Combined SynopsisSol Emergency Drydock 2025 PDF 12.31.24.pdf
PDF 954 KB Posted
- Attached to
- Emergency Drydock Services for US Dredge Wheeler
- Solicitation number
- W912P825R0008
About this file
This is a Combined Synopsis/Solicitation for emergency drydock services for the U.S. Army Corps of Engineers Dredge Wheeler, with responses due by 2:00pm local time on January 3, 2025. The solicitation (W912P825R0008) requires the contractor to provide all management, supervision, labor, facilities, utilities, equipment, tools, and materials for drydocking services over a 21-day period starting around January 6, 2025. The work includes starboard tailshaft replacement, starboard strut and stern tube bearing replacement, starboard propeller hub and blade replacement, starboard stern tube gland seal maintenance, and sea chest strainer maintenance.
The solicitation is set aside 100% for small businesses under NAICS code 336611 (Ship Building and Repair) with a size standard of 1,300 employees. Award will be made on best value considering technical capability, past performance, and price, with technical capability and price combined being significantly more important than past performance. Due to emergency needs, drydock locations within 1,500 miles of New Orleans may be rated more favorably. The contractor must provide a drydock capable of handling the 408-foot vessel with minimum clearances specified, along with required services including power, lighting, air, water, sanitation, crane service, parking, and bilge cleaning. The Corps of Engineers will remain aboard during repairs with a nominal crew.
View the file
Other files
Show all 24
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
COMBINED SYNOPSIS/SOLICITATION FOR COMMERCIAL ITEMS
General Information
Document Type: Combined Synopsis/Solicitation Solicitation Number: W912P825R0008 Posted Date: December 31, 2024 Original Response Date: 2:00pm, local time, January 3, 2025 Current Response Date: 2:00pm, local time, January 3, 2025 Product or Service Code: J020 - Maint/Repair/Rebuild Of Equipment-
Ship And Marine Equipment Set Aside: 100% Total Small Business NAICS Code: 336611 – Ship Building and Repair
Contracting Office Address
7400 Leake Avenue New Orleans, LA 70118-3651
Description
This is a combined synopsis/solicitation for commercial items prepared in accordance with the format in Federal Acquisition Regulation (FAR) subpart 12.6, “Streamlined Procedures for Evaluation and Solicitation for Commercial Items,” as supplemented with additional information included in this notice. This announcement constitutes the only solicitation; proposals are being requested, and a written solicitation document will not be issued.
This solicitation is a Request for Proposals (RFP). The solicitation document and incorporated provisions and clauses are those in effect through Federal Acquisition Circular (FAC) 2023-01.
The associated North American Industrial Classification System (NAICS) code for this procurement is 336611, with a small business size standard of 1,300 people.
The U. S. Army Corps of Engineers, New Orleans District, 7400 Leake Avenue, New Orleans, LA 70118-3651, is seeking to procure Emergency Dry-Docking Services for the Dredge Wheeler.
All interested companies shall provide proposals for the following:
SECTION B
SCHEDULE OF PRICES
Item Description Qty. U/I Unit Price
Amount
0001 Drydocking and Service 21 Day 0002 Cover For Stacks 1 Job 0003 Starboard Items 0003AA Starboard Tailshaft Replacement 1 Job 0003AB Starboard Strut and Stern Tube Bearing
Replacement 1 Job
0003AC Starboard Propeller Gub and Blade Replacement 1 Job 0003AD Starboard Stern Tube Gland Seal Maintenance 1 Job 0004 Sea Chest Strainers 1 Job 0005 (Optional) Services of Machinist (outside) 500 Hr 0006 (Optional) Machining (inside shop) 200 Hr 0007 Welding 0007AA (Optional) Mild Steel Welding 500 Hr 0007AB (Optional) Low Hydrogen Welding 500 Hr 0008 Dock Trials 1 Job 0009 (Optional) Growth Rate 1000 Hr
This labor hourly rate shall be used in pricing all contract changes in accordance with the clause of Section H-2A entitled "COMPOSITE LABOR HOUR RATE FOR CONTRACT
CHANGES.”
NOTE: This bid schedule includes an estimated quantity for evaluation purpose only. Actual hours may be lower or
Higher.
0010 Percent Mark-Up (%) % The percent mark-up applies only to materials, parts, and sub-contract service in growth work only.
NOTE: This percentage will be evaluated for reasonableness
MANDATORY $
OPTIONAL $
TOTAL $
NOTE 1: All requirements in the schedule under the ITEM and Description/Specs./Work Statement.
The citation "0001 DD-1" gives the necessary information for proper bid preparation for Contract Line Item 0001.
EXAMPLE ITEM Spec. DESCRIPTION 0001 DD-1 Berthage, Drydocking and Services
NOTE 2: Payments for items identified as (Optional) will be paid in accordance with the provisions located in SECTION H, at paragraph H-2, "Optional Item." Payment shall be calculated by multiplying the bid Optional (U/P) by the actual Quantity (Qty.) used - (U/P x
QTY).
NOTE 3: The use of any particular product or commodity name is only given as a point of reference and any product or commodity that will satisfy solicitation or contract performance requirements may be offered. It is further requested that offeror submit manufacturer's specifications or information sheets delineating those like characteristics.
PERFORMANCE WORK STATEMENT
PART 1 – GENERAL INFORMATION AND REQUIREMENT
1. WORK TO BE DONE. (Information) In accordance with the Master Ship Repair Agreement, for Repair and Alteration of Vessels (MSRA), the Contractor shall furnish all management, supervision, labor and all facilities, utilities, equipment, tools, lubricants, fuels, materials and articles (excluding Government furnished property) necessary to fully execute the work items specified herein.
