This is a Combined Synopsis/Solicitation for a fish relocation project issued by the U.S. Army Corps of Engineers, Philadelphia District. The solicitation (W912BU25QA003) seeks a contractor to capture, collect, identify, and relocate native fish species from the Delaware City Dredged Material Placement Facility (DMPF) to an approximately 28-acre pond within the Chesapeake and Delaware Canal Conservation Area. The project requires the contractor to provide all necessary equipment, vessels, vehicles, and materials to complete the fish relocation effort, which is anticipated to take two to three days and must commence within two weeks of contract issuance.
Key requirements include obtaining a Delaware Scientific Collection Permit, developing a Health and Safety Plan, and preparing a summary report documenting the relocation methods, fish species list, and project details. The contractor must identify and separately handle native and non-native fish species, with non-native species to be killed and disposed of according to DNREC regulations. The solicitation is a Full and Open Request for Quote under NAICS Code 114111 (Finfish Fishing), with quotes due by 3:00 PM EDT on April 15, 2025. Vendors must be registered in SAM.gov and submit pricing information, CAGE code, and Unique Entity Identification number.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
COMBINED SYNPOSIS/SOLICITATION
W912BU25QA003
Delaware City Dredged Material Placement Facility Fish Relocation U.S. ARMY CORPS OF ENGINEERS, Philadelphia District
This is a re-solicitation of COMBINED SYNPOSIS/SOLICITATION W912BU25QA002
This is a combined synopsis/solicitation for commercial products or commercial services prepared in accordance with the format in subpart 12.6, as supplemented with additional information included in this notice. This announcement constitutes the only solicitation; quotes are being requested and a written solicitation will not be issued. A Statement of Work (SOW) is included with additional information for the line item. This office will not accept any telephonic, written, or faxed requests for a copy of the solicitation.
Request for quotation (RFQ):
CLIN DESCRIPTION
0001 The Contractor shall supply all equipment, vessels, vehicles, and materials needed to capture, collect, identify, and relocate the native fish species within the Delaware City Dredged Material Placement Facility in accordance with the specifications listed in the SOW.
Inspection and Acceptance: At Delivery.
Period of Performance: The fish relocation field effort is anticipated to require about two to three days to complete and will need to commence within two weeks after the issuance of the contract. One electronic copy of the draft summary report will be submitted to the Corps point of contact for review within 30 days after the fish relocation is complete.
Solicitation document and incorporated provisions and clauses are those in effect through Federal Acquisition Circular 2024-07, published 29 August 2024. Clauses and Provisions are available online at https://www.acquisition.gov.
This solicitation is Full and Open Request for Quote under NAICS Code 114111- Finfish Fishing.
Quotes shall be emailed to Kevin Hannings at Kevin.j.hannings@usace.army.mil, Brian Cox at Brian.W.Cox@usace.army.mil, and Cherita W illiams at Cherita.L.Williams@usace.army.mil no later than 3:00 PM EDT on Tuesday, 15 April 2025. Quotes shall include pricing information, vendor CAGE code, and Unique Entity Identification number (UEI). All vendors must be registered and active in SAM.gov.
KO Authority:
Only a warranted Contracting Officer (either a Procuring Contracting Officer (PCO) or an Administrative Contracting Officer (ACO)), acting within their appointed limits, has the authority to issue modifications or otherwise change the terms and conditions of this contract. If an individual other than the Contracting Officer attempts to make changes to the terms and conditions of this contract, you shall not proceed with the change and shall immediately notify the Contracting Officer. Proceeding with any work not authorized by the Contracting Officer will be at the Contractor's own risk.
FY-2025 Scope of Work USACE Philadelphia District
Delaware City Dredged Material Placement Facility Fish Relocation Project
(12/4/2024)
Introduction
The work under this purchase order is for the proposed capture and relocation of native fish species from an 85-acre waterbody (herein the “DMPF Pond”) within the Federally owned and maintained Delaware City Dredge Material Placement Facility (DMPF) to an approximately 28-acre pond (herein the “Relocation Pond”) within the Federally owned Chesapeake and Delaware (C&D) Canal Conservation Area. The DMPF Pond is located at 39.563608°, - 75.604391° and is depicted on Figure
1. The Relocation Pond is located at 39.545874°, -75.696403° and depicted on Figure 2. The Relocation Pond is located approximately five (5) miles west of the DMPF pond and both waterbodies have access via gravel roadways. The fish relocation effort is to be completed prior to the placement of dredged materials from the Delaware River, Philadelphia to Sea Federal navigation channel which is tentatively scheduled to begin in April of 2025.
Points of Contact
Colin Greenwood Michael Hart USACE, Philadelphia District Resources Branch
USACE, Philadelphia District Environmental Operations Division
1650 Arch Street 1650 Arch Street Philadelphia, PA 19103-2004 Philadelphia, PA 19103-2004 Colin.M.Greenwood@USACE.army.mi Michael.F.Hart@usace.army.mil
(215) 656-2338 (O) 401-632-6816 (C) (215) 656-6513 (O) (215) 982-0478
Overview The purchase order includes the planning and field efforts for the successful capture and relocation of native fish species from the DMPF Pond to the Relocation Pond in advance of the placement of dredged materials into the Delaware City DMPF. The Contractor shall supply all equipment, vessels, vehicles, and materials needed to capture, collect, identify, and relocate the native fish species present in the DMPF Pond. A Delaware Scientific Collection Permit/Fish Stocking Permit is required from the Delaware Department of Natural Resources and Environmental Control (DNREC) Division of Fish and Wildlife (DFW) for the fish relocation effort and will be obtained prior to the work by the USACE, with technical assistance from the Contractor. Vehicular access may be restricted at the collection and relocation locations. The contractor shall coordinate in advance with USACE for access needs and dates.
