About this file

This is a Sources Sought Information Form for an Indefinite Delivery/Indefinite Quantity (IDIQ) Job Order Contract (JOC) for plumbing and HVAC projects in the Metro San Diego area. The Navy's Naval Facilities Engineering Command Southwest is seeking small businesses (including 8(a), HUBZone, Women-Owned, and Service-Disabled Veteran-Owned) to perform construction, repair, and renovation work at Naval Base Coronado, Naval Base Point Loma, Naval San Diego, and MCAS Miramar.

The contract is valued at $40 million, with a base two-year performance period and one three-year option period, resulting in a potential five-year contract. Task orders will range from $2,000 to $1,500,000, targeting NAICS code 238220 (Plumbing, Heating, and Air-Conditioning Projects) with a small business size standard of $19 million. Interested contractors must submit detailed information including business type, bonding capacity, work locations, project experience, and safety rates by May 27, 2025, to Billie Crockett via email. The government will use this sources sought information to determine whether the future solicitation will be a small business set-aside or full and open competition.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SOURCES SOUGHT – CONTRACTOR INFORMATION FORM

for METRO SAN DIEGO (NAVAL BASE CORONADO, POINT LOMA, AND SAN DIEGO, AND MCAS MIRAMAR) AOR, CA, PLUMBING, HVAC IDIQ JOC

Use this form to provide contractor’s general information. Please limit response to one page. The box at the bottom of this form may be used to clarify any requested information.

1. Contractor Information:
UEI:
CAGE Code:
Firm Name:
Address:
Name of POC for firm:
Phone Number of POC:
Email of POC:

2. Type of Business: (check all that apply)

|_| SBA certified 8(a) firm
|_| SBA certified HUBZone Small Business
|_| Service-Disabled Veteran-Owned Small Business
|_| Small Business

|_| Women-Owned Small Business

3. Bonding Capacity:

Surety Name:
Maximum bonding capacity per project:
$
Aggregate maximum bonding capacity:
$

4. Locations. Identify the locations you are willing and capable to work: (check all that apply)

|_| Naval Base Coronado (AOR)
|_| Naval Base Point Loma (AOR)
|_| Naval San Diego (AOR)
|_| MCAS Miramar (AOR)

If you are not willing and capable to work in locations noted above, explain why not:

5. This space may be used to provide any additional information to clarify the above items only:

Form may be expanded. Please DO NOT change content of the form.

(Rev. 11/15)

SOURCES SOUGHT – CONSTRUCTION EXPERIENCE PROJECT DATA FORM

for METRO SAN DIEGO (NAVAL BASE CORONADO, POINT LOMA, AND SAN DIEGO, AND MCAS MIRAMAR) AOR, CA, PLUMBING, HVAC IDIQ JOC

Use this form (one per project) to provide supporting information that demonstrates project experience relevant to the subject announcement. Submit up to five (5) projects. Please limit response to two pages per project.

1.
Contractor Name:
2.
Project No. (check one):
|_| - 1|_| - 2|_| - 3|_| - 4|_| - 5
3.
Contract Number:
Delivery/Task Order No.:
Project Number:
Title:
Location:
4.
Award Date (mm/dd/yy):
5.
Final Contract Price:
$
Completion Date (mm/dd/yy):
(includes all options and mods)
Project is % complete (as of sources sought issuance date)
This is the |_| total project |_| subcontract price.
6.
Type of work:
|_| New Construction|_| Repair|_| Renovation
7.
Customer/Owner Name:
Point of Contact Name/Title: (person with project knowledge)
POC Phone Number:
POC Email Address:
8.
Were you the Prime contractor for this project?
|_| Yes|_| No
Were you a subcontractor for this project?
|_| Yes|_| No
If subcontractor, who was the Prime contractor?
9.
Type of Contract (check all that apply):

|_| Design-Build |_| Design-Bid-Build

|_| Other (explain):

10. Provide a detailed description of the project:

11. Percentage of work you self-performed on this project: %. Provide a detailed description of the work your firm self-performed on this project:

Form may be expanded. Please DO NOT change content of the form.