Commissioning Plan.pdf
PDF 284 KB Posted
- Attached to
- Y1DZ--620-14-108 l Building 17 Sprinklers
- Solicitation number
- 36C24221B0002
About this file
This document is a presolicitation notice for project 620-18-109 to replace the sprinkler system in Building 17 at the Hudson Valley Healthcare System Montrose Campus in Montrose, New York. The contractor shall provide all materials, equipment, personnel and supervision to replace the sprinkler system per contract drawings, specifications and applicable codes. The contract completion time is 365 calendar days from notice to proceed. This is a 100% set-aside for a Service-Disabled Veteran-Owned Small Business. Prospective contractors must be registered in the VetBiz and SAM databases and approved under NAICS 238220 with a size standard of $15 million. The cost range is $250,000 to $500,000 and bid, performance and payment bonds are required. The solicitation will be released on or around October 20, 2020. Questions are due by October 16, 2020 and must be emailed to Dany.Humphreys2@va.gov.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| S02 - Specs.pdf | ||
| 36C24221B0002_2.docx | DOCX document | |
| S02 - Drawings.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
23 Mechanic Street Springville, NY 14141
2745 Broadway Buffalo, NY 14227 encorus.com 716.592.3980
COMMISSIONING PLAN
For:
Building 17 Sprinklers
Contract Documents
Prepared For:
Department of Veterans Affairs
VA Hudson Valley Healthcare System
Franklin Delano Roosevelt Campus
2094 Albany Post Road
Montrose, NY 10548
August 25, 2020
VA CONTRACT NO. 36C24219C0209
BUILDING 17 SPRINKLERS CONTRACT DOCUMENTS
VA HUDSON VALLEY HEALTHCARE SYSTEM | MONTROSE, NY 08/25/20
TABLE OF CONTENTS
Table of Contents Commissioning Plan I. Introduction II. Commissioning Goals III. Project Description IV. Commissioning Scope V. Systems to Be Commissioned VI. Commissioning Team VII. Commissioning Communications and Document Distribution VIII. Pre-Design Phase Commissioning: Not used IX. Design Phase Commissioning X. Construction and Acceptance Phase Commissioning XI. Warranty Phase Commissioning: Not used XII. Team Member Roles and Responsibilities XIII. Commissioning Schedule XIV. Appendix A – Preliminary Log of Required Documentation
Table 1 - Commissioning Scope Table 2 - Systems to Be Commissioned Table 3 - Commissioning Team Table 4 - Communication Distribution Matrix Table 5 - Commissioning Team Roles and Responsibilities Table 6 - Commissioning Schedule Table 7 - Functional Testing Activities Table 8 - Preliminary Summary of all the Pre Functional Checklists
COMMISSIONING PLAN
I. Introduction
The Department of Veterans Affairs (VA) is committed to commissioning new facilities and systems required for the reliable, safe, and secure operation of the Building 17 Sprinkler System replacement at the Hudson Valley Healthcare System in Montrose, NY. This process will verify that systems are complete and functioning properly upon project completion and that the facilities maintenance staff has appropriate system documentation and training.
Commissioning consists of systematically documenting that specified components and systems have been installed and started up properly and then functionally tested to verify that systems are complete and functioning properly upon project completion and that the VAMC Facilities
Management (FMD) staff has the appropriate system documentation and training.
This document is intended to be a roadmap for the parties involved in the Commissioning process. The document will explain the systems to be commissioned, the process activities, the procedures to follow throughout the commissioning process, and the roles and responsibilities for each party involved. The commissioning activities will begin during the design phase of the project and proceed through the warranty period.
The team members for this project are committed to commissioning this system required for the reliable, safe, and secure operation. This process is intended to verify that the system is properly installed, configured and operating in accordance with the requirements of the project and that operating personnel are adequately prepared to successfully operate the facility at project turnover.
For this project, the Department of Veterans Affairs establishes AE Design contracts for Design
Phase and Construction Period Services. This was awarded under Contract No.
36C24219C0209 to Encorus Group of Springville New York. Due to the small scope of the project the CO and COR have concurred that Encorus Group will provide Commissioning
Services for this project.
The Department also establishes a construction contract with a Prime Contractor (TBD) to provide construction services. Both contracts are administered by a VA Contracting Officer and his/her designated representative. During both the Design and Construction Phases, these representatives are referred to as the CO or COR. On every project, the authority to modify any contract is strictly limited to the Contracting Officer.
In this structure, all communications on contractual issues are strictly limited to communications between the VA and these two prime contractors (AE Team and Prime Contractor). It is the practice of the VA to require that communication between other parties to the contracts (AE
Sub-consultants, Subcontractors and Vendors) be routed through these two prime contractors and the VA.
This Commissioning Plan has been developed to recognize that, in the execution of the
Commissioning Process, the Commissioning Agent must develop effective methods to communicate with every member of the construction team involved in delivering commissioned systems while simultaneously respecting the exclusive contract authority of the Contracting
Officer. Thus, all procedures outlined in this manual must be executed within the following limitations:
1. The Commissioning Agent may maintain a continuous open communication with the AE team, including sub-consultants, the Contractor and subcontractors and the Owner’s team to facilitate a collaborative commissioning process subject to the specific limitations outlined below.
2. All communications shall be copied to the VA COR.
3. All Communications shall include specific reference to these contract limitations (e.g., “All issues identified in this Commissioning Issues Log are subject to Paragraph 2.5: Contractual
Relationships in the VA Commissioning Process Manual.”