I. Fish Capture and Relocation
A. Pre-Project Planning & Health and Safety Documentation
During the early stage of the project, the USACE anticipates there will be two (2) meetings between USACE representatives and the Contractor to discuss and plan for the field effort. The fish capture is anticipated to be performed via a boat with mounted electrofishing equipment and/or with seine netting, however the USACE will work with the Contractor to develop the most effective method for the fish capture. Prior to the implementation of the fish relocation, the USACE requests a Health and Safety Plan or similar documentation from the Contractor which outlines the methods to be used during the field effort and how the work will be accomplished safely.
B. Field Effort
This portion of the purchase order includes completion of the fish capture from the DMPF Pond and transfer of fish to the Relocation Pond. While no fish surveys have been conducted for the DMPF Pond and the quantity of fish is unknown, DNREC DFW provided a list of fish species which were documented from fish kills in 2010 and 2016 and from a 2018 statewide survey of licensed anglers. The 2018 survey indicated 2,174 angling trips were made to the DMPF Pond and over 8,600 fish were caught by anglers. The following fish species are known to be present in the DMPF Pond (per DNREC DFW, 20 June 2024), however other unidentified native and non- native species may also be present.
Largemouth bass Striped bass Black crappie Bluegill Chain pickerel White perch Catfish (not identified to species level) Common carp Mosquito fish
In accordance with the requirements from DNREC DFW, non-native species including blue catfish, flathead catfish, common carp, mirror carp, and northern snakeheads that may inhabit the DMPF Pond must be killed and disposed of per DNREC regulations and cannot be transferred to the Relocation Pond. As such the Contractor will need to provide staff members trained in fish identification so the non- native species are not inadvertently transferred with the native species to the Relocation Pond.
The typical water depths in the DMPF Pond are typically between four to five feet but due to historic drought conditions in the summer and fall of 2024, the depths during a site visit on 22 October 2024 were approximately three to four feet. The DMPF is also dominated by submerged aquatic vegetation (SAV) which mainly includes hydrilla (Hydrilla verticillata) and Eurasian watermilfoil (Myriophyllum spicatum) and may also include coontail (Ceratophyllum demersum).
The depths in the Relocation Pond averaged approximately 12 feet during a site visit on 22 October 2024 and no SAV was observed within the pond.
The dominance of the SAVs and existing depths of the DMPF pond may present challenges for the type of vessel needed for electrofishing. It should be noted that the USACE acknowledges that not all fish will be captured by electrofishing or seine netting methods within the DMPF Pond and there will likely be a fish kill during the dewatering of the pond or placement of dredged materials within the pond. However, the USACE expects the Contractor to make every effort to capture and safely relocate as many of the native fish as possible. DNREC has requested that Mr. Eric Ludwig, Regional Wildlife Area Manager, be notified when the date(s) of the fish capture and relocation is finalized. DNREC DFW has also indicated that a fish kill of greater than five (5) fish needs to be immediately reported to DNREC fisheries staff. DNREC DFW staff also may be present during the fish capture and relocation.
C. Reporting Requirements
The Contractor will be required to provide a brief summary report following the fish capture and relocation effort as part of the purchase order. The summary report should include, but not be limited to, the following items:
Fish relocation methods and equipment utilized.
Native fish species list and relative abundance.
Non-native fish species list and relative abundance.
Method for the disposal of non-native fish species.
List of personnel who worked on the project and their qualifications.
Photographs documenting the field work effort.
D. Quality Assurance/Quality Control
To minimize the risk of any non-native, invasive species being captured and transferred to the Relocation Pond, a Quality Assurance/Quality Control (QA/QC) Program shall be implemented by the Contractor under the guidance of the USACE. The goal of the QA/QC program is to ensure the collection and identification of fish species is accurate to prevent the potential introduction of non-native species to the Relocation Pond. During the fish relocation field effort, USACE staff will be present to assist with the QA/QC program.
E. Period of Performance
The fish relocation field effort is anticipated to require about two to three days to complete and will need to commence within two weeks after the issuance of the contract. One electronic copy of the draft summary report will be submitted to the Corps point of contact for review within 30 days after the fish relocation. The draft summary report must be a polished product and an accurate representation of the content of the final summary report. The draft must be clean-typed, complete with figures, tables and sections (as applicable). Any graphics will appear in the same format and general location in the draft reports as they will in the final summary report.
The Corps will provide the contractor with comments on the draft report. The Contractor will then have an additional two weeks to revise and submit a final summary report. The contractor shall submit an electronic copy of the final summary report with any applicable appendices. When the Corps accepts the final summary report the contract will be complete.
F. Inspection
Work will be conducted under the general discretion of the Contracting Officer and shall be subject to inspection by his appointed inspectors to ensure strict compliance with the terms of the contract. The presence of the inspector shall not relieve the contractor of responsibility for the proper execution of the work in accordance with the specifications.
