City of Radford is seeking bids for Contaminated Soil Removal on a previous Foundry site.
Solicitation number
81544
Issued by
Richmond County, Virginia

About this file

This is a bid form issued by the City of Radford, Virginia for soil excavation work at the Former Radford Foundry site. The project involves the removal of contaminated soil from Exposure Area B, which encompasses approximately 0.77 acres to a depth of one foot. The scope includes mobilization, installation of erosion control measures, excavation and disposal of both non-hazardous (40 tons) and RCRA hazardous soil (375 tons), backfilling with clean soil (1,315 tons total, including protective soil cover), and site stabilization covering 3,600 square yards with seeding.

The bid form is structured as a unit price contract with seven major line items: mobilization, erosion control installation, non-hazardous soil removal and disposal, hazardous soil removal and disposal, clean fill placement, seeding/stabilization, and erosion control removal. Each line item requires bidders to provide unit prices and total prices. The project specifically addresses contamination from lead, PCBs, and arsenic, requiring proper handling and disposal at approved Sub-title C and D facilities, with comprehensive documentation including manifests, weight tickets, and certificates of disposal.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

Bid Form
Exposure Area B Soil Excavation
Former Radford Foundry
Radford, VA
Bidder Name:
Bidder Address:

Date:

BID FORM
ItemDescriptionQuantityUnitUnit
PriceTotal
PriceGeneral Scope of Work
1Mobilization1each$ - 0Project setup; HASP preparation; training; permittin;, submittals; mobilization/demobilization of equipment, materials and cre;, soil sampling and analyses; coordination with the City on final areas and volumes of excavation; excavation area layout; equipment and personnel decontamination including decontamination water and water disposal.
2Installation of Soil Erosion and Sediment Control Measures1each$ - 0Installation and maintenance of silt fence, silt sock and construction entrance, stormwater management
3Non-hazardous Soil Excavation, Transportation and Disposal
3aExcavate, load and transport to disposal facility40Ton$ - 0Means and methods to safely excavate soils identified for removal to the lines and grades established, loading onto licensed/permitted trucks, truck bed liners as required, soil conditioning as reqiuired for acceptable transport, manifests or bills of lading for each load transported off-site. Copies of all minfiests/bills of labding to be maintained on site and copies provided to the City.
3bDisposal costs40Ton$ - 0Disposal approvals and disposal of non-hazardous waste soils and incidental materials (e.g., PPE) at permitted and City-approved Sub-title D facility. Submittal of certified weigh tickets and Certificates of Disposal/Destruction to the City for each load of soil transported off-site.
4RCRA Characterisitically Hazardous Soil Excavation, Transportation and Disposal
4aExcavate, load and transport to disposal facility375Ton$ - 0Means and methods to safely excavate soils identified for removal to the lines and grades established, loading onto licensed/permitted trucks, truck bed liners as required, soil conditioning as reqiuired for acceptable transport, VADEQ manifests for each load transported off-site. Copies of all minfiests/bills of labding to be maintained on site and copies provided to the City.
4bDisposal costs375Ton$ - 0Disposal approvals and disposal of RCRA Characterisitically Hazardous Waste soils and incidental materials (e.g., PPE) at permitted and City-approved Sub-title C facility. Submittal of certified weigh tickets and Certificates of Disposal/Destruction to the City for each load of soil transported off-site.
5Soil Approval, Procurement, Delivery, Placement, Grading and Tracking in (~415 tons to fill excavation void and ~900 tons for protective soil cover)1,315Ton$ - 0Approval of acceptable source of soil, procurement, delivery, placment, grading and tracking in. Submittal of certified weigh tickets to the City.
6Seeding and Stabilization3,600SY$ - 0Procurement, delivery, application, stabilization and watering (as necessary to establish growth) of acceptable seeding mixture and rate of application
7Removal of Soil Erosion and Sediment Control Measures1each$ - 0Removal and off-site disposal of soil erosion and sediment controls, final site restoration

Total Price Bid: $ - 0