4. All information from the Commissioning Agent to any party to the project must be transmitted with the following clear limitations:
a. No communications (verbal or written) will be deemed to constitute direction that modifies the terms of any contract between the Department of Veterans Affairs and any party to the construction project.
b. Commissioning Issues communicated in writing to the Contractor or AE Team and copied to the COR are provided to all parties to the contract to expedite communication. All issues must be understood as the professional opinion of the Commissioning Agent and suggestions for issue resolution only until expressly approved as direction by the COR.
c. In the event that any Commissioning Issues and suggested resolutions are deemed to require either an official interpretation of the construction documents or are determined to require a modification of the contract documents, Contracting Officer or designated COR will issue an official directive to this effect.
d. All parties to the Commissioning Process shall be individually responsible for alerting the COR of any issues that they deem to constitute a potential contract change prior to acting on these issues.
e. Authority for design and construction issues resolution rests solely with the Contracting Officer and his/her designated representative with appropriate technical guidance from the AE Team and/or Commissioning Agent.
Abbreviations
List of Acronyms Acronym Meaning A/E Architect / Engineer Design Team AHJ Authority Having Jurisdiction CAR Corrective Action Notice CD Construction Documents CO Contracting Officer CONTR Installation Contractors COR Contracting Officers Representative CPM Construction Project Manager CxA Commissioning Agent DD Design Documents FMD VMAC Facilities Management Staff FPT Functional Performance Test O&M Operations and Maintenance PFC Pre-functional Checklist PFT Pre-functional Test QC Quality Control RFI Request for Information TBD To Be Determined VA Veterans Administration VACO VA Central Office VAPM VA Project Manager VAMC VA Medical Center
II. Commissioning Goals
The Commissioning Authority has developed specific Commissioning Goals to emphasize the role commissioning will play in the design and construction processes:
● Meet or exceed VAMC Project Requirements
● Optimize Systems Operations
● System operation and performance verification o Site Inspections o Pre-Functional checklists o Performance Test results o Equipment startup
● Integrate Testing Schedules into Construction Schedule
● Coordination of trades
● Early identification and resolution of issues
● Clear and open communications
III. Project Description
A. The primary goal of this project is to replace the existing sprinklers in Building 17 at the Hudson
Valley Healthcare System in Montrose, NY. Encorus Group will provide the necessary design for the replacement of the sprinkler system within the building. The project includes:
1. Installation of a new water supply for the sprinkler system. Flushing of water main to clear debris.
2. New wet pipe sprinkler system riser with isolation valve, alarm check valve and appropriate alarm trim.
3. Installation of floor control valves and floor test/drains for each floor.
4. Installation of cross and branch mains, sprinkler heads as shown on the design shop drawings.
5. Installation of new flow alarms and valve tamper switches at each floor control and tamper switch on the main riser isolation valve.
6. Installation of a manual Class 1 Standpipe riser in each stair tower.
7. Installation of Fire Alarm System interface modules for flow and tamper switches.
8. Pre-function and testing and inspection of the sprinkler systems.
9. Acceptance testing and inspection of the sprinkler system.
10. Re-acceptance testing of the fire alarm system.
IV. Commissioning Scope
A. Mr. John T. Allan, Sr. Fire Protection Engineer, will provide commissioning services to support the Building 17 Sprinkler System project.
B. Design Phase Commissioning Services will be provided by Encorus Group Engineering, P.C.
C. Construction Phase Commissioning Services will be provided at the Construction Site in
Montrose, NY.
D. The scope of Commissioning Services described above will be based off the 2018 edition of
NFPA 3, Recommended Practice for the Commissioning of Fire Protection and Life Safety
Systems.
E. Commissioning activities will include the tasks and deliverables outlined in Table 1 below.
Table 1 - Commissioning Scope
Commissioning Scope
Project Phase Task Description Deliverable
Design Commissioning Specifications
Prepare Commissioning Specification “Section 01 91 13 – General Commissioning Requirements” to be included in project manual.
Commissioning Specification
Prepare Commissioning Specification for Division 21 – Fire Protection, to provide detailed commissioning, operations & maintenance and training requirements for individual technical specification sections.
Commissioning Specifications
Design Preliminary Commissioning Plan
Prepare Preliminary Commissioning Plan that describes the Commissioning Process, Commissioning Team with specific Roles and Responsibilities. The Commissioning Plan will include description of systems to be commissioned.
Preliminary Commissioning Plan
Construction Final Commissioning Plan
Based on the final construction documents, update the Preliminary Commissioning Plan to identify specific systems to be commissioned. The Final Commissioning Plan will also include specific individual roles and responsibilities and Preliminary Pre-Functional Checklists and Functional Test Plans for systems to be commissioned.
Final Commissioning Plan.
Commissioning Scope
Project Phase Task Description Deliverable
Construction Duration Schedule for Commissioning Activities
Based on Final Commissioning Plan, prepare a duration schedule to show the duration, predecessors and successors for commissioning activities. This duration schedule will be provided to the Construction Manager to include commissioning activities in the project construction schedule. This will allow commissioning activities to be smoothly integrated into the overall construction process.
Duration schedule with commissioning activities, predecessors, successors and key milestones.
Construction Pre-Functional Checklists (PFT)
Prepare PFT Checklists for systems, components and/or equipment to be commissioned. These PFT Checklists will be used to document completion of system, component and/or equipment installation and to determine system readiness for functional testing.
PFT Checklists should be completed by the installing contractors to document the installation process. Completed PFT Checklists are to be submitted to the CxA a minimum of seven days prior to testing.
Completed Systems Readiness Checklists will be spot checked by the CxA to verify systems are ready for testing.
Final Pre- Functional Checklists for use by contractors and CxA.