AMOUNT
Fish Capture and Relocation FFP The contractor shall provide all equipment, vessels, vehicles, and materials needed to capture, collect, identify, and relocate the native fish species within the Delaware City Dredged Material Facility in accordance with the specifications listed in the SOW.
FOB: Destination
PSC CD: F020
NET AMT
INSPECTION AND ACCEPTANCE TERMS
Supplies/services will be inspected/accepted at:
CLIN INSPECT AT INSPECT BY ACCEPT AT ACCEPT BY
0001 Destination Government Destination Government
DELIVERY INFORMATION
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE
0001 1 Job
CLIN DELIVERY DATE QUANTITY SHIP TO ADDRESS DODAAC /
CAGE
0001 30-MAY-2025 1 N/A
FOB: Destination
CLAUSES INCORPORATED BY REFERENCE
52.204-26 Covered Telecommunications Equipment or Services--
Representation.
OCT 2020
52.209-10 Prohibition on Contracting With Inverted Domestic Corporations
NOV 2015
52.212-1 Instructions to Offerors--Commercial Products and Commercial Services
SEP 2023
52.212-3 Alt I Offeror Representations and Certifications--Commercial Products and Commercial Services (MAY 2024) Alternate I
FEB 2024
52.226-8 Encouraging Contractor Policies To Ban Text Messaging While Driving
MAY 2024
52.232-39 Unenforceability of Unauthorized Obligations JUN 2013 52.233-3 Protest After Award AUG 1996 52.233-4 Applicable Law for Breach of Contract Claim OCT 2004 252.203-7000 Requirements Relating to Compensation of Former DoD SEP 2011
252.203-7002 Officials Requirement to Inform Employees of Whistleblower Rights DEC 2022
252.203-7005 Representation Relating to Compensation of Former DoD Officials
SEP 2022
252.204-7003 Control Of Government Personnel Work Product APR 1992 252.204-7015 Notice of Authorized Disclosure of Information for Litigation JAN 2023
Support
252.204-7016 Covered Defense Telecommunications Equipment or Services -- Representation
DEC 2019
252.204-7017 Prohibition on the Acquisition of Covered Defense Telecommunications Equipment or Services -- Representation
MAY 2021
252.204-7018 Prohibition on the Acquisition of Covered Defense Telecommunications Equipment or Services
JAN 2023
252.204-7019 Notice of NIST SP 800-171 DoD Assessment Requirements NOV 2023 252.204-7020 NIST SP 800-171 DoD Assessment Requirements NOV 2023 252.225-7048 Export-Controlled Items JUN 2013 252.232-7010 Levies on Contract Payments DEC 2006 252.244-7000 Subcontracts for Commercial Products or Commercial
Services
NOV 2023
Provisions incorporated by reference:
52.252-1 Solicitation provisions incorporated by reference. See https://www.acquisition.gov/ 52.212-1 Instructions to Offerors-Commercial Products and Commercial Services 52.204-19 Incorporation by Reference of Representations and Certifications.
52.204-24 Representation Regarding Certain Telecommunications and Video Surveillance Services or Equipment.
52.204-25 Prohibition on Contracting for Certain Telecommunications and Video Surveillance Services or Equipment.
52.204-26 Covered Telecommunications Equipment or Services-Representation.
52.204-29 Federal Acquisition Supply Chain Security Act Orders Representation and Disclosures.
52.226-8 Encouraging Contractor Policies to Ban Text Messaging While Driving.
52.232-39 Unenforceability of Unauthorized obligations 52.232-40 Providing Accelerated Payments to Small Business Subcontractors.
52.240-1 Prohibition on Unmanned Aircraft Systems Manufactured or Assembled by American.
Security Drone Act-Covered Foreign Entities 52.212-4 Contract Terms and Conditions-Commercials Products and Commercials Services
(a) Inspection/Acceptance. The Contractor shall only tender for acceptance those items that conform to the requirements of this contract. The Government reserves the right to inspect or test any supplies or services that have been tendered for acceptance. The Government may require repair or replacement of nonconforming supplies or reperformance of nonconforming services at no increase in contract price. If repair/replacement or reperformance will not correct the defects or is not possible, the Government may seek an equitable price reduction or adequate consideration for acceptance of nonconforming supplies or services. The Government must exercise its post acceptance rights-
(1) Within a reasonable time after the defect was discovered or should have been discovered; and
(2) Before any substantial change occurs in the condition of the item, unless the change is due to the defect in the item.
(b) Assignment. The Contractor or its assignee may assign its rights to receive payment due as a result of performance of this contract to a bank, trust company, or other financing institution, including any Federal lending agency in accordance with the Assignment of Claims Act (31 U.S.C. 3727). However, when a third party makes payment (e.g., use of the Governmentwide commercial purchase card), the Contractor may not assign its rights to receive payment under this contract.
(c) Changes. Changes in the terms and conditions of this contract may be made only by written agreement of the parties.
(d) Disputes. This contract is subject to 41 U.S.C. chapter 71, Contract Disputes. Failure of the parties to this contract to reach agreement on any request for equitable adjustment, claim, appeal or action arising under or relating to this contract shall be a dispute to be resolved in accordance with the clause at Federal Acquisition Regulation (FAR) 52.233-1, Disputes, which is incorporated herein by reference. The Contractor shall proceed diligently with performance of this contract, pending final resolution of any dispute arising under the contract.
