Complete RFQ 5 03 24.pdf

PDF 9 MB Posted

Attached to
Water Treatment Plant Improvements General Contractor Prequalification, RFQ
Solicitation number
23-9360PL
Issued by
Moffat County, Colorado

About this file

This is a Request for Qualifications (RFQ) issued by the Avondale Water and Sanitation District (AWSD) in Colorado for general contractor services to improve their existing water treatment plant. The project involves removing and replacing existing Manganese Green Sand (MGS) filters and related piping in Water Treatment Plant #1 (WTP#1), inspecting and refurbishing Granular Activated Carbon (GAC) filters in WTP#2, and replacing existing turbine pumps with three new vertical turbine pumps. A mandatory pre-submittal site inspection is scheduled for May 30, 2024, at 9:00 AM, and interested contractors must submit their Statement of Qualifications (SOQ) electronically by June 14, 2024, at 3:00 PM through BidNet Direct.

The project budget is estimated at $606,976.49, which includes a 15% contingency. Key project challenges include maintaining water service to existing users during construction, removing MGS filters from a building with limited access, and coordinating electrical and control upgrades with Black Hills Energy. The evaluation process will assess contractors based on management experience, personnel qualifications, similar project experience, and references. To be prequalified, contractors must achieve a minimum score of 70 points across four evaluation criteria categories and provide a commitment letter for payment and performance bonds covering 100% of the estimated construction cost.

View the file

Other files

File Type Posted
Tables 1.xlsx XLSX spreadsheet

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

WATER TREATMENT PLANT IMPROVEMENTS – AVONDALE

WATER AND SANITATION DISTRICT (AWSD)

PROJECT NUMBER: 23-9360

REQUEST FOR QUALIFICATIONS (RFQ)

FOR

GENERAL CONTRACTOR PREQUALIFICATION

Submission Deadline: Friday, June 14, 2024, 3:00 P.M., Local Time

Submit One Electronic Copy of Statement of Qualifications (SOQ) to:

BidNet Direct (www.bidnetdirect.com)

Date Issued: May 3, 2024

Awarding Authority: Avondale Water and Sanitation District

TABLE OF CONTENTS

1. GENERAL PROJECT INFORMATION………………………………………………………….……………………………………………..Page 1

2. DETAILED PROJECT DESCRIPTION……………………………………………………….……………………………………………..Pages 2-3

3. GENERAL INSTRUCTIONS…………………………………………………………..……………………………………………….……..Pages 3-5

4. TENTATIVE BUDGET…………………………………………………………………………………………………………………..…………..Page 5

5. TENTATIVE SCHEDULE……………………………………………………………………………………………………………………………Page 6

APPENDIX A:

1. Statement of Qualifications Form 1: Contact Information……………………………………………………………………..Page 1

2. Statement of Qualifications Form2: Checklist………………………………………………………………………………………..Page 1

3. Statement of Qualifications Form 3: Ownership…………………………………………………………………………………….Page 2

4. Statement of Qualifications Form 4: Management………………………………………………………………………………..Page 2

5. Statement of Qualifications Form 5: Previous Experience……………………………………………………………………..Page 3

6. Statement of Qualifications Form 6: References…………………………………………………………………………………..Page 3

APPENDIX B:

Photo Exhibit 1: Existing MGS Filter and Piping in WTP#1…………………………………………………………………………………..Page 1 Photo Exhibit 2: Existing MGS Filter and Piping in WTP#1………………………………………………………………………………….Page 2 Photo Exhibit 3: Existing Pumps and Piping in WTP#1……………………………………………………………………………………….Page 3

APPENDIX C:

Photo Exhibit 4: GAC Filters WTP# 2…………………………………………………………………………………………………………………..Page 1 Photo Exhibit 5: Treated Water Discharge Pipe………………………………………………………………………………………………….Page 2

Sheet FP-1: Floor Plan Finished Piping Layout…………………………………………………………………………………………………..1 Page Sheet CS-1: Cross Section 1……………………………………………………………………………………………………………………………… 1 Page Sheet CS-2: Cross Section 2……………………………………………………………………………………………………………………………….1 Page Plant Component List…………………………………………………………………………………………………………………………………………1 Page

LIST OF FIGURES:

Figure 1: Schematic of AWSD Existing Treatment Process………………………………………………………………………….……..Page 1 Figure 2: Existing Water Treatment Site Layout…………………………………………………………………………………………………Page 2

