Compliance Manual (1).pdf

PDF 2 MB Posted

Attached to
Capital Region Timber Bridge Feasibility Initiative
Solicitation number
2140536
Issued by
Saratoga County, New York

About this file

Summary

This is the Northern Border Regional Commission (NBRC) Grant Administration & Compliance Manual for February 2026, which provides comprehensive guidance for recipients of federal grant funding from NBRC, a partnership between the federal government and the states of New York, Vermont, New Hampshire, and Maine. The manual covers three primary grant programs: the Catalyst Program designed to stimulate economic growth through projects such as public water and wastewater infrastructure modernization, workforce development, and outdoor recreation expansion; the Forest Economy Program supporting forest-based industries and infrastructure; and the Timber for Transit Program advancing wood-based materials in transportation infrastructure. NBRC grant awards are made available in two funding rounds annually, with successful applicants notified in June (spring cycle) or December (fall cycle). Key project initiation requirements include completion of negotiations, execution of Local Development District (LDD) contracts for grant administration (unless waived), issuance of either a Partial or Full Notice to Proceed before any NBRC or matching funds can be committed or expended, and satisfaction of National Environmental Policy Act (NEPA) requirements, which vary from Categorical Exclusion reviews (typically under one month) to Environmental Assessment reviews (six to twelve-plus months requiring estimated consultant costs of $10,000 to $25,000). Grantees must secure a Full Notice to Proceed within one year of award date, and all match funding must be committed within one year following the award year.

LDD grant administration costs are eligible NBRC expenses limited to $8,000 for awards of $400,000 or less, or 2 percent of the NBRC requested amount for awards exceeding $400,000, with costs included as a dedicated line item in project budgets. All procurement actions must follow federal standards under 2 CFR 200.318 through 200.327, including methods of purchasing ranging from micro-purchases (under $15,000) to competitive sealed bids and competitive proposals, with sole source procurement permitted only with written NBRC authorization and documented justification. Projects must comply with the Build America, Buy America Act (BABAA) requirements for infrastructure projects issued after May 8, 2023, mandating that all iron, steel, manufactured products, and construction materials be produced in the United States, with limited waivers available for de minimis purchases (up to 5 percent of project costs or $1,000,000 maximum), small grants at or below $350,000, and minor components. Equipment purchases exceeding $10,000 require prior NBRC approval and must include periodic inventories every two years, while real property acquisitions and improvements of $250,000 or greater require a Notice of Federal Interest to be filed and recorded. Grantees are required to submit bi-annual Performance Progress Reports (SF-PPR) and annual Financial Reports (SF-425) by specified deadlines, with closeout documentation due within 90 days of project completion, and must maintain supporting documentation for three years from submission of the final financial report in accordance with 2 CFR 200.334.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

NBRC Grant Administration & Compliance Manual 1 2026

NBRC Grant Administration & Compliance Manual

February 2026

Northerder Regional Commission

Table of Contents updated March 18, 2026

NBRC Grant Administration & Compliance Manual 2 February 2026

Overview

Overview of Local Development Districts (LDD)

LDD Contracts with Grantee

Scope of LDD Contract

Timing of Awards and Project Initiation

Notice of Award

Completion of Negotiations

Local Development District (LDD) Contract

Grant Agreement

National Environmental Protection Act (NEPA)

Partial Notice to Proceed

Full Notice to Proceed

Securing Match

Procurement

Code of Conduct

Solicitation

Competition

Small/Minority/Women/Veteran-Owned Businesses, Labor Surplus Area Firms

Bonding

Methods of Purchasing

Micro-Purchases

Simplified Acquisition Procedures

Competitive Sealed Bids

Competitive Proposals

Noncompetitive Proposals/Sole Source

Contract Award

Contract Administration

Project Signage

Property

Types of Property

Equipment

NBRC Grant Administration & Compliance Manual 3 February 2026

Real Property

Real Property Monitoring

Reporting

Closeout Reporting

Requests for Reimbursements

Timing of Reimbursements

Completing the SF270

How long does it take to receive funds?

Types of Changes

Change in Key Personnel (Authorized Official)

Budget Redirection and/or Scope of Work Change

Requests for Extension

Other Project Changes

Programmatic Compliance

Enforcement of Compliance

Monitoring

Site Visits

Records Retention and Access

Dispute and Appeals

Place of Record

Website

Contacts

APPENDIX A: PROJECTS FUNDED THROUGH THE NBRC-USDA PARTNERSHIP

APPENDIX B: BUILD AMERICA BUY AMERICA ACT

APPENDIX C: COMMUNITY SITE VISIT PROTOCOL

APPENDIX D: GLOSSARY OF TERMS

Northerder Regional Commission

NBRC Grant Administration & Compliance Manual 4 February 2026

Overview

The Northern Border Regional Commission (NBRC) is one of ten Federal-State partnerships created to improve the economic vitality of a region sharing common attributes. Authorized by Congress in 2008 (PUB.L. 110–246, Sec. 14217) and first appropriated with funds by Congress in 2010, NBRC was reauthorized in the 2014 Farm Bill, in 2018, and again in 2024.

The NBRC is a partnership between the federal government and the states of New York, Vermont, New Hampshire, and Maine. NBRC targets resources to promote economic growth strategies and projects within its member states. The Commission is composed of a Federal Co- Chair appointed by the President and confirmed by the United States Senate, and the Governors of each state. The Governors are represented on the NBRC by their chosen alternate.

The decision-making process of the Commission is comprised of these five voting members.