(e) Definitions. The clause at FAR 52.202-1, Definitions, is incorporated herein by reference.
(f) Excusable delays. The Contractor shall be liable for default unless nonperformance is caused by an occurrence beyond the reasonable control of the Contractor and without its fault or negligence such as, acts of God or the public enemy, acts of the Government in either its sovereign or contractual capacity, fires, floods, epidemics, quarantine restrictions, strikes, unusually severe weather, and delays of common carriers. The Contractor shall notify the Contracting Officer in writing as soon as it is reasonably possible after the commencement of any excusable delay, setting forth the full particulars in connection therewith, shall remedy such occurrence with all reasonable dispatch, and shall promptly give written notice to the Contracting Officer of the cessation of such occurrence.
(g) Invoice.
(1) The Contractor shall submit an original invoice and three copies (or electronic invoice, if authorized) to the address designated in the contract to receive invoices. An invoice must include-
(i) Name and address of the Contractor;
(ii) Invoice date and number;
(iii) Contract number, line item number and, if applicable, the order number;
(iv) Description, quantity, unit of measure, unit price and extended price of the items delivered;
(v) Shipping number and date of shipment, including the bill of lading number and weight of shipment if shipped on Government bill of lading;
(vi) Terms of any discount for prompt payment offered;
(vii) Name and address of official to whom payment is to be sent;
(viii) Name, title, and phone number of person to notify in event of defective invoice; and
(ix) Taxpayer Identification Number (TIN). The Contractor shall include its TIN on the invoice only if required elsewhere in this contract.
(x) Electronic funds transfer (EFT) banking information.
(A) The Contractor shall include EFT banking information on the invoice only if required elsewhere in this contract.
(B) If EFT banking information is not required to be on the invoice, in order for the invoice to be a proper invoice, the Contractor shall have submitted correct EFT banking information in accordance with the applicable solicitation provision, contract clause (e.g., 52.232-33, Payment by Electronic Funds Transfer-System for Award Management, or 52.232-34, Payment by Electronic Funds Transfer-Other Than System for Award Management), or applicable agency procedures.
(C) EFT banking information is not required if the Government waived the requirement to pay by
EFT.
(2) Invoices will be handled in accordance with the Prompt Payment Act ( 31 U.S.C. 3903) and Office of Management and Budget (OMB) prompt payment regulations at 5 CFR Part 1315.
(h) Patent indemnity. The Contractor shall indemnify the Government and its officers, employees and agents against liability, including costs, for actual or alleged direct or contributory infringement of, or inducement to infringe, any United States or foreign patent, trademark or copyright, arising out of the performance of this contract, provided the Contractor is reasonably notified of such claims and proceedings.
(i) Payment.-
(1) Items accepted. Payment shall be made for items accepted by the Government that have been delivered to the delivery destinations set forth in this contract.
(2) Prompt payment. The Government will make payment in accordance with the Prompt Payment Act ( 31 U.S.C. 3903) and prompt payment regulations at 5 CFR Part 1315.
(3) Electronic Funds Transfer (EFT). If the Government makes payment by EFT, see 52.212-5(b) for the appropriate EFT clause.
(4) Discount. In connection with any discount offered for early payment, time shall be computed from the date of the invoice. For the purpose of computing the discount earned, payment shall be considered to have been made on the date which appears on the payment check or the specified payment date if an electronic funds transfer payment is made.
(5) Overpayments. If the Contractor becomes aware of a duplicate contract financing or invoice payment or that the Government has otherwise overpaid on a contract financing or invoice payment, the Contractor shall-
(i) Remit the overpayment amount to the payment office cited in the contract along with a description of the overpayment including the-
(A) Circumstances of the overpayment (e.g., duplicate payment, erroneous payment, liquidation errors, date(s) of overpayment);
(B) Affected contract number and delivery order number, if applicable;
(C) Affected line item or subline item, if applicable; and
(D) Contractor point of contact.
(ii) Provide a copy of the remittance and supporting documentation to the Contracting Officer.
(6) Interest.
(i) All amounts that become payable by the Contractor to the Government under this contract shall bear simple interest from the date due until paid unless paid within 30 days of becoming due. The interest rate shall be the interest rate established by the Secretary of the Treasury as provided in 41 U.S.C. 7109, which is applicable to the period in which the amount becomes due, as provided in (i)(6)(v) of this clause, and then at the rate applicable for each six-month period as fixed by the Secretary until the amount is paid.
(ii) The Government may issue a demand for payment to the Contractor upon finding a debt is due under the contract.
(iii) Final decisions. The Contracting Officer will issue a final decision as required by 33.211 if–
(A) The Contracting Officer and the Contractor are unable to reach agreement on the existence or amount of a debt within 30 days;
(B) The Contractor fails to liquidate a debt previously demanded by the Contracting Officer within the timeline specified in the demand for payment unless the amounts were not repaid because the Contractor has requested an installment payment agreement; or
(C) The Contractor requests a deferment of collection on a debt previously demanded by the Contracting Officer (see 32.607-2).
(iv) If a demand for payment was previously issued for the debt, the demand for payment included in the final decision shall identify the same due date as the original demand for payment.
(v) Amounts shall be due at the earliest of the following dates:
(A) The date fixed under this contract.