REQUEST FOR QUALIFICATIONS

GENERAL CONTRACTOR SERVICES FOR THE EXISTING WATER TREATMENT PLANT IMPROVEMENTS

All perspective Qualified Firms:

1. GENERAL PROJECT INFORMATION

The Avondale Water and Sanitation District (AWSD) is soliciting electronically sealed qualification packages for GENERAL CONTRACTOR SERVICES FOR THE EXISTING WATER TREATMENT PLANT IMPROVEMENTS. Pricing is not submitted as a part of this evaluation process for submitted qualification proposals. Interested parties shall submit one (1) complete proposal package electronically, with all the required documents before the RFQ due date and time of 3:00 PM Local Time, Friday, June 14, 2024.

The Question-and-Answer period shall be closed on June 13, 2024, 3:00 PM Locale Time. All questions shall be directed to BidNet Direct (www.bidnetdirect.com)

A Mandatory Pre-Submittal Site Inspection shall be held on Thursday, May 30, 2024, 9:00 AM Local Time at the Avondale Water and Sanitation District Office located at 321 Third Lane, Avondale, CO 81022.

2. DETAILED PROJECT DESCRIPTION

The present treatment process utilizes filtration via 2 existing Granular Activated Carbon (GAC) pressure filters, in series with 2 existing Manganese Green Sand (MGS) filters and gas hypo chlorination. Please see Figure 1: Schematic of AWSD Existing Treatment Process:

Figure 1: Schematic of AWSD Existing Treatment Process

The GAC filters, which are presently being utilized, are located in a separate building (WTP NO. 2) from the rest of the treatment process. WTP. NO. 3 is currently not in use. They were installed to remove contamination from the Pueblo Chemical Depot, by the U.S. Army.

In order to facilitate the removal of PFAS, PFAO and other related compounds, AWSD intends to remove the existing filter media, inspect the filter units, perform any necessary cleaning and repairs, and place the refurbished filters back in service at their present location.

In addition, the existing MGS filters and related piping shall be removed from the main treatment building (WTP NO.

1). All piping which is currently plumbed through the clearwell shall be removed and replaced. Also, the existing turbine pumps shall be removed and replaced with three proposed vertical turbine pumps, a steel, one-piece pump manifold and a recordable flow meter at the point of discharge to the distribution system.

Figure 2 is the site layout of the existing treatment buildings and utilities:

Figure 2: Existing Water Treatment Site Layout

The General Contracting services shall include evaluation of the existing process and layout, piping and utilities, design recommendations and cost estimates for same. Once the scope of work is finalized the selected General Contractor shall negotiate with the Owner (AWSD) and prepare a price proposal for all of the proposed work.

The key issues during the proposed upgrade project shall be as follows:

1. Keeping the existing users in water during construction. The average daily use during the months of July through September is approximately 220,000 Gallons/Day. There are two existing potable water storage tanks which provide a maximum storage of 1.25 Million Gallons. This represents just over 5 days of potable water usage. Construction shall be staged such that there is always 2 full days of usage in the storage tanks.

2. Removal of the existing Manganese Green Sand (MGS) filters from WTP#1. During the original treatment plant construction, the existing MGS filters were installed prior to the building being complete. Presently, there is no access to WTP#1 large enough to remove the existing filter vessels. Therefore, they shall require dismantling to remove them.

3. Removal of existing piping from the existing clearwell. One of the pipes to be removed is from an abandoned well which is no longer in service and can be taken out of the clearwell without restoration. Another pipe to be removed is the connection to the distribution system from the clearwell. The remaining pipe to be removed are the shafts of the existing turbine pumps. All of the proposed pumps and related manifold and piping will need to be in place prior to removal of the existing pumps.

4. Electrical and Control Upgrades. These shall need to be coordinated with Black Hills Energy and AWSD, to ensure that customers are not out of service.

3. GENERAL INSTRUCTIONS

Requests for Qualifications (RFQ) and Statement of Qualifications (SOQ) forms are available on bidnetdirect.com and from Jesik Consulting.