Each State also has a State Program Manager, who serves as the primary point of contact for entities interested in NBRC funding.

By investing in projects that address shared regional challenges and common opportunities, the NBRC plays a critical role in helping rural communities retool their economies for the future.

The Northern Border region is poised for economic revitalization if it can modernize its infrastructure, invest in business and workforce development, and build its capacity for community economic development. The NBRC is uniquely positioned to make these pivotal improvements possible.

By statute (40 U.S.C. §15702), the NBRC is required to annually assess the level of economic and demographic distress in its service area. The resulting designations reflect whether the NBRC can provide grants within a county.

Only projects within the NBRC’s service area are eligible for funding under 40 U.S.C. §15733.

NBRC Grant Programs

This manual covers compliance for projects funded by the Northern Border Regional Commission’s three competitive grant programs. Where there are discrepancies or differences, those will be noted or specifically called out for the various programs. This Compliance Manual is primarily intended for recipients of the NBRC grant funding. Entities seeking grant funding from the NBRC should refer to the NBRC Grant Programs User Manual for more information.

Catalyst The Catalyst Program is designed to stimulate economic growth and inspire partnerships that improve rural economic vitality across the four-state NBRC region. NBRC encourages projects that take a creative approach to addressing an economic need or opportunity in the region, alleviate economic distress, and contribute to economic growth.

https://www.nbrc.gov/uploads/005%20ABOUT%20NBRC/40%20USC%2C%20Subtitle%20V.pdf https://uscode.house.gov/view.xhtml?path=/prelim@title40/subtitle5&edition=prelim https://www.nbrc.gov/content/program-areas

NBRC Grant Administration & Compliance Manual 5 February 2026

Successful projects support a broad range of economic development initiatives such as, but not limited to, projects that modernize and expand access to public water and wastewater services, revitalize transportation infrastructure, establish workforce development programs and facilities, grow the outdoor recreation economy, and provide access to new childcare and healthcare facilities.

• Economic Development Administration (EDA) Collaboration Grant:

Funded under the Catalyst program, beginning in 2019, Congress directed the EDA to collaborate with the NBRC to fund projects aligned with the economic development objectives of both Agencies. The unique partnership between the NBRC and EDA has extended the ability of both Agencies to fund economic development projects in the NBRC region.

• United States Department of Agriculture (USDA) Collaboration Grant:

Funded under the Catalyst program, beginning in 2019, Congress directed the USDA to collaborate with NBRC to fund projects aligned with the economic development objectives of both Agencies. The unique partnership between the NBRC and USDA has extended the ability of both Agencies to fund economic development projects in the NBRC region.

Forest Economy Program (FEP) The Forest Economy Grant Program stimulates economic growth in the forest-based industries, including new technologies and viable business models, across the NBRC four-state region. The Forest Economy Program supports a broad range of economic development initiatives, including infrastructure, which directly supports timber and forest-based industries.

The Forest Economy Grant Program will prioritize funding for projects that demonstrate both readiness and projected direct impacts on the region’s forest economy and communities.

Projects must be consistent with the investment priorities of the Forest Economy Program, and where applicable, advance local forest economy initiatives.

Timber for Transit (T4T) The purpose of the Timber for Transit Program is to advance the use of wood-based materials and composites (advanced wood materials) through applied research and demonstration projects that showcase the suitability of such materials to transportation and transportation adjacent infrastructure.

Highly competitive projects will demonstrate and widely promote the utility of high value forest products (e.g. glued laminated timber, cross laminated timber, composite materials, etc.) in transportation infrastructure and planning for extreme weather readiness. Transportation infrastructure shall mean construction, alteration, or repair, for the purpose of transporting people and goods, including fixed installations and rights of way necessary for transporting

NBRC Grant Administration & Compliance Manual 6 February 2026 from one point to another, including infrastructure that improves economic mobility for individuals.

Overview of Local Development Districts (LDD)

The NBRC Federal-State partnership is aided by a group of regional organizations called Local Development Districts (LDDs) that assist the NBRC in its outreach activities and administer NBRC investments for grantees. All NBRC awardees are required to work with an LDD as a grant administration and documentation support/technical assistance partner, unless an LDD waiver was approved at the preapplication phase of the process. LDD’s will work alongside grantees in the GMS and with reimbursements and other administration tasks.

LDDs provide feedback to the Commission on its current programs and assist in identifying future areas of focus for the Commission. LDDs are either an already existing federally designated Economic Development District, as certified by the US Economic Development Administration, or an organization similar in nature to a regional planning commission or regional development commission.

LDDs are knowledgeable about other Federal and State programs that help fund economic and community development projects. They are also aware of local concerns, as most engage in regional economic development planning to varying degrees. All are recognized by the NBRC as being proficient in administering Commission funds for grantees.

LDDs are compensated for their grant administration services through a reimbursement process with the grantee. The grant administration fee for NBRC awards is as follows:

• $8,000 for awards of $400,000 or less.

• 2% of NBRC requested amount for awards above $400,00. LDD grant administration costs are an NBRC eligible cost for an amount not to exceed the formula. LDD grant administration costs must be reflected as a line item within the project budget (SF424cbw) submitted.

LDDs are compensated for their grant administration services through a reimbursement process with the grantee. The grant administration fee for NBRC awards is as follows:

• $8,000 for awards of $400,000 or less.

• 2% of NBRC requested amount for awards above $400,000. LDD grant administration costs are an eligible NBRC cost for an amount not to exceed the formula. LDD grant administration costs must be reflected as a line item within the budget (SF424cbw) submitted for the project.

