Copy of Mulino Airport Area Paving Package Bid Tab analysis.xlsx

XLSX spreadsheet 23 KB Posted

Attached to
Cheese Shredded Blend
Solicitation number
S-29100-00007330
Issued by
Marion County, Oregon

About this file

This document is a bid tabulation analysis for the Mulino Airport Area Paving Package, a public works project involving three separate paving sections across different roadways. The project encompasses paving work on Adkins Circle, Airport Road, and Fish Road/South Buff Road, with bid submissions received from four contractors: KNL Industries, Inc., S-2 Contractors, Knife River Corp. Northwest, and North Santiam Paving Co. The work includes asphalt pavement installation, subgrade stabilization, removal of existing surfacing at various depths, aggregate base and shoulder placement, temporary traffic control, erosion control, and monument box installation. Quantities vary by section, with asphalt paving ranging from 400 to 1,300 tons across the three projects, subgrade stabilization from 290 to 400 square yards, and removal of surfacing quantities between 1,120 and 7,310 square yards depending on the section. No specific response dates, site visits, or bidders' conference information is detailed in this bid tab analysis document.

The bid tabulation presents unit prices and total costs for all line items across the four competing bidders, with total project bids ranging from $842,065.00 to $1,043,751.00. The analysis identifies the low and high unit prices for each bid item and calculates average unit prices and totals across all bidders. KNL Industries submitted the lowest overall bid at $842,065.00, while S-2 Contractors submitted the highest at $1,041,280.00. Significant bid variations exist on certain items, particularly mobilization costs and aggregate shoulders, with some unit prices varying by more than 100 percent between bidders. The document does not specify contract terms, renewal options, set-asides, or funding sources, serving solely as a comparative analysis of the received bids for evaluation purposes.

View the file

Other files

File Type Posted
Cheese Variety~2.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Bid Tabs

