Construction Specification .pdf
PDF 11 MB Posted
- Solicitation number
- 36C24225B0048
About this file
This document is a construction specification for renovating the Dialysis Unit at the Northport VA Medical Center in New York. The project (VA Project #632-17-107) involves a comprehensive renovation of approximately 5,330 square feet on the third floor of Building 200, with work scheduled to begin August 8, 2023.
The renovation encompasses multiple technical disciplines including architecture, fire protection, interior design, structural engineering, mechanical, electrical, and health facility planning. Key scope elements include demolition of existing spaces, abatement of hazardous materials, installation of new medical gas systems, replacement of HVAC equipment, electrical systems upgrades, and potential modifications to the existing reverse osmosis water treatment system. The project will be completed in multiple phases to maintain ongoing hospital operations, with specific requirements for infection control, dust prevention, and maintaining hospital services throughout construction. The specifications include detailed requirements for materials, installation methods, testing, and commissioning across architectural, mechanical, electrical, plumbing, and fire protection systems.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C24225B0048 0002.docx | DOCX document | |
| Construction Drawings_IV.pdf | ||
| 632-17-107_Design Report_Bid Document Subm_compress.pdf | ||
| Construction Drawings_III.pdf | ||
| Construction Drawings_V.pdf | ||
| 36C24225B0048 0003.docx | DOCX document | |
| Construction Drawings_II.pdf | ||
| Construction Drawings_I.pdf | ||
| 36C24225B0048 0001.docx | DOCX document | |
| Construction Drawings_01.pdf | ||
| Construction Drawings_02.pdf | ||
| P07_Wage Determination_Suffolk.txt | TXT text file | |
| 852.219-75 VA NOTICE OF LIMITATIONS ON SUBCONTRACTING-CERTIFICATE.docx | DOCX document | |
| FAR 52.225-2 Buy American Certification.pdf | ||
| 36C24225B0048_1.docx | DOCX document |
Show all 15
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Renovate Dialysis Northport VAMC Building 200
Project No. 632-17-107
SPECIFICATIONS
Bid Document Submission
79 Middleville Road Northport, NY 11768
August 8th, 2023
Northport VA Medical Center, Northport NY VA Project #632-17-107 Renovate Dialysis Bid Document Submission 08/08/2023
00 01 10-1
DEPARTMENT OF VETERANS AFFAIRS
VHA MASTER SPECIFICATIONS
TABLE OF CONTENTS
Section 00 01 10
SECTION NO. DIVISION AND SECTION TITLES DATE
DIVISION 00 - SPECIAL SECTIONS
00 01 15 List of Drawing Sheets 08.08.23
DIVISION 01 - GENERAL REQUIREMENTS
01 00 00 General Requirements 08.08.23 01 32 16.15 Project Schedules (Small Projects – Design/Bid/Build 08.08.23 01 33 23 Shop Drawings, Product Data, and Samples 08.08.23 01 35 26 Safety Requirements 08.08.23 01 42 19 Reference Standards 08.08.23 01 45 00 Quality Control 08.08.23 01 45 29 Testing Laboratory Services 08.08.23 01 45 35 Special Inspections 08.08.23 01 57 19 Temporary Environmental Controls 08.08.23 01 58 16 Temporary Interior Signage 08.08.23 01 74 19 Construction Waste Management 08.08.23 01 81 13 Sustainable Construction Requirements 08.08.23 01 91 00 General Commissioning Requirements 08.08.23
DIVISION 02 – EXISTING CONDITIONS
02 41 00 Demolition 08.08.23 02 82 11 Traditional Asbestos Abatement 08.08.23 02 82 13.13 Glovebag Asbestos Abatement 08.08.23 02 82 13.19 Asbestos Floor Tile and Mastic Abatement 08.08.23
DIVISION 03 – CONCRETE
03 52 00 Lightweight Concrete Roof Insulation 08.08.23
DIVISION 04 – MASONRY
04 01 00 Maintenance of Masonry 08.08.23 04 05 13 Masonry Mortaring 08.08.23
DIVISION 05 – METALS
05 12 00 Structural Steel Framing 08.08.23 05 40 00 Cold-Formed Metal Framing 08.08.23
DIVISION 06 – WOOD, PLASTICS AND COMPOSITES
06 10 00 Rough Carpentry 08.08.23
00 01 10-2
06 20 00 Finish Carpentry 08.08.23
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
07 01 50.19 Preparation for Re-Roofing 08.08.23 07 21 13 Thermal Insulation 08.08.23 07 22 00 Roof and Deck Insulation 08.08.23 07 52 16.11 Cold Adhesive Styrene-Butadiene-Styrene Modified
Bituminous Membrane Roofing 08.08.23
07 60 00 Flashing and Sheet Metal 08.08.23 07 71 00 Roof Specialties 08.08.23 07 72 00 Roof Accessories 08.08.23 07 81 00 Applied Fireproofing 08.08.23 07 84 00 Firestopping 08.08.23 07 92 00 Joint Sealants 08.08.23
DIVISION 08 - OPENINGS
08 11 13 Hollow Metal Doors and Frames 08.08.23 08 14 00 Interior Wood Doors 08.08.23 08 17 10 Integrated Door Assemblies 08.08.23 08 31 13 Access Doors and Frames 08.08.23 08 32 13 Isolation Room Sliding Glass Doors 08.08.23 08 41 13 Aluminum-Framed Entrances and Storefronts 08.08.23 08 51 13 Aluminum Windows 08.08.23 08 71 00 Door Hardware 08.08.23 08 71 13 Automatic Door Operators 08.08.23 08 80 00 Glazing 08.08.23
DIVISION 09 – FINISHES