Construction Prepare Functional Performance Test (FPT) Plans
Based on final construction documents (including applicable changes), and approved submittals, prepare FPT Plans for systems to be commissioned. Draft FPT Plans will be issued for review by owner and installing contractors.
Final Functional Test Plans will be prepared incorporating review comments received from owner and contractors.
Draft FPT Plans for review by owner, installing contractors, CxA and DDC vendor.
Final FPT Plans for use in systems testing.
Phase Task Description Deliverable
Construction Warranty Review Review contractor’s and manufacturer’s warranties for general conformance with specifications and owner’s requirements.
CxA Review Log
Construction Systems Functional Testing
Direct FPT for systems to be commissioned. Testing will be conducted as detailed on the specific FPT Plan for each system to be commissioned.
Functional testing will require support from the owner, fire alarm contractor, sprinkler contractor and specialty-systems installing contractors. Installing contractors must be available to respond to issues and problems identified during testing.
Executed FPT Plans.
Document in CxA Issues Log
Construction Final Commissioning Report
Compile a comprehensive commissioning report documenting all commissioning activities, including but not limited to:
● Commissioning scope
● Test methods and results
● Outstanding commissioning issues
● Issues log
● Commissioning plan
● PFT Checklists
Scope includes one submission of a preliminary report for owner review. Scope includes one submission of the Final Commissioning Report that incorporates owners review comments.
Preliminary Commissioning Report – 1 hardcopy for owner review.
Final
Report – 1 hardcopy plus 2 electronic submissions on
CD/DVD.
Construction Master Issues Log Maintain a Commissioning Issues Log to document commissioning issues identified during construction and functional testing.
The Commissioning Issues Log will include recommended responsible party and recommendations for resolution of the issue. The Commissioning Issues Log will also be used to document progress toward resolution and the final resolution
Issues Log
Phase Task Description Deliverable
Warranty Post-Occupancy Warranty Checkup
Return to the project approximately 10 months into the 12 month warranty period to review the building operation with the facility staff and discuss outstanding issues related to commissioning and outstanding warranty issues. Provide suggestions for improvements. Assist facility staff in developing reports, documents and requests for service to remedy outstanding problems. We have assumed this will be performed during a (TBD)-day site visit approximately 10 months after substantial completion
Field Observation Report
Warranty Final Commissioning Report Amendment
Amend Final Commissioning Report to document the Warranty Phase commissioning activities.
Amendment to Final
Report.
V. Systems to Be Commissioned
The systems and equipment to be commissioned are outlined in the table below. A more detailed list of specific systems and equipment is provided in Appendix A.
Table 2 - Systems to Be Commissioned
Systems To Be Commissioned
System Pre-
Functional Checklists
Equipment Startup
Functional Testing
Sample Size
Remarks
Div 21 - Fire Protection
Fire Protection Systems Yes Yes Yes All Per NFPA 13
Div 28 – Electronic Safety and Security
Fire Detection and Alarm Systems
Yes No Yes All Per NFPA 72
VI. Commissioning Team
The Commissioning Team shall consist of representatives from the following parties involved in the design and construction of this facility. The time at which individual members join the team and the level of their participation during the different phases of the project will vary from member to member.
Roles and Responsibilities for the Commissioning Team members are described elsewhere in this Commissioning Plan.
Commissioning Team Contact information is provided in Table 3.
Table 3 - Commissioning Team
Commissioning Team
Item Team Member Description Contact Information
COR VAMC-
Contracting Officer’s Representative
Program Management Representative responsible for contractual and technical aspects of the project.
Name
Organization
Address
City, State Zip
Phone:
Email:
FMD VAMC-Facilities Management Department
Representative of the Facilities Management Department
Name
Organization
Address
City, State Zip
Phone:
Email:
QA VAMC-Quality Assurance Coordinator
FMD Quality Assurance coordinator for Commissioning activities
Name
Organization
Address
City, State Zip
Phone:
Email:
CxA Commissioning Agent
Project Manager for Commissioning Agent
Name: John T. Allan
Organization: Encorus Group
Address: 23 Mechanic St.
City, State Zip Springville, NY 14141
Phone: 716-244-2657
Email: jallan@encorus.com
CPM Construction Project Manager
(CPM)
Contractor’s Project Manager responsible for construction and coordination of sub-contractors
Name
Organization
Address
City, State Zip
Phone:
Email:
Commissioning Team
Item Team Member Description Contact Information
FP Fire Protection
Sprinkler Contractor
Commissioning Representative for the Sub-contractor responsible for installation of fire protection systems
Name
Organization
Address
City, State Zip
Phone:
Email:
EC Electrical Contractor or Fire Alarm Contractor
Commissioning Representative for the Sub-contractor responsible for installation of MV and LV electrical systems
Name
Organization
Address
City, State Zip
Phone:
Email:
VII. Commissioning Communications and Document Distribution
Table 4 outlines the submittal and distribution requirements for various documents used in the commissioning process.
Table 4 - Communication Distribution Matrix
Communication Distribution Matrix
Document Prepared by: Submitted to: Copies to: Comments
Schematic Design Documents A/E COR
● QA
● CxA
● CPM
A/Eteam submits direct to VAMC. COR distributes.
Design Development Documents
A/E COR
● QA
● CxA
● CPM
A/Esubmits direct to VAMC Building Department as separate submission
General Commissioning Requirements Specification Section (01 91 00)
CxA COR
● QA
● A/E
A/E submits direct to VAMC.
COR distributes.