A. Contents of Statement of Qualifications Application Package

The required Statement of Qualifications Package shall include the following:

1. Statement of Qualifications Form 1 – Contact Information

2. Statement of Qualifications Form 2 - Checklist

3. Statement of Qualifications Form 3 - Ownership

4. Statement of Qualifications Form 4 - Management

5. Statement of Qualifications Form5 – Previous Experience

6. Statement of Qualifications Form 6 - References

B. Sources of Information Considered

Respondent General Contractors must submit documentation for the four (4) evaluation criteria categories listed herein. Prequalification will be based on the submitted information and materials as well as information on prior project performance, information obtained from references, information obtained from governmental agencies and entities, and such other information as may be obtained relating to the evaluation criteria categories. The Prequalification Committee will also give consideration to the evaluation provided by any member of the Committee who has had direct experience with the Respondent Contractor. The Prequalification Committee may also request and review additional information as necessary to clarify or supplement the information provided to or obtained by the Awarding Authority. You must include all of the SOQ forms (1-6) attached hereto. You must give complete and accurate answers to all questions and provide all of the information requested. Making a materially false statement in this SOQ submission is grounds for rejection and debarment.

C. Evaluation Procedure

The Awarding Authority has established a Prequalification Committee for the purpose of reviewing and evaluating responses to this RFQ. The Prequalification Committee shall evaluate interested General Contractors based on the evaluation criteria set forth herein and assign points for each evaluation criterion category and subcategory provided herein. The Prequalification Committee shall prepare a written evaluation score form for each respondent General Contractor that provides a composite point rating and a specific point rating for each of the evaluations. The Prequalification Committee shall only prequalify those General Contractor firms that have achieved the minimum points required in each category set forth herein and a minimum total score of seventy (70) points.

Only General Contractor firms achieving the minimum score required in each evaluation category set forth herein, as well as a minimum total score of seventy (70) points overall shall be prequalified and invited to submit bids. An interested General Contractor’s score shall be made available to the General Contractor upon request.

D. Criteria For Prequalification

Interested General Contractors submitting a SOQ and supporting information in any other form will not be prequalified. The Prequalification Committee shall review and evaluate the information submitted by interested General Contractors in accordance with the point scheme set forth below. Also, the RFQ shall set forth the available points for each evaluation sub-category in order to provide interested General Contractors prior notice of the points available in each sub-category. Joint ventures must provide information about each of the joint venture partners.

1. Management Experience:

a. Business Owners: Provide the name, title, including a detailed description of the role and job responsibilities, scope of work and numbers of years with the firm for each of the business owner(s) of the firm. If the respondent General Contractor is a partnership, YOU MUST provide the requested information for each general and limited partner. If the respondent General Contractor is a corporation or limited liability company, YOU MUST provide the requested information for each officer, director and/or member. (15 points available)

2. Management Personnel: Provide the name, title, including a detailed description of the role and job responsibilities, scope of work, education, construction experience, years with the firm and list of all projects completed for all management personnel who will have any direct or indirect responsibility over the Project, including but not limited to project executives, project managers, field superintendents and field engineers.

(15 points available)

3. Similar Project Experience: Provide the project name(s), description, scope of work, original contract sum, final contract sum with explanation, and date of completion for each and every similar project undertaken by the firm in the last 10 years. For purposes of this RFQ, “similar projects” shall mean Water Treatment Plants.

(30 points available)

4. References:

a. Project References: Provide reference information for owners and architects for each and every project listed in your response. Information provided shall at least include project name and the names of the owners and architects, with current address, current telephone, and fax numbers, and contact person for each.

(30 points available)

5. Mandatory Requirements:

a. Bonding Capacity: Interested General Contractors must provide a commitment letter (from a surety company licensed to do business in the State of Colorado and whose name appears on the United States Treasury Department Circular 570) for payment and performance bonds in an amount equal to or greater than one hundred percent (100%) of the estimated construction cost for Project.

(10 points available)

ALL OF THE DOCUMENTS CONTAINED IN APPENDIX A ARE AVAILABLE ELECTRONICALLY. RESPONDENTS ARE

ENCOURAGED TO UTILIZE THE SOQ SPREADSHEET WHICH CAN BE MODIFIED AS NEEDED.

