College_Woods_Improvements_-_Bid_Specifications.pdf
PDF 631 KB Posted
- Attached to
- East Rock College Woods Improvements
- Solicitation number
- 2026-ITB-345
- Issued by
- New Haven County, Connecticut
About this file
This is a bid specification document issued by the City of New Haven for improvements to the College Woods area of East Rock Park in Connecticut. The project encompasses enhancements to pedestrian pathways, landscape plantings, and site furnishings within the park. The specifications detail requirements for multiple construction components including tree protection and safety measures, processed aggregate base and bituminous pavement for walking pathways, stainless steel handrails, bicycle racks, unclassified excavation, crushed stone pathways with geotextile fabric, post-and-rope fencing, trash receptacles, landscape planting, loaming, seeding, sodding, and topsoil placement. The document does not specify item quantities, response dates, due dates, site visit requirements, or bidder conference information. No award dates or contract term information is provided in the specifications.
The document establishes detailed material and construction standards for all work components, referencing compliance with Connecticut Department of Transportation standards, ASTM specifications, ANSI standards for arboricultural operations, and ADA accessibility requirements. Pricing is structured as unit prices for various pay items, including measurements by cubic yard for excavation and aggregate base, tons for bituminous pavement, linear feet for fencing and handrails, and per-unit pricing for site furnishings such as bicycle racks and trash receptacles. The specifications require contractors to adhere to tree protection protocols overseen by the City's Tree Warden, with damage compensation calculated at $250 per inch of diameter at breast height for removed trees. The document emphasizes environmental protection, pedestrian safety, and quality assurance throughout all construction phases, but contains no information regarding funding sources, budget allocations, set-asides, or incumbent contractor details.
View the file
Other files
Show all 16
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
City of New Haven College Woods Improvements Contract Specifications
Contents College Woods Improvements Contract Specifications
SECTION 01 56 40 – TREE PROTECTION AND TREE SAFETY STANDARDS
MATERIALS OF CONSTRUCTION
Section 2.01 - DEFINITIONS
Section 2.02 STONE AND GRAVEL
Section 2.07.01 CONCRETE CLASS “B” AE CONCRETE MIXTURE FOR FLATWORK
Section 20.02 PROCESSED AGGREGATE BASE AND PAVEMENT
20.02.1 DESCRIPTION
20.02.2 MATERIALS
20.02.3 CONSTRUCTION METHODS
20.02.4 METHOD OF MEASUREMENT
20.02.5 BASIS OF PAYMENT
SECTION 05 52 00 – STAINLESS STEEL HANDRAILS
1.0 GENERAL
1.1 SUMMARY
1.2 REFERENCES
1.3 SUBMITTALS
1.4 QUALITY ASSURANCE
1.5 DELIVERY, STORAGE, AND HANDLING
2.0 PRODUCTS
2.1 MATERIALS
2.2 FABRICATION
2.3 FINISHES
3.0 EXECUTION
3.1 EXAMINATION
3.2 INSTALLATION
3.3 CLEANING AND PROTECTION
3.4 FINAL ACCEPTANCE
SECTION 12 93 13 — BICYCLE RACKS
1.0 DESCRIPTION
2.0 REFERENCES
3.0 PRODUCTS
3.1 Manufacturer
3.2 Designation