NBRC Grant Administration & Compliance Manual 7 February 2026

If grant administration assistance is needed, beyond the total available under the formula, those must be paid for with matching funds.

Benefits of a Local Development District

• Regional collaboration and partnership with other LDDs and a Federal Agency.

• Opportunity to assist NBRC in developing future programs that benefit the region.

• LDDs will be the designated grant administrators for competitive grant investments within their region.

• Federal legislation states that the Northern Border Regional Commission, “shall enhance the capacity of, and provide support for, local development districts (LDD) in its region.” It outlines responsibilities that LDDs have once they are designated.:

• “Operate as a lead organization serving multi-county areas in the region at the local level”;

and,

• “Assist the Commission in outreach activities for local governments, community development groups, the business community, and the public”; and,

• “Serve as a liaison between State and local governments, nonprofit organizations, educational institutions, the business community, and citizens”; and,

• “Assist those described above to identify, assess, and facilitate projects and programs to promote economic development of the region.”

• LDDs shall attend both quarterly and annual training sessions provided by NBRC staff.

LDD Contracts with Grantee

All grantees are required to contract with a Local Development District (LDD) unless they are a state agency or have requested and been granted an LDD waiver from the NBRC at the preapplication phase of the process. Documentation of the grant administration contract must be provided to NBRC as part of the documentation required to receive a Partial or Full Notice to Proceed.

LDDs will have the choice between invoicing a grantee for hours of work performed or for quarterly advancements for services. The payment structure they choose for your project will be outlined in the LDD Contract. Advance payments must be limited to the amount needed and be timed with actual, immediate cash requirements of the recipient in executing the contract.

If a grantee is granted an LDD waiver and wishes to self-administer, they are held to the same allowance as an LDD ($8,000 for awards of no more than $400,000 and 2% for all awards above $400,001). The cost of same must be included in the project budget (SF424cbw) as a dedicated line item.

Engage with your LDD early in the process for support.

NBRC Grant Administration & Compliance Manual 8 February 2026

NBRC will allow a grantee to request a reimbursement for LDD costs only, in alignment with the ratio allowed. If an LDD chooses to invoice the grantee for quarterly advancements, their contract must include the following:

• Total amount of contract not to exceed the allowed amount

• Period of performance of the LDD contract, in alignment with the project’s grant agreement

• Language that addresses a situation where the project may not be completed within the period of performance, (e.g. project requires an extension to complete and still needs LDD assistance)

• A detailed description of the intended LDD support services they will be undertaking

• Method of payment specific to the intended invoicing and reimbursement schedule the parties are agreeing to

• Detailed description of costs and activities that will occur each quarter

• Details on labor categories and associated hourly rates for each LDD staff person who will be working on the contract

• Language addressing a situation where LDD costs are advanced, and the project ends abruptly Scope of LDD Contract

LDDs and grantees are required to host a Project Kickoff Meeting at the beginning of the award to go over roles and responsibilities of grant administration. The date of this meeting should be recorded in the LDD contract. LDDs shall have the following scope of services pertaining to the Grant Administration:

• Partial and/or Full Notice to Proceed Documentation: Assist with preparing and submitting required documentation to NBRC. For projects funded from 2024 forward, this includes assistance with uploading the LDD contract in the GMS, assist with getting the Partial Notice to Proceed (PNTP) for LDD costs in place and submitting their matching funds documentation.

• Quarterly & Annual Reporting: Ensure the accurate and timely submission of quarterly and annual reports that provide a meaningful overview of project status.

• Reimbursement Requests: Provide guidance on preparing and submitting reimbursement requests, including the SF-270 form, to ensure requests are accurate and within the approved budget. Grantees are responsible for tracking expenses and maintaining financial records. LDDs may assist with documentation for NBRC desk reviews and verification of reimbursed and matching funds.

• Contract Amendments: Assist with amendments such as changes to authorized officials, budget revisions, extensions, or scope changes.

• Closeout Reporting: Ensure timely and accurate submission of all required closeout materials.

• General Assistance: Provide guidance on procurement responsibilities, securing contractors, and general NBRC grant requirements.

NBRC Grant Administration & Compliance Manual 9 February 2026

NOTE: LDDs are not responsible for conducting procurement activities, evaluating bids, interviewing consultants, or performing services beyond those outlined in the grant administration contract.

Project management by an LDD is an allowable cost but is outside the scope of the LDD contract. These costs require prior written approval from NBRC, must be listed separately from LDD administration costs in the project budget, and should be governed by a separate contract between the grantee and the LDD. Project management is not considered a sole source activity.

Timing of Awards and Project Initiation

All NBRC grant programs are made available in two rounds of funding in Spring and Fall. FY 24 awards and onward will be managed within NBRC’s Grants Management System (GMS). All grant lifecycle phases, steps, and documentation requirements will be communicated and maintained within the online grant record. Please see Appendix C for additional guidance.

NBRC Grant Administration & Compliance Manual 10 February 2026

NBRC notifies successful applicants of their award amount in June (spring cycle) or December (fall cycle) via a letter sent by email to the project’s Authorized Official (AO). This letter will come through the Grants Management System (GMS) portal. Please note, this is not an approval to expend funds.

Reminder: A notice of award is not approval to expend funds. A Partial or Full Notice to Proceed (Step 6 &7) must be issued to commit (i.e., execute a contract for services) or expend both NBRC funds and match/cost share funds.