09 05 16 Subsurface Preparation for Floor Finishes 08.08.23 09 06 00 Schedule for Finishes 08.08.23 09 22 16 Non-Structural Metal Framing 08.08.23 09 29 00 Gypsum Board 08.08.23 09 30 13 Ceramic/Porcelain Tiling 08.08.23 09 51 00 Acoustical Ceilings 08.08.23 09 54 16 Luminous Sky-Image Ceilings 08.08.23 09 65 13 Resilient Base and Accessories 08.08.23 09 65 16 Resilient Sheet Flooring 08.08.23 09 65 19 Resilient Tile Flooring 08.08.23 09 67 23.20 Resinous Epoxy Base With Vinyl Chip Broadcast (RES 2) 08.08.23 09 68 00 Carpeting 08.08.23 09 72 16 Vinyl-Coated Fabric Wall Covering 08.08.23 09 91 00 Painting 08.08.23 09 96 59 Resinous Specialty Glazed Coating Systems for Walls, Ceilings, Wallboard, and Block CMU (RES-W1, RES-W2) 08.08.23
DIVISION 10 – SPECIALTIES
10 11 13 Chalkboards and Markerboards 08.08.23
00 01 10-3
10 11 23 Tackboards 08.08.23 10 13 00 Directories 08.08.23 10 14 00 Signage 08.08.23 10 21 23 Cubicle Curtain Tracks 08.08.23 10 25 13 Patient Bed Service Walls 08.08.23 10 26 00 Wall and Door Protection 08.08.23 10 28 00 Toilet, Bath, and Laundry Accessories 08.08.23 10 44 13 Fire Extinguisher Cabinets 08.08.23
DIVISION 11 – EQUIPMENT
11 26 00 Unit Kitchens 08.08.23 11 41 00 Food Storage Equipment 08.08.23 11 73 00 Ceiling Mounted Patient Lift System 08.08.23
DIVISION 12 – FURNISHINGS
12 22 16 Drapery Track and Accessories 08.08.23 12 24 00 Window Shades 08.08.23 12 31 00 Manufactured Metal Casework 08.08.23 12 32 00 Manufactured Wood Casework 08.08.23 12 34 00 Manufactured Plastic Casework 08.08.23 12 35 70.21 Medication Cabinet 08.08.23 12 36 00 Countertops 08.08.23
DIVISION 13 - SPECIAL CONSTRUCTION
13 05 41 Seismic Restraint Requirements for Non-Structural
Components 01-21
DIVISION 21- FIRE SUPPRESSION
21 13 13 Wet-Pipe Sprinkler Systems 08.08.23
DIVISION 22 – PLUMBING
22 05 11 Common Work Results for Plumbing 08.08.23 22 05 23 General-Duty Valves for Plumbing Piping 08.08.23 22 05 33 Heat Tracing for Plumbing Piping 08.08.23 22 07 11 Plumbing Insulation 08.08.23 22 08 00 Commissioning of Plumbing Systems 08.08.23 22 11 00 Facility Water Distribution 08.08.23 22 13 00 Facility Sanitary and Vent Piping 08.08.23 22 40 00 Plumbing Fixtures 08.08.23 22 62 00 Vacuum Systems for Laboratory and Healthcare
Facilities 08.08.23
22 63 00 Gas Systems for Laboratory and Healthcare Facilities 08.08.23
00 01 10-4
DIVISION 23 – HEATING, VENTILATING, AND AIR
CONDITIONING (HVAC)
23 05 11 Common Work Results for HVAC 08.08.23 23 05 12 General Motor Requirements for HVAC and Steam
Generation Equipment 08.08.23
23 05 41 Noise and Vibration Control for HVAC Piping and Equipment
08.08.23
23 05 93 Testing, Adjusting, and Balancing for HVAC 08.08.23 23 07 11 HVAC and Boiler Plant Insulation 08.08.23 23 08 00 Commissioning of HVAC Systems 08.08.23 23 09 23 Direct-Digital Control System for HVAC 08.08.23 23 21 13 Hydronic Piping 08.08.23 23 22 13 Steam and Condensate Heating Piping 08.08.23 23 31 00 HVAC Ducts and Casings 08.08.23 23 34 00 HVAC Fans 08.08.23 23 36 00 Air Terminal Units 08.08.23 23 37 00 Air Outlets and Inlets 08.08.23 23 40 00 HVAC Air Cleaning Devices 08.08.23 23 74 13 Packaged, Outdoor, Central-Station Air-Handling Units 08.08.23 23 82 16 Air Coils 08.08.23
DIVISION 26 – ELECTRICAL
26 05 11 Requirements for Electrical Installations 08.08.23 26 05 19 Low-Voltage Electrical Power Conductors and Cables 08.08.23 26 05 26 Grounding and Bonding for Electrical Systems 08.08.23 26 05 33 Raceway and Boxes for Electrical Systems 08.08.23 26 05 73 Overcurrent Protective Device Coordination Study 08.08.23 26 08 00 Commissioning of Electrical Systems 08.08.23 26 09 23 Lighting Controls 08.08.23 26 24 16 Panelboards 08.08.23 26 27 26 Wiring Devices 08.08.23 26 29 11 Motor Controllers 08.08.23 26 29 21 Enclosed Switches and Circuit Breakers 08.08.23 26 43 13 Surge Protective Devices 08.08.23 26 51 00 Interior Lighting 08.08.23
DIVISION 27 – COMMUNICATIONS
27 05 11 Requirements for Communications Installations 08.08.23 27 05 26 Grounding and Bonding for Communications Systems 08.08.23 27 05 33 Raceways and Boxes for Communications Systems 08.08.23 27 10 00 Control, Communication and Signal Wiring 08.08.23 27 15 00 Communications Structured Cabling 08.08.23 27 51 16 Public Address and Mass Notification Systems 08.08.23 27 52 23 Nurse Call and Code Blue Systems 08.08.23
DIVISION 28 – ELECTRONIC SAFETY AND SECURITY
28 05 00 Common Work Results for Electronic Safety and Security 08.08.23
00 01 10-5
28 05 13 Conductors and Cables for Electronic Safety and Security
08.08.23
28 05 26 Grounding and Bonding for Electronic Safety and Security
08.08.23
28 05 28.33 Conduits and Backboxes for Electronic Safety and Security
08.08.23
28 08 00 Commissioning of Electronic Safety and Security Systems
08.08.23
28 13 00 Physical Access Control System 08.08.23 28 23 00 Video Surveillance 08.08.23 28 31 00 Fire Detection and Alarm 08.08.23
00 01 15 - 1
SECTION 00 01 15
LIST OF DRAWING SHEETS
The drawings listed below accompanying this specification form a part of the contract.