E. Tentative Budget

The following is the Project Budget for Water Treatment Plant Improvements:

REQUEST FOR QUALIFICATIONS - WATER TREATMENT PLANT IMPROVEMENTS -

AVONDALE WATER AND SANITATION DISTRICT - MAY 3, 2024 - PRELIMINARY

BUDGET

DESCRIPTION UNITS QUATITY UNIT PRICE TOTAL PRICE

Demolition of Existing Facilities LS 1 $65,000.00 $65,000.00 Remove and Dispose of existing filter media LS 1 $20,000.00 $20,000.00 Clean and Refurbish existing filter vessel LS 1 $20,000.00 $20,000.00 Replace old filter media (Material Cost) CF 318 $224.00 $71,232.00 Replace old filter media (Labor Cost) LS 1 $15,000.00 $15,000.00 New Piping and Valves (Sch. 80. Ductile Iron) LS 1 $30,000.00 $30,000.00 Proposed Concrete Work inside WTP#1 LS 1 $7,000.00 $7,000.00 Proposed Pump Manifold LS 1 $12,500.00 $12,500.00 Proposed 300 GPM VT Pump (Material Cost) EA 1 $9,800.00 $9,800.00 Proposed 125 GPM VT Pump (Material Cost) EA 1 $4,673.64 $4,673.64 Proposed 50 GPM VT Pump (Material Cost) EA 1 $2,600.00 $2,600.00 Proposed 300 GPM VT Pump (Labor Cost) EA 1 $5,000.00 $5,000.00 Proposed 125 GPM VT Pump (Labor Cost) EA 1 $5,000.00 $5,000.00 Proposed 50 GPM VT Pump (Labor Cost) EA 1 $5,000.00 $5,000.00 New Electrical and Controls LS 1 $250,000.00 $250,000.00 Final Cleaning and Disinfection EA 1 $5,000.00 $5,000.00

SUB-TOTAL $527,805.64

15% CONTINGENCY $79,170.85

GRAND TOTAL $606,976.49

F. Tentative Schedule

The following is the tentative project schedule:

REQUEST FOR QUALIFICATIONS - WATER TREATMENT PLANT IMPROVEMENTS - AVONDALE WATER AND SANITATION

DISTRICT - MAY 3, 2024, PRELIMINARY SCHEDULE

DESCRIPTION WEEK ENDING

5-

May 12-

May 19-

May 26-

May 2-

Jun 9-

Jun 16- Jun

23- Jun

30- Jun

7- Jul

14- Jul

21- Jul

28- Jul

4- Aug

11- Aug

18- Aug

25- Aug

1- Sep

Publish Request for Qualifications (RFQ)

RFQ Questions and Answer Period

RFQ Mandatory Pre-Submittal Site Insp.

RFQ Deadline

Selection Committee Review

Selection of General Contractor by Board

Contract Negotiations

Plan submittal to CDPHE

Water Treatment Plant Improvements

Certificate of Substantial Completion

Final Walkthrough

Improvement Complete and Accepted

APPENDIX A

1. Statement of Qualifications Form 1: Contact Information

STATEMENT OF QUALIFICATIONS FORM 1 - WATER TREATMENT

PLANT IMPROVEMENTS - AVONDALE WATER AND SANITATION

DISTRICT (AWSD) - May 3, 2024 (SOQ Form 1) CONTACT

INFORMATION

PROJECT NAME

WATER TREATMENT PLANT UPGRADES – AVONDALE

WATER AND SANITATION DISTRICT (AWSD)

PROJECT NUMBER 23-9360

AWARDING AUTHORITY AVONDALE WATER AND SANITATION DISTRICT (AWSD)

GENERAL CONTRACTOR NAME

GENERAL CONTRACTOR MAILING

ADDRESS

GENERAL CONTRACTOR STREET ADDRESS

TELEPHONE NUMBER

FACSIMILE NUMBER

CONTACT PERSON/TITLE

2. Statement of Qualifications Form 2: Checklist

STATEMENT OF QUALIFICATIONS CHECK LIST - WATER TREATMENT PLANT

IMPROVEMENTS - AVONDALE WATER AND SANITATION DISTRICT (AWSD) -

May 3, 2024 (SOQ Form 2) CHECKLIST Did you E-mail the Statement of Qualifications and all associated forms to Ken@jesik.us prior to the submittal deadline?

Did you attached the resumes of owners and management personnel identified in your response to Forms 3 and 4?

Did you attach the contact information for all of your references?

Did you attach a commitment letter for payment and performance bonds?