(B) The date of the first written demand for payment, including any demand for payment resulting from a default termination.
(vi) The interest charge shall be computed for the actual number of calendar days involved beginning on the due date and ending on-
(A) The date on which the designated office receives payment from the Contractor;
(B) The date of issuance of a Government check to the Contractor from which an amount otherwise payable has been withheld as a credit against the contract debt; or
(C) The date on which an amount withheld and applied to the contract debt would otherwise have become payable to the Contractor.
(vii) The interest charge made under this clause may be reduced under the procedures prescribed in FAR 32.608-2 in effect on the date of this contract.
(j) Risk of loss. Unless the contract specifically provides otherwise, risk of loss or damage to the supplies provided under this contract shall remain with the Contractor until, and shall pass to the Government upon:
(1) Delivery of the supplies to a carrier, if transportation is f.o.b. origin; or
(2) Delivery of the supplies to the Government at the destination specified in the contract, if transportation is f.o.b. destination.
(k) Taxes. The contract price includes all applicable Federal, State, and local taxes and duties.
(l) Termination for the Government’s convenience. The Government reserves the right to terminate this contract, or any part hereof, for its sole convenience. In the event of such termination, the Contractor shall immediately stop all work hereunder and shall immediately cause any and all of its suppliers and subcontractors to cease work. Subject to the terms of this contract, the Contractor shall be paid a percentage of the contract price reflecting the percentage of the work performed prior to the notice of termination, plus reasonable charges the Contractor can demonstrate to the satisfaction of the Government using its standard record keeping system, have resulted from the termination. The Contractor shall not be required to comply with the cost accounting standards or contract cost principles for this purpose. This paragraph does not give the Government any right to audit the Contractor’s records. The Contractor shall not be paid for any work performed or costs incurred which reasonably could have been avoided.
(m) Termination for cause. The Government may terminate this contract, or any part hereof, for cause in the event of any default by the Contractor, or if the Contractor fails to comply with any contract terms and conditions, or fails to provide the Government, upon request, with adequate assurances of future performance. In the event of termination for cause, the Government shall not be liable to the Contractor for any amount for supplies or services not accepted, and the Contractor shall be liable to the Government for any and all rights and remedies provided by law. If it is determined that the Government improperly terminated this contract for default, such termination shall be deemed a termination for convenience.
(n) Title. Unless specified elsewhere in this contract, title to items furnished under this contract shall pass to the Government upon acceptance, regardless of when or where the Government takes physical possession.
(o) Warranty. The Contractor warrants and implies that the items delivered hereunder are merchantable and fit for use for the particular purpose described in this contract.
(p) Limitation of liability. Except as otherwise provided by an express warranty, the Contractor will not be liable to the Government for consequential damages resulting from any defect or deficiencies in accepted items.
(q) Other compliances. The Contractor shall comply with all applicable Federal, State and local laws, executive orders, rules and regulations applicable to its performance under this contract.
(r) Compliance with laws unique to Government contracts. The Contractor agrees to comply with 31 U.S.C. 1352 relating to limitations on the use of appropriated funds to influence certain Federal contracts; 18 U.S.C. 431 relating to officials not to benefit; 40 U.S.C. chapter 37, Contract Work Hours and Safety Standards; 41 U.S.C. chapter 87, Kickbacks; 49 U.S.C. 40118, Fly American;
and 41 U.S.C. chapter 21 relating to procurement integrity.
(s) Order of precedence. Any inconsistencies in this solicitation or contract shall be resolved by giving precedence in the following order:
(1) The schedule of supplies/services.
(2) The Assignments, Disputes, Payments, Invoice, Other Compliances, Compliance with Laws Unique to Government Contracts, and Unauthorized Obligations paragraphs of this clause;
(3) The clause at 52.212-5.
(4) Addenda to this solicitation or contract, including any license agreements for computer software.
(5) Solicitation provisions if this is a solicitation.
(6) Other paragraphs of this clause.
(7) The Standard Form 1449.
(8) Other documents, exhibits, and attachments.
(9) The specification.
(t) [Reserved]
(u) Unauthorized Obligations.
(1) Except as stated in paragraph (u)(2) of this clause, when any supply or service acquired under this contract is subject to any End User License Agreement (EULA), Terms of Service (TOS), or similar legal instrument or agreement, that includes any clause requiring the Government to indemnify the Contractor or any person or entity for damages, costs, fees, or any other loss or liability that would create an Anti-Deficiency Act violation ( 31 U.S.C. 1341), the following shall govern:
(i) Any such clause is unenforceable against the Government.
(ii) Neither the Government nor any Government authorized end user shall be deemed to have agreed to such clause by virtue of it appearing in the EULA, TOS, or similar legal instrument or agreement. If the EULA, TOS, or similar legal instrument or agreement is invoked through an "I agree" click box or other comparable mechanism (e.g., "click-wrap" or "browse-wrap" agreements), execution does not bind the Government or any Government authorized end user to such clause.
(iii) Any such clause is deemed to be stricken from the EULA, TOS, or similar legal instrument or agreement.
(2) Paragraph (u)(1) of this clause does not apply to indemnification by the Government that is expressly authorized by statute and specifically authorized under applicable agency regulations and procedures.
(v) Incorporation by reference. The Contractor’s representations and certifications, including those completed electronically via the System for Award Management (SAM), are incorporated by reference into the contract.