Drawing # Title
ARCHITECTURAL
G001 TITLE SHEET
G002 GENERAL INFORMATION
G003 GENERAL INFORMATION
G004 3RD FLOOR LIFE SAFETY PLAN
AD101.0 PHASE 1 2nd, 4th & ROOF FLOOR PLAN DEMOLITION
A101.0 PHASE 1 2nd, 4th & ROOF FLOOR PLAN CONSTRUCTION
AD101.1 PHASE 1 3rd FLOOR PLAN DEMOLITION
A101.1 PHASE 1 3rd FLOOR PLAN CONSTRUCTION
AD101.20 PHASE 2 2ND FLOOR PLAN DEMOLITION & CONSTRUCTION
AD101.2 PHASE 2 3rd FLOOR PLAN DEMOLITION
A101.2 PHASE 2 3rd FLOOR PLAN CONSTRUCTION
AD101.2A PHASE 2A 3rd FLOOR PLAN DEMOLITION
A101.2A PHASE 2A 3rd FLOOR PLAN CONSTRUCTION
AD101.30 PHASE 3 2ND FLOOR PLAN DEMOLITION
AD101.3 PHASE 3 3RD FLOOR PLAN DEMOLITION
A101.3 PHASE 3 3RD FLOOR PLAN CONSTRUCTION
A100 3RD FLOOR DIALYSIS NEW FLOOR PLAN
A102 3RD FLOOR REFLECTED CEILING PLAN
A103 3RD FLOOR ENLARGED PLAN A
A104 3RD FLOOR ENLARGED PLAN B
A105 4TH FLOOR DIALYSIS NEW FLOOR PLAN
A106 PARTIAL ROOF PLAN
A107 SPRINKLER PLAN
A200 INTERIOR ELEVATIONS
A201 INTERIOR ELEVATIONS
A202 INTERIOR ELEVATIONS
A203 ENLARGED PLANS & INTERIOR ELEVATIONS
A204 ENLARGED PLANS & INTERIOR ELEVATIONS
A205 ENLARGED PLANS & INTERIOR ELEVATIONS
A206 ENLARGED PLANS & INTERIOR ELEVATIONS
A207 ENLARGED PLANS & INTERIOR ELEVATIONS
A208 ENLARGED PLANS & INTERIOR ELEVATIONS
00 01 15 - 2
A209 ENLARGED PLANS & INTERIOR ELEVATIONS
A210 ENLARGED PLANS & INTERIOR ELEVATIONS
A300 SECTIONS
A301 WALL SECTIONS & DETAILS
A302 WALL SECTIONS
A303 WALL SECTIONS
A410 INTERIOR 3D VIEWS
A500 MILLWORK & INTERIOR DETAILS
A501 MILLWORK & INTERIOR DETAILS
A502 MILLWORK & INTERIOR DETAILS
A503 MILLWORK & INTERIOR DETAILS
A504 MILLWORK & SPECIAL EQUIPMENT DETAILS
A505 CEILING DETAILS
A506 ROOF DETAILS
A507 ROOF DETAILS
A601 DOOR AND WINDOW SCHEDULES
A602 PARTITION TYPES & SCHEDULE
A603 SIGNAGE DETAILS & SCHEDULE
A604 SIGNAGE LOCATION PLAN
A605 3RD FLOOR DEDUCT ALTERNATE PLAN
A606 3RD FLOOR REFLECTED CEILING DEDUCT ALTERNATE PLAN
A700 LOW VOLTAGE PLAN
I001 3RD FLOOR FINISH SCHEDULE AND MATERIAL LEGEND
I002 3RD FLOOR FINISH PLAN
I003 3RD FLOOR FINISH PLAN
Q103 3RD FLOOR EQUIPMENT PLAN
STRUCTURAL
S000 GENERAL NOTES – STRUCTURE
S001 SPECIAL INSPECTIONS
S100 PARTIAL PLANS – ROOF AND DUNNAGE
MECHANICAL
M001 MECHANICAL COVER SHEET
MD102.1 SECOND FLOOR – HVAC – DEMOLITION – PHASE 1
MD102.2 SECOND FLOOR – HVAC – DEMOLITION – PHASE 2
MD103.1 THIRD FLOOR – HVAC – DEMOLITION – PHASE 1
MD103.2 THIRD FLOOR – HVAC – DEMOLITION – PHASE 2
00 01 15 - 3
MD103.3 THIRD FLOOR – HVAC – DEMOLITION – PHASE 3
MD202.1 SECOND FLOOR – HVAC PIPING – DEMOLITION – PHASE 1
MD202.2 SECOND FLOOR – HVAC PIPING – DEMOLITION – PHASE 2
MD203.1 THIRD FLOOR – HVAC PIPING – DEMOLITION – PHASE 1
MD203.2 THIRD FLOOR – HVAC PIPING – DEMOLITION – PHASE 2
M103.1 THIRD FLOOR – HVAC – NEW WORK – PHASE 1
M103.2 THIRD FLOOR – HVAC – NEW WORK – PHASE 2
M103.3 THIRD FLOOR – HVAC – NEW WORK – PHASE 3
M104.1 FOURTH FLOOR – HVAC – NEW WORK – PHASE 1
M105.1 ROOF – HVAC – NEW WORK – PHASE 1
M202.1 SECOND FLOOR – HVAC PIPING – NEW WORK – PHASE 1
M202.2 SECOND FLOOR – HVAC PIPING – NEW WORK – PHASE 2
M203.1 THIRD FLOOR – HVAC PIPING – NEW WORK – PHASE 1
M203.2 THIRD FLOOR – HVAC PIPING – NEW WORK – PHASE 2
M301 THIRD FLOOR – MECHANICAL – PRESSURIZATION
M401 MECHANICAL PART PLANS
M501 MECHANICAL DETAILS
M502 MECHANICAL DETAILS
M503 MECHANICAL DETAILS
M504 MECHANICAL DETAILS
M601 MECHANICAL CONTROLS
M701 MECHANICAL SCHEDULES
ELECTRICAL
E001 ELECTRICAL COVER SHEET
E002 ELECTRICAL LEGEND AND ABBREVIATIONS
ED103.1 PARTIAL THIRD FLOOR PLAN - ELECTRICAL DEMOLITION - PHASE 1
E103.1 PARTIAL THIRD FLOOR PLAN - LIGHTING - PHASE 1
ED103.2 PARTIAL THIRD FLOOR PLAN - ELECTRICAL DEMOLITION - PHASE 2
E103.2 PARTIAL THIRD FLOOR PLAN - LIGHTING - PHASE 2
ED103.3 PARTIAL THIRD FLOOR PLAN - ELECTRICAL DEMO. - PHASE 2A & 3
E103.3 PARTIAL THIRD FLOOR PLAN - LIGHTING - PHASE 2A AND 3
ED105.1 PARTIAL ROOF AND PENTHOUSE ELECTRICAL DEMOLITION
E203.1 PARTIAL THIRD FLOOR PLAN – POWER – PHASE 1
E203.2 PARTIAL THIRD FLOOR PLAN – POWER – PHASE 2
E203.3 PARTIAL THIRD FLOOR PLAN – POWER – PHASE 2A & 3
E204.1 PARTIAL FOURTH FLOOR PLAN
E205.1 PARTIAL ROOF AND PENTHOUSE FLOOR PLAN
00 01 15 - 4
E303.1 PARTIAL THIRD FLOOR PLAN – PHASE 1 CABLE TRAY
E303.2 PARTIAL THIRD FLOOR PLAN – PHASE 2 CABLE TRAY
E401 ELECTRICAL PART PLANS
E402 ELECTRICAL PART PLANS
E501 ELECTRICAL DETAILS
E502 ELECTRICAL DETAILS
E601 PARTIAL RISER DIAGRAM – DEMOLITION
E602 PARTIAL RISER DIAGRAM – NEW WORK
E701 LIGHTING CONTROL DIAGRAMS
E801 ELECTRICAL SCHEDULE
E802 PANELBOARD SCHEDULE
E803 PANELBOARD SCHEDULE
E804 PANELBOARD SCHEDULE
TECHNOLOGY
T001 LEGEND
T101.1 PHASE 1 3RD FLOOR PLAN CONSTRUCTION
T101.2 PHASE 2 3RD FLOOR PLAN CONSTRUCTION
T101.2A PHASE 2A 3RD FLOOR PLAN CONSTRUCTION
T101.3 PHASE 3 3RD FLOOR PLAN CONSTRUCTION
T201.1 PHASE 1 4TH FLOOR PLAN CONSTRUCTION
T401.1 DETAILS & SCHEDULES
T402.1 DETAILS
T501.1 ENLARGED TR PLAN
FIRE PROTECTION
FP001 FIRE PROTECTION COVER SHEET
FPD103.1 THIRD FLOOR - FIRE PROTECTION - DEMOLITION - PHASE 1
FPD103.2 THIRD FLOOR - FIRE PROTECTION - DEMOLITION - PHASE 2
FPD103.2A THIRD FLOOR - FIRE PROTECTION - DEMOLITION - PHASE 2A
FPD103.3 THIRD FLOOR - FIRE PROTECTION - DEMOLITION - PHASE 3
FP103.1 THIRD FLOOR - FIRE PROTECTION - NEW WORK - PHASE 1
FP103.2 THIRD FLOOR - FIRE PROTECTION - NEW WORK - PHASE 2
FP103.2A THIRD FLOOR - FIRE PROTECTION - NEW WORK - PHASE 2A