3. Statement of Qualifications Form 3: Ownership

REQUEST FOR QUALIFICATIONS - WATER TREATMENT PLANT

IMPROVEMENTS - AVONDALE WATER AND SANITATION

DISTRICT - MAY 3, 2024 (SOG Form 3) OWNERSHIP

NAME TITLE ROLE/JOB RESPONSIBILITES # YEARS EDUCATION/

SCOPE OF WORK WITH FIRM EXPERIENCE

4. Statement of Qualifications Form 4: Management

AVONDALE WATER AND SANITATION DISTRICT - MAY 3, 2024 (SOQ Form 4)

MANAGEMENT

NAME TITLE ROLE/JOB RESPONSIBILITES # YEARS EDUCATION/ COMPLETED

SCOPE OF WORK WITH FIRM EXPERIENCE PROJECTS

5. Statement of Qualifications Form 5: Previous Experience

AVONDALE WATER AND SANITATION DISTRICT - MAY 3, 2024 (SOQ FORM 5)

PREVIOUS EXPERIENCE

PROJECT NAME PROJECT PROJECT DESCRIPTION AND ORIGINAL AND FINAL DATE

& LOCATION OWNER SPECIFIC SCOPE CONTRACT AMOUNT COMPLETED

6. Statement of Qualifications Form 6: References

AVONDALE WATER AND SANITATION DISTRICT - MAY 3, 2024 (SOQ FORM 6)

REFERENCES

OWNER NAME COMPANY NAME CONTACT PERSON/ADDRESS TELEPHONE E-MAIL

OWNER

DESIGNER

APPENDIX B

Photo Exhibit 1: Existing MSG Filter and piping in WTP #1

Photo Exhibit 2: Existing MSG Filter and piping in WTP #1

Photo Exhibit 3: Existing Pumps and piping in WTP #1

APPENDIX C

Photo Exhibit 4: GAC Filters WTP# 2

Photo Exhibit 5: Treated Water Discharge Pipe WTP# 2

A

B

C

D E

F F

G H

I

J J

J J

K L

M N

O

O

P Q

QR

R

S

T

U

T

V W

A1

X

Y

Z

A1

B1

CS-1

CS-2

FP-1

Potable Water Treatment Plant Floor Plan Finished Piping Layout

Scale: 1/4"-1'-0"

8 6 4 0 4 8

AutoCAD SHX Text 3'-4"

AutoCAD SHX Text 5'-4"

AutoCAD SHX Text 2'-8"

AutoCAD SHX Text 1'-4"

AutoCAD SHX Text 11'-3 " (11.31')

AutoCAD SHX Text 23/32

AutoCAD SHX Text 8'-9 " (8.81')

AutoCAD SHX Text 23/32

AutoCAD SHX Text 6'-9 " (6.81')

AutoCAD SHX Text 23/32

AutoCAD SHX Text 4'-2 " (4.24')

AutoCAD SHX Text 29/32

AutoCAD SHX Text 3'-8 " (3.70')

AutoCAD SHX Text 11/32

AutoCAD SHX Text 3'-5 " (3.44')

AutoCAD SHX Text 11/32

AutoCAD SHX Text 6'-0" (6.00')

AutoCAD SHX Text Existing Raw Water Line From

AutoCAD SHX Text Shallow Well (To be replaced)

AutoCAD SHX Text Proposed Raw Water Line From

AutoCAD SHX Text Shallow Well (6"%%C DI Pipe)

AutoCAD SHX Text Proposed Raw Water Line From

AutoCAD SHX Text A.V.C. Service Line (6"%%C DI Pipe)

AutoCAD SHX Text Existing Overflow Line from

AutoCAD SHX Text Clearwell (To Remain)

AutoCAD SHX Text Proposed Raw Water Line From

AutoCAD SHX Text Deep Well (to be abandoned)

AutoCAD SHX Text 2'-6"

AutoCAD SHX Text (2.50')

AutoCAD SHX Text 4'-0"

AutoCAD SHX Text 1'-4"

AutoCAD SHX Text 1'-4 "

AutoCAD SHX Text (1.375')

AutoCAD SHX Text 1/2

AutoCAD SHX Text 3'-4 "

AutoCAD SHX Text (3.375')

AutoCAD SHX Text 1/2

AutoCAD SHX Text 800 W. 8th St.