(End of clause) Alternate I (Nov 2021). When a time-and-materials or labor-hour contract is contemplated, substitute the following paragraphs (a), (e), (i), (l), and (m) for those in the basic clause.
(a) Inspection/Acceptance. (1) The Government has the right to inspect and test all materials furnished and services performed under this contract, to the extent practicable at all places and times, including the period of performance, and in any event before acceptance. The Government may also inspect the plant or plants of the Contractor or any subcontractor engaged in contract performance. The Government will perform inspections and tests in a manner that will not unduly delay the work.
(2) If the Government performs inspection or tests on the premises of the Contractor or a subcontractor, the Contractor shall furnish and shall require subcontractors to furnish all reasonable facilities and assistance for the safe and convenient performance of these duties.
(3) Unless otherwise specified in the contract, the Government will accept or reject services and materials at the place of delivery as promptly as practicable after delivery, and they will be presumed accepted 60 days after the date of delivery, unless accepted earlier.
(4) At any time during contract performance, but not later than 6 months (or such other time as may be specified in the contract) after acceptance of the services or materials last delivered under this contract, the Government may require the Contractor to replace or correct services or materials that at time of delivery failed to meet contract requirements. Except as otherwise specified in paragraph (a)(6) of this clause, the cost of replacement or correction shall be determined under paragraph (i) of this clause, but the "hourly rate" for labor hours incurred in the replacement or correction shall be reduced to exclude that portion of the rate attributable to profit. Unless otherwise specified below, the portion of the "hourly rate" attributable to profit shall be 10 percent. The Contractor shall not tender for acceptance materials and services required to be replaced or corrected without disclosing the former requirement for replacement or correction, and, when required, shall disclose the corrective action taken. [Insert portion of labor rate attributable to profit.] (5)(i) If the Contractor fails to proceed with reasonable promptness to perform required replacement or correction, and if the replacement or correction can be performed within the ceiling price (or the ceiling price as increased by the Government), the Government may-
(A) By contract or otherwise, perform the replacement or correction, charge to the Contractor any increased cost, or deduct such increased cost from any amounts paid or due under this contract; or
(B) Terminate this contract for cause.
(ii) Failure to agree to the amount of increased cost to be charged to the Contractor shall be a dispute under the Disputes clause of the contract.
(6) Notwithstanding paragraphs (a)(4) and (5) above, the Government may at any time require the Contractor to remedy by correction or replacement, without cost to the Government, any failure by the Contractor to comply with the requirements of this contract, if the failure is due to-
(i) Fraud, lack of good faith, or willful misconduct on the part of the Contractor's managerial personnel; or
(ii) The conduct of one or more of the Contractor’s employees selected or retained by the Contractor after any of the Contractor’s managerial personnel has reasonable grounds to believe that the employee is habitually careless or unqualified.
(7) This clause applies in the same manner and to the same extent to corrected or replacement materials or services as to materials and services originally delivered under this contract.
(8) The Contractor has no obligation or liability under this contract to correct or replace materials and services that at time of delivery do not meet contract requirements, except as provided in this clause or as may be otherwise specified in the contract.
(9) Unless otherwise specified in the contract, the Contractor's obligation to correct or replace Government-furnished property shall be governed by the clause pertaining to Government property.
(e) Definitions. (1) The clause at FAR 52.202-1, Definitions, is incorporated herein by reference. As used in this clause-
(i) "Direct materials" means those materials that enter directly into the end product, or that are used or consumed directly in connection with the furnishing of the end product or service.
(ii) "Hourly rate" means the rate(s) prescribed in the contract for payment for labor that meets the labor category qualifications of a labor category specified in the contract that are-
(A) Performed by the contractor;
(B) Performed by the subcontractors; or
(C) Transferred between divisions, subsidiaries, or affiliates of the contractor under a common control.
(iii) "Materials" means-
(A) Direct materials, including supplies transferred between divisions, subsidiaries, or affiliates of the contractor under a common control;
(B) Subcontracts for supplies and incidental services for which there is not a labor category specified in the contract;
(C) Other direct costs (e.g., incidental services for which there is not a labor category specified in the contract, travel, computer usage charges, etc.);
(D) The following subcontracts for services which are specifically excluded from the hourly rate:
[Insert any subcontracts for services to be excluded from the hourly rates prescribed in the schedule.]; and
(E) Indirect costs specifically provided for in this clause.
(iv) "Subcontract" means any contract, as defined in FAR subpart 2.1, entered into with a subcontractor to furnish supplies or services for performance of the prime contract or a subcontract including transfers between divisions, subsidiaries, or affiliates of a contractor or subcontractor. It includes, but is not limited to, purchase orders, and changes and modifications to purchase orders.
(i) Payments. (1) Work performed. The Government will pay the Contractor as follows upon the submission of commercial invoices approved by the Contracting Officer:
(i) Hourly rate.
(A) The amounts shall be computed by multiplying the appropriate hourly rates prescribed in the contract by the number of direct labor hours performed. Fractional parts of an hour shall be payable on a prorated basis.
(B) The rates shall be paid for all labor performed on the contract that meets the labor qualifications specified in the contract. Labor hours incurred to perform tasks for which labor qualifications were specified in the contract will not be paid to the extent the work is performed by individuals that do not meet the qualifications specified in the contract, unless specifically authorized by the Contracting Officer.