Completion of Negotiations

After the award, NBRC works with grantees to complete any required negotiations, including submission of missing or revised documents. All negotiations must be successfully completed before funds are available for use.

For funds to be allocated to a project, the Authorized Official must acknowledge the award, provide required financial information, and complete any application revisions requested by

NBRC.

All required negotiations and document revisions will be completed through NBRC’s Grants Management System (GMS).

Reminder: The allocation of federal funds is not approval to expend funds. A Partial or Full Notice to Proceed (Step 6 &7) must be issued to commit (i.e., execute a contract for services) or expend both NBRC funds and match/cost share funds.

Scheduling a Project Kick Off Meeting with the LDD should happen at this stage, to finalize any terms of agreement for the LDD contract. The LDD provides grant administration review and support, to assist grantees to learn with a built-in tech assistance provider, throughout the entire performance period. You may not incur any other expenses related to this contract until you receive either a Partial Notice to Proceed or a Full Notice to Proceed. To be reimbursed for LDD grant administration services, you need to receive a PNTP or NTP (Step 6 &7).

For Grantees awarded funding prior to 2024, the required PNTP documentation must be submitted to NBRC via admin@nbrc.gov. For projects funded from FY24 forward, the request

Notice of Award

Local Development District (LDD) Contract mailto:admin@nbrc.gov

NBRC Grant Administration & Compliance Manual 11 February 2026 must be made via NBRC’s Grants Management System (GMS). See Step 6, Partial Notice to Proceed for additional information

Please see the Role of the Local Development Districts (LDD) and Notice to Proceed section of this manual for more information.

An executed LDD contract (if applicable) is part of the documentation required to be submitted to receive a Notice to Proceed. All grantees are required to contract with an LDD unless they applied for and were approved for a waiver in advance of the submission of their application for funding, are a Local Development District or are an agency of State Government.

There will be no third-party grant administration for NBRC grants. Consistent with its congressional mandate to build the capacity of Local Development Districts (LDDs), NBRC sole sources grant administration work to LDDs. Grantees may use LDDs for administrative assistance. State agencies and entities that have received an approved LDD waiver from NBRC are exempt from this requirement.

Once all required application support documents have been obtained, NBRC issues Grant Agreements for projects. The following must be completed to issue a grant agreement:

• Obligation of Federal Funds (Step 2)

• Executed LDD Contract (Step 3) (not required to be issued a grant agreement but is required if a project will be seeking a Partial Notice to Proceed (PNTP) for grant administration costs.)

The grant agreement serves as the contract between NBRC and the grantee. It includes basic project information and all applicable grant provisions.

Other items covered in the Grant Agreement:

• Budget: Approved expenditure line items may not be changed without prior written NBRC approval (2 CFR 200.308).

• Construction: The agreement will identify whether the project is construction or non-construction, which determines additional reporting requirements, including Build America Buy America Act (BABAA)

• Real Estate and/or Equipment: The agreement will note any real estate, easement, or equipment purchases, which carry additional reporting requirements.

Grant Agreement https://www.nbrc.gov/content/local-development-districts

NBRC Grant Administration & Compliance Manual 12 February 2026

• Sub-recipients: The agreement outlines any funds sub-awarded to entities other than the recipient. All other contracts, except LDD administration, must follow federal procurement procedures.

Enacted in 1970, the National Environmental Policy Act (NEPA) requires federal agencies to consider the environmental impacts of their actions and decisions before proceeding. NEPA does not mandate choosing the action with the least environmental impact; it ensures that potential environmental effects are considered in agency decision-making before a Notice to Proceed is issued.

To analyze potential environmental impacts and streamline the NEPA process, NBRC will:

• Work with our environmental consultant to review your submitted NEPA intake form, which helps determine the required level of NEPA review.

• Notify you, the grantee, of the NEPA documentation that must be completed and submitted to NBRC.

• When NEPA requirements are being met for another federal funder, review that funder’s findings to determine if NBRC can adopt them.

Depending on the level of NEPA analysis required (see below), the NEPA process may take longer than the other required approvals needed to receive a Notice to Proceed. Grantees may request a project amendment to adjust the project budget and timeline, if a determination is made that your project requires a higher level of environmental review than was initially anticipated. NBRC can also issue a Partial Notice to Proceed to cover costs related to completing NEPA. See the Partial Notice to Proceed section of this manual for additional guidance.

These include, but are not limited to, the National Environmental Policy Act (NEPA), which prohibits the obligation or expenditure of project related NBRC funds and non-NBRC funds for activities with physical impacts or which limit the choice of alternatives until the environmental review process is completed and removal of environmental review grant conditions are received from NBRC.

IMPORTANT! No vendor contracts, commitments of funds or expenditure of match funding without NBRC approval is allowable. Federal requirements on funding restrict NBRC from allowing funds to be deployed until specific requirements are met. NEPA must be satisfied before the grantee makes an irreversible or irretrievable commitment to resources.

National Environmental Protection Act (NEPA)

NBRC Grant Administration & Compliance Manual 13 February 2026

Levels of NEPA Analysis

Categorical Exclusion (CATEX): A category of actions that is predetermined to not individually or cumulatively have a significant effect on the human environment (i.e., planning only, workforce training programs)

• Typically for maintenance, repair or renovation and non-construction activities

• Brief review, no public comment period unless another federal requirement is triggered

• Typically completed in < 1month.

• No public comment period (unless another federal requirement is triggered, such as

Section 106 (historical structures)

• If project is a CATEX, NBRC in coordination with our environmental consultant, will prepare, execute and issue CATEX Determination.