3.3 Construction
3.4 Finish
3.5 Installation Method
4.0 SUBMITTALS
5.0 DELIVERY, STORAGE, AND HANDLING
6.0 INSTALLATION
6.1 General
6.2 Location and Orientation
6.3 Surface-Mount Installation
6.4 Protection
7.0 FIELD QUALITY CONTROL
8.0 CLEANING AND CLOSEOUT
9.0 MEASUREMENT AND PAYMENT
Section 20.08 UNCLASSIFIED EXCAVATION
20.01.01 DESCRIPTION
20.08.2 MATERIALS
20.08.3 CONSTRUCTION METHODS
20.08.4 METHOD OF MEASUREMENT
20.08.5 BASIS OF PAYMENT
32 11 23 — WELL-GRADED #8 ANGULAR CRUSHED STONE (6" DEPTH) PATH WITH NON-WOVEN
GEOTEXTILE FABRIC
SECTION 32 31 19 – POST-AND-ROPE FENCE (PRESSURE-TREATED POSTS WITH MANILA JUTE ROPE)
PART 1 – GENERAL
1.1 SUMMARY
1.2 REFERENCES
1.3 SUBMITTALS
1.4 QUALITY ASSURANCE
PART 2 – PRODUCTS
2.1 WOOD POSTS
2.2 ROPE
2.3 HARDWARE
PART 3 – EXECUTION
3.1 EXAMINATION
3.2 INSTALLATION OF POSTS
3.3 ROPE INSTALLATION
3.4 FINISHING
3.5 PROTECTION
3.6 MEASUREMENT AND PAYMENT
SECTION 32 33 23 — TRASH RECEPTACLES
1.0 DESCRIPTION
2.0 REFERENCES
3.0 PRODUCTS
3.1 Manufacturer
3.2 Designation
3.3 Construction
3.4 Finish
3.5 Capacity
3.6 Installation Method
4.0 SUBMITTALS
5.0 DELIVERY, STORAGE, AND HANDLING
6.0 INSTALLATION
6.1 General
6.2 Location and Orientation
6.3 Mounting
6.4 Protection
7.0 FIELD QUALITY CONTROL
8.0 CLEANING AND CLOSEOUT
9.0 MEASUREMENT AND PAYMENT
SECTION 32 93 00 – PLANTING
PART 1 – GENERAL
1.1 SUMMARY
1.2 RELATED DOCUMENTS
1.3 REFERENCES
1.4 SUBMITTALS
1.5 QUALITY ASSURANCE
1.6 DELIVERY, STORAGE, AND HANDLING
1.7 PROJECT CONDITIONS
1.8 WARRANTY
PART 2 – PRODUCTS
2.1 PLANT MATERIALS
2.2 TOPSOIL & PLANTING MIX
2.3 FERTILIZER
2.4 MULCH
2.5 STAKING AND GUYING MATERIALS
PART 3 – EXECUTION
3.1 EXAMINATION
3.2 PLANTING BED PREPARATION
3.3 TREE PLANTING
3.4 SHRUB PLANTING
3.5 PERENNIALS, GRASSES, AND GROUNDCOVERS
3.6 MULCHING
3.7 WATERING
3.8 CLEANING AND PROTECTION
3.9 MAINTENANCE
3.10 MEASUREMENT AND PAYMENT
Section 50.01 LOAMING, SEEDING AND SODDING
50.01.1 DESCRIPTION
50.01.2 MATERIALS
50.01.3 CONSTRUCTION METHODS
50.01.4 METHOD OF MEASUREMENT
50.01.5 BASIS OF PAYMENT
Section 50.02 FURNISH AND PLACE TOPSOIL
SECTION 01 56 40 – TREE PROTECTION AND TREE SAFETY STANDARDS
PART 1 – GENERAL
Trees are critical green infrastructure with qualitative and quantitative benefits. The preservation and protection of existing trees in and around construction sites is imperative during the planning, execution, and post-construction phases of development. Contractor is required to work with and notify Tree Warden of any planned or unforeseen tree impacts.
SAFETY STANDARDS
A. All equipment to be used and all work to be performed must be in full compliance with the most current revision of American National Standards Institute Z133 Safety Requirements for Arboricultural Operations. These standards are made part of this contract by this reference.
B. Personal Protective Equipment (PPE) is required by all in all circumstances.
C. The Contractor shall be solely responsible for pedestrian and vehicular safety and control within the work site and shall provide the necessary warning devices, barricades, and ground personnel needed to give safety, protection, and warning to persons and vehicular traffic within the area.