Communication Distribution Matrix
Document Prepared by: Submitted to: Copies to: Comments
Progress CD Drawings and Specs A/E COR
● QA
● CxA
Final Construction Documents A/E COR
● QA
● CxA
● CPM
A/E submits direct to VAMC as separate submission.
Final Commissioning Plan
CxA COR
● QA
● A/E
● CPM
● TAB
Design team submits direct to VAMC. COR distributes.
Duration Schedule for Commissioning Activities CxA COR
● QA
● CPM
Initial submission included in Final Commissioning Plan
Updates provided as necessary
Submittals and Shop Drawings
CPM COR
● A/E
● CxA
● QA
Submittals and Shop Drawings are submitted to the A/E as separate submission
Final Pre-Functional Checklists CxA COR
● CPM
Executed Pre- Functional Checklists
CPM COR
Contractor Startup Reports CPM COR
● CxA
● A/E
Final Functional Test Procedures CxA COR
O&M Manuals
CPM COR
● QA
● FMD
Warranty and other Closeout Documents
CPM COR
● QA
Communication Distribution Matrix
Document Prepared by: Submitted to: Copies to: Comments
Warranty and Closeout Comment Log
CxA COR
● QA
System Functional Testing Field Reports
CxA COR
Construction Observations Field Reports
CxA COR
Final
Report
CxA COR
● COR
● TAB
Construction O/A/C Meeting minutes CPM COR
● QA
Master Issues Log CxA COR
Change Orders, ASI, RFI A/E
CPM
COR
● QA
● CxA
Master Issues Log CxA COR
Report Amendment
CxA COR ● CPM
VIII. Pre-Design Phase Commissioning: Not used.
IX. Design Phase Commissioning
Schematic Design Phase: The goals of the commissioning tasks in the Schematic Design
Phase of the project include the following:
1. The CxA, COR, and CPM representatives will review and provide written comments on the
Schematic Design documents submitted by the A/E. The focus of the CxA review will be on adherence to the Design Narrative. The review comments will be geared towards aligning the design and design narrative with the Design Document and/or updating the Design
Narrative with decisions approved by VA during the Schematic Design Phase.
Design Development Phase: The goals of the commissioning tasks in the Design Development
Phase of the project include the following:
1. The CxA will prepare the Preliminary Commissioning Plan to provide an initial framework for commissioning activities that will follow. This Preliminary Commissioning Plan will be aligned with the project scope and schedule. It will be reviewed by the COR, CPM and other interested parties.
2. The CxA will also prepare preliminary commissioning specifications to be included in the project manual. The preliminary specifications will include Section 01 91 00 – GENERAL
COMMISSIONING REQUIREMENTS as well as language to be included in other, Division
21, and Division 22, specification sections. The A/E will review the preliminary commissioning specifications and provide written comments to the CxA. The CxA will revise the Preliminary Commissioning Specification and re-submit to the A/E.
Construction Document Phase: The goals of the commissioning tasks in the Construction
Document Phase of the project include the following:
1. The A/E will prepare final construction documents that will be used to construct the project.
A progress set of drawings and specifications will be issued for review at approximately the
65% CD stage. The CxA, COR, and CPM will review the progress set to verify that the design is proceeding in accordance with the Design Narrative.
2. The CxA will prepare a final, detailed list of systems and equipment to be commissioned.
3. The CxA will prepare preliminary Pre-Functional Checklists and Systems Functional
Performance Test procedures for each type of system to be commissioned. These will be published in the Preliminary Commissioning Plan to be included as an informational appendix to Specification Section 01 91 00 – GENERAL COMMISSIONING
REQUIREMENTS that will be issued for bid.
4. A review conference will be conducted to coordinate review comments and provide direction for adjustments in the design prior to issuing the final construction documents.
5. The A/E will issue to the COR the final Construction Documents, including drawings, narrative and specifications. These will be reviewed by the CxA, COR, VAMC User, and
FMD. The CPM will also review the final construction documents and prepare the final estimates of construction costs.
X. Construction and Acceptance Phase Commissioning
The CxA will prepare the Construction Commissioning Plan that incorporates any changes due to the Final Construction Documents, Design Narrative. This Commissioning Plan outlines the commissioning activities during the Construction and Acceptance Phase of the project.
A Commissioning Kickoff Meeting will be held at the start of construction to describe the commissioning process for the Construction Team which includes the CPM, installing sub-contractors (Mechanical, Electrical, Plumbing, and others). Preliminary Pre-Functional
Checklists and Functional Test Plans will be included to describe the level of involvement required of all parties.
The CxA will provide preliminary Commissioning Milestones, predecessors, successors, and durations to the CPM. The CPM will be able to use these data to integrate commissioning activities into the project construction schedule. The CxA will align commissioning activities with the construction schedule for each construction phase.
The Commissioning Agent will witness selected equipment startups for relevant system components. The purpose will be to observe any issues that may arise that would affect equipment or system operations.
The installing contractors and the CPM will prepare equipment training plans intended to provide basic equipment operating and maintenance procedures. The installing contractors and the CPM will prepare training plans that will outline the training to be provided and the intended outcome of the training. The CxA will review the training plans to determine that the training will meet the requirements of the specifications and the FMD staff.
The Commissioning Agent will prepare Pre-Functional Checklists that the installing sub-contractors will complete to document equipment and systems are complete and ready for testing.
The Commissioning Agent will also prepare detailed System Functional Performance Test plans that will provide detailed step-by-step procedures that will be used to verify system operations under all operating conditions.
The installing sub-contractors are encouraged to use the System Functional Test Plans as a tool for pre-testing the equipment and systems prior to the “official” functional testing. This will allow early detection and resolution of problems.