Environmental Assessment (EA): Prepared when an action may or may not cause significant impacts

• Typically for new construction activities

• Robust review, typically ranging from 6 – 12+ months

• Often require hiring a consultant to create NEPA Environmental Assessments

• Estimate $10,000-$25,000 (based on project details)

• Work with NBRC to secure a Partial Notice to Proceed (PNTP) to complete NEPA

• Preliminary design plans for NEPA may also require securing a PNTP

• Utilize NBRC’s EA Template and Guidance document for detailed instructions guidance, and examples see www.nbrc.gov/nepa

• EA Draft review Process generally requires 2-4 reviews and each review by

NBRC/environmental consultant takes 1-2 weeks. Includes a 30-day public comment period

• Finding of No Significant Impact (FONSI) - NEPA satisfied, grantee can move to securing a Full Notice to Proceed

Environmental Impact Statement (EIS): Prepared when an action is expected to cause a significant impact on the human environment

Please Note: Even if a project may qualify for a CATEX, additional requirements, such as Section 106 (historic structure), Section 7 (Endangered Species), and 8-Step Analysis (Floodplains & Wetlands) also need to be taken into consideration from both budget and timeline perspectives.

Understanding NEPA Implementation Across Federal Agencies

1. Varied Implementation: Each federal agency implements the NEPA differently.

2. Agency-Specific Procedures: Agencies are required to adhere to their own NEPA procedures and guidelines.

3. Example: USDA vs. NBRC:

PRO TIP!

Plan for a 6–12-month review period!

http://www.nbrc.gov/nepa

NBRC Grant Administration & Compliance Manual 14 February 2026

• USDA Experience: A project categorized as a CATEX under USDA regulations.

• NBRC Regulations: The same project may not be considered a CATEX under NBRC regulations.

4. Takeaway: Experience with NEPA procedures in one agency does not guarantee the same outcomes in another agency.

Categorical Exclusion (CATEX)

• Renovations/Replacement o Do not change the functional use of property

• Demolition (non NRHP eligible structures)

• Additions (on adjacent disturbed land)

• Acquisition and installation of equipment

• Small new construction projects (on previously disturbed land)

Environmental Assessment (EA)

• Renovations that change the functional use of property

• Demolition on National Register of Historic Places (NRHP) or eligible places

• Additions on previously undisturbed lands

• Larger new construction

NEPA Resources

• NBRC Website

• Local Development Districts: Some LDD partners are familiar with completing NEPA

(whether or a prior NBRC award or through other federal funders). If an LDD can assist a grantee with completion of NEPA, this is an eligible NBRC cost and is separate from the LDD grant administration allowance. If a grantee needs assistance with completing NEPA and access to NBRC grant funds to complete NEPA, they should consider requesting a Partial Notice to Proceed (PNTP) to cover NEPA related costs as well as LDD grant administration assistance.

• Contractors: In some instances, it may make sense for an applicant to work with a contractor with NEPA experience to support the development of NEPA documents.

While NBRC does not require a stand-alone NEPA contract to be competitively bid, as the nature of the activity is limited in nature and often falls under the federal government’s micro-purchase, grantees are encouraged to solicit estimates from an adequate number of qualified sources. If the contract exceeds the federal government’s micro-purchase threshold of $15,000, grantees must solicit an adequate number of qualified sources as part of the process.

If the grantee’s own procurement procedures establish a lower dollar limit than that established by the federal government, for the micro-purchase and/or simple acquisition threshold, the lower limit must be followed. In addition to inclusion of clauses that define a sound complete and enforceable agreement, the grantee will https://www.nbrc.gov/content/NEPA

NBRC Grant Administration & Compliance Manual 15 February 2026 ensure that the contract contains in text or adopts by reference the clauses contained in 2 CFR 200, Appendix II, as applicable.

• State Historic Preservation Offices. Contact information for these offices can be found on the NEPA resources page of the NBRC website here: NEPA Resources.

A Partial Notice to Proceed (PNTP) can be utilized to cover the following expenses that may be incurred prior to a Full Notice to Proceed is issued, in alignment with the project budget (SF424cbw):

• LDD assistance (Up to 50% of the LDD fee is allowable). LDD costs can be incurred back to confirmation of the commitment of funds for the award.

• Tasks associated to complete NEPA including environmental consultants as approved by NBRC (scope, budget, timeline). See detailed NEPA contract guidance above.

Reminder: The date of a Partial Notice to Proceed is very important!

All grantees must receive a Partial or Full Notice to Proceed before they can commit or expend any NBRC funds or match funds that are part of the NBRC funded project.

The following items must be in place for a Partial Notice to Proceed to be issued.

• Completion of Negotiations (Step 2)

• Executed LDD Contract (Step 3) (if applicable)

• Fully executed Grant Agreement (Step 4)

• Budget, scope of work to be completed, & timeline for completion (Includes NEPA and all other assistance)

• Form 1002 Committed Match Form and Documentation of Committed Match to support

PNTP activities and costs only (if applicable)

The PNTP request submittal must include the following:

• Executed PNTP Request Form o This form will provide NBRC with a clear understanding of project activities and associated costs o The PNTP NBRC creates and issues to the grantee will provide clear authorization language of the activities and funds covered by the PNTP

• Any required documentation not previously provided to NBRC in Steps 2-4, such as NEPA scope, budget and timeline and/or NBRC Form 1002 Committed Match and Supporting Documentation (if applicable)

Partial Notice to Proceed https://www.ecfr.gov/current/title-2/subtitle-A/chapter-II/part-200 https://www.nbrc.gov/content/NEPA https://www.nbrc.gov/content/administration

NBRC Grant Administration & Compliance Manual 16 February 2026

Projects requiring a Notice of Federal Interest as required per 45 CFR 1303.46 may incur costs as authorized in the PNTP, for LDD grant administration and NEPA related activities, and are eligible to be reimbursed for costs of same before the NFI is recorded. If the project involves purchase of property, and those funds are being considered as part of match/cost share, a PNTP may need to be requested if the closing will occur prior to the project securing a Full Notice to Proceed.