D. Blocking of public streets shall not be permitted unless prior arrangements have been made with the City of New Haven and is coordinated with appropriate departments. Traffic control and any additional costs incurred on the contractor’s behalf is the responsibility of the Contractor unless arrangements are made with the Tree System Coordinator/Tree Warden.
LIABILITY FOR DAMAGE TO PROPERTY AND/OR PLANT MATERIAL
Any tree damage caused by the Contractor should be repaired immediately at no additional expense and to the satisfaction of the City of New Haven. Trees damaged beyond repair, as judged by a qualified arborist acceptable to the City of New Haven and the Contractor, whose expenses shall be jointly covered by both parties, are to be removed at no expense to the City, and replaced according to the Tree Fund Policy. The Tree Fund exists to incentivize the preservation of existing street trees and to provide compensation for lost ecosystem benefits when the impacts on a street tree are significant enough to warrant removal or when a tree is illegally removed or damaged. The money paid into the Tree Fund is used to support urban forest management city-wide. Payments into the tree fund are calculated at a rate of $250/inch of DBH, diameter at breast height (4.5’), for each tree removed. The payment can be adjusted on a 1:1 basis for caliper inches of new trees replanted.
Replacement tree plantings must be warrantied for 3 years from the date of planting and the contractor is responsible for watering the new trees at a rate of 25 gallons/week from April through October. Contractor will be responsible for all costs associated with removing the trees and replanting. Including, but not limited to, the removal of trees, stumps, hauling of all debris, traffic control, and replanting costs. Damage to other plant material, such as shrubs and perennials, is calculated at the reproduction replacement value and subject to the same establishment protocol.
Funds invoiced for damage to trees and plants will be deducted from moneys owed the contractor.
PART 2 – MATERIALS
Tree protection fence. U channel post and 4' h standard plastic safety fence. Coordinate location and extents in field with City Tree Warden and Landscape Architect, typ.
PROTECTION OF TREES DURING CONSTRUCTION
Contractor must adhere to all tree protection and preservation specifications set forth in the ANSI A300 Standards and are required to attend an on-site meeting with the Tree Warden prior to starting any work to review expectations and tree protection standards. Contractor to supply the Tree Warden with tree preservation plans, created and administered by a CT Licensed Arborist, before any work begins. actively engaged in the field of arboriculture. Arborists must be registered with the State of Connecticut as an arborist business and operate under a valid CT arborist license. The tree preservation plan shall include, but is not limited to:
• Inventory of existing trees on the site, including species, diameter, and condition
• Identify construction site entry and exit
• Parking for construction and personal vehicles
• Material tagging and storage
• Identify Tree Protection Zones (TPZ) and appropriate fencing and signage
• Monitoring plan
During the project, contractor must:
• Minimize soil compaction and utilize mulch or other materials to avoid compaction
• Do not stockpile materials or equipment within the Tree Protection Zone (TPZ)
• Absolutely no mechanical damage to trees within and around the work zone.
This includes damage to the root zone, trunk, bark, and canopy.
• No pruning of branches or cutting tree roots without written permission from the Tree Warden.
• Notify the Tree Warden of any changes
The Tree Warden will regularly monitor the work site. If at any point, deviations from the Tree Protection/Preservation Plan are observed, the Tree Warden will document and immediately halt work in the affected zone. Contractor will be required to remedy work practices before starting work again.
WORK COMPLETION
All work shall be performed in a manner that does not damage curbing, sidewalks, public and private property, or other infrastructure. The contractor shall be responsible for any damage that occurs. The Contractor shall restore any damaged turf areas and grades due to vehicular or mechanical operations. At the direction of the City, Contractor will reseed the area with approved grass seed.
MATERIALS OF CONSTRUCTION
Section 2.01 - DEFINITIONS
2.01.01 ABBREVIATIONS
Abbreviations used in the contract are in lieu of and are to be construed the same as the respective expression represented below.