(C) Invoices may be submitted once each month (or at more frequent intervals, if approved by the Contracting Officer) to the Contracting Officer or the authorized representative.
(D) When requested by the Contracting Officer or the authorized representative, the Contractor shall substantiate invoices (including any subcontractor hours reimbursed at the hourly rate in the schedule) by evidence of actual payment, individual daily job timecards, records that verify the employees meet the qualifications for the labor categories specified in the contract, or other substantiation specified in the contract.
(E) Unless the Schedule prescribes otherwise, the hourly rates in the Schedule shall not be varied by virtue of the Contractor having performed work on an overtime basis.
(1) If no overtime rates are provided in the Schedule and the Contracting Officer approves overtime work in advance, overtime rates shall be negotiated.
(2) Failure to agree upon these overtime rates shall be treated as a dispute under the Disputes clause of this contract.
(3) If the Schedule provides rates for overtime, the premium portion of those rates will be reimbursable only to the extent the overtime is approved by the Contracting Officer.
(ii) Materials.
(A) If the Contractor furnishes materials that meet the definition of a commercial product at FAR 2.101, the price to be paid for such materials shall not exceed the Contractor’s established catalog or market price, adjusted to reflect the-
(1) Quantities being acquired; and
(2) Any modifications necessary because of contract requirements.
(B) Except as provided for in paragraph (i)(1)(ii)(A) and (D)(2) of this clause, the Government will reimburse the Contractor the actual cost of materials (less any rebates, refunds, or discounts received by the contractor that are identifiable to the contract) provided the Contractor-
(1) Has made payments for materials in accordance with the terms and conditions of the agreement or invoice; or
(2) Makes these payments within 30 days of the submission of the Contractor’s payment request to the Government and such payment is in accordance with the terms and conditions of the agreement or invoice.
(C) To the extent able, the Contractor shall-
(1) Obtain materials at the most advantageous prices available with due regard to securing prompt delivery of satisfactory materials; and
(2) Give credit to the Government for cash and trade discounts, rebates, scrap, commissions, and other amounts that are identifiable to the contract.
(D) Other Costs. Unless listed below, other direct and indirect costs will not be reimbursed.
(1) Other Direct Costs. The Government will reimburse the Contractor on the basis of actual cost for the following, provided such costs comply with the requirements in paragraph (i)(1)(ii)(B) of this clause:[Insert each element of other direct costs (e.g., travel, computer usage charges, etc. Insert "None" if no reimbursement for other direct costs will be provided. If this is an indefinite delivery contract, the Contracting Officer may insert "Each order must list separately the elements of other direct charge(s) for that order or, if no reimbursement for other direct costs will be provided, insert ‘None’."]
(2) Indirect Costs (Material Handling, Subcontract Administration, etc.). The Government will reimburse the Contractor for indirect costs on a pro-rata basis over the period of contract performance at the following fixed price:[Insert a fixed amount for the indirect costs and payment schedule. Insert "$0" if no fixed price reimbursement for indirect costs will be provided. (If this is an indefinite delivery contract, the Contracting Officer may insert "Each order must list separately the fixed amount for the indirect costs and payment schedule or, if no reimbursement for indirect costs, insert ‘None’)."]
(2) Total cost. It is estimated that the total cost to the Government for the performance of this contract shall not exceed the ceiling price set forth in the Schedule and the Contractor agrees to use its best efforts to perform the work specified in the Schedule and all obligations under this contract within such ceiling price. If at any time the Contractor has reason to believe that the hourly rate payments and material costs that will accrue in performing this contract in the next succeeding 30 days, if added to all other payments and costs previously accrued, will exceed 85 percent of the ceiling price in the Schedule, the Contractor shall notify the Contracting Officer giving a revised estimate of the total price to the Government for performing this contract with supporting reasons and documentation. If at any time during the performance of this contract, the Contractor has reason to believe that the total price to the Government for performing this contract will be substantially greater or less than the then stated ceiling price, the Contractor shall so notify the Contracting Officer, giving a revised estimate of the total price for performing this contract, with supporting reasons and documentation. If at any time during performance of this contract, the Government has reason to believe that the work to be required in performing this contract will be substantially greater or less than the stated ceiling price, the Contracting Officer will so advise the Contractor, giving the then revised estimate of the total amount of effort to be required under the contract.
(3) Ceiling price. The Government will not be obligated to pay the Contractor any amount in excess of the ceiling price in the Schedule, and the Contractor shall not be obligated to continue performance if to do so would exceed the ceiling price set forth in the Schedule, unless and until the Contracting Officer notifies the Contractor in writing that the ceiling price has been increased and specifies in the notice a revised ceiling that shall constitute the ceiling price for performance under this contract. When and to the extent that the ceiling price set forth in the Schedule has been increased, any hours expended and material costs incurred by the Contractor in excess of the ceiling price before the increase shall be allowable to the same extent as if the hours expended and material costs had been incurred after the increase in the ceiling price.