Once the project receives a Full Notice to Proceed, recordation of the NFI must occur when property is purchased or when construction or renovation begins. A copy of the notarized NFI and proof of recordation must be provided to NBRC before reimbursement of funds is authorized under the Full Notice to Proceed. Fees charted for recording or modifying the NFI may be charged to the grant.

No reimbursements will be processed for work conducted prior to receiving a Partial or Full Notice to Proceed. In addition, any match/cost share funds committed (i.e., executed contracts for service) or expended prior to the issuance of a Partial or Full Notice to Proceed will NOT be eligible.

If a grantee requires a Partial Notice to Proceed for some project activity other than LDD assistance and/or completion of NEPA, such as to cover a down payment on property acquisition, please contact NBRC for guidance via admin@nbrc.gov.

IMPORTANT! No vendor contracts, commitments of funds or expenditure of match funding without NBRC approval are allowed. Federal requirements on funding restrict NBRC from allowing funds to be deployed until specific requirements are met.

These include, but are not limited to, the National Environmental Policy Act (NEPA), which prohibits the obligation or expenditure of projects related NBRC funds and non-NBRC funds for activities with physical impacts or which limit the choice of alternatives until the environmental review process is completed and removal of environmental review grant conditions are received from NBRC.

NBRC requires its grantees to secure a Full Notice to Proceed (NTP) within a year of date of award. Failure to secure a Full NTP within that time will require the grantee to submit a request for an NTP extension documenting the challenges and delays to date and the intended timeline to secure an NTP. The extension requires review and approval from the State(s) where the project was funded. If granted, the NTP extension will be for one year. NBRC reserves the right to not allow multiple extensions on the same project if significant progress toward securing an NTP is not satisfactorily demonstrated.

Full Notice to Proceed https://www.ecfr.gov/current/title-45/subtitle-B/chapter-XIII/subchapter-B/part-1303/subpart-E/section-1303.46

NBRC Grant Administration & Compliance Manual 17 February 2026

Reminder: The date of a Full Notice to Proceed is important!

A Full Notice to Proceed (NTP) authorizes the grantee to commit and expend funds for all project related activities in alignment with the project budget (SF424cbw) on file.

The following items MUST be in place before a Full Notice to Proceed will be issued.

• Obligation of Federal Funds (Step 2)

• Executed LDD Contract (Step 3) (if applicable)

• Fully executed Grant Agreement (Step 4)

• Documentation of satisfactory completion of National Environmental Policy Act (NEPA)

(Step 5)

• NBRC Form 1002: Documentation of committed match. The amount of match listed in the grant agreement must be committed to serve as match for the project and not been previously committed or expended. The amount of match in the Grant Agreement must align with Form 1002 and commitment documentation from each source listed must be provided. Form 1002 and the committed match documentation must be combined as one PDF prior to submission.

Important: No vendor contracts, commitments of funds or expenditure of match funding without NBRC approval is allowable. Federal requirements on funding restrict NBRC from allowing funds to be deployed until specific requirements are met.

These include, but are not limited to, the National Environmental Policy Act (NEPA), which prohibits the obligation or expenditure of project related NBRC funds and non-NBRC funds for activities with physical impacts or which limit the choice of alternatives until the environmental review process is completed and removal of environmental review grant conditions are received from NBRC.

Securing Match

The amount of match is identified within the executed grant agreement for the project in alignment with the SF424cbw (project budget) on file.

Documentation of committed match (NBRC Form 1002) together with letters of commitment from all match sources listed on Form 1002 must be submitted to NBRC.

• Grantee provided match: Letter from the appropriate authority stating that the entity will provide the match. Letter is required to have the following elements: 1. states the amount of the commitment, 2. contains the dates that the commitment will cover, consistent with the period of performance in the grant agreement.

Please note: If the funds will be used for paying staff within the grantee’s organization, the letter should also state the following: 1. the # of hours staff are anticipated to work

NBRC Grant Administration & Compliance Manual 18 February 2026 on the project, 2. the pay of those staff, and 3. the indirect cost rate that will be used, consistent with the grant agreement (if applicable).

• Municipal lending: Requires proof of authorization to spend. This may be different for different states, but may take the form of city council approval, a Town or City manager who has been authorized for all these transactions, or demonstration of town meeting approval. It is the grantee’s obligation to ensure that they have the appropriate authority to loan funds for the project, but there must be some sort of authorization documented. In the case of town meeting, this may mean that a Notice to Proceed is not issued until after that time - meaning that no part of the scope can be completed until such time.

• Letter of cash commitment from another source other than the grantee: A letter is required to have the following elements: 1. states the amount of the commitment, and 2.

contains a date that the award was made. A letter of submission (or ‘application received’ or ‘pending’) is NOT a letter of commitment.

• In-Kind Services: Provide a written plan of how the volunteer in-kind donation will be calculated. The volunteer rate may be used as match and should be consistent with the national average, current value of Volunteer Time. Volunteers may not be: (a) counted for the same activity in a different project (counted twice), or (b) be federal employees.

