Construction Cost Breakdown Form.xls
XLS spreadsheet 57 KB Posted
- Solicitation number
- W15QKN-25-Q-A122
About this file
The file is a Construction Cost Breakdown Form Excel template for a U.S. Army construction project in Orangeburg, NY. The solicitation (W15QKN-25-Q-A122) is a 100% small business set-aside for drainage system improvements and front entrance relocation at a military facility. The project is classified under NAICS code 237110 (Water and Sewer Line Construction), with a $45 million size standard, and will be awarded as a firm-fixed-price contract with a 210-day performance period.
Key submission requirements include providing a detailed cost breakdown using the attached Excel template, a technical capability statement, proof of SAM registration, valid insurance certificate, and comprehensive proposal documentation. Proposals are due via email to Mitchell Douglas and Jasmyne Peterson, with all questions to be submitted by April 22, 2025. The government requires detailed pricing information, including labor, equipment, and material costs, with a mandatory bond submission within 10 calendar days of award. The project is being managed by the Army Contracting Command - New Jersey on behalf of the 99th Readiness Division.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 25-Q-A122 - DBA WD NY20250020 (d. 03.14.2025).txt | TXT text file | |
| NY050-ORANGEBURG-SOW.docx | DOCX document | |
| Solicitation - W15QKN25QA122.pdf | ||
| NY050-ORANGEBUR-WORK IDENTIFICATION MAP.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet2
| ID | Sort | Type | Description (to include labor,equipment, material type and grade) | Quantity | Unit Measure | Labor in Manhours | Equipment | Material | Total Cost | ||||||||
| Crew (skill set) | Labor Hours | Total Hrs | City Cost Index | Unit Cost* | Total Labor Cost* | Unit Cost | Total Equipment Cost | City Cost Index | Unit Cost | Total Material Cost | |||||||
| Totals | |||||||||||||||||
| GENERAL CONTRACTOR | |||||||||||||||||
| OVERHEAD | $ - 0 | ||||||||||||||||
| $ - 0 | |||||||||||||||||
| PROFIT | $ - 0 | ||||||||||||||||
| $ - 0 | |||||||||||||||||
| BOND | $ - 0 | ||||||||||||||||
| GRAND TOTAL | $ - 0 | ||||||||||||||||
| Unit Cost* | Cost for one labor hour of the specified crew | ||||||||||||||||
| Total Labor Cost* | "=Unit Cost x Total Hours" |