Copy of IFB Lump Sum Division Spreadsheet.xlsx
XLSX spreadsheet 15 KB Posted
- Attached to
- Y1PZ--Gravesite Expansion Rock Island National Cemetery 821CM3030 - Construction Project
- Solicitation number
- 36C78620B0005
About this file
This spreadsheet template provides a lump sum bid breakdown by construction division for the Y1PZ--Gravesite Expansion Rock Island National Cemetery 821CM3030 construction project. The Department of Veterans Affairs National Cemetery Administration solicitation seeks bids for expanding gravesites at the Rock Island National Cemetery. The template lists 34 construction divisions and includes spaces to provide lump sum pricing for each division, as well as total pricing for the base work under CLINs 0001-0002 and eight bid options. Bidders must submit a completed bid by division using this template with their response to solicitation number 36C78620B0005 by the unspecified due date. Award is expected to be a fixed-price construction contract for expanding gravesites at the Rock Island National Cemetery.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C78620B0005 0006.docx | DOCX document | |
| RINC_2006_Geotech.pdf | ||
| 36C78620B0005 0005.docx | DOCX document | |
| 36C78620B0005_2.docx | DOCX document | |
| S02 - Visitor_Access_Form.pdf | ||
| P01 - 821CM3030-RINC-SPECS.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| This Division List is copied from: NCA MASTER CONSTRUCTION SPECIFICATIONS (https://www.cfm.va.gov/til/ncaSpec.asp) |
| Lump Sums are required for each Division that will be utilized in this project to total the final lump sum number. |
If a Division is not being used put N/A in that field.
You can Add additional items you feel are appropriate.
| IFB Number |
| Project Name |
| Division | CLIN1 | CLIN 2 | TOTAL CLIN 0001 & 0002 | BID OPTION 1 | BID OPTION 2 | BID OPTION 3 | BID OPTION 4 | BID OPTION 5 | BID OPTION 6 | BID OPTION 7 | BID OPTION 8 | GRAND TOTAL CLIN 0001, 0002, and BID OPTIONS 1-8 |
| Division 0 | ||||||||||||
| Special Sections | $ | $ | $ | $ | $ | $ | $ | $ | $ | $ | $ | $ |
| Division 1 | ||||||||||||
| General Requirements | $ | $ | $ | $ | $ | $ | $ | $ | $ | $ | $ | $ |
| Division 2 | ||||||||||||
| Existing Conditions | $ | $ | $ | $ | $ | $ | $ | $ | $ | $ | $ | $ |
| Division 3 | ||||||||||||
| Concrete | $ | $ | $ | $ | $ | $ | $ | $ | $ | $ | $ | $ |
| Division 4 | ||||||||||||
| Masonry | $ | $ | $ | $ | $ | $ | $ | $ | $ | $ | $ | $ |
| Division 5 | ||||||||||||
| Metals | $ | $ | $ | $ | $ | $ | $ | $ | $ | $ | $ | $ |
| Division 6 | ||||||||||||
| Wood and Plastic | $ | $ | $ | $ | $ | $ | $ | $ | $ | $ | $ | $ |
| Division 7 | ||||||||||||
| Thermal and Moisture | $ | $ | $ | $ | $ | $ | $ | $ | $ | $ | $ | $ |
| Division 8 | ||||||||||||
| Doors and Windows | $ | $ | $ | $ | $ | $ | $ | $ | $ | $ | $ | $ |
| Division 9 | ||||||||||||
| Finishes | $ | $ | $ | $ | $ | $ | $ | $ | $ | $ | $ | $ |
| Division 10 | ||||||||||||
| Specialties | $ | $ | $ | $ | $ | $ | $ | $ | $ | $ | $ | $ |
| Division 11 | ||||||||||||
| Equipment | $ | $ | $ | $ | $ | $ | $ | $ | $ | $ | $ | $ |
| Division 12 | ||||||||||||
| Furnishings | $ | $ | $ | $ | $ | $ | $ | $ | $ | $ | $ | $ |
| Division 13 | ||||||||||||
| Special Construction | $ | $ | $ | $ | $ | $ | $ | $ | $ | $ | $ | $ |
| Division 22 | ||||||||||||
| Plumbing | $ | $ | $ | $ | $ | $ | $ | $ | $ | $ | $ | $ |
| Division 23 | ||||||||||||
| Heat, Ventilating, and Air Conditioning | $ | $ | $ | $ | $ | $ | $ | $ | $ | $ | $ | $ |
| Division 25 | ||||||||||||
| Integrated Automation | $ | $ | $ | $ | $ | $ | $ | $ | $ | $ | $ | $ |
| Division 26 | ||||||||||||
| Electrical | $ | $ | $ | $ | $ | $ | $ | $ | $ | $ | $ | $ |
| Division 27 | ||||||||||||
| Communications | $ | $ | $ | $ | $ | $ | $ | $ | $ | $ | $ | $ |
| Division 28 | ||||||||||||
| Electronic Safety and Security | $ | $ | $ | $ | $ | $ | $ | $ | $ | $ | $ | $ |
| Division 31 | ||||||||||||
| Earthwork | $ | $ | $ | $ | $ | $ | $ | $ | $ | $ | $ | $ |
| Division 32 | ||||||||||||
| Exterior Improvements | $ | $ | $ | $ | $ | $ | $ | $ | $ | $ | $ | $ |
| Division 33 | ||||||||||||
| Utilities | $ | $ | $ | $ | $ | $ | $ | $ | $ | $ | $ | $ |
| Bonds | ||||||||||||
| $ | $ | $ | $ | $ | $ | $ | $ | $ | $ | $ | $ | |
| TOTAL PRICE | CLIN1 | CLIN 2 | TOTAL CLIN 0001 & 0002 | BID OPTION 1 | BID OPTION 2 | BID OPTION 3 | BID OPTION 4 | BID OPTION 5 | BID OPTION 6 | BID OPTION 7 | BID OPTION 8 | |
| $ | $ | $ | $ | $ | $ | $ | $ | $ | $ | $ |
TOTAL CONTRACT PRICE (CLINS 0001 & 0002 PLUS ADD ALTERNATE OPTIONS 0001 THROUGH 0008): $