FPD103.3 THIRD FLOOR - FIRE PROTECTION - NEW WORK - PHASE 3
FIRE ALARM
FA001 FIRE ALARM COVER SHEET
00 01 15 - 5
FA103.1 PARTIAL THIRD FLOOR PLAN – FIRE ALARM – PHASE 1
FA103.2 PARTIAL THIRD FLOOR PLAN – FIRE ALARM – PHASE 2
FA103.3 PARTIAL THIRD FLOOR PLAN – FIRE ALARM – PHASE 2A
FA105.1 PARTIAL ROOF AND PENTHOUSE PLAN – FIRE ALARM – PHASE 1
FA501 FIRE ALARM DETAILS
PLUMBING
P001 PLUMBING COVER SHEET
PD102.1 SECOND FLOOR – PLUMBING DEMOLITION – PHASE 1
PD102.2 SECOND FLOOR – PLUMBING DEMOLITION – PHASE 2
PD102.3 SECOND FLOOR – PLUMBING DEMOLITION – PHASE 3
PD103.1 THIRD FLOOR – PLUMBING – DEMOLITION – PHASE 1
PD103.2 THIRD FLOOR – PLUMBING – DEMOLITION – PHASE 2
PD103.3 THIRD FLOOR – PLUMBING – DEMOLITION – PHASE 3
P102.1 SECOND FLOOR – PLUMBING - NEW WORK - PHASE 1
P102.2 SECOND FLOOR – PLUMBING - NEW WORK - PHASE 2
P103.1 THIRD FLOOR – PLUMBING – NEW WORK – PHASE 1
P103.2 THIRD FLOOR – PLUMBING – NEW WORK – PHASE 2
P103.3 THIRD FLOOR – PLUMBING – NEW WORK – PHASE 3
P501 PLUMBING DETAILS
P601 PLUMBING RISER DIAGRAMS
P602 PLUMBING RISER DIAGRAMS
P603 PLUMBING RISER DIAGRAMS
MEDICAL GAS
MG001 MEDICAL GAS COVER SHEET
MGD103.1 THIRD FLOOR – MEDICAL GASES – DEMOLITION – PHASE 1
MGD103.2 THIRD FLOOR – MEDICAL GASES – DEMOLITION – PHASE 2
MGD103.2 THIRD FLOOR – MEDICAL GASES – DEMOLITION – PHASE 3
MG103.1 THIRD FLOOR – MEDICAL GASES – NEW WORK – PHASE 1
MG103.2 THIRD FLOOR – MEDICAL GASES – NEW WORK – PHASE 2
MG601 MEDICAL GAS DIAGRAMS
- - - E N D - - -
01 00 00 -1
SECTION 01 00 00
GENERAL REQUIREMENTS
GENERAL
1.1 SAFETY REQUIREMENTS
A. Refer to section 01 35 26, SAFETY REQUIREMENTS for safety and infection control requirements
1.2 GENERAL INTENTION
A. Contractor shall completely prepare site for building operations, including demolition and removal of existing structures, and furnish labor and materials and perform work for the renovation of 3rd floor Dialysis Unit at Bldg. No. 200, Northport VA Medical Center as required by drawings and specifications.
B. Visits to the site by Bidders may be made only by appointment with the Medical Center Engineering Officer.
C. Offices of The Pettit Group LLC , as Architect-Engineers, will render certain technical services during construction. Such services shall be considered as advisory to the Government and shall not be construed as expressing or implying a contractual act of the Government without affirmations by Contracting
Officer or his duly authorized representative.
D. Before placement and installation of work subject to tests by testing laboratory retained by Department of Veterans Affairs, the Contractor shall notify the Resident Engineer in sufficient time to enable testing laboratory personnel to be present at the site in time for proper taking and testing of specimens and field inspection. Such prior notice shall be not less than three workdays unless otherwise designated by the Resident
Engineer.
E. All employees of general contractor and subcontractors shall comply with VA security management program and obtain permission of the VA police, be identified by project and employer, and restricted from unauthorized access.
01 00 00 -2
1.3 STATEMENT OF BID ITEM(S)
A. ITEM I, RENOVATE DIALYSIS: ARCHITECTURAL SCOPE
1. Work includes demolition of the current space as necessary per the construction drawings and general construction, alterations, and necessary removal of existing structures and construction and certain other items.
2. This project is located within the Northport VA Medical
Center, Building 200, Northport NY. The project involves all design work and construction administration services needed to support the Renovation of the Dialysis Unit.
3. The existing Dialysis Unit currently is a combination of waiting room, outpatient exams, check-in areas, and administrative offices.
4. This Project includes renovation of approximately 5,330 square feet of existing space located at the third floor of the main hospital building (Building 200). Approximately 60% of this space was previously demolished and partially constructed for clinical space. The scope of work includes consideration of the existing utilities and work, including assessing the capability of the existing 1 year old RO water plant to meet the needs of the new design. This design will include a phasing plan to maintain operations, including but not limited to provisions for temporary water supply during commissioning of new clinical space.
5. Technical disciplines include but are not limited to architecture, fire protection engineering, interior design, structural engineering, mechanical engineering, electrical engineering, health facility planning, industrial hygiene, scheduling, and cost estimating. The design will comply with
VA-adopted codes and standards including VA Directives, Design
Manuals, Master Construction Specifications, Design Criteria and other Guidance on the Technical Information Library
(http://www.cfm.va.gov/til/).
http://www.cfm.va.gov/til/
01 00 00 -3
6. The renovation includes abatement of all hazardous materials and demolition of all existing utilities deemed not reusable and architectural features within the project area. The design may include areas existential to the footprint for mechanical and service systems.