2. VESSEL DATA. (Information) The dredge WHEELER is an all-steel, sea-going hopper dredge. The dimensions of the hull are:
Length Overall 408 feet -3 inches Length Between Perpendiculars 384 feet -0 inches Breadth Molded 78 feet -0 inches Breadth at Wheelhouse Catwalks 82 feet -0 inches Registered Gross Tonnage 10,614.47 long tons Lightship Displacement 9,846.25 long tons Ballast, Fuel and Water 600 long tons (approx.)
3. CONTRACT DRAWINGS. (Information) The work shall conform to the following contract drawings, all of which form a part of these performance work statement and are available in the contracting office of U.S. Army Corps of Engineer, New Orleans District, 7400 Leake Ave, New Orleans, Louisiana, 70118. All drawings are available in electronic forms (PDF files or other Word Scanning files). There will be no hard copies of drawings (bluelines, zerox, etc.) to be sent out.
AVONDALE SHIPYARD (ASI) DRAWINGS
Dwg. No. Title
01-03-01 General Arrangement, Outboard Profile 01-03-02 General Arrangement, Inboard Profile 01-03-03 General Arrangement, Hold 01-03-04 General Arrangement, 2nd Deck 01-03-05 General Arrangement, Main Deck 01-03-06 General Arrangement, Upper Deck 01-03-07 General Arrangement, Poop, Fo'c'sle and Top of Hopper 01-03-08 General Arrangement, Boat Dk, Bridge Dk and Upper Bridge Dk 01-03-09 General Arrangement, Navigating Dk, Pilothouse and Top of pilothouse 07-00-01 Docking Plan 11-07-02 Stacks 29-01-08 Stability Booklet
MISCELLANEOUS SYSTEMS
21908 Shafting Arrangement 21976 Pressure Shrunk Coupling 22076 Shafting Assembly With E105-4 Propeller 22189 E104-4 Propeller Hub Assembly 22323 Propeller Blades 22385 & B/M Hydraulic Power Unit Assy. Propulsion Sys.Inc.
22437 & B/M Servo Box Assy. Propulsion Sys.Inc.
4. INTERFERENCE AND LOAD SUPPORT.
Remove and reinstall any interference required to accomplish the work specified without additional contract time or cost to the Government. Interference is defined as any part of the vessel or other equipment, whether installed or portable, that must be removed or disturbed to accomplish the work specified. Approval shall be obtained from Government Inspector prior to disconnecting piping or other vessel services. Drain lines shall be by-passed or diverted to prevent damage by flooding. All damaged or missing fasteners shall be replaced with fasteners of the same type as original. New gaskets, packing and seals shall be installed on all disturbed connections and proven leak free.
Damaged lagging and insulation shall be repaired or replaced. All new work or disturbed old work shall be cleaned and painted in accordance with this specification and existing color scheme. Upon reinstallation, all interferences shall be returned to their original operational condition and position.
During disassembly and removal process, the Contractor shall provide support for or secure as necessary the remaining items or sections, i. e. dragarms, dredge piping, davits, walkways, trunnions, service frames, adjustable weirs, etc. All costs incurred on these bases shall be included in the bid price for the respective item of work.
5. TECHNICAL SERVICE REPRESENTATIVES.
There are several items which require the work to be accomplished under the supervision of a specific technical service representative, which will be provided by the Contractor. However, utilization of the specified representative is not mandatory. The Contractor may elect to procure the services of another individual or firm that has the necessary technical qualifications, experience or expertise. The name of the individual or firm and the qualifications, expertise or experience relative to the work to be accomplished shall be submitted to the Contracting Officer Representative for approval prior to starting the work. The Contractor remains solely responsible for the satisfactory completion of all work and the reliable operation of all systems specified herein. The cost of these representatives will be included in the bid price for the respective item(s) of work.
A daily report will be prepared by each technical service representative and submitted directly to the Contracting Officer Representative within 24 hours. The report will be the responsibility of the technical service representative, and will describe conditions noted with recommendations for corrective action, all work performed that day, parts used and any additions or modifications made to the existing equipment. If the Contractor requires any reports in addition to these, the Contracting Officer Representative will be furnished a copy of the reports.
The representatives listed below have the necessary technical qualifications, experience and expertise and are recommended for any applicable items in which they are specified:
a) PROPULSION SYSTEMS INC.
Propulsion Systems, Inc.
609 NW 45TH Street Seattle, WA. 98107
(206) 789-0944
b) THORDON BEARINGS INC.
Thordon Bearings, Inc.
3225 Mainway Burlington, Ontario L7M 1A6
CANADA
(905) 335-1440
6. GAS-FREEING AND GAS-FREE CERTIFICATE (If Applicable).
Before beginning any hot work or any other work involving the use of an open flame, or any other means of igniting flammables, clean and gas-free the affected spaces as required by Clause 5(e), OSHA Safety and Health Standards (29 CFR 1915), and these specifications. Spaces requiring the gas-freeing shall be "Safe For Men - Safe for Fire (Safe for Hot Work)".
Until all hot work or all other work involving the use of an open flame or any other means of igniting flammables is completed, maintain the affected spaces in a "Safe For Workers - Safe For Fire" condition.
Test affected spaces. Testing and certification shall be accomplished by a certified chemist who is approved for this type of work by the National Fire Protection Association.
Furnish and display at the entrance to the affected spaces and at the primary gangway "Gas-free " or "Safe for Workers - Safe for Fire (Safe for Hot Work)" certificate(s). Furnish to the Contracting Officer Representative one additional copy.