Mulino Airport Area Paving Package Bid Tabulations
KNL Industries, Inc.S-2 ContractorsKnife River Corp. NorthwestNorth Santiam Paving Co.Low/High AnalysisAverage of the Bids
Bid ItemUnitQuantityUnit PriceTotalUnit PriceTotalUnit PriceTotalUnit PriceTotalLow UPHigh UPAverage Unit PriceAverage Total
100EXTRA WORK DONE ON FORCE ACCOUNT BASISFA1$ 17,000.00$ 17,000.00$ 17,000.00$ 17,000.00$ 17,000.00$ 17,000.00$ 17,000.00$ 17,000.00$ 17,000.00$ 17,000.00$ 17,000.00$ 17,000.00
101MOBILIZATIONLS1$ 30,000.00$ 30,000.00$ 20,000.00$ 20,000.00$ 15,000.00$ 15,000.00$ 82,300.00$ 82,300.00$ 15,000.00$ 82,300.00$ 36,825.00$ 36,825.00
102TEMPORARY WORK ZONE TRAFFIC CONTROL, COMPLETE FOR S ADKINS CIRLS1$ 7,500.00$ 7,500.00$ 20,000.00$ 20,000.00$ 30,035.00$ 30,035.00$ 17,700.00$ 17,700.00$ 7,500.00$ 30,035.00$ 18,808.75$ 18,808.75
103TEMPORARY PROJECT INFORMATION SIGNSSF30$ 30.00$ 900.00$ 70.00$ 2,100.00$ 17.00$ 510.00$ 37.00$ 1,110.00$ 17.00$ 70.00$ 38.50$ 1,155.00
104TEMPORARY REMOVABLE TAPELF135$ 3.00$ 405.00$ 3.00$ 405.00$ 6.50$ 877.50$ 3.75$ 506.25$ 3.00$ 6.50$ 4.06$ 548.44
105EROSION CONTROLLS1$ 1,000.00$ 1,000.00$ 2,000.00$ 2,000.00$ 1,450.00$ 1,450.00$ 750.00$ 750.00$ 750.00$ 2,000.00$ 1,300.00$ 1,300.00
106POLLUTION CONTROL PLANLS1$ 1,000.00$ 1,000.00$ 500.00$ 500.00$ 918.00$ 918.00$ 300.00$ 300.00$ 300.00$ 1,000.00$ 679.50$ 679.50
107ASPHALT PAVEMENT SAW CUTTINGLF410$ 2.00$ 820.00$ 4.00$ 1,640.00$ 3.40$ 1,394.00$ 2.80$ 1,148.00$ 2.00$ 4.00$ 3.05$ 1,250.50
108REMOVAL OF SURFACINGS, 1-2 INCH DEEPSQYD5,990$ 3.50$ 20,965.00$ 4.00$ 23,960.00$ 4.00$ 23,960.00$ 2.75$ 16,472.50$ 2.75$ 4.00$ 3.56$ 21,339.38
109REMOVAL OF SURFACINGS, 2-3 INCH DEEPSQYD880$ 4.00$ 3,520.00$ 5.00$ 4,400.00$ 5.70$ 5,016.00$ 4.10$ 3,608.00$ 4.00$ 5.70$ 4.70$ 4,136.00
11012 INCH SUBGRADE STABILIZATIONSQYD400$ 60.00$ 24,000.00$ 70.00$ 28,000.00$ 46.00$ 18,400.00$ 53.00$ 21,200.00$ 46.00$ 70.00$ 57.25$ 22,900.00
111INSTALL CAST IRON MONUMENT BOXESEA9$ 500.00$ 4,500.00$ 500.00$ 4,500.00$ 370.00$ 3,330.00$ 1,150.00$ 10,350.00$ 370.00$ 1,150.00$ 630.00$ 5,670.00
1123/4 INCH - 0 AGGREGATE BASETON1,250$ 40.00$ 50,000.00$ 50.00$ 62,500.00$ 46.00$ 57,500.00$ 47.00$ 58,750.00$ 40.00$ 50.00$ 45.75$ 57,187.50
113AGGREGATE SHOULDERS (1-1/2"-0)TON850$ 40.00$ 34,000.00$ 100.00$ 85,000.00$ 40.50$ 34,425.00$ 40.00$ 34,000.00$ 40.00$ 100.00$ 55.13$ 46,856.25
114AGGREGATE APPROACH: AGGREGATE BASETON10$ 100.00$ 1,000.00$ 100.00$ 1,000.00$ 180.00$ 1,800.00$ 340.00$ 3,400.00$ 100.00$ 340.00$ 180.00$ 1,800.00
115LEVEL 2, 1/2 INCH ACPTON1,300$ 110.00$ 143,000.00$ 114.00$ 148,200.00$ 93.50$ 121,550.00$ 110.00$ 143,000.00$ 93.50$ 114.00$ 106.88$ 138,937.50
116EXTRA FOR ASPHALT APPROACHESEA9$ 400.00$ 3,600.00$ 1,000.00$ 9,000.00$ 830.00$ 7,470.00$ 700.00$ 6,300.00$ 400.00$ 1,000.00$ 732.50$ 6,592.50