7. Demolition of the existing project area includes, but is not limited to the removal of finishes, fixtures, interior walls, ceilings (to the upper floor slab and penetrations), lighting, electrical distribution, HVAC equipment, medical gas systems, fire/alarm systems, IT systems (to include BMS) and any existing/abandoned plumbing/mechanical piping.
8. The Hospital services will remain unchanged throughout construction. The Pettit Team will be responsible for appropriate phasing of the project to minimize impact to adjacent clinics, existing offices, permit safe passage and circulation, and minimize infection control requirements. The
Pettit Team will design and show all infection control / dust prevention measures required.
9. For all VA active systems under a maintenance contract, the buildout is to be completed by the prime contractor. Tie-ins are part of the GC’s contract; the prime contractor is to hire
VA maintenance contractor for final tie-in and acceptance to ensure warranties can remain in effect without conflict. The prime contractor is responsible for all programming, as well as infrastructure build-out and equipment make ready. This would include all temporary installation & removal within the construction/contract area, so areas are not damaged by others. The prime contractor can perform the work themselves, subcontractors, or hire the VA maintenance contractor directly.
10. The VA will be responsible for the temporary installation, operation, and emergency response portion with the temporary rented/leased DI water equipment/system only; Dialysis service will coordinate creating a purchase order for this temporary
01 00 00 -4 equipment. The prime contractor is not responsible for managing healthcare operations within their contract.
11. All Med-Gas devices, system tie-ins are to be performed by the prime contractor and these costs are to be covered under this contract at no additional cost to the Government. The prime contractor is responsible for contracting directly with the VA’s vendor tie-ins. The VA med-gas maintenance contractor will take over the handoff after final connections and monitor all system additions after connection.
12. Contractor to remove/relocate existing patient lifts from the construction area (see phasing plan). Contractor to turn over all removed components to the Government. Contractor to deliver safely removed components to a storage room located at
Northport Facility; Building / Room are to be determined & coordinated with the Government.
B. ITEM II, RENOVATE DIALYSIS: ELECTRICAL WORK:
1. Existing Conditions
a. A survey to document the existing electrical conditions within the area of work has been conducted by a third-party
MEP firm. This survey and a confirming survey investigating the branch panelboard’s source are the bases of our electrical design for this project. The facility’s essential electrical systems are broken into two branches:
life safety and critical. Current codes require three branches: life safety, critical, and equipment. Separation of the Essential Electrical Systems is outside the scope for this project. Both critical and equipment loads will be connected to the existing critical branch.
2. Demolition
a. Existing electrical devices, lighting fixtures, connections, wiring and conduit in the area of renovation will be demolished back to the source of power. The existing electrical panelboards will be removed in phase 1.
01 00 00 -5
Branch circuits feeding later phases will be backfed by new panelboards until they are demolished in phases 2, 2A and 3
3. New Work
a. The electrical systems and devices will be designed in accordance with the VA Electrical and Lighting Design
Manuals. Existing electrical loads will be determined to insure adequate power availability. New panelboard installations will be reviewed, along with adequate spare capacity. Documentation for de-energized work or shutdown impact to be determined for all panelboard work.
b. The building’s original normal and critical branch circuit panelboards in the space will be replaced in kind and reserved for the connection of existing loads. Two new panels for normal and critical loads will be provided for the new loads. In the penthouse, the existing motor control center will be utilized to feed the new rooftop equipment. In addition, a critical 208Y/120V panel in the penthouse will be replaced to allow for the addition of circuit breakers to serve new heat tracing.
c. As part of the mechanical design, a new roof top air handling unit is being provided. The largest mechanical load is the supply fan portion of the air handling unit consisting of two 5HP fans. An existing air handling unit currently supply the dialysis suite will be demolished as part of this project.
d. Specific information on the electrical systems is below:
1) Fire Alarm
a) New fire alarm initiation and notification devices will be provided throughout the areas of renovation and will be connected to the existing fire alarm system. An additional NAC booster panel will be required.
2) Lighting, Devices and Lighting Controls
01 00 00 -6
a) Luminaires will be provided and designed to comply with the 2015 International Energy Conservation Code.
LED luminaires will be provided to comply with lighting power density requirements and to provide dimmable lighting control. Lighting controls will be low voltage, 0-10V with occupancy sensors and distributed relays in non-patient care areas.
3) Low Voltage
a) Successful Security Bidder to coordinate with Division
08 with respect to the Physical Access Control (PACS) locking hardware for doors shown with electronic locks. The PACS controller equipment will be installed on the fourth floor and run down to the 3rd floor
Dialysis renovation where the door locations for card reader, door position switch(es), REX motion, electrified locking hardware are shown on the drawings. The head-end access control server/workstations are existing and the new equipment from this project will be administrated and controlled from the existing system.
b) Successful Security Bidder to install cameras at locations shown both within the Dialysis area shown on the drawings. The surveillance cameras will be routed to the OIT closet located in the Dialysis renovation area. Successful Security Bidder will connect cameras to the OIT existing network equipment. Coordination is required for network port and IP information with OIT.
Recording and administration of the cameras will be connected to the existing servers and workstations for the campus surveillance system.
c) Demo any existing paging speakers in the renovation area. Care should be given to the existing circuit, denoting on the drawings where the connection into the
01 00 00 -7 space was broken and that it did not impact areas other than the renovation space.
d) New paging work: Successful Bidder to extend existing
Paging speaker circuit into renovated space. Ensure amplifiers can handle the added capacity and tap the new installed speakers to the existing circuit.
e) GC to Coordinate cabling efforts & monitoring w/
Resident Engineer, COR & VA vendor’s; GC to allow access to others, for joint activity, after the walls are completed but prior to the ceilings going in.
4) Additional Requirements
a) Cabling
i. Conductors will be copper, single conductor THHN-
THWN - solid for 10 AWG and smaller, stranded for
8 AWG and larger.
ii. The minimum wire size to be used for lighting and power systems is 12 AWG.
iii. Smaller gauge cable may be used for lighting controls where required.
b) Raceways and Conduit
i. Install all power conductors in conduit.
ii. The minimum conduit size will be trade size 3/4-inch.
iii. Conduit will be EMT.
iv. Route low voltage wiring, such as that for lighting controls, in raceway.
c) Wiring Devices
i. Provide hospital grade switches and receptacles in non-patient care areas. Provide hospital grade receptacles in patient care areas.
ii. Devices should be ivory in color, where connected to normal power panelboards, and red in color with the word “Emergency” in white letters, where
01 00 00 -8 connected to emergency power panelboards.