The cost of testing, providing gas-free certificate(s), and physically gas freeing affected spaces shall be included in and proportioned among the bid prices for each item of work requiring cleaning and gas-freeing of a compartment.
PART 2 – SCOPE OF WORK
001 BERTHAGE, DRYDOCKING AND SERVICES.
Drydock facility must be available starting on or about 06 January 2024.
The Contractor shall furnish pilot service and tugs service to safely escort/move the ship from entrance channel sea buoy closest to Contractor's facility to Contractor's drydock. Thereafter, the Contractor shall provide these pilot and tugs services to move/escort the ship while the vessel is in his possession, including moving/escorting the ship from contractor’s drydock to contractor’s wetberth or vice versa. The contractor shall also provide these pilot and tugs services when the ship departs from the contractor’s drydock or wetberth to sea buoy. Refer to Section F for details of delivery and return of the vessel. Delivery and return will be coordinated with the Contracting Officer Representative.
Upon receipt of the vessel, the Contractor shall drydock the vessel for such time that will be necessary to complete all underwater work included in these specifications. The time at wet-dock berthing or other prior to starting any work, shall not exceed two (2) calendar days prior to entering the drydock. Prior to drydocking, the Contractor shall prepare a proposed blocking plan, utilizing the data on ASI Dwg. No. 07-00-01 Docking Plan, and submit the blocking plan to the Contracting Officer Representative for approval. The drydock shall be capable of handling the vessel as follows:
The following are the estimated ship’s draft at time of arrival and the drydock requirement:
The ship will arrive at the contractor drydock at the estimated draft of 19’-8” feet Aft and 17 feet Forward (Arrangement shall be worked out between the government and the contractor prior to drydocking to off load fuel to achieve this estimated draft. The fuel shall be returned to the ship at the date mutually agreed).
During drydocking and undocking process, there must be a minimum of one (1) foot clearance between the bottom of keel plate and the top of the blocks. Upon drydocking, all blocks shall be checked and wedged up for firm contact with the hull.
For safety reason, the drydock (graving or floating) must have a minimum of 5 ft clearance on each side of the ship from the breadth of wheelhouse catwalks to the drydock inside walls. In another words, drydock with an internal width clearance of less than 92 ft shall not be acceptable.
During the drydocking and undocking procedures while the ship is in the contractor possession, the contractor shall provide the services of a pilot, tugboats and all line handlers (aboard and ashore) and all required lines.
DRYDOCK SUBMITTALS -- Unless specified otherwise, at least forty eight (48) hours prior to docking/undocking the vessel, submit to the Contracting Officer Representative the following:
Drydock certification submittal. Prior to award of the Contract, submit to the Contracting Officer certification for the drydock or tentative drydocks to be used to lift the vessel. Ensure that the drydock is certified for docking the vessel of the dimensions and weight given by one of the following:
(1) US Navy, Naval Sea Systems Command
(2) American Bureau of Shipping (ABS)
(3) An independent registered Professional Engineer, who shall cover the inspection requirements of item (1) or (2) above.
The Inspection Certificate shall be within three (3) years if the age of the dock is less than ten (10) years old and within two (2) years if the age of the dock is over ten (10) years old.
Note: Floating drydocks shall be one integral unit. The Government will not allow the coupling of two rated docks to meet the load requirements of the vessel.
Certification inclusions. Regardless of the type of certification provided, submit to the Government’s Technical Point of Contact the information regarding the docking facility, as applicable:
(1) Drainage and dewatering systems
(2) Mooring systems for floating docks
(3) Fire protection services
(4) Fire alarm locations
(5) Emergency power
(6) Emergency ballast/dewatering pumps
(7) Structural Examination with Load per Foot Rating
Stability and block loading calculations. Submit to the Contracting Officer Representative docking/undocking calculations as follows, including the effect of all dockmaster authorized weight additions/removals or shifts as the result of ship's actions or the contract scope of work.
(1) Blocking
(2) Stability of the vessel afloat
(3) Vessel Stability for keel touch
(4) Draft at Instability
(5) Vessel's GM when water is at top of blocks
(6) ** System Stability when water is at top of blocks
(7) ** System Stability when pontoon deck is awash
(8) ** System Stability when pontoon deck breaks surface
(9) ** Pumping Plan
** Submit for Floating Drydocks Only
Documentation of drydocking significant events. The Contractor shall submit the following information in a separate written report to the Contracting Officer Representative within 48 hours after docking and undocking the vessel.
The precise time that the vessel's first extremity crossed the drydock boundary upon docking. The precise time that the vessel's last extremity crossed the drydock boundary upon undocking. The forward and aft draft readings just before docking and immediately after undocking.
Manning document. Provide a list of drydocking operations which describes all stations to be manned, functions to be performed, and the experience and training qualifications of personnel carrying out each function, including casualty and damage control qualifications.
Dockmaster. The dockmaster assigned by the Contractor shall provide a resume of training and experience and meet one of the following criteria:
(1) Has served as a dockmaster at the type of facility for which the individual is qualified during at least 10 dockings or undockings, of which one has been accomplished within the previous 6 months.
(2) Has served under a dockmaster in an apprentice/assistant role during at least 20 dockings or undockings, of which 10 have been performed at the type of facility for which the individual is qualified. One docking or undocking shall have been conducted within the previous 6 months.
(3) Has served under a dockmaster in an apprentice or assistant role during at least 10 dockings or undockings and has served as a dockmaster at the type of facility for which the individual is qualified during at least 5 dockings or undockings, of which one has been accomplished within the previous 6 months.