AutoCAD SHX Text Pueblo, CO 81003

AutoCAD SHX Text

(719) 582-5588

AutoCAD SHX Text www.jesik.us

AutoCAD SHX Text

NW

AutoCAD SHX Text

NE

AutoCAD SHX Text

SE

AutoCAD SHX Text

SW

AutoCAD SHX Text

NNE

AutoCAD SHX Text

ENE

AutoCAD SHX Text

ESE

AutoCAD SHX Text

WNW

AutoCAD SHX Text

SSE

AutoCAD SHX Text

WSW

AutoCAD SHX Text

NNW

AutoCAD SHX Text

SSW

AutoCAD SHX Text E

AutoCAD SHX Text W

UWV

T

SB1

N M

C1

D1

E1 O

P

P

OF1

CS-1

Potable Water Treatment Plant Cross Section 1

Scale: 1/4"-1'-0"

8 6 4 0 4 8

AutoCAD SHX Text Existing Overflow Line from

AutoCAD SHX Text Clearwell (To Remain)

AutoCAD SHX Text Existing Raw Water Line From

AutoCAD SHX Text Shallow Well (To be replaced)

AutoCAD SHX Text 12'-0"

AutoCAD SHX Text Maximum Liquid Level

AutoCAD SHX Text 9"

AutoCAD SHX Text

EXISTING CLEARWELL

AutoCAD SHX Text 800 W. 8th St.

AutoCAD SHX Text Pueblo, CO 81003

AutoCAD SHX Text

(719) 582-5588 www.jesik.us

A

B

C

E

FF

O O

A1Z

U

P

T T

CS-2

Potable Water Treatment Plant Cross Section 2

Scale: 1/4"-1'-0"

8 6 4 0 4 8

AutoCAD SHX Text 3'-6"

AutoCAD SHX Text 2'-0"

AutoCAD SHX Text 2'-0"

AutoCAD SHX Text 2'-6"

AutoCAD SHX Text 10'-0"

AutoCAD SHX Text 4'-0"

AutoCAD SHX Text 6"%%C DI Raw Water from Shallow Well Wrapped

AutoCAD SHX Text w/heat tape, insullation and metal jacket

AutoCAD SHX Text 6"%%C DI Raw Water from AVC Trunk Line Wrapped

AutoCAD SHX Text w/heat tape, insullation and metal jacket

AutoCAD SHX Text Proposed 6"%%C Finished Water Line From

AutoCAD SHX Text Clearwell to Distribution System

AutoCAD SHX Text 6"%%C DI Raw Water from Shallow Well Wrapped

AutoCAD SHX Text 12'-0"

AutoCAD SHX Text

EXISTING CLEARWELL

AutoCAD SHX Text 800 W. 8th St.

AutoCAD SHX Text Pueblo, CO 81003

AutoCAD SHX Text

(719) 582-5588 www.jesik.us

Designation Description Length A High Service Pump (Gould VIT 300 GPM @ 150') B Medium Service Pump (Gould VIT 150 GPM @ 150') C Low Service Pump (Gould VIT 50 GPM @ 150') D Prefabricated flanged manifold E Flow Meter F 6"x4" Fl.xFl. Reducer G 6" Butterfly Valve H 4" Butterfly Valve I 2" Butterfly Valve J Pressure Gauge

K 6"ø DI Pipe Finished Water to Distribution System Insulated and Heated

L 6" Fl.xMJ 90° Bend Insulated and Heated M 6" Fl.xFl. 90° Bend N 6" Fl.xFl. DI Pipe Segment 3.63 O Strainrite SRDH-2-3F-Twin Bag Filters P 6"Fl.x2"Fl. DI Cross Q 2 inch ø Butterfly Valve R Strainrite 2"ø piping and valve components S 6"x6"x6" Tee Fl.xFl.xFl.

T 6" Fl.xFl. Butterfly Valve U 6"x6"x6" Tee Fl.xFl.xBlind Fl.

V 6"ø Fl.xFl. DI Spool 1.28 W 6"ø Fl.xFl. DI Spool 1.28 X 6"ø Fl.xFl. DI Spool 0.87 Y 6"ø Fl.xPE DI Pipe Segment 3.26 Z 6"ø Fl.xPE DI Pipe Segment 4.02

A1 6"ø MJ 90° Bend w/Megalug Assembly B1 6"ø Fl.xFl. DI Pipe 4.83 C1 6"ø Fl.xFl. DI Spool 0.60 D1 6"x6"x6" Tee Fl.xFl.xFl.

E1 6"ø Fl.xFl. DI Pipe Segment 3.87 F1 6"ø Fl.xPE DI Pipe Segment 2.58

Cover
TOC
RFQ
RFQ Page 6 Schedule
Appendix A
Appendix B
Appendix C
FP-1
Sheets and Views
AWSD TP 1-8.5x11 Floor Plan 1
CS-1
Sheets and Views
AWSD TP 1-CS-1
CS-2
Sheets and Views
AWSD TP 1-CS-2

Plant Components

File details come from the government source that posted it. Updated .