This is an amendment with questions and answers for solicitation CORHQ-24-Q-0555 issued by the Federal Deposit Insurance Corporation (FDIC) for SUMO Scheduler software subscription renewal. The amendment extends the RFQ due date from January 31, 2025 to February 10, 2025 at 1 p.m.
The Q&A clarifies several key points: this is a renewal of an existing software subscription with fixed quantities; no custom integrations are anticipated; there is no limit on authenticated community users; support will be provided by the OEM according to SLAs outlined in the RFQ; technical acceptability will be based on incorporation of all items in Section B Price Schedule; and this will be a single award. The pricing must be submitted using either the Section B Price Schedule in the solicitation or the Excel file attached to the SAM.gov posting. Security requirements are defined in Clauses 7.4.2-01 and 7.4.2-02, and payment follows the Prompt Payment Act guidelines.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| CORHQ-24-Q-0555 Updated 1.31.25.pdf | ||
| CORHQ-24-Q-0555 SUMO Scheduler.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF AWARD
1. CONTRACT ID CODE
2. AMENDMENT/MODIFICATION NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ. NO. 5. PROJECT NO. (If applicble)
7. ADMINISTERED BY (If other than Item 6) CODE
FDIC 3700/56 (3-08)
FACILITY CODE
9A. AMENDMENT OF SOLICIATION NO.
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NO.
10B. DATED (SEE ITEM 11)
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended, is not extended.
Offer must acknowledge receipt of this amendment by signing in Block 15b below and including the signed amendment with the offeror's proposal.
12. N/A
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO THE CHANGE ORDERS CLAUSE
B. THIS MODIFICATION IS ENTERED INTO PURSUANT TO THE AUTHORITY OF THE FDIC CONTRACTING OFFICER
C. THIS MODIFICATION IS ENTERED INTO PURSUANT TO MUTUAL AGREEMENT OF THE PARTIES
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remain unchanged and in full force and effect.
15C. DATE SIGNED
15A. NAME AND TITLE OF SIGNER (Type or print)
16C. DATE SIGNED
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
14. DESCRIPTION OF AMENDMENT/MODIFICATION
PAGE OF PAGES
6. ISSUED BY CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code) (X)
CODE
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
CORHQ-24-Q-0555 / 0001
hamjackson Highlight hamjackson Highlight
Solicitation Number CORHQ-24-Q-0555 SUMO Scheduler
Questions & Answers
CONTROLLED//FDIC BUSINESS
1. Will the FDIC purchase directly from SUMO, or will it need to procure through a reseller/partner?
Answer: The FDIC will receive proposals from any qualified seller.
2. Please confirm whether the quantities listed in the pricing schedule are fixed or if adjustments are anticipated during the performance period.
Answer: Quantities are fixed.
3. Are there specific SLA (Service Level Agreement) requirements for support and maintenance services beyond what is outlined in the RFQ?
Answer: The SLA requirements are outlined in the RFQ.
4. Could the FDIC clarify the expected response and resolution times for urgent after-hours support mentioned in the subscription maintenance?
Answer: After-hours support should be clarified by the OEM.
5. Does the FDIC anticipate any custom integrations with existing systems beyond what is supported out-of-box, and if so, what are the parameters?
Answer: FDIC does not anticipate custom integrations.
6. What process should be followed if additional configurations or data migrations beyond the stated limits are needed during the contract term?
Answer: Not applicable.
7. Please clarify how ‘basic support’ (30%) is defined and what it entails compared to premium support options.
Answer: Support options should be clarified by the OEM.
8. Is there a limit on the number of authenticated community users who can self-schedule appointments under the subscription?
Answer: No.
9. Please confirm whether the FDIC has any existing licenses or systems that will integrate with SUMO Scheduler or if this will be a completely new implementation.
Answer: This is a renewal of an existing software subscription.
CORHQ-24-Q-0555 / 0001
10. Is there a specific format or template for submitting the pricing schedule in Section B?
Answer: The Section B Price Schedule in the solicitation is the specific format that needs to be submitted. You can also use the Excel file that is attached the SAM.gov posting for this solicitation.
11. What is the expected process for FDIC approval of invoices, and what is the average payment timeline, as referenced under Section G?
Answer: Invoices are approved based on the guidelines in Clauses 7.5.13-01, 7.5.13-12, 7.5.13-13, and 7.5.13-14. Payment timelines follow the Prompt Payment Act.
12. Could the FDIC confirm the required submission format for the Representations and Certifications in Section K?
Answer: Section K clause 7.3.2-46 – Integrity and Fitness Representations and Certifications must be completed. It can be completed with that clause in the solicitation or a separate document with the information provided in the clause.
13. Would the FDIC consider extending the submission deadline to allow vendors more time to prepare comprehensive responses?
Answer: RFQ date will be extended.
14. Does the FDIC require specific cybersecurity certifications or audits for contractors and subcontractors handling sensitive FDIC data?
Answer: Security requirements for the contract are defined in Clause 7.4.2-01 and 7.4.2-02.
15. Are there restrictions or preferences regarding the geographical location of the contractor's performance, especially for remote tasks?
Answer: There are no services associated with this requirement. Support is provided by the OEM.
16. Are there restrictions or pre-approvals required for subcontractors if proposed by the contractor?
Answer: There are no services associated with this requirement. Support is provided by the OEM.
17. What specific evaluation criteria will be applied to determine "technical acceptability" as stated in Section M?
Answer: Technical acceptability is confirming that the offeror’s quote incorporates all items as stated in Section B Price Schedule.
18. Will any site visits or virtual demonstrations be required as part of the evaluation process?
Answer: No
19. Does the FDIC anticipate making multiple awards from this RFQ, or will this be a single award?
Answer: Single award
20. If there are changes to the contract after the award, what is the process for incorporating these changes, particularly with regard to pricing or scope adjustments?
Answer: Any changes made after contract award will result in a modification were both parties will need to sign for it to take effect. Exceptions are changes in FDIC personnel and administrative errors.
In those cases, the CO will issue a modification unilaterally.
| IDCode: |
| Page: 1 |
| Pages: 4 |
| AmendNo: 0001 |
| EffDate: 01/31/2025 |
| ReqNo: |
| ProjNo: |
| IssCode: |
| IssuedBy: Federal Deposit Insurance Corporation |
DOA/ASB
3501 Fairfax Dr Arlington, VA 22226 hamjackson@fdic.gov
| AdmCode: |
| AdminBy: Hamilton Jackson |
571-214-1297 hamjackson@fdic.gov
| ContName: |
| ContStrt: |
| ContCnty: |
| ContSt: |
| ContZIP: |
| Code: |
| FacCode: |
| SolChgYs: Yes |
| SolChgNo: |
| SolAmdNo: CORHQ-24-Q-0555 |
| AmendDate: 01/08/2024 |
| ModNo: |
| ModDate: |
| Amended: Yes |
| OffrExt: Yes |
| OffrNoEx: |
| ChgeOrd: |
| ChgeOrder: |
| Modify: |
| SuppAgre: |
| SuppAuth: |
| ModOthr: |
| OthrSpec: |
| NoReq: |
| Require: |
| Copies: |
| Descript: The purpose of this modification is to provide questions and answers to the solicitation and to extend the RFQ due date from January 31, 2025 to 1 p.m. Monday, February 10, 2025. |
Questions and Answers for the solicitation can be found on page 2 of this Amendment.
| SignName: |
| SignTitl: |
| ContDate: |
| CoName: Hamilton Jackson |
| CoTitle: Contracting Officer |
| CODate: |
File details come from the government source that posted it. Updated .