Price Schedule Template

CONTRACT PRICE SCHEDULE
SOLICITATION NUMBER: 140P5223Q0011
PARK - PMIS: 246038
DEVELOPED AREA: Santa Rosa Area (Opal Beach) Hwy 399
PROJECT TITLE: CYCLIC RESTRIPE J. EARLE BOWDEN WAY ROAD AND PARKING LOTS
Notice: Offerors are required to submit, a minimum, an offer that conforms to the solicitation documents with pricing for all line items. Failure to do so may render the quotation or offer unacceptable. On lump-sum line items, provide the total price only. For all unit-priced line items, provide the unit price and the extended total price. If no specific line item exists for a portion of the work, include the costs in a related item. In case of error in calculation of extended prices, the unit price governs. In case of error in summation, the total of the corrected amounts govern. Round totals and extended prices to whole dollars. The Government reserves the right to award all, some or none. Pricing will be evaluated for price reasonableness IAW FAR 13.106-3 (a) and or (b) if necessary. Best value to the Government will be based only on price and past performance. Contracting offices may conduct comparative evaluations of offers.
CONTRACT LINE ITEM NUMBER (CLIN)CONTRACT LINE ITEM (CLI) TITLEQUANTITYUNIT OF MEASUREUNIT PRICETOTAL PRICE
1A7.4 miles of double yellow line and solid white edge line on main road1LUMP SUM0.00
1B7.4 miles of bike lane identification (multiple bike pavement markings)1LUMP SUM
1CParking area drive lane markings at Opal Beach Entrance Fee Station (all hand work)1LUMP SUM
1DParking Lot 32A (~57 regular Parking Spaces plus 2 ABA parking spaces of 3 required)1LUMP SUM
1EParking Lot 33A (~55 parking spaces; plus 2 ABA spaces of 3 required)1LUMP SUM
1FParking Lot 36A (~55 parking spaces; plus 2 ABA spaces of 3 required)1LUMP SUM
1GOpal Beach Parking Lot 34A (~140 parking spaces including required ABA spaces1LUMP SUM
1HOpal Beach Parking Lot 34B (~108 parking spaces including required ABA spaces1LUMP SUM
1JOpal Beach Parking Lot 34C (~70 parking spaces including required ABA spaces1LUMP SUM
1KOpal Beach Parking Lot 34D (~81 parking spaces including required ABA spaces1LUMP SUM
1LOpal Beach Parking Lot 34E (~101 parking spaces including required ABA spaces1LUMP SUM
TOTAL BASE PRICE (Contract Line Item Number 1A through1L) ------------------------------------$0.00

&RPARK - PMIS

CPS - &P

Design-Bid-Build Sample

CONTRACT PRICE SCHEDULE
SOLICITATION NUMBER: N2011080811
PARK - PMIS: YELL 012345
DEVELOPED AREA: Old Faithful
PROJECT TITLE: Johnstonian Visitors Center
Notice: Refer to FAR Clause 52.217-5, Evaluation of Options, as prescribed in FAR 17. Offerors are required to submit, a minimum, an offer that conforms to the solicitation documents with pricing for Base line items and all option line items. Failure to do so may render the proposal unacceptable. On lump-sum line items, provide the total price only. For all unit-priced line items, provide the unit price and the extended total price. If no specific line item exists for a portion of the work, include the costs in a related item. In case of error in calculation of extended prices, the unit price governs. In case of error in summation, the total of the corrected amounts govern. Round totals and extended prices to whole dollars. The Government reserves the right to award any or no options at or after the time of award. At the option of the Government, the period for exercise of options at the proposed prices shall extend 180 calendar days from the date of award. Pricing will be evaluated based on what is determined to be the best value to the Government. Options may be exercised in any combination, order, or grouping deemed in the judgment of the Contracting Officer to offer the best value to the Government.
In addition to the offer that conforms to the solicitation documents, offerors are encouraged to submit alternate proposals that will result in cost savings to the Government. Such proposals shall clearly identify why the acceptance of the alternate proposal would be advantageous to the Government, see FAR Clause 52.215-1, Instructions to Offerors - Competitive Acquisition-Alternate II and DSC-36 Clause (Instructions for Submission of Offers and Other Information) in Section L of the Solicitation.
CONTRACT LINE ITEM NUMBER (CLIN)CONTRACT LINE ITEM (CLI) TITLEQUANTITYUNIT OF MEASUREUNIT PRICETOTAL PRICE
1Visitors Center1Lump Sum$0.00
2Water Line400L.F.- 0
3Sanitary Sewer line200L.F.- 0
4Rock Excavation150C.Y.- 0
TOTAL BASE PRICE (Contract Line Item Number 1 through 4) ------------------------------------$0.00
5OPTION A, Geothermal Wells1Lump Sum$ - 0
6OPTION B, Photovoltaic system1Lump Sum- 0
TOTAL PRICE FOR ALL OPTIONS (Contract Line Item Numbers 5 and 6) -------------------------------------------$0.00
TOTAL PROPOSED PRICE - BASE PLUS ALL OPTIONS (Contract Line Item Numbers 1 through 6) -------------$0.00
All measurement and payment information is included in the project specifications, Section 012700.

&RYELL - 012345

CPS - &P

Design-Build Sample

CONTRACT PRICE SCHEDULE
SOLICITATION NUMBER: N2011080811
PARK - PMIS: YOSE 012345
DEVELOPED AREA: Yosemite Valley
PROJECT TITLE: Design and Build a New Structure
Notice: Refer to FAR Clause 52.217-5, Evaluation of Options, as prescribed in FAR 17. Offerors are required to submit, a minimum, an offer that conforms to the solicitation documents with pricing for Base line items and all option line items. Failure to do so may render the proposal unacceptable. On lump-sum line items, provide the total price only. If no specific line item exists for a portion of the work, include the costs in a related item. In case of error in summation, the total of the corrected amounts govern. Round totals and extended prices to whole dollars. The Government reserves the right to award any or no options at or after the time of award. At the option of the Government, the period for exercise of options at the proposed prices shall extend 180 calendar days from the date of award. Pricing will be evaluated based on what is determined to be the best value to the Government. Options may be exercised in any combination, order, or grouping deemed in the judgment of the Contracting Officer to offer the best value to the Government.
In addition to the offer that conforms to the solicitation documents, offerors are encouraged to submit alternate proposals that will result in cost savings to the Government. Such proposals shall clearly identity why the acceptance of the alternate proposal would be advantageous to the Government, see FAR Clause 52.215-1, Instructions to Offerors - Competitive Acquisition-Alternate II and DSC-36 Clause (Instructions for Submission of Offers and Other Information) in Section L of the Solicitation.
CONTRACT LINE ITEM NUMBER (CLIN)CONTRACT LINE ITEM (CLI) TITLEQUANTITYUNIT OF MEASUREUNIT PRICETOTAL PRICE
1Design1Lump Sum$0.00
2Construction1Lump Sum$0.00
TOTAL BASE PRICE (Contract Line Item Number 1 through 2) ---------------------------------------------------------$0.00
3OPTION A, Photovoltaic System1Lump Sum$0.00
TOTAL PRICE FOR ALL OPTIONS (Contract Line Item Number 3 ) -----------------------------------------------------$0.00
TOTAL PROPOSED PRICE - BASE PLUS ALL OPTIONS (Contract Line Item Numbers 1 through 3) ------------$0.00

&RYOSE - 012345

CPS - &P

File details come from the government source that posted it. Updated .