lifts. It outlines the commissioning procedures and inspection requirements for patient lift systems, including verifying proper structural connections, checking the rails/tracks and end stops, inspecting the lift unit and straps, and conducting load testing. The checklist must be completed by an inspector and signed off by a VA representative and the Manager of the Service using the lifts.

The related federal contract opportunity is a Sources Sought Notice for Patient Lift Service and Maintenance for the Fort Meade VA Medical Clinic. The Department of Veterans Affairs is seeking information from interested and capable firms to facilitate acquisition decision-making. The applicable NAICS code is 811210, and the Small Business Administration's Limitations on Subcontracting requirement applies. Responses are due by 4:00 PM Central Time on June 6, 2024.

View the file

Other files

File Type Posted
36C26324Q0858_1.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

1 of 2 Serial Number:

Corrective and Preventive Maintenance Checklist for Ceiling Mounted and Portable Patient Lifts The commissioning for a patient ceiling and portable lift system(s) shall include, but not be limited to, the following points as components of the commissioning procedures.

Verify that ceiling mounted and portable patient lifts are not installed in treatment units with actively suicidal patients.

Facility: Manufacturer:

Lift Location: Model:

VAMC Contact: Serial Number:

VAMC Contact's Phone Number: Mfgr Contact:

Inspector: Mfgr Contact's Phone Number:

Inspector's Phone Number: Date:

Structure Complete

Verify proper connections of the lift's structural system to the building’s structure (including seismic bracing if applicable).

Verify proper interface at the ceiling (hard deck or soft tile) and proper installation of all protective features around the support rods and rails/tracks.

Verify proper structural component sizing and physical installation to make sure that proper structural system is in place and properly installed to support the lift.

NOTES:

Rails/Tracks and End Stops PASS FAIL

1 Verification that all fasteners and set screws are properly tightened on the trollies and rails/tracks.

Ensure that the rail/track is free of gaps (unless required by design). If included in installation, verify rail turntable function, exchanger function, gate alignment, and safety block installation.

Confirm track is clean and clear of all debris. (Use manufacturer’s recommended cleaning materials to avoid damage to the motor case and other components.)

4 Verification that all manufacturer specified end stops or docking gates are properly installed.

Lift Unit and Straps PASS FAIL

1 Inspection of lift unit casing for cracks and alignment.

2 Verification that the lift unit charges properly.

Inspection and activation of hand control for full operation (e.g., up, down, left, right) and “return to charge” function if applicable.

Confirm any and all lift unit indicator lights are functioning. (e.g., red service warning light, charging state light)

5 Inspection and activation of emergency up/down lift unit control buttons if applicable.

6 Full extension and inspection of lift strap for loose threads or frays.

7 Inspection of spreader bar and clips for cracks and for loose or missing rings or cotter pins.

2 of 2 Serial Number:

Load Testing PASS FAIL

Verification of any “soft start” or “soft stop” features and that lifting speed does not exceed 2.5 inches per second with “zero” load.

Verification of load testing and deflection testing at lift listed maximum for each lift unit at its maximum rated lift capacity. Conduct this test in three progressive stages starting with a 100 lbs. load, then 50% of maximum rated lift capacity, then 100% of maximum rated lift capacity.

Verification of any “soft start” and “soft stop” features and that lifting speed does not exceed 1.5 inches per second under maximum rated lift capacity.

4 Verification of function of emergency stop at maximum rated lift capacity.

5 Verification of emergency lowering feature at maximum rated lift capacity.

Inspector COMPLETE

After the activities listed in the above checklist and in the manufacturers installation/operations/owner’s manual(s) have been completed, the inspector shall release the ceiling mounted and portable lift installation to VA representative.

SIGNATURE: DATE:

TITLE:

VA Representative COMPLETE

After the activities listed in the above checklist and in the manufacturers installation/operations/owner’s manual(s) have been completed, the VA representative shall release the ceiling mounted and portable lift installation to the Manager of the Service using the ceiling mounted and portable lifts.

Manager of the Service Using the Ceiling Mounted Lifts COMPLETE

Verify and confirm that VA clinical staff have been trained to operate the ceiling mounted and portable patient lift prior to releasing the ceiling mounted lift for use.