Faceplates shall be stainless steel.
iii. Exterior (Outdoor) Receptacles: Provide weather resistant (WR) type with raintight while in-use covers and provide with integral ground fault
(GFCI) protection in accordance with the NEC.
iv. In toilet rooms and other areas of the building within 6 feet of a sink, provide receptacles with integral ground fault (GFCI) protection in accordance with the NEC.
d) Grounding and Bonding
i. Feeders will each include an individual equipment grounding conductor.
ii. All branch circuits will have a green equipment ground wire pulled with all circuits.
e. Motors
1) Provide motors, in general, with combination switch and fused disconnects and across-the-line motor starters.
2) Provide safety switches, in general, of the heavy-duty type.
f. Enclosures
1) Interior enclosures for equipment controls and disconnects will generally be general duty NEMA type 1.
Exterior enclosures will in general be weatherproof NEMA type 3R.
g. Identification
1) Identification of wiring and raceways shall meet minimum industry practice and requirements except provide supplemental identification where requested, for the benefit of building operation and maintenance personnel.
h. Testing and Field Instructions
1) Testing will be performed by the contractor.
01 00 00 -9
2) The contractor will be required to instruct the Owner’s
Representative on the proper operation and maintenance of the equipment and systems.
4. Calculations
a. The following calculations are included the design package.
1) Lighting Calculations
2) Electrical Load Calculations for Panelboards (shown on
Panelboard Schedules on drawings)
C. ITEM III, RENOVATE DIALYSIS: MECHANICAL WORK:
1. Existing Conditions
a. A survey to document the existing conditions was performed by a Henry Adams. At this time, the narrative and design are based on existing conditions and mechanical infrastructure indicated on available record drawings and the survey done by Henry Adams
2. Demolition
a. As part of this renovation, all existing services will be removed back to the point of concealment or the main.
3. New Work
a. Ductwork
1) Galvanized G90 steel round and rectangular sheet metal for supply, return and exhaust air. All ductwork details and leakage standards will conform with SMACNA requirements.
2) Flexible ductwork will be prohibited on this project.
b. Diffusers, Registers, and Grilles
1) Factory fabricated steel or aluminum with fixed or adjustable air discharge pattern and opposed blade damper for diffusers and registers.
2) Sidewall, supply and return registers where applicable with horizontal face.
3) Modular square louvered faced ceiling supply diffusers.
4) Modular square perforated faced ceiling return or exhaust air grille.
01 00 00 -10
5) Linear diffuser for perimeter space at windows with insulated plenum.
c. Ventilation, Area Pressurization and Air Changes
1) Outdoor air will be provided as required to offset exhaust, but not less than the minimum required by Code and VA Design Guidelines.
2) The overall space pressurization will be reviewed to ensure that VA requirements for individual space pressurization is followed, and the overall suite is maintained at a positive pressurization.
3) The VA Design Guide will be reviewed for room pressurization relationships, room air change requirements and outdoor air ventilation requirements.
4) Negatively and positively pressurized spaces will be designed per code and VA Design Guidelines.
d. Air Distribution
1) Supply: Air distribution will be, in general, overhead through ceiling mounted diffusers.
2) Return: Air will be returned, through ceiling mounted registers to return air main ductwork in the ceiling.
3) Exhaust Air Systems: No new exhaust fans are anticipated for this project. Toilet rooms and other spaces requiring exhaust will be connected through ceiling mounted registers to existing exhaust mains in the ceiling.
e. Proposed Equipment
1) Single Duct Air Terminal Units: New VAV boxes are proposed for all spaces based on VA design requirements and ASHRAE requirements for zoning. A maximum of three spaces will be connected to a single VAV box. All VAV boxes will have an integral sound attenuator (if required) and hot water reheat coil on the discharge.
2) Exhaust Fans: No new exhaust fans are proposed at this time. All exhaust ductwork will be connected to the
01 00 00 -11 existing exhaust mains located above the ceiling. The existing exhaust fans will have capacity for the exhaust airflow requirements of the project after removal of the existing exhaust grilles.
3) Reheat Hot Water: No heating water systems are proposed for this renovation. All reheat piping will be connected to existing reheat piping located above the ceiling.
4) The existing Air Handling Unit was found to be inadequate in airflow capacity to serve the new area. The existing unit is sized per airflow requirements at the time the building was constructed. Airflow requirements have since increased and the unit does not have the available airflow capacity to provide the required air changes to each space. As such, a new air handling unit will be provided. This unit will be located on the roof above the
4th floor on steel dunnage with vibration isolation. The existing steam and chilled water in the penthouse was found to have sufficient capacity to connect the new unit heating and cooling coils. Steam condensate will drain by gravity to existing mains on the 4th floor. A steam humidifier will be included in the AHU. Ducts will be routed down a new shaft provided on the 4th floor. The proposed new AHU will have a chilled water cooling coil, steam preheat coil, steam humidifier, supply fan, MERV-8 and 11 pre-filters and MERV-14 final filters. The new rooftop piping will be heat traced as required. A separate return fan will be provided on the roof as required by the new VA emergency epidemic requirements.
The unit and coils will be sized to handle 100% outdoor air during emergency epidemic mode. Control sequence is provided for manual activation of emergency epidemic mode.
f. Piping
1) All new piping shall be:
01 00 00 -12
a) Piping shall be per VA Master specifications.
4. Calculations
a. The following calculations are expected to be performed as part of the design process (See appendix H of the design narrative.)
1) Ventilation Air
2) Cooling Load Calculation (sensible and latent room loads, sensible and latent ventilation loads, sensible and latent total loads) at peak Outdoor air dry Bulb and wet
Bulb conditions per the VA HVAC Design Manual or ASHRAE
170.
3) Heating Load Calculation for the rooms and the ventilation load at peak Winter outdoor design conditions.
4) Calculation showing the LAT's leaving the chilled water coil (both dB and wB) in accordance with standard ASHRAE equations.
5) Air Balance
6) Dialysis Space Block Load calculation
7) Humidification load calculation at peak winter outdoor RH conditions.
8) Psychometric Analysis
9) AHU supply fan external static pressure calculation. AHU supply fan total static pressure calculation (assuming the worst case scenario with loaded filters).
D. ITEM IV, RENOVATE DIALYSIS: Plumbing & Fire Protection
Narrative
1. Existing Conditions
a. A survey to document the existing conditions was performed by Henry Adams. At this time, the narrative and design are based on existing conditions and plumbing and fire protection infrastructure indicated on available record drawings and the survey done by Henry Adams.
2. Demolition
01 00 00 -13
a. As part of this renovation, existing branch sanitary lines will be demolished back to the sanitary main on the floor below. Existing vent lines will be demolished to a point where they turn up to the floor above. Existing domestic cold, hot and hot water recirculation piping will be demolished back to the existing mains. Any piping not reconnected to as part of the renovation will be capped.