Additionally, their time must be recorded and be submitted for reimbursements. You may not include any indirect cost rate in addition to the rate calculated at the time of the grant agreement. The indirect cost rate identified in the grant agreement will be the rate for the performance period of the project. While the national rates may fluctuate, it is not feasible to renegotiate these rates during the project period.

• Municipal Force Accounts: These types of accounts may be used. Recipients must document that they have the staff and experience. Force account work is limited to work that the municipality can demonstrate is within the technical skill and managerial ability of the recipient and its forces. The recipient must provide an accounting of time and costs and provide appropriate documentation of indirect costs. Both staff salaries, and cost of mobilization and fees for vehicles may be counted as match when those costs are appropriately documented.

• Land or other donated real property or equipment: NOTE: land transfers may not take place until after the Notice to Proceed has been issued. A Letter of Intent from the current property owner will suffice and should include: 1. commitment to provide the land to the project; 2. the sale and ‘appraised’ value of the land; 3. anticipated date of transaction; and

4. identification of the property.

Please note: The donation of land or other real property requires a certified commercial appraisal. A municipal assessment is not an appraisal. The certified commercial appraisal https://independentsector.org/resource/value-of-volunteer-time/

NBRC Grant Administration & Compliance Manual 19 February 2026 of the land and/or real property must not be older than 18 months. Even if the property is being donated, a certified commercial appraisal is required. An appraisal of the property must have been completed within the past 18 months, and a copy of same provided to NBRC as part of the documentation required for the project to be issued a Notice to Proceed. NOTE: A municipal assessment is NOT an appraisal. NBRC utilizes an appraisal as a tool to evaluate reasonableness of the value of the property.

• Equipment: Recipients may match the NBRC award with the value of equipment and supplies provided to the project by themselves or by third parties. The value of property provided by a grant recipient must be consistent with the Uniform Guidance Subpart E.

When property is donated by third parties, special rules apply: the value of donated equipment and supplies cannot be higher than the fair market value of the property at the time of the donation. The entity that is donating equipment must provide a letter with the following elements: 1. date that the equipment will be transferred to the grantee; 2. market value of the equipment; 3. description of the equipment.

Match requirements may be met by other Federal grants where authorized for up to 80% of the total project cost, so as not to exceed the maximum federal contribution allowed as outlined in Supplements to Federal grant programs 40 USC 15506.

NBRC funds can, however, be used to satisfy the non-federal cost sharing or match requirements for a project under another Federal grant program for which NBRC is not the sole or primary funding source as outlined in 40 USC 15507. In these instances, NBRC funds would not count towards the federal share of the total project. With NBRC approval, section 15507 can be applied to any project when NBRC is not the sole or primary funder with unmet match requirements.

Neither costs, nor the value of third-party in-kind contributions, may count towards satisfying a cost sharing or matching requirement of a grant agreement if they have been, or will be, counted towards satisfying a cost sharing or matching requirement of another Federal grant agreement, a federal procurement contract, or any other award of Federal funds.

Cost financed by program income may count towards satisfying a cost sharing or matching requirement if it is expressly permitted in the terms of the grant agreement. NBRC has opted to regard program income through the addition method as outlined in 2 CFR 200.307(b)(2). If you are unsure if the program you are intending to use is allowable, please contact NBRC via admin@nbrc.gov.

Program income as defined in 2 CFR 200.307, means gross income earned by the recipient or subrecipient that is directly generated by a supported activity or earned as a result of the award during the period of performance. Grant-related income shall include, but not be limited, to income from service fees, sales of commodities, or usage or rental fees. All grant-related income shall be reported to NBRC in the progress and final reports required by the Grant https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title40-section15506&num=0&edition=prelim https://www.congress.gov/bill/118th-congress/senate-bill/4367/text?s=5&r=1&q=%7B%22search%22%3A%22s.4367%22%7D https://www.ecfr.gov/current/title-2/subtitle-A/chapter-II/part-200/subpart-D/section-200.307 https://www.ecfr.gov/current/title-2/subtitle-A/chapter-II/part-200/subpart-D/section-200.307

NBRC Grant Administration & Compliance Manual 20 February 2026

Agreement. If program income is earned as a result of expenditures, it must be spent on allowable eligible costs of the project.

Under the award, program income shall be added to funds committed to the project by NBRC and recipient and used to further eligible project activities or be deducted from the total project or program allowable cost in determining the net costs on which the federal share of costs is based. As outlined in 2 CFR 200.307(c) the recipient is not accountable for program income earned after the period of grant support unless NBRC requires otherwise.

Costs and third-party in-kind contributions counting towards satisfying a cost sharing or matching requirement must be verifiable from the records of the recipients and subrecipients.

These records must show how the value placed on third-party in-kind contributions was derived. To the extent feasible, volunteer services will be supported by the same methods that the organization uses to support the allocability or regular personnel costs.

All match must be committed within 1 year following the award year. For example, if you received a 2025 Catalyst award in the Spring Round (June), all match necessary to complete the project must be secured by July 1, 2026. For the Fall Round, when awards are made in December, the match to complete the project must be secured by the end of the following December.

When seeking NBRC funding, entities must consider meeting this programmatic benchmark.

This amount of time allows for extraordinary situations that may occur. If a grantee encounters programmatic challenges and realizes they will not be able to meet this deadline, they should be proactively communicating with NBRC, the State Program Manager(s) where the project was funded, and the project’s LDD (when applicable), to discuss the situation and determine the best path forward.

