The document describes a state and local contract opportunity for the purchase of a 20C-2 Cooling tower at the Western Illinois Correctional Center in Illinois. The project overview indicates the estimated cost is $40k for a force draft counter flow closed circuit cooler that must be compatible with the existing utilities. The required options include series flow operation with factory mounted crossover piping, an electric heater, capacity fan dampers, flange coil connections, and an energy efficient motor.
The contract opportunity has an ID of 66ab72f07cf5b14e190c00fa and is specific to the Illinois Department of Corrections for the WICC - Cooling Tower - JRS project. No additional details are provided regarding response dates, due dates, award dates, or contract term.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| BOA Cooling Tower~1.docx | DOCX document | |
| Cooling Tower Waiver.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Western Illinois Correctional Center is seeking the purchase of a fluid cooler.
Project Description: estimated $40k Purchase of a 20C-2 Cooling tower, must be a compatible with our existing utilities. Unit is force draft counter flow closed circuit cooler.
| Options: | |
| - Series flow operation with factory mounted crossover piping | |
| - Electric Heater (2KW) ( 0 degree F. Ambient) with thermostat and low water cutoff | |
| - Capacity fan dampers | |
| - Flange coil connections | |
| - Energy efficient Motor |