It is the expectation that System Functional Testing will demonstrate that the systems perform in accordance with design criteria, construction documents and VA requirements. Functional testing pre-requisites are that the system components and equipment are completely installed, all required power connections are complete, all required control connections and control functions are operational, and that required air and hydronic testing and balancing has been completed.
Functional testing of each system to be commissioned will be conducted by the CxA.
Upon completion of all commissioning activities, including resolution of all issues on the
Commissioning Master Issues Log, the CxA will prepare and issue the Final Commissioning
Report. This report will include the final version of the Commissioning Plan, copies of all
Commissioning Meeting Minutes, Commissioning Field Observation Reports, Pre-Functional
Checklists, Functional Performance Test results, and the Commissioning Master Issues Log.
The report will also include blank copies of the Functional Test Plans for use by FMD for future re-commissioning activities.
XI. Warranty Phase Commissioning: Not used.
XII. Team Member Roles and Responsibilities
The following is an outline of team member responsibilities in the Design, Construction and
Acceptance, and Warranty phases of the commissioning process. These responsibilities are meant to be limited to those tasks related to the commissioning process and are not intended to be representative of each team member’s contractual responsibilities for other aspects of this project.
In the table that follows, the tasks identified for the “CxA” include the Commissioning Project
Manager, Commissioning Technical Lead, or other Commissioning Specialists and sub-consultants as directed by the CxA.
In the table that follows, the tasks identified for the “A/E” includes the MEP Engineers.
In the table that follows, the tasks identified for “Contractor” include the Construction Project
Manager, as well as the commissioning representatives for the installing sub-contractors, as directed by the Construction Project Manager.
Table 5 - Commissioning Team Roles and Responsibilities
Commissioning Team Roles and Responsibilities
Project Phase Cx Task Description
Team Member Responsibility
Design Review Owner’s Project Requirements (Contract SOW)
Review VAMC Design Criteria and Owner’s Project Requirement document prior to submission to LEED Facilitator.
COR Prepare and issue Owner’s Project Requirements based on specific requirements, Ed Specs and District Design Criteria.
CxA Review and comment on Owner’s Project Requirements.
Submit comments to the COR and QA.
A/E Review for understanding project requirements.
CPM None.
Design Review Design Narrative
Review the Design Narrative Document
VA COR Receive and distribute Basis of Design documents to CPM, CxA, and other VAMC agencies as necessary.
CxA Review Design Narrative document.
Provide comment log to COR and A/E.
A/E Prepare Phase 1 (Schematic Design) and Design Narrative to describe design approach.
CPM None.
Design Review Schematic design
Review Schematic Design for familiarization, general conformance with Owner’s Project Requirements, Basis
COR Receive and distribute Schematic Design package to Peer Reviewer, CxA, and other VAMC agencies as necessary.
CxA Review Schematic Design Provide comment log to COR and QA.
Phase Cx Task Description
Team Member Responsibility of Design and VAMC Design Criteria.
A/E Prepare Schematic Design.
Provide responses to CxA review comments.
Incorporate changes into design as directed by COR.
CPM None
Design Design Development design
Review Design Development design for familiarization, general conformance with Owner’s Project Requirements, Design Narrative, and VA Design Criteria.
COR Receive and distribute Design Development package to Peer Reviewer, CxA, DDC and other VAMC agencies as necessary.
CxA Review Design Development drawings and specs.
Update Design Narrative Provide comment log to COR and QA.
A/E Prepare Design Development drawings and specs.
Provide responses to CxA review comments.
Incorporate changes into design as directed by COR.
CPM None
Design Commissioning Specifications
Prepare Commissioning Specification “Section 01 91 00 – General Commissioning Requirements” to be included in project manual.
Prepare
COR Review, comment and approve Cx specifications as part of project manual review.
CxA Prepare Cx Specification Section 01 91 13.
Prepare systems commissioning specifications.
A/E Incorporate commissioning specifications into Project Manual.
Phase Cx Task Description
Team Member Responsibility
Specification for Division 21 – Fire Protection, Division 22
– Plumbing, to provide detailed commissioning, operations & maintenance and training requirements for individual technical specification sections.
CPM None.
Design Preliminary Commissioning Plan
Prepare Preliminary Commissioning Plan that describes the Commissioning Process, The Commissioning Plan will include description of systems to be commissioned.
COR Review Cx Plan Provide comments to CxA.
CxA Prepare Cx Plan Submit to COR and QA
A/E Review Cx Plan relative to A/E roles and responsibilities.
CPM None.
Design Focused Construction Document Review (Progress Set)
Perform a focused review of a Construction Document progress submission (recommend review prior to the 50% CD stage).
VAMC
COR
Receive and distribute Progress Set drawings and specs to QA, CxA, DDC and other VAMC agencies as necessary.
CxA Review Progress Set drawings and specs.
Update Design Narrative Provide comment log to COR and QA.
A/E Prepare Progress Set drawings and specs.
Provide responses to CxA review comments.
Incorporate changes into design as directed by COR.
CPM None
Phase Cx Task Description
Team Member Responsibility
Design Focused Construction Document Review
Perform a focused review of the final Construction Document submission. This review will include a back check of commissioning comments provided during previous reviews.
COR Receive and distribute Construction Documents package to QA, CxA, DDC and other VAMC agencies as necessary.
CxA Review Construction Document drawings and specs.
Update Design Narrative Provide comment log to COR and QA.
A/E Prepare Construction Documents drawings and specs.
Provide responses to CxA review comments.
CPM None.
Design Design Phase Meetings
Participate Design Phase meetings.