Immediately after drydocking, provide and install temporary scupper drains and sewage pumpout lines of suitable sizes from the drains and overboard discharge lines, as required to prevent water draining down the ship's sides. Leave temporary drain lines connected throughout drydock. Remove all drain lines after completion of drydock work. The Contractor shall be responsible for disposing of sewage treatment plant effluent.
INSPECTION POINT. Prior to undocking the vessel, a pre-undocking conference shall be held with representatives of the contractor, Government Inspectors, and ship’s crew in attendance. The plan for undocking shall be reviewed and agreed upon. The hazardous energy/lock out status of the ship’s equipment will be reviewed and updated at this time. A determination shall be made of what systems or equipment require tag out prior to undocking. The Contractor and a representative of the Contracting Officer will perform a joint pre-undocking inspection in accordance with the checklist provided in attachment J-1, section J to ensure that the vessel is in all respects ready to be re-floated. The checklist (only applicable items) shall be completed by the Contractor, verified by the Government Inspectors and submitted to the Contracting Officer Representative prior to the undocking. Undock the vessel, after all underwater work and the pre-undocking inspection have been completed.
When necessary, while the vessel is in the Contractor’s possession, provide berthing for the vessel.
The Contractor shall provide all mooring lines and fenders sufficient in strength, quantity, location and quality to prevent damage to the vessel and the dock. Provide all necessary labor, material, services and equipment as required to safely move the vessel while it is in Contractor's facility. In addition, provide adequate protection in the case of adverse weather conditions (i.e., hurricane).
This shall include, but not be limited to, providing tugs on standby (to be sufficient in quantity and size), pilot service, extra mooring lines with chafing gear and anchors aboard and ready. Provide all line handlers aboard and ashore as needed. Bollards used for the WHEELER shall not be shared with other ships.
Provide services to the dredge in accordance with the requirements of Section H, paragraph H-4 at all times while the vessel is moored or drydocked within the Contractor's facility. The Master or Senior Officer aboard the vessel must be notified whenever firefighting/damage control capabilities are reduced significantly, such as when the CO2 system is taken off line. The Contractor shall also inform the Master or Senior Officer when these services are returned.
If there is any sandblasting work within 100 yards from the ship, the contractor must cover the stacks and secured in such a manner as to withstand high winds. There are four (4) main engines and three
(3) ship's service generators which will need covers. After all work has been completed and prior to starting the engines, the covers must be removed.
002 COVER FOR STACKS. Furnish labor and materials to construct a temporary cover over the smoke stacks to prevent rain from entering the stacks while the vessel is in the drydock. The covers shall be placed on the stack and secured in such a manner as to withstand high winds. There are four (4) main engines and three (3) ship's service generators which will need covers. After all work has been completed and prior to starting the engines, the covers shall be removed. Refer to ASI Dwg. 11-07- 02.
003 PROPELLERS, SHAFTING AND CONTROLLABLE PITCH SYSTEM INFORMATION).
The propellers aboard the dredge WHEELER are controllable pitch type (hydraulic powered), Model E105/4, manufactured by PSI/Liaaen. There are four propeller blades mounted on each hub. The total diameter (tip to tip) is approximately 150 inches. Port and starboard pitch systems are independent of each other. Each system consists of an oil distribution or servo box, and hydraulic power unit assembly. These units send and receive oil from the hub, controlling pitch direction.
Hydraulic oil is sent to and from the hub through an oil tube extending through the line and tailshafts from the servo box to the hub. The hydraulic power unit assembly includes two (2) servo oil pumps (25 hp motors), one (1) hub oil pump (1 hp), a hydraulic oil pressure gage panel, an oil distribution manifold, and three (3) pressure relief valves. Each system contains one (1) main oil reservoir (110 gallon capacity) and one (1) hub oil head tank (10 gallon capacity). Refer to Propulsion Systems Inc./Atlantic Industrial Technology Dwg. 11333 for power unit assembly details, PSI Dwg. 22437 for servo box details, and PSI Dwg. 22076 for shafting details.
Note: In reference to items 003.1 and 003.3 below, it is required that a Propulsion Systems Inc. (PSI) field technical representative be present on site during all work performed, including at the dock trial, line item 008. A copy of the representative’s daily reports must be furnished as the Contractor receives them.
003.1 STARBOARD TAILSHAFT REPLACEMENT.
The propeller tailshaft is approximately 47 ft – 2 inches long and weighs an estimated 25,000 lbs. The approximate hub assembly dry weight is 12,100 lbs. The coupling weighs approximately 2,500 lbs.
Remove the upper and lower halves of the rope guard, which is spot welded around the circumference and between the halves. Disassemble the pressure shrunk coupling at the forward tailshaft end on the vessel interior using Contractor (PSI) furnished pressure injection pumps. The pressure shrunk coupling will be re-used. Remove the propeller blades under item 003.3, note: blade bolts shall be reused. Remove the hub assembly from the ship and prepare & crate it for return shipment to the government’s storage facility. (Note: It will be necessary to remove and reuse hub bolts and flange cover. The starboard hub flange cover is filled with tallow, the contractor shall remove, dispose the tallow and clean the flange cover and the exterior of the hub thoroughly). Hub mounting bolts have a welded lock bar and are torqued to 6,955 ft.-lbs. Impact wrenches are not allowed for removal or installation of bolts. The Government will furnish a replacement hub.