117PAVEMENT BAR, TYPE B-HSSQFT45$ 30.00$ 1,350.00$ 50.00$ 2,250.00$ 50.00$ 2,250.00$ 65.00$ 2,925.00$ 30.00$ 65.00$ 48.75$ 2,193.75
200EXTRA WORK DONE ON FORCE ACCOUNT BASISFA1$ 5,000.00$ 5,000.00$ 5,000.00$ 5,000.00$ 5,000.00$ 5,000.00$ 5,000.00$ 5,000.00$ 5,000.00$ 5,000.00$ 5,000.00$ 5,000.00
201MOBILIZATIONLS1$ 13,000.00$ 13,000.00$ 8,000.00$ 8,000.00$ 12,600.00$ 12,600.00$ 41,350.00$ 41,350.00$ 8,000.00$ 41,350.00$ 18,737.50$ 18,737.50
202TEMPORARY WORK ZONE TRAFFIC CONTROL, COMPLETE FOR S AIRPORT RDLS1$ 10,000.00$ 10,000.00$ 7,000.00$ 7,000.00$ 23,940.00$ 23,940.00$ 10,750.00$ 10,750.00$ 7,000.00$ 23,940.00$ 12,922.50$ 12,922.50
203TEMPORARY PROJECT INFORMATION SIGNSSF30$ 30.00$ 900.00$ 70.00$ 2,100.00$ 17.00$ 510.00$ 37.00$ 1,110.00$ 17.00$ 70.00$ 38.50$ 1,155.00
204TEMPORARY REMOVABLE TAPELF150$ 3.00$ 450.00$ 3.00$ 450.00$ 6.50$ 975.00$ 3.75$ 562.50$ 3.00$ 6.50$ 4.06$ 609.38
205EROSION CONTROLLS1$ 1,000.00$ 1,000.00$ 1,000.00$ 1,000.00$ 1,800.00$ 1,800.00$ 750.00$ 750.00$ 750.00$ 1,800.00$ 1,137.50$ 1,137.50
206POLLUTION CONTROL PLANLS1$ 1,000.00$ 1,000.00$ 500.00$ 500.00$ 915.00$ 915.00$ 300.00$ 300.00$ 300.00$ 1,000.00$ 678.75$ 678.75
207ASPHALT PAVEMENT SAW CUTTINGLF300$ 2.00$ 600.00$ 5.00$ 1,500.00$ 3.40$ 1,020.00$ 2.75$ 825.00$ 2.00$ 5.00$ 3.29$ 986.25
208REMOVAL OF SURFACINGS, 1-2 INCH DEEPSQYD1,120$ 3.50$ 3,920.00$ 5.00$ 5,600.00$ 8.15$ 9,128.00$ 5.00$ 5,600.00$ 3.50$ 8.15$ 5.41$ 6,062.00
209REMOVAL OF SURFACINGS, 2-3 INCH DEEPSQYD880$ 4.00$ 3,520.00$ 5.00$ 4,400.00$ 7.75$ 6,820.00$ 6.50$ 5,720.00$ 4.00$ 7.75$ 5.81$ 5,115.00
21012 INCH SUBGRADE STABILIZATIONSQYD290$ 75.00$ 21,750.00$ 70.00$ 20,300.00$ 46.00$ 13,340.00$ 53.00$ 15,370.00$ 46.00$ 75.00$ 61.00$ 17,690.00
211CAST IRON MONUMENT BOXESEA1$ 500.00$ 500.00$ 500.00$ 500.00$ 370.00$ 370.00$ 1,150.00$ 1,150.00$ 370.00$ 1,150.00$ 630.00$ 630.00
2123/4 INCH - 0 AGGREGATE BASETON370$ 40.00$ 14,800.00$ 50.00$ 18,500.00$ 44.50$ 16,465.00$ 52.00$ 19,240.00$ 40.00$ 52.00$ 46.63$ 17,251.25
213AGGREGATE SHOULDERS (1-1/2"-0)TON260$ 40.00$ 10,400.00$ 100.00$ 26,000.00$ 65.00$ 16,900.00$ 48.00$ 12,480.00$ 40.00$ 100.00$ 63.25$ 16,445.00
214AGGREGATE APPROACH: AGGREGATE BASETON10$ 100.00$ 1,000.00$ 100.00$ 1,000.00$ 180.00$ 1,800.00$ 340.00$ 3,400.00$ 100.00$ 340.00$ 180.00$ 1,800.00
215LEVEL 2, 1/2 INCH ACPTON400$ 110.00$ 44,000.00$ 114.00$ 45,600.00$ 107.50$ 43,000.00$ 127.00$ 50,800.00$ 107.50$ 127.00$ 114.63$ 45,850.00
216EXTRA FOR ASPHALT APPROACHESEA3$ 400.00$ 1,200.00$ 1,000.00$ 3,000.00$ 820.00$ 2,460.00$ 1,000.00$ 3,000.00$ 400.00$ 1,000.00$ 805.00$ 2,415.00
217PAVEMENT BAR, TYPE B-HSSQFT50$ 30.00$ 1,500.00$ 50.00$ 2,500.00$ 50.00$ 2,500.00$ 65.00$ 3,250.00$ 30.00$ 65.00$ 48.75$ 2,437.50