COR Schedule, facilitate and attend meetings
CxA Attend approximately selected meetings to discuss Commissioning Issues.
A/E Conduct meetings
Provide meeting minutes to COR, CxA and others as directed by COR.
CPM None
Design Focused Design Review Meetings
Attend Design Review meetings with to review the design and specific commissioning design review comments.
COR Schedule, facilitate and attend meetings.
CxA Attend meetings to discuss commissioning review comments.
A/E Attend meetings to discuss design and to respond to commissioning and DDC comments.
CPM None.
Phase Cx Task Description
Team Member Responsibility
Construction Final Commissioning Plan
Based on the final construction documents, update the Preliminary Commissioning Plan to identify specific systems to be commissioned. The Final Commissioning Plan will also include specific individual roles and responsibilities and preliminary Pre- Functional Checklists and Functional Test Plans for systems to be commissioned.
COR Review and approve Commissioning Plan.
Provide comments to CxA and
QA.
CxA Prepare Final Commissioning Plan.
Prepare preliminary Pre- Functional Checklists Prepare Preliminary Systems Functional Performance Test procedures.
Issue to COR and QA.
Incorporate comments into Cx Plan revisions as necessary.
A/E Review Cx Plan relative to A/E roles and responsibilities.
Provide comments to COR and CxA.
CPM Review Cx Plan relative to CPM and installing sub-contractor’s roles and responsibilities.
Provide comments to COR and CxA.
Construction Construction Commissioning Kick Off meeting
Conduct an initial commissioning meeting with all contractors and commissioning team members. The purpose of the meeting will be to establish the purpose and proposed process for commissioning this facility in the construction, acceptance and warranties phases of the project.
COR Schedule, facilitate and attend meeting.
CxA Conduct meeting.
Prepare, present and discuss commissioning tasks, roles and responsibilities.
Prepare meeting agenda and minutes.
A/E Not Required to Attend
CPM Attend meeting.
Phase Cx Task Description
Team Member Responsibility
Construction Duration Schedule for Commissioning Activities
Based on Final Commissioning Plan, prepare a duration schedule to show the duration, predecessors and successors for commissioning activities. This duration schedule will be provided to the CPM to include commissioning activities in the project construction schedule.
This will allow commissioning activities to be smoothly integrated into the overall construction process.
COR Review commissioning schedule data.
Coordinate with CPM to incorporate commissioning activities into project schedule.
CxA Prepare and issue commissioning activities schedule, including durations and predecessors.
Review project schedule prepared by CPM.
A/E None.
CPM Incorporate commissioning activities into Master Construction Schedule.
Construction Submittal and Shop Drawing Review List
Based on final construction documents, prepare a list of selected submittals and shop drawings for review by the Commissioning Authority.
COR None.
CxA Prepare list of submittals and shop drawings to be provided to the CxA.
A/E None.
CPM None.
Construction Submittal and Shop Drawing Review
Review selected submittals and shop drawings to support the commissioning process. Review will be for the purpose of developing appropriate Pre- Functional Checklists and Functional Test
COR Receive and distribute submittals and shop drawings.
Distribute selected submittals and shop drawings to CxA.
Review and approve submittals
CxA Review selected submittals and shop drawings.
Prepare issue comment log.
Phase Cx Task Description
Team Member Responsibility
Plans. Reviews will focus on the ability to commission the systems, maintainability and general conformance to owner’s requirements.
Commissioning review of submittals and shop drawings does not replace the A/E responsibility for approval.
A/E Review submittals and shop drawings.
Provide comments and recommendations to COR.
CPM Prepare and issue submittals and shop drawings.
Incorporate COR comments into revised submittals and shop drawings.
Construction Pre-Functional Checklists
Prepare Pre- Functional Checklists for systems, components and/or equipment to be commissioned. These Pre-Functional Checklists will be used to document completion of system, component and/or equipment installation and to determine
COR Review checklists Provide comments to CxA
CxA Prepare preliminary checklists.
Issue to COR and CPM for review
Incorporate changes into final checklists as necessary.
A/E None.
Phase Cx Task Description
Team Member Responsibility system readiness for functional testing.
Pre-Functional Checklists should be completed by the installing contractors to document the installation process.
Completed Pre- Functional Checklists are to be submitted to the commissioning authority a minimum of seven days prior to testing.
Completed Pre- Functional Checklists will be spot checked by the commissioning authority to verify systems are ready for testing.
CPM Provide copies of sub-contractor QC installation checklists to CxA for review.
Review checklists prepared by CxA
Provide comments to CxA
Construction Review Contractor Equipment Startup Reports
Commissioning authority will review selected equipment startup reports prepared by installing contractor.
Commissioning Agent will witness selected equipment startup procedures. Seven days prior notice is required to schedule
COR Receive and distribute Contractor Startup Reports
CxA Witness selected contractor equipment startups.
Review selected Contractor Startup Reports.
Provide comment log to COR and QA.
A/E Review Contractor Startup Reports.
Phase Cx Task Description
Team Member Responsibility commission authority witnessing the startup.
CPM Complete Contractor Startup Reports
Issue to COR and CxA.
Construction Prepare Functional Test Procedures
Based on final construction documents (including applicable changes), and approved submittals, prepare Functional Test Procedures for systems to be commissioned. Draft Functional Test Procedures will be issued for review by owner, installing contractors and DDC Vendor.
Final Functional Test Procedures will be prepared incorporating review comments received from owner, contractors or DDC Vendor.
COR Review preliminary Functional Test Procedures.
Provide comments to CxA
CxA Prepare preliminary Functional Test Procedures.