Domestic cold water, hot water and hot water recirculation piping will be capped and valved if not reconnected to.
Domestic water dead legs shall be removed.
b. Existing medical gas piping will be demolished back to the main and reconnected as part of the renovation. Oxygen and vacuum outlets will be provided at each dialysis station.
c. Existing sprinkler piping and heads will be demolished as part of the renovation back to the sprinkler main located above the ceiling.
3. New Work
a. Plumbing Fixtures
1) Water Closets – Wall-hung or floor mounted vitreous china with electronic flush valve
2) Bariatric Water Closets - Floor mounted vitreous china with manual flush valve and bariatric kick stand for bariatric support.
3) Lavatory – Wall-hung vitreous china with gooseneck wrist blade faucet.
4) Service Sink – Terrazzo with wall-mounted faucet mounted above sink with pail hook.
5) Clinical Service Sink – Wall-hung vitreous china with manual flush valve and bedpan washer.
6) Staff Lounge Sink – Countertop mounted stainless steel sink with wristblade faucet and hose spray.
7) Dialysis Wall Box – Recessed ABS Resin Wall Box with Cool
Grey Finish. Provided with male outlet, hose brackets and indirect drain
01 00 00 -14
8) Emergency eye and face wash – Wall mounted with stainless steel bowl and thermostatic mixing valve.
9) All sinks will have temperature limiting devices (hot water mixing valves).
b. Piping
1) Piping shall be per VA Master specifications.
c. Reverse Osmosis Equipment
1) The existing reverse osmosis system is of adequate capacity and will be reused to supply treated water to the new dialysis boxes. Piping will be demolished and reinstalled to accommodate phasing and new dialysis box locations. See the Marcor cut sheets and shop drawings within “Appendix G.”
d. Fire Sprinklers
1) New fire sprinklers shall be quick-response in accordance with VA Fire Protection Design Manual.
E. ITEM V, RENOVATE DIALYSIS: STRUCTURAL WORK:
1. Existing Conditions
a. To facilitate the installation of the new Dialysis Suite at
VA Northport Third Floor Renovation the following design load criteria will be used:
1) Live Loads (per VA Structural Design Manual):
a) Ward Rooms: 40psf
b) Corridors in Wards: 60psf
2. Dunnage
a. The new air handler unit requires structural steel support to provide adequate clearance between the roof and the unit. The dunnage will be constructed out of pipe posts, wide flange beams, and angle braces. All exterior steel shall be galvanized. The support and attachments will be designed for the code seismic loading required for mechanical support. Guy line bracing wires will brace the new exhaust stack.
3. Slab Openings
01 00 00 -15
a. New saw-cut slab openings are required to run mechanical ductwork vertically through the penthouse and fourth floor slabs. These new openings will be supported by steel channels framing the opening and supported by the existing concrete beams. The new steel will be attached to the existing beams with steel angles and post-installed expansion anchors. The new steel will require spray fireproofing to restore the fire rating of the floor system, see architectural report, drawings, and specifications for more details.
b. All new core drill locations are to be scanned using sub surface scanning at all new core locations, to coordinate the location of any existing conduit or reinforcement with the new cores.
4. Patient Lift System
a. The preliminary loading of the proposed patient lifts has been evaluated. The existing third floor structure is capable of supporting the additional load of the lift system. The lift manufacturer shall design the attachment and support of the lift within the new cold formed metal walls. The manufacturer shall consider the design criteria on the structural drawings when designing their connections.
5. Seismic Considerations
a. The scope of the renovations to the building do not meet the requirements for seismic evaluation outlined in VA H-
18-8 or ASCE 41. The building area of the proposed renovation does not exceed 50% if the total building area.
The project will not total more than 30% of the value of the existing facility. No significant structural alterations are being made to the existing building based on the IEBC. The additions will not increase the lateral loading on the building by more than 10%.
01 00 00 -16
b. New equipment such as the new Air Handler Unit and the
Patient Lifts will require seismic certification per VA H-
18-8 based on the building’s seismic design category.
c. New cold formed partition walls are non-structural partitions/ non-bearing walls. No additional seismic detailing would be required by code.
6. Applicable Codes
a. IEBC 2018 INTERNATIONAL EXISTING BUILDING CODE
b. ACI 318-19 BUILDING CODE REQUIREMENTS FOR REINFORCED
CONCRETE & COMMENTARY
c. AISC 360-16 SPECIFICATION FOR STRUCTURAL STEEL BUILDINGS
7. Applicable Specifications
a. 014529 Testing Laboratory Services
b. 024100 Demolition
c. 033053 CIP Concrete (Short Form)
d. 051200 Structural Steel Framing
8. Calculations
a. Calculations of the existing slab (See Appendix I)
F. ITEM VI: RENOVATE DIALYSIS: DEDUCT ALTERNATES
1. Deduct Alternate 1: In Lieu of providing smartglass within the sliding doors leading into stations #8 & #10. Provide Standard glazing with built in, between the glass panel, adjustable white shades.
2. Deduct Alternate 2: In Lieu of providing smartglass as station
#7. Provide standard glazing with built in, between the glass panel, adjustable white shades.
3. Deduct Alternate 3: In Lieu of providing sound batt insulation at all interior walls with STC wall rating of 45, provide sound batt at all interior wall to achieve a STC rating of 40.
4. Deduct Alternate 4: In Lieu of providing sound isolation within all interior partitions, only provide sound isolation within eh partition wall surrounding the conference room, exam room, and treatment area’s with a STC rating of 40.
01 00 00 -17
5. Deduct Alternate 5: In lieu of providing the Skyfactory ceiling element accent lighting and surrounding drywall soffit within the waiting/ reception area, continue the surrounding / adjacent ACT grid and tile pattern as shown.
6. Deduct Alternate 6: In lieu of providing the Skyfactory ceiling element accent lighting and surrounding drywall soffit near the nurse’s / treatment stations, continue the surrounding / adjacent ACT grid and tile pattern as shown.
1.4 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR
A. Drawings and contract documents may be obtained from the website where the solicitation is posted. Additional copies will be at Contractor's expense.
1.5 CONSTRUCTION SECURITY REQUIREMENTS
A. Security Plan:
1. The security plan defines both physical and administrative security procedures that will remain effective for the entire duration of the project.
2. The General Contractor is responsible for assuring that all sub-contractors working on the project and their employees also comply with these regulations.
B. Security Procedures:
1. General Contractor’s employees shall not enter the project site without appropriate badge. They may also be subject to inspection of their personal effects when entering or leaving the project site.
2. Before starting work the General Contractor shall give one week’s notice to the Contracting Officer so that security arrangements can be provided for the employees. This notice is separate from any notices required for utility shutdown described later in this section.