300EXTRA WORK DONE ON FORCE ACCOUNT BASISFA1$ 19,000.00$ 19,000.00$ 19,000.00$ 19,000.00$ 19,000.00$ 19,000.00$ 19,000.00$ 19,000.00$ 19,000.00$ 19,000.00$ 19,000.00$ 19,000.00
301MOBILIZATIONLS1$ 35,000.00$ 35,000.00$ 20,000.00$ 20,000.00$ 15,000.00$ 15,000.00$ 77,750.00$ 77,750.00$ 15,000.00$ 77,750.00$ 36,937.50$ 36,937.50
302TEMPORARY WORK ZONE TRAFFIC CONTROL, COMPLETE FOR S FISH RD/S BUFF RDLS1$ 10,000.00$ 10,000.00$ 20,000.00$ 20,000.00$ 23,016.00$ 23,016.00$ 23,700.00$ 23,700.00$ 10,000.00$ 23,700.00$ 19,179.00$ 19,179.00
303TEMPORARY PROJECT INFORMATION SIGNSSF15$ 30.00$ 450.00$ 70.00$ 1,050.00$ 17.00$ 255.00$ 37.00$ 555.00$ 17.00$ 70.00$ 38.50$ 577.50
304TEMPORARY REMOVABLE TAPELF75$ 3.00$ 225.00$ 3.00$ 225.00$ 6.00$ 450.00$ 3.75$ 281.25$ 3.00$ 6.00$ 3.94$ 295.31
305EROSION CONTROLLS1$ 1,000.00$ 1,000.00$ 2,000.00$ 2,000.00$ 1,775.00$ 1,775.00$ 750.00$ 750.00$ 750.00$ 2,000.00$ 1,381.25$ 1,381.25
306POLLUTION CONTROL PLANLS1$ 1,000.00$ 1,000.00$ 500.00$ 500.00$ 915.00$ 915.00$ 300.00$ 300.00$ 300.00$ 1,000.00$ 678.75$ 678.75
307ASPHALT PAVEMENT SAW CUTTINGLF230$ 2.00$ 460.00$ 4.00$ 920.00$ 3.40$ 782.00$ 2.75$ 632.50$ 2.00$ 4.00$ 3.04$ 698.63
308REMOVAL OF SURFACINGS, 1-2 INCH DEEPSQYD5,320$ 3.50$ 18,620.00$ 4.00$ 21,280.00$ 4.95$ 26,334.00$ 2.75$ 14,630.00$ 2.75$ 4.95$ 3.80$ 20,216.00
309REMOVAL OF SURFACINGS, 2-3 INCH DEEPSQYD2,390$ 4.00$ 9,560.00$ 5.00$ 11,950.00$ 3.85$ 9,201.50$ 4.00$ 9,560.00$ 3.85$ 5.00$ 4.21$ 10,067.88
31012 INCH SUBGRADE STABILIZATIONSQYD400$ 60.00$ 24,000.00$ 70.00$ 28,000.00$ 46.00$ 18,400.00$ 53.00$ 21,200.00$ 46.00$ 70.00$ 57.25$ 22,900.00
311CAST IRON MONUMENT BOXESEA1$ 500.00$ 500.00$ 500.00$ 500.00$ 370.00$ 370.00$ 1,150.00$ 1,150.00$ 370.00$ 1,150.00$ 630.00$ 630.00
3123/4 INCH - 0 AGGREGATE BASETON1,320$ 40.00$ 52,800.00$ 50.00$ 66,000.00$ 45.15$ 59,598.00$ 50.50$ 66,660.00$ 40.00$ 50.50$ 46.41$ 61,264.50
313AGGREGATE SHOULDERS (1-1/2"-0)TON940$ 40.00$ 37,600.00$ 100.00$ 94,000.00$ 39.50$ 37,130.00$ 42.00$ 39,480.00$ 39.50$ 100.00$ 55.38$ 52,052.50
314AGGREGATE APPROACH: AGGREGATE BASETON10$ 100.00$ 1,000.00$ 100.00$ 1,000.00$ 180.00$ 1,800.00$ 350.00$ 3,500.00$ 100.00$ 350.00$ 182.50$ 1,825.00
315LEVEL 2, 1/2 INCH ACPTON1,300$ 110.00$ 143,000.00$ 114.00$ 148,200.00$ 94.40$ 122,720.00$ 115.00$ 149,500.00$ 94.40$ 115.00$ 108.35$ 140,855.00
316EXTRA FOR ASPHALT APPROACHESEA20$ 400.00$ 8,000.00$ 1,000.00$ 20,000.00$ 740.00$ 14,800.00$ 600.00$ 12,000.00$ 400.00$ 1,000.00$ 685.00$ 13,700.00
317PAVEMENT BAR, TYPE B-HSSQFT25$ 30.00$ 750.00$ 50.00$ 1,250.00$ 50.00$ 1,250.00$ 65.00$ 1,625.00$ 30.00$ 65.00$ 48.75$ 1,218.75
Total$ 842,065.00Total$ 1,041,280.00$ 855,225.00Total$ 1,043,751.00Average$ 945,580.25
$344,560.00$432,455.00$342,885.50$420,819.75
$134,540.00$152,950.00$159,543.00$180,657.50
$362,965.00$455,875.00$352,796.50$442,273.75
$842,065.00$1,041,280.00$855,225.00$1,043,751.00