Issue to COR , CPM
Incorporate comments into final Functional Test Procedures as necessary.
A/E None.
CPM Distribute preliminary Functional Test Procedures to COR, CxA and other installing sub-contractors.
Review preliminary Functional Test Procedures
Provide comments to CxA
Construction Review O & M Manuals
Review Operations and Maintenance Manuals submitted by contractors. Manuals will be reviewed for clarity, organization, usability and general conformance with specifications and owner’s requirements.
COR Distribute O&M Manuals to CxA and A/E.
Review and approve O&M Manuals.
CxA Review O&M Manuals.
Provide comment log to COR and QA.
A/E Review O&M Manuals.
CPM Prepare and issue O&M Manuals to COR.
Phase Cx Task Description
Team Member Responsibility
Construction Prepare Systems Manuals for commissioned systems
Prepare detailed systems manuals for commissioned systems. The manuals will provide operating staff the information needed to understand and optimally operate the commissioned systems. The manuals will describe system design, components, capacity and sequences of operations. Manuals will include descriptions of interactions with other systems and common systems failure modes and responses.
COR Review and approve Systems Manuals.
Distribute Systems Manuals to
FMD.
CxA Using O&M Manuals, Basis of Design, and Construction Documents, prepare Systems Manual.
A/E None.
CPM None>
Construction Review Training Plans
Review contractor and manufacturer training plans and agendas for general conformance with specifications and owner’s requirements.
Observe selected training for quality of training and for general conformance with the training plan and agenda.
COR Schedule and facilitate training sessions.
FMD staff attends training sessions.
CxA Review Training Plans.
Provide comment log Witness selected training sessions.
A/E None.
CPM In conjunction with installing sub-contractors and/or manufacturers’ representatives, conduct training sessions.
Phase Cx Task Description
Team Member Responsibility
Construction Warranty Review
Review contractor’s and manufacturer’s warranties for general conformance with specifications and owner’s requirements.
COR Distribute warranty documents to FMD and CxA
Review and approve warranty documents
CxA Review warranty documents.
Provide comment log
A/E Review warranty documents and provide comments.
CPM Prepare and issue warranty documents
Incorporate comments into final warranty documents.
Construction Systems Functional Testing
Witness and document functional testing for systems to be commissioned.
Testing will be conducted as detailed on the specific Functional Test Plan for each system to be commissioned.
Functional testing will require support from the CPM and COR. .
COR Schedule, facilitate and witness systems functional testing.
FMD staff should assist in functional testing as additional systems training opportunity.
CxA Witness systems functional testing using previously prepared Functional Test Procedures.
Document systems testing on Functional Test Procedures.
Issue Field Reports to document deficiencies.
Update Master Commissioning Issues Log to document and track deficiencies.
A/E Review test documentation
Phase Cx Task Description
Team Member Responsibility
CPM CPM to conduct functional testing by operating systems in accordance with functional test procedures.
Make corrections, repairs or adjustments to systems during testing as directed by the COR.
Correct outstanding deficiencies after testing as directed by the
COR.
Report corrective actions to COR and CxA upon completion.
Construction Systems Functional Retesting
Retest systems with deficiencies as recommended by the CxA and directed by the COR
(Note: Retesting is not included in the scope of commissioning services and is provided as an additional service.
The costs associated with retesting may be recovered from the Construction Manager in accordance with appropriate contract provisions.)
COR Approve retesting as recommended by CxA.
Schedule and coordinate retesting.
CxA Make recommendations for necessary retesting.
Coordinate with COR to schedule retesting after deficiencies are corrected.
A/E None
CPM Make necessary system repairs, adjustments and/or corrections prior to retesting.
Coordinate retesting as directed and approved by the COR.
Conduct systems retesting by operating systems as directed by COR and functional test procedures.
Construction COR None.
Phase Cx Task Description
Team Member Responsibility
Construction Observation
Conduct visits to the construction site to observe construction activities. Specific attention will be given to installation of fire water main tie-in, sprinkler system piping installtion and alarm system interface to the sprinkler system tamper and flow switches for general conformance with specifications and manufacturer’s installation requirements.
Specific attention will also be given to installation of site utilities, site improvements and building envelope construction for general conformance with plans, specifications and manufacturer’s installation requirements.
CxA Conduct Construction Observation visits to observe construction progress, systems/equipment installation and general quality of construction.
Prepare Field Report to document general and specific observations and issues.
Update Master Issues Log to document and track specific issues reported on Field Report.
Monitor and verify corrective actions.
Update Master Issues Log to document corrective action progress and completion.
A/E Review Master Issues Log
CPM Review Field Reports
Review Master Issues Log
Provide corrective actions as directed by the COR to resolve outstanding issues.
Construction Final Commissioning Report
Compile a comprehensive commissioning report documenting all commissioning
COR Review preliminary Commissioning Report.
Provide comments to CxA.
Review and approve Final Commissioning Report
Phase Cx Task Description
Team Member Responsibility activities, including but not limited to:
Commissioning scope
Test methods and results
Outstanding commissioning issues
Issues log
Commissioning plan
Status reports
Submittal and O&M manual reviews
Training record
Pre-Functional Checklists
Design Review Comments
CxA Prepare preliminary Commissioning Report.
Incorporate VA comments into final report.
Issue Final Commissioning Report.
A/E Review Final Commissioning Report
CPM Review Final Commissioning report
Report on progress and completion of corrective actions.
Construction Owner Architect and Construction Manager Meetings (Construction Phase)
Attend selected Owner/Architect/Contr actor Meetings to discuss commissioning issues, review the Commissioning Issues Log, and to maintain awareness of general construction schedule and issues.