Proceed with removal of the tailshaft and prepare it (put back in stanchions that come with the new shaft, provide wooden battens to properly support the shaft in the stanchions) for shipping back to the government’s storage facility. Remove the oil tube from the tailshaft. Inspect, clean, and dress the oil tube in its entirety.
Remove from stanchions and prepare the new, Government furnished tailshaft, part no. 21965, for installation by first removing it from its cradles. If the shaft is to be lifted from overhead by a hoisting device, insure an adequate spreader bar is used to prevent the shaft from bending. Remove protection from liners and clean all corrosion protection and dirt from shaft exterior and entire shaft bore. Take Micrometer readings on the coupling end of the new Government furnished shaft and submit a reading report to the government. Perform Dye Penetrant testing of the flange radius under the witness of the government inspectors. INSPECTION POINT. Install the oil tube through the shaft bore. Protect shaft/oil tube ends with temporary plastic wrapping. Install flange cover on shaft.
Aboard the vessel, perform maintenance on the stern tube gland seal assembly covered under item
003.4 below. Replace the inflatable seal for the gland seal with a government furnished seal. The contractor shall provide all new O-rings required for this replacement.
After all work and inspections have been completed in item 003.2, reinstall the tailshaft into the ship.
Prior to installing the existing coupling, use micrometer measurements from the coupling end of the shaft and ensure pressure shrunk coupling sleeve bore is within specified clearance per referenced PSI drawing 21976 and also PSI technical representative recommendations). Provide o-ring seals described above. Reconnect oil tube and re-install hydraulic coupling. Install the propeller hub and propeller blades under item 003.3. Drill a new set screw hole for inner oil tube set screw landing when installing inner oil tube. Provide and weld new contractor furnished lock bar on hub mounting bolts. Tap out rope guard mounting holes in strut housing. Modify rope guard length to accommodate the new shaft length, giving a final clearance of 0.200 inches with a tolerance of plus 0.060, minus 0.000 inches. Reinstall rope guard halves using lock wire on mounting bolts and spot welding to strut housing. INSPECTION POINT. Demonstrate rope guard clearance readings (between rope guard and tailshaft flange cover) to the Government Inspector. Clean, prime, and paint welded or disturbed areas.
003.2 STARBOARD STRUT AND STERN TUBE BEARING REPLACEMENT.
In reference to work item 003.2, it is required that a local Thordon Bearing representative be present on-site during all work performed.
Coordinate this work with the work in item 003.1, starboard tail shaft replacement.
Provide labor, material, and equipment to remove the inspection covers along the starboard strut/ stern tube and grind off the spot welds that are securing the retainer rings to the strut and stern castings. There are three Thordon bearings inside the strut/ stern tube that need to be cut out and replaced with new government furnished bearings.
After removing the old bearings, clean the casting housings thoroughly. Provide labor, equipment, materials, and subcontract to take laser (or optical) alignment of the starboard strut, stern tube, Cooper bearing and reduction gear flange. Provide the Government with an alignment reading report.
The Government will provide three new rough cut Thordon bearings for the starboard strut and stern tube. The Contractor shall machine the Government furnished bearing and install under the supervision of an on-site Thordon representative. Prior to machining the Thordon bearings, provide the Government with calculations of the final bearing machined dimensions. The Thordon bearings are freeze fit and will require the proper equipment to submerse the bearings in liquid nitrogen in preparation for the installation.
After installation of Thordon bearings, provide laser alignment to verify all final dimensions.
INSPECTION POINT.
The Contractor shall re-install the removed steel retainer rings along with all fasteners.
Inspect all studs for inspection cover mounting. Submit a final report of all closing fits, clearances and conditions.
INSPECTION POINT. The Government Inspector shall inspect before reassembly of inspection covers.
003.3 STARBOARD PROPELLER HUB AND BLADE REPLACEMENT.
The Government will supply the following Parts:
Part No. Description Qty.
22486 Inner Oil Tube Wrench 1 Ea.
22323LH Left Hand Propeller Blade 1 Set (set of 4) 19938 Blade Lifting Tool 1 Ea.
D22189-LH Propeller Hub Assembly, LH 1 Ea.
The contractor will supply the following Parts:
(Note: These parts shall be purchased directly from PSI due to the proprietary information)
25332-A Rev D Blade Seals 4 Ea.
22015-19-B Blade Bolt Washers, Hub 32 Ea.
(Note: The contractor shall provide the government a quantity of 4 each (blade seal), and 64 each (blade bolt washer) for spare).
Install new, Government furnished hub and blades. Note: The contractor must provide temporary shelter to protect the (starboard) propeller hub and blades AT ALL TIME throughout the contract period to ensure that no water, paint, dirt or other contaminants enter the hub interior or seals.
Each blade weighs 2,345 lbs. Two welded locking bars must be removed from the bolts of each blade. A Government- furnished lifting device, part no. 19938, will be provided. Test each propeller blade bolt (total of 32) for cracks by dye penetrant method. INSPECTION POINT. Notify the Government Inspector and USCG for witnessing of non-destructive test. Upon removal, the new government furnished propeller blades’ palm faces and edges shall be protected by rubber gasket material with fabricated, galvanized sheet metal covers. The old propeller blades shall be installed back in the government furnished steel pallets and protective blade palm covers, bolted down to the steel pallets. Disassembly and reassembly of blades shall be done in accordance with PSI's manual which is available on the vessel. The contractor shall verify/measure blade bearing clearances (palm faces and edges) on the government furnished blades prior to installation. Blade bolt torque shall be verified with a torque meter. Impact wrenches are not allowed for blade bolt removal or reinstallation. Provide and weld new contractor furnished blade bolt locking bars. Inspect for leaks and leave propeller blades ready for service. Check the pitch of the blades to insure that the blades are pitching to the zero, full ahead and full astern marks at the hub prior to undocking. INSPECTION POINT. This test shall be witnessed by the Government Inspector and USCG Inspector.
