This document is a Project Description for the purchase of a cooling tower for the Western Illinois Correctional Center. The project entails the estimated $40k purchase of a 20C-2 Cooling tower that must be compatible with the existing utilities. The unit required is a force draft counter flow closed circuit cooler with options including series flow operation with factory mounted crossover piping, electric heater, capacity fan dampers, flange coil connections, and an energy efficient motor.

The document provides detailed specifications for the required cooling tower, but does not include information about response dates, due dates, site visits, bidder's meetings, award dates, or the term of the contract including any renewal options. Pricing terms, set asides, incumbents, funding requirements and sources, and other salient commercial details are also not provided.

View the file

Other files

File Type Posted
BOA Cooling Tower~1.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Western Illinois Correctional Center is seeking the purchase of a fluid cooler.

Project Description: estimated $40k Purchase of a 20C-2 Cooling tower, must be a compatible with our existing utilities. Unit is force draft counter flow closed circuit cooler.

Options:
- Series flow operation with factory mounted crossover piping
- Electric Heater (2KW) ( 0 degree F. Ambient) with thermostat and low water cutoff
- Capacity fan dampers
- Flange coil connections
- Energy efficient Motor