If the project cannot move forward, these funds can be returned to NBRC and will be reallocated to the State(s) where the project was funded and made available in a future round of funding.

Procurement

Procurement actions involve the purchase of goods and services needed to support the grant award. When conducting procurement transactions under a Federal award, a State or Indian Tribe must follow the same policies and procedures it uses for procurements with non-Federal funds. If such policies and procedures do not exist, States and Indian Tribes must follow the procurement standards in Title 2/Part 200 §§ 200.318 through 200.327. In addition to its own https://www.ecfr.gov/current/title-2/subtitle-A/chapter-II/part-200/subpart-D/section-200.307 https://www.ecfr.gov/current/title-2/subtitle-A/chapter-II/part-200/subpart-D/subject-group-ECFR45ddd4419ad436d/section-200.318 https://www.ecfr.gov/current/title-2/subtitle-A/chapter-II/part-200/subpart-D/subject-group-ECFR45ddd4419ad436d/section-200.327

NBRC Grant Administration & Compliance Manual 21 February 2026 policies and procedures, a State or Indian Tribe must also comply with the following procurement standards: §§ 200.321, 200.322, 200.323, and 200.327. All other recipients and subrecipients, including subrecipients of a State or Indian Tribe, must follow the procurement standards in §§ 200.318 through 200.327.

2 CFR 200 Appendix II must be contained in text or adopted by reference.

Made in America laws are applicable to federal financial assistance (such as grants). In accordance with the policy of the United States Government, consistent with applicable law, use, terms and conditions of Federal financial assistance awards and federal procurements, recipients must maximize the use of goods, products, and materials produced in, and services offered, in the United States. Whenever possible, the recipient shall procure goods, products, materials, and services from sources that will help American businesses compete in strategic industries and help America’s workers thrive. See 2 CFR 184 for more information.

“Made in America Laws” means all statutes, regulations, rules, and Executive Orders relating to Federal financial assistance awards or Federal procurement, including those that refer to “Buy America” or “Buy American,” that require, or provide a preference for, the purchase or acquisition of goods, products, or materials produced in the United States, including iron, steel, and manufactured goods offered in the United States. “Made in America Laws” include laws requiring domestic preference for maritime transport, including the Merchant Marine Act of 1920 (Public Law 66-261), also known as the Jones Act, and domestic content preference for infrastructure programs including the Build America, Buy America Act (BABAA) enacted on November 15, 2021.

All grantees must comply with the Infrastructure Investment and Jobs Act (IIJA) and the Build America, Buy America Act (the Act), Pub. L. No. 117-58, §§ 70901-52, including the implementing requirements at 2 CFR Part 184 and M-24-02, as summarized here. None of the funds provided under this award may be used for an infrastructure project unless:

a. All iron and steel used in the project are produced in the United States. This means all manufacturing processes, from the initial melting stage through the application of coatings, occurred in the United States.

b. All manufactured products used in the project are produced in the United States. This means the manufactured product was manufactured in the United States, and the cost of the components of the manufactured product that are mined, produced, or manufactured in the United States is greater than 55 percent of the total cost of all components of the manufactured product, unless another standard for determining the minimum amount of domestic content of the manufactured product has been established under applicable law or regulation.

c. All construction materials are manufactured in the United States. This means that all manufacturing processes for the construction material occurred in the United States.

The construction material standards are listed in the definitions section below.

Use this language in your RFP/RFQ to ensure compliance.

https://www.ecfr.gov/current/title-2/subtitle-A/chapter-II/part-200/subpart-D/subject-group-ECFR45ddd4419ad436d/section-200.321 https://www.ecfr.gov/current/title-2/subtitle-A/chapter-II/part-200/subpart-D/subject-group-ECFR45ddd4419ad436d/section-200.327 https://www.ecfr.gov/current/title-2/subtitle-A/chapter-II/part-200/subpart-D/subject-group-ECFR45ddd4419ad436d/section-200.318 https://www.ecfr.gov/current/title-2/subtitle-A/chapter-II/part-200/subpart-D/subject-group-ECFR45ddd4419ad436d/section-200.327 https://www.ecfr.gov/current/title-2/subtitle-A/chapter-II/part-200/appendix-Appendix%20II%20to%20Part%20200 https://www.ecfr.gov/current/title-2/subtitle-A/chapter-I/part-184?toc=1

NBRC Grant Administration & Compliance Manual 22 February 2026

Incorporation into an infrastructure project - The Buy America preference only applies to articles, materials and supplies that are consumed in, incorporated into, or affixed to an infrastructure project. As such, it does not apply to tools, equipment, and supplies, such as temporary scaffolding, brought to the construction site and removed at or before the completion of the infrastructure project. Nor does a Buy America preference apply to equipment and furnishings, such as movable chairs, desks, and portable computer equipment, that are used at or within the finished infrastructure project but are not an integral part of the structure or permanently affixed to the infrastructure project.

All recipient and subrecipient contracts under NBRC financial assistance awards for infrastructure, issued on or after May 8, 2023, must include a contract provision explaining the Build America, Buy America Act (BABAA) requirements and a self-certification where contractors can certify compliance with domestic preference requirements outlined in BABAA, unless NBRC waives the BABAA requirement.

BABAA Contract Level Compliance

All recipient and subrecipient contracts under NBRC financial assistance awards for infrastructure, issued on or after May 8, 2023, must include a contract provision explaining the Build America, Buy America Act (BABAA) requirements and a self-certification where contractors can certify…