003.4 STARBOARD STERN TUBE GLAND SEAL MAINTEANCE.
While in drydock, disassemble the starboard tailshaft packing gland. Remove compression gland and packing material. Remove the split gland housing. Separate halves, but do not use prying tools.
Clean all components and fasteners. Remove the inflatable seal retainer flange. Submit a CONDITION REPORT with findings including packing gland condition to the Contracting Officer Representative. Replace the seal with a Government furnished split seal. Apply Government furnished Sealant, Manufactured by BF Goodrich, Elastolock 2995 liberally to joint grooves and surfaces, clamp with wood, and allow to cure 24 hours to cure. Reassemble the seal flange to the base ring. Reassemble the gland housing using new contractor furnished: 0.275 inch O-ring material, 1/16 inch thick Buna-N gasket material and Permatex liquid gasket. Provide and install 7 rows of (government furnished) 1 inch x 1 inch Teflon impregnated packing in stuffing box. Tie off two rows of additional packing on the bulkhead near each gland. Adjust gland nuts for proper packing tension.
Do not over tighten. While the ship is entering the water, adjust as necessary to allow slight seal leakage. INSPECTION POINT. The Government Inspector shall be present for packing installation and adjustment.
004 SEA CHEST STRAINERS
In drydock, open both sides of the two (2) interior sea chest duplex strainers located in the No. 2 void spaces, port and starboard. Remove all debris and trash. INSPECTION POINT. Notify the Government inspector for inspection when the baskets in the two No. 2 voids’ strainers have been removed.
On the starboard side sea strainer only, replace the disc and all retaining hardware on the outboard side of the strainer with new government furnished equipment. On both port and starboard side sea strainers, clean chain wheel drive mechanisms and port discs and lubricate all moving parts.
INSPECTION POINT. After replacing hardware (starboard side only), cleaning and lubricating all moving parts, contact the government for inspection and manually test operation of the chain wheel mechanisms.
INSPECTION POINT. Contact the government inspector for inspection.
Reassemble all strainers following inspection and prior to undocking. The contractor shall provide all new 3/16 inch thick, one piece gaskets.
005 (OPTIONAL) SERVICES OF MACHINIST (OUTSIDE). Provide the services of a qualified outside machinist as specified in writing by the Government Inspector. This will include any hand and small power tools needed to perform general shipboard work not specifically included in these performance work statement. An estimated total of 500 hours shall be used for bidding purposes.
006 (OPTIONAL) MACHINING (INSIDE SHOP). Remove from ship worn or damaged parts and transport to contractor’s machine shop to repair, or machine new parts as required and reinstall back on the ship. An estimated total of 200 hours shall be used for bidding purposes.
007 WELDING (Information). Furnish qualified electric and gas welders; fully equipped, including, welding machines, scaffolding or staging, gas welding equipment and rods and apply build-up or straight welding wherever directed in writing by the Contracting Officer Representative. Welders shall be qualified for the type welds required. The list of qualified welders to be utilized will be provided to the Contracting Officer Representative prior to the start of work. When scaffolding labor is required for authorized welding under this item, and is not otherwise paid for under these performance work statement, scaffolding labor may be included. The following estimated welding hour quantities shall be used for bidding purposes:
007.1 (OPTIONAL) MILD STEEL WELDING - Bid on 500 hours.
007.2 (OPTIONAL) LOW HYDROGEN WELDING - Bid on 500 hours.
008 DOCK TRIALS. When all work has been completed, the vessel shall be subjected to dock trials listed herein to make necessary adjustments and determine that the work performed meets the requirements of the specifications. All tests and trials shall be conducted by the ship crew under the witness of the government, and appropriate technical service representatives (if applicable). The dock trials shall be conducted between 0600 and 1800 hours. Defects in the Contractor's work shall be immediately remedied by the Contractor, and the affected unit re-tested under the same working conditions until proven satisfactory.
Dock tests shall be conducted at a wet dock not less than 600 feet long, equipped with sufficient mooring bitts of adequate strength to hold the vessel securely to the dock.
Upon completion of dock trials and final acceptance by the Government, the vessel will be returned to the Government in accordance with Section F, paragraph F-2.
PART 3 – QUALITY ASSURANCE SURVEILLANCE PLAN (QASP)
1. This section identifies the method of surveillance the government’s Quality Assurance Personnel (QAP) will use to verify the quality of the contractor’s performance. Surveillance methos is periodic inspection (in addition to the scheduled inspection as called out in the work statement above).
2. Re-performance of unacceptable services at no additional cost is the preferred course of action when appropriate.
3. Method of surveillance will be 100% inspection by the QAP. Surveillance will be performed as specified in the Service Delivery Summary (SDS) in paragraph 5 below.
4. Where appropriate, methods for administering and evaluating services not included in the Service Delivery Summary are to be developed by the QAP.
a. The government retains the right to inspect required tasks not shown on the Service Delivery Summary. Inspection of these services will be in the same general manner as SDS items. The results of these inspections shall be documented. Any results that require minor corrective actions, the government inspector shall discuss the deficiencies with the appropriate shipyard personnel. Any major deficiency shall be provided to the contracting officer for action.
b. The following non-SDS items may be observed periodically during the contract period.
* Employees identification badges if working on any repair work for the Dredge Wheeler whether on board or on the drydock.