(4) Access to records. At any time before final payment under this contract, the Contracting Officer (or authorized representative) will have access to the following (access shall be limited to the listing below unless otherwise agreed to by the Contractor and the Contracting Officer):
(i) Records that verify that the employees whose time has been included in any invoice meet the qualifications for the labor categories specified in the contract;
(ii) For labor hours (including any subcontractor hours reimbursed at the hourly rate in the schedule), when timecards are required as substantiation for payment-
(A) The original timecards (paper-based or electronic);
(B) The Contractor’s timekeeping procedures;
(C) Contractor records that show the distribution of labor between jobs or contracts; and
(D) Employees whose time has been included in any invoice for the purpose of verifying that these employees have worked the hours shown on the invoices.
(iii) For material and subcontract costs that are reimbursed on the basis of actual cost-
(A) Any invoices or subcontract agreements substantiating material costs; and
(B) Any documents supporting payment of those invoices.
(5) Overpayments/Underpayments. Each payment previously made shall be subject to reduction to the extent of amounts, on preceding invoices, that are found by the Contracting Officer not to have been properly payable and shall also be subject to reduction for overpayments or to increase for underpayments. The Contractor shall promptly pay any such reduction within 30 days unless the parties agree otherwise. The Government within 30 days will pay any such increases, unless the parties agree otherwise. The Contractor’s payment will be made by check. If the Contractor becomes aware of a duplicate invoice payment or that the Government has otherwise overpaid on an invoice payment, the Contractor shall-
(i) Remit the overpayment amount to the payment office cited in the contract along with a description of the overpayment including the-
(A) Circumstances of the overpayment (e.g., duplicate payment, erroneous payment, liquidation errors, date(s) of overpayment);
(B) Affected contract number and delivery order number, if applicable;
(C) Affected line item or subline item, if applicable; and
(D) Contractor point of contact.
(ii) Provide a copy of the remittance and supporting documentation to the Contracting Officer.
(6)(i) All amounts that become payable by the Contractor to the Government under this contract shall bear simple interest from the date due until paid unless paid within 30 days of becoming due. The interest rate shall be the interest rate established by the Secretary of the Treasury, as provided in 41 U.S.C. 7109, which is applicable to the period in which the amount becomes due, and then at the rate applicable for each six month period as established by the Secretary until the amount is paid.
(ii) The Government may issue a demand for payment to the Contractor upon finding a debt is due under the contract.
(iii) Final Decisions. The Contracting Officer will issue a final decision as required by 33.211 if-
(A) The Contracting Officer and the Contractor are unable to reach agreement on the existence or amount of a debt in a timely manner;
(B) The Contractor fails to liquidate a debt previously demanded by the Contracting Officer within the timeline specified in the demand for payment unless the amounts were not repaid because the Contractor has requested an installment payment agreement; or
(C) The Contractor requests a deferment of collection on a debt previously demanded by the Contracting Officer (see FAR 32.607-2).
(iv) If a demand for payment was previously issued for the debt, the demand for payment included in the final decision shall identify the same due date as the original demand for payment.
(v) Amounts shall be due at the earliest of the following dates:
(A) The date fixed under this contract.
(B) The date of the first written demand for payment, including any demand for payment resulting from a default termination.
(vi) The interest charge shall be computed for the actual number of calendar days involved beginning on the due date and ending on-
(A) The date on which the designated office receives payment from the Contractor;
(B) The date of issuance of a Government check to the Contractor from which an amount otherwise payable has been withheld as a credit against the contract debt; or
(C) The date on which an amount withheld and applied to the contract debt would otherwise have become payable to the Contractor.
(vii) The interest charge made under this clause may be reduced under the procedures prescribed in FAR 32.608-2 in effect on the date of this contract.
(viii) Upon receipt and approval of the invoice designated by the Contractor as the "completion invoice" and supporting documentation, and upon compliance by the Contractor with all terms of this contract, any outstanding balances will be paid within 30 days unless the parties agree otherwise. The completion invoice, and supporting documentation, shall be submitted by the Contractor as promptly as practicable following completion of the work under this contract, but in no event later than 1 year (or such longer period as the Contracting Officer may approve in writing) from the date of completion.
(7) Release of claims. The Contractor, and each assignee under an assignment entered into under this contract and in effect at the time of final payment under this contract, shall execute and deliver, at the time of and as a condition precedent to final payment under this contract, a release discharging the Government, its officers, agents, and employees of and from all liabilities, obligations, and claims arising out of or under this contract, subject only to the following exceptions.
(i) Specified claims in stated amounts, or in estimated amounts if the amounts are not susceptible to exact statement by the Contractor.
(ii) Claims, together with reasonable incidental expenses, based upon the liabilities of the Contractor to third parties arising out of performing this contract, that are not known to the Contractor on the date of the execution of the release, and of which the Contractor gives notice in writing to the Contracting Officer not more than 6 years after the date of the release or the date of any notice to the Contractor that the Government is prepared to make final payment, whichever is earlier.
(iii) Claims for reimbursement of costs (other than expenses of the Contractor by reason of its indemnification of the Government against patent liability), including reasonable incidental expenses, incurred by the Contractor under the terms of this contract relating to patents.
(8) Prompt payment. The Government will make payment in accordance with the Prompt Payment Act (31 U.S.C. 3903) and prompt payment regulations at 5 CFR part 1315.
(9) Electronic Funds Transfer (EFT). If the Government makes payment by EFT, see 52.212-5(b) for the appropriate EFT clause.
(10) Discount. In connection with any discount offered for early payment, time shall be computed from the date of the invoice.