COR Schedule, facilitate and attend meetings.
CxA Attend selected meetings to review commissioning issues.
A/E Attend meetings.
CPM Conduct meetings.
Prepare and issue Meeting Minutes.
Construction Master Issues Log
Maintain a Commissioning Issues Log to document
COR Review Master Issues Log Coordinate and direct corrective actions to resolve commissioning issues.
Phase Cx Task Description
Team Member Responsibility commissioning issues identified during construction and functional testing. The Commissioning Issues Log will include recommended responsible party and recommendations for resolution of the issue.
The Commissioning Issues Log will also be used to document progress toward resolution and the final resolution
CxA Provide monthly updates to Master Commissioning Log.
Provide updated Master Commissioning.
Log after each Construction Visit to document specific issues observed during the visit.
Update Master Issues Log to document progress on corrective actions.
Update Master Issues Log to document completion of corrective actions.
A/E None.
CPM Review Master Issues Log.
Provide status of corrective actions.
Provide notification of corrective action completion.
XIII. Commissioning Schedule
The following is a general outline of the Commissioning Schedule for the commissioning tasks that will be performed on the project site or at the Commissioning Agent Offices:
Table 6 - Commissioning Schedule
Commissioning Schedule
Project Phase
Task Duration Schedule Predecessors
Design Review Design Narrative
3 weeks Comments submitted concurrent with design review comments
Receive Design Narrative
Design Commissioning Specifications
3 weeks Specifications issued concurrent with Phase 2 comment log
Receive Phase 2 drawings and specifications
Design Preliminary Commissioning Plan
3 weeks Preliminary Cx Plan issued concurrent with DD-1 comment log
Receive DD-1 drawings and specifications
Design Focused Final Construction Document Review
3 weeks Comment log issued 3 weeks after receipt of final CDs
Receive Final Construction Document drawings and specifications
Construction Preliminary Commissioning Plan
3 weeks Concurrent with Final CD Design review
Receive Final CD drawings and specifications.
Construction Duration Schedule for Commissioning Activities
None Issued as part of Final Commissioning Plan
Preliminary construction schedule
Construction Pre-Functional Checklists
TBD Preliminary checklists issued approximately 4 months prior to substantial completion
Final checklists issued approximately 3 months prior to substantial completion
Receive equipment submittals
Receive installing contractor’s QC checklists
Commissioning Schedule
Phase
Task Duration Schedule Predecessors
Construction Prepare Functional Test Procedures
TBD Preliminary Functional Test Procedures issues approximately 4 months prior to substantial completion.
Final Functional Test Procedures issues approximately 3 months prior to substantial completion
Receive all requested equipment submittals and shop drawings.
Receive DDC submittal and final sequences of operations.
Construction Systems Functional Testing
TBD Functional testing to begin coordinated with construction schedule and systems completion
See separate table.
Construction Final Commissioning Report
6 weeks Preliminary Commissioning Report issued approximately 6 weeks after completing Functional Testing
Functional Testing completed.
Construction Master Issues Log 1 day Master Issues Log will be updated and issued following each progress meeting and/or Construction Observation visit
Construction Observation visit and/or progress meeting.
Warranty Post-Occupancy Warranty Checkup
TBD Scheduled approximately 10 months after substantial completion
Initial Functional Testing is complete.
Seasonal/deferred testing is complete.
Receive FMD work order log for HVAC equipment.
The following is a general outline of the Commissioning Schedule for the Functional Testing activities that will be performed at the construction site. This information is provided to assist the General Contractor in incorporating the commissioning activities into the overall construction schedule:
Table 7 - Functional Testing Activities
Functional Testing Activities
System Test
Duration Schedule Predecessors Notes
Fire Protection Systems
Facility Water Supply
B-17 Water Supply tie-in to existing fire main
1 day 1 week prior notice by CPM
Piping complete, connection to water source.
Trench open and joints exposed where possible.
Burry pipe between joints to secure.
● Verify calibrated test gauges
● Witness selected pipe pressure testing
● Inspect installation
● Verify installation of proper mechanical restraints
● Documentation per
NFPA 13
Sprinkler System
B-17 new sprinkler system.
2 days 1 week prior notice by CPM
Piping complete
● Verify calibrated test gauges.
● Inspect all piping
● Inspect all hangers
● Inspect sprinkler riser and trim
● Inspect sprinkler heads for temperature rating and orientation.
● Verify no sprinkler head obstructions.
● Witness selected pipe pressure testing
● Document per NFPA 13.
Fire Alarm System 1 day 1 week prior notice by CPM
Fire Alarm devices wired in and fire alarm panel programming completed.
● Witness Re-Acceptance testing per NFPA 72
● Document per NFPA 72.
XIV. Appendix A – Preliminary Log of Required Documentation
The following log provides a preliminary summary of all the Pre Functional Checklists, Functional
Performance Tests and Integrated Systems tests that will be required to complete the
Commissioning process.
The log is preliminary and will be updated based on the components and systems installed by the contractor on the project. It will also be updated to reflect any clarifications or changes in the construction documents that may be reflected by ASIs, ESI, Addendum or other amendments to the construction documents.
Table 8 - Preliminary Summary of all the Pre Functional Checklists
Systems to be Commissioned
Equip Tag
System Pre-
Functional Checklist
Functional Test
Protocol
Sample Size
Notes
Fire & Life Safety Systems
Underground Fire Main Lead-in
‐ Underground Supply Piping Flushing of
Main
Fire Sprinkler…
This is the start of the file's text. The full file is on GovTribe.