* Work manner of employees.
* Safety compliance (Safety Plan & EM-385-1).
5. Service Delivery Summary
Performance
Objectives
PWS
Reference
Surveillance
Method
Performance
Threshold
All general contract requirements are complied without deficiencies or safety violations.
Part 1 (General
Information & Requirement) Items 1 to 6
100% visual inspection of work site
Zero (0) defects allowed.
100% Re-performance of all defective work is required. Other remedies allowed by FAR Clause 52.212-4 also apply.
All required service for drydocking and other berthages services are provided in a timely manner without deficiencies.
Part 2 (Scope of Work)
Item 001
100% visual inspection and operation of affected equipment
Zero (0) defects allowed.
100% Re-performance of all defective work is required. Other
All required measurements shall be performed and submitted in a timely manner.
Items 002 thru inspection
Zero (0) defects allowed.
100% Re-performance of all defective work is required. Other
All repair work shall be performed using the most efficient labor in a timely manner without any safety violations.
inspection of work site and testing of equipment as required
Zero (0) defects allowed.
100% Re-performance of all defective work is required. Other
All repair work shall be free of defects and the equipment repaired shall work properly.
Part 2 (Scope of Work) inspection and test run of all repaired equipment
Zero (0) defects allowed.
100% Re-performance of all defective work is required. Other
All required service for dock trials are complied without deficiencies or safety violations.
Part 2
Items 008 inspection and test run of all applicable equipment
Zero (0) defects allowed.
100% Re-performance of all defective work is required. Other
SECTION D
NOT USED
SECTION E
INSPECTION AND ACCEPTANCE
E-l GENERAL INSPECTION AND TESTS - QUALITY CONTROL AND QUALITY ASSURANCE
a. The Contractor shall provide and maintain an inspection (Quality Control) program covering all work specified in the Contract utilizing a designated organizational element and personnel not involved in the work. The Contractor shall perform, or have performed, all inspections and tests required to substantiate that the supplies and services submitted to the Government for acceptance conform to the drawings, work statement and contract requirements herein.
b. The Contractor's inspection system shall be documented, and the records shall be available for review prior to award of the Contract and throughout the life of the contract. For each work statement item, the Contractor shall determine and record the inspections and tests to be accomplished, the observations made, any deficiencies found and the corrective action taken.
In addition to the inspections and tests which the Contractor is to perform to assure contract performance and quality of product, all inspections and tests specified in the work statement will also be included in the inspection system.
c. Quality Assurance (QA) inspections will be performed by Government personnel at those stages of work necessary to determine conformance with the contract requirements. Generally a QA inspection will be made for each item of work, including growth work, to verify that the work has been completed as specified and the item is ready for testing. In addition, QA inspections will also be made for those initial and in-progress inspections specified in the various specification items. Required inspection points are denoted in the work statement with the words "INSPECTION POINT" in bold letters.
d. The Contractor shall submit after award the quality control assurance program to be utilized to assure the Government that all work conforms to the requirements of the work statement.
The program shall include a list and schedule of all inspections to be made, a list of the Contractor's personnel who will be planning, coordinating, performing or witnessing the inspections and tests and the form to document procedures to be followed by Contractor and Government personnel. A copy of the forms to be used to record the inspections made, the deficiencies noted and corrective actions taken will also be included.
e. The Contractor will notify the Contracting Officer Representative, in writing, at least 12 hours in advance of the time and date of each inspection and test. If the Government Inspector is not present at the scheduled time, the Contractor will proceed with the inspection or test and document the results as required herein. If the scheduled inspection is to verify completion of an item of work, the notice will include a signed certification that all materials and workmanship meet all requirements of the work statement, that all work has been satisfactorily completed and the item is ready for inspection.
f. Any defects in workmanship or material will be remedied by the Contractor at no additional cost to the Government, and fully re-tested. Witnessing tests and inspections by the Government Inspector and signing of related documentation does not constitute acceptance of the item, and does not relieve the Contractor of the responsibility of assuring that the work and material conform to the requirements of the work statement.
g. A copy of the inspection documentation, duly signed by the Contractor and Government Inspectors (including U.S. Coast Guard and ABS Inspectors, when applicable) will be furnished to the Contracting Officer Representative within 48 hours after each inspection and/or test.
Payment for each item, including growth work, will be contingent on receipt by the Contracting Officer Representative of the Completion Report recording the specific work accomplished, date(s) work was done and the shop or craft performing the work. No item shall be considered 100 percent complete on the progress report, until this report, signed by the Government Inspector, has been submitted to the Contracting Officer Representative.
h. Work subcontracted and performed away from the shipyard is also covered by this inspection system. The prime Contractor cannot delegate the authority to witness or perform, and sign for tests and inspections conducted away from the shipyard, without written approval of the Contracting Officer Representative. If the Subcontractor has an established Quality Control program with designated organization element and personnel, the prime Contractor may designate an appropriate individual in that organization as his authorized representative and complete the testing and inspection report as described above. Such designation shall clearly indicate that the individual is an employee of a Subcontractor and shall be subject to the approval of the Contracting Officer Representative. The Government Inspector will witness tests and make inspections at the Subcontractor's plant in accordance with Paragraphs (c) and
(e) above.
i. Upon satisfactory completion of items of these specifications performed by any Subcontractor, the Prime Contractor will furnish the Contracting Officer Representative an exact reproduced copy of each completed testing and inspection report relative to that item in accordance with Paragraph (g) above.