3. No photography of VA premises is allowed without written permission of the Contracting Officer. Patients and staff are not to be photographed at any time.
01 00 00 -18
4. VA reserves the right to close down or shut down the project site and order General Contractor’s employees off the premises in the event of a national emergency. The General Contractor may return to the site only with the written approval of the
Contracting Officer.
C. Guards:
1. The General Contractor shall provide unarmed guards at the project site after construction hours.
2. The Contractor shall provide the guards and VA police with communication devices as directed.
3. The general Contractor shall install equipment for recording guard rounds to ensure systematic checking of the premises.
D. Key Control:
1. The General Contractor shall provide duplicate keys and lock combinations to the Resident Engineer for the purpose of security inspections of every area of project including tool boxes and parked machines and take any emergency action.
2. The General Contractor shall install all permanent cores at completion of the work. See Section 08 71 00, DOOR HARDWARE and coordinate.
E. Document Control:
1. Before starting any work, the General Contractor/Sub
Contractors shall submit an electronic security memorandum describing the approach to following goals and maintaining confidentiality of “sensitive information”.
2. The General Contractor is responsible for safekeeping of all drawings, project manual and other project information. This information shall be shared only with those with a specific need to accomplish the project.
3. Certain documents, sketches, videos or photographs and drawings may be marked “Law Enforcement Sensitive” or
“Sensitive Unclassified”. Secure such information in separate containers and limit the access to only those who will need it
01 00 00 -19 for the project. Return the information to the Contracting
Officer upon request.
4. These security documents shall not be removed or transmitted from the project site without the written approval of
Contracting Officer.
5. All paper waste or electronic media such as CD’s and diskettes shall be shredded and destroyed in a manner acceptable to the
VA.
6. Notify Contracting Officer and Site Security Officer immediately when there is a loss or compromise of “sensitive information”.
7. All electronic information shall be stored in specified location following VA standards and procedures using an
Engineering Document Management Software (EDMS).
Security, access and maintenance of all project drawings, both scanned and electronic shall be performed and tracked through the EDMS system.
“Sensitive information” including drawings and other documents may be attached to e-mail provided all VA encryption procedures are followed.
F. Motor Vehicle Restrictions
1. Vehicle authorization request shall be required for any vehicle entering the site and such request shall be submitted
24 hours before the date and time of access. Access shall be restricted to picking up and dropping off materials and supplies.
2. A limited number of permits shall be issued for General
Contractor and its employees for parking in designated areas only. Contractor to coordinate with VA Medical Center Facility
Manager.
1.6 OPERATIONS AND STORAGE AREAS (FAR 52.236-10)
A. The Contractor shall confine all operations (including storage of materials) on Government premises to areas authorized or approved by the Contracting Officer. The Contractor shall hold
01 00 00 -20 and save the Government, its officers and agents, free and harmless from liability of any nature occasioned by the
Contractor's performance.
B. Temporary buildings (e.g., storage sheds, shops, offices) and utilities may be erected by the Contractor only with the approval of the Contracting Officer and shall be built with labor and materials furnished by the Contractor without expense to the Government. The temporary buildings and utilities shall remain the property of the Contractor and shall be removed by the Contractor at its expense upon completion of the work. With the written consent of the Contracting Officer, the buildings and utilities may be abandoned and need not be removed.
C. The Contractor shall, under regulations prescribed by the
Contracting Officer, use only established roadways, or use temporary roadways constructed by the Contractor when and as authorized by the Contracting Officer. When materials are transported in prosecuting the work, vehicles shall not be loaded beyond the loading capacity recommended by the manufacturer of the vehicle or prescribed by any Federal, State, or local law or regulation. When it is necessary to cross curbs or sidewalks, the Contractor shall protect them from damage. The Contractor shall repair or pay for the repair of any damaged curbs, sidewalks, or roads.
D. Working space and space available for storing materials shall be as determined by the Resident Engineer.
E. Workers are subject to rules of Medical Center applicable to their conduct.
F. Execute work in such a manner as to interfere as little as possible with work being done by others. Keep roads clear of construction materials, debris, standing construction equipment and vehicles at all times.
G. Execute work so as to interfere as little as possible with normal functioning of Medical Center as a whole, including operations of utility services, fire protection systems and any
01 00 00 -21 existing equipment, and with work being done by others. Use of equipment and tools that transmit vibrations and noises through the building structure, are not permitted in buildings that are occupied, during construction, jointly by patients or medical personnel, and Contractor's personnel, except as permitted by
Resident Engineer where required by limited working space.
1. Do not store materials and equipment in other than assigned areas.
2. Schedule delivery of materials and equipment to immediate construction working areas within buildings in use by
Department of Veterans Affairs in quantities sufficient for not more than two work days. Provide unobstructed access to
Medical Center areas required to remain in operation.
3. Where access by Medical Center personnel to vacated portions of buildings is not required, storage of Contractor's materials and equipment will be permitted subject to fire and safety requirements.
H. Phasing:
1. The Medical Center must maintain its operation 24 hours a day 7 days a week. Therefore, any interruption in service must be scheduled and coordinated with the Resident Engineer to ensure that no lapses in operation occur. It is the CONTRACTOR'S responsibility to develop a work plan and schedule detailing, at a minimum, the procedures to be employed, the equipment and materials to be used, the interim life safety measure to be used during the work, and a schedule defining the duration of the work with milestone subtasks. The work to be outlined shall include, but not be limited to:
2. To ensure such executions, Contractor shall furnish the
Resident Engineer with a schedule of approximate phasing dates on which the Contractor intends to accomplish work in each specific area of site, building or portion thereof. In addition, Contractor shall notify the Resident Engineer two weeks in advance of the proposed date of starting work in each
01 00 00 -22 specific area of site, building or portion thereof. Arrange such phasing dates to ensure accomplishment of this work in successive phases mutually agreeable to Medical Center
Director, Resident Engineer and Contractor, as follows:
3. Phase 1 – The existing dialysis suite, consisting of 9 patient care units and one isolation room, will remain active throughout this phase. The existing water treatment room
(A349), equipment storage / repair shop (A345), and restrooms
(A348a & A349) will remain operational & accessible throughout this phase. Once the designated construction area is demolished, including roof / 4th floor penetrations for the new rooftop HVAC unit and ductwork. Construction on the new suite can commence with VA COR approval.
a. Install temporary construction barriers within existing 3rd floor dialysis corridor (at the existing construction entry), within the corridor (running from A344 / A346 to existing restroom A349), within the supply closet (A350A), and at the end of existing dialysis unit adjacent to station # 1 / HVAC room (A354). Please see sheet AD101.1 for clarification.
b. Ensure all existing wall construction / construction barriers are properly built to ensure a continuous barrier between the area of work and active adjacent rooms as shown on the phase i demo plan.