E-2 DETAILED INSPECTIONS AND CONDITION REPORTS.
a. Many items in the performance work statement call for a detailed inspection and a written report to be submitted to the Contracting Officer Representative. Each particular item will specify which areas are to be inspected and by whom, whether it be the Contractor or a Subcontractor. Every report shall include, but is not limited to: (a) what was inspected, (b) condition of item inspected, (c) recommendation of repairs and/or replacement. All costs incurred for these services shall be reflected in each particular bid item.
b. Unless otherwise specified herein, the items that require inspection by the Contractor with written report to be furnished to the Contracting Officer Representative must be completed within ten (10) days after vessel enters shipyard. The Contractor shall furnish the written reports for these items within 48 hours after each inspection.
E-3 QUALITY OF ARTICLES, MATERIALS AND EQUIPMENT.
a. Where articles, materials and equipment are required to conform to standard specifications or test of Government or other authorities incorporated by reference, they will conform to the respective editions, including amendments specified.
b. Any samples and descriptive data required shall:
(1) Be submitted within the time specified in these specifications, or, if not specified, within a reasonable time before use to permit inspection and testing.
(2) Be shipped prepaid and delivered, as specified in these specifications, or as directed by the Contracting Officer.
(3) Be marked to show the name of the material, trade name of manufacturer, place of origin, name and location of the project where the material represented by the sample is to be used, and the name of the Contractor submitting the sample.
(4) Samples not subjected to destruction tests may be retained until completion of the work but thereafter will be returned to the Contractor, if he so requests in writing, at his own expense.
Failure of any sample to pass the specified requirements will be sufficient cause for refusal to consider further any samples from the same manufacturer whose materials failed to pass the tests.
NOTE TO PROCUREMENT: Proposed Clauses incorporated by reference:
52.246-2 INSPECTION OF SUPPLIES – FIXED PRICE
52.246-4 INSPECTION OF SERVICES – FIXED PRICE
52.246-16 RESPONSIBILITY FOR SUPPLIES
SECTION F
DELIVERIES AND PERFORMANCE
F-l DELIVERY OF VESSEL. The Government shall deliver the vessel to the area in front of the Contractor's drydock. For the purpose of computing the Contract time, the closest hour that the vessel is placed in control of the Contractor's tug boat, or delivered by the Government to the Contractor's shipyard, shall be considered as time of commencement. Pilot and Tug services to be provided under the performance work statement, part 2 – scope of work, item 001.
F-2 RETURN OF THE VESSEL. Contractor shall coordinate and complete the various items of work in sufficient time to allow for aligning and starting up the support systems needed for dock trials. After the dock trial, the contractor shall provide a wet berth for the ship to take on the fuel offloaded prior to drydocking. After all repairs and trials are completed, the Government shall accept return of the vessel at the wet berth where the dock trial was performed. Upon the ship departure, Pilot and Tug services shall be provided under the performance work statement, part 2 – scope of work, item 001.
The time of returning the vessel to the Government shall be the closest hour after acceptance of the vessel by the Government.
F-3 DELIVERY SCHEDULE. The work will be completed within twenty-one (21) calendar days after delivery of the dredge (see F-1) to the Contractor.
F-4 COMMENCEMENT, EXECUTION AND COMPLETION.
a. The Contractor shall be required to commence work under the Contract immediately upon delivery of the vessel to him, to execute the work with diligence and to complete the work within the time stated in the Contract.
F-5 SCHEDULE AND PROGRESS OF WORK. Each prospective Contractor shall submit with his bid a schedule for accomplishing all work. The schedule shall include a bar chart for each item, including unit price items, and shall show start and completion date of all items, including dock trials. The chart shall indicate the order in which the Contractor proposes to accomplish all work. Items shall be scheduled for earliest possible completion, commensurate with good ship repair practice and availability of materials.
Physically meet with the Contracting Officer Representative daily to discuss progress, problems and forthcoming schedule requirements. If, in the opinion of the Contracting Officer, the Contractor falls behind the progress schedule, the Contractor shall take such steps as may be necessary to improve his progress and the Contracting Officer may require him to increase the number of shifts and/or overtime operations, days of work, and/or amount of plant and to submit such supplementary schedules in chart form as may be deemed necessary to demonstrate the manner in which the agreed rate of progress will be regained, all without additional cost to the Government.
Failure of the Contractor to comply with the requirements of the Contracting Officer under this provision may be grounds for determination by the Contracting Officer that the Contractor is not executing the work with such diligence as will insure completion within the time specified.
Upon such determination, the Contracting Officer may terminate the Contractor's right to proceed with the work, or any separable part thereof, in accordance with Clause 252.217-7009, DEFAULT.
F-6 PROTECTION OF MATERIAL & WORK. At the beginning of the contract period, a jointly conducted condition survey shall be made of the entire vessel, including all machinery, piping, decks, bulkheads, overheads, hopper areas, electrical wiring and fixtures, and the condition of all equipment and areas recorded in a written report submitted to the Contracting Officer Representative. At the conclusion of the repair work and prior to dock trials, the joint condition survey will be conducted again and any damages or disturbed conditions noted on the vessel but not recorded on the initial survey will be repaired by the Contractor at his expense.
The interior house deck at the upper deck level must be swept clean daily since this deck shall be used to enter/exit the engine room and auxiliary machinery room. Notes: The contractor shall clean all grease and other contamination caused by his workers. The upper deck passageways shall be mopped and bulkheads wiped clean prior to vessel departure.
Openings for all hatches removed (if applicable) shall be covered during non-working periods and during inclement weather. Temporary covers shall be constructed of plywood.
This is the start of the file's text. The full file is on GovTribe.