(A) A.A.S.H.T.O. American Association of State Highway and Transportation Officials
(B) A.C.I. American Concrete Institute
(C) A.I.S.C. American Institute of Steel Construction
(D) A.S.A. American Standards Association
(E) A.S.T.M. American Society of Testing Materials
(F) A.W.P.A. American Wood Preservers Association
(G) A.W.S. American Welding Society
(H) A.W.W.A. American Water Works Association
(I) C.H.D. State of Connecticut State Highway Department Standard Specifications for Roads, Bridges, and Incidental Construction.
(J) D.F.P.A. Douglas Fir Plywood Association
(K) S.P.A. Southern Pine Association
(L) W.C.L.A. West Coast Lumberman's Association
(M) W.R.I. Wire Reinforcement Institute
(N) O.S.H.A. Occupational Safety and Health Administration
(O) DOT Form 818 Standard Specifications for Roads, Bridges and Incidental Construction
2.01.02 STANDARD SPECIFICATIONS
Whenever any reference is made to a standard of any agency, authority or association, it shall mean the latest standard or tentative standard of the agency, authority, or association as to materials, testing procedures, inspection or other specification pertaining to any or all phases of the work, whichever is applicable.
Section 2.02
STONE AND GRAVEL
Stone, gravel, gravel fill, subbase, gravel base, pervious structure backfill, free draining material, and crusher-run stone shall be in total and complete conformance with the requirements of the "Connecticut Department of Transportation Standard Specifications for Roads, Bridges, and Incidental Construction, Form 818 or the most current edition, Division III, Materials Section M.01 Aggregates and Section M.02 Granular Fill, Subbase, Granular Base And Surfaces, Stone Base, Pervious Structure Backfill, Free-Draining Material, Crusher-Run Stone."
Section 2.07.01
CONCRETE CLASS “B” AE CONCRETE MIXTURE FOR FLATWORK
Portland cement concrete shall be in conformance with the requirements of the Connecticut Department of Transportation Standard Form 818 Materials Section M.03, and adhere to the mix design proportions and data below.
MATERIAL DATA
Material Source/Type Specific Gravity
Unit Weight % Absorption
Water Domestic supply 1.00
Cement LaFarge 3.15
Slag LaFarge Newcem 2.93
Flyash Headwaters 2.42
3/4" Stone ASTM C-33 2.90
1/2" Stone ASTM C-33 2.90
3/8" Stone ASTM C-33 2.90
Concrete Sand ASTM C-33 2.67
Water Reducer ASTM C494 Type A&F
Air Entraining Agent
ASTM C260
Retarder ASTM C494 Type B&D
MIX DESIGN PROPORTIONS
Material Proportions (SSD)
Volume Weight
Water 4.57 Cu. Ft. 285 lb/cy
Cement 2.33 Cu. Ft. 458 lb/cy
Newcem 0.84 Cu. Ft. 153 lb/cy
Flyash 0 Cu. Ft. lb/cy
% Air Entrained 1.35 Cu. Ft. 5.00%
Total Aggregate 17.87 Cu. Ft. 3120 lb/cy
3/4" Stone (lbs,ssd) 4.97 Cu. Ft. 900 lb/cy
1/2" Stone (lbs,ssd) 2.49 Cu. Ft. 450 lb/cy
3/8" Stone (lbs,ssd) 2.49 Cu. Ft. 450 lb/cy
Concrete Sand (lbs,ssd) 7.92 Cu. Ft. 1320 lb/cy
Total 26.96 Cu. Ft. lb/cy
Water Reducer 3.0 oz/cwt 36.0 oz/cy
A.E.A. 0.5 oz/cwt 5.0 oz/cy
Retarder 0.0 oz/cy
Aggregate Percentages
3/4" Stone 27.81%
1/2" Stone 13.93%
3/8" Stone 13.93%
Sand 44.32%
Total 100.00%
Section 20.02
PROCESSED AGGREGATE BASE AND PAVEMENT
20.02.1 DESCRIPTION
Paving for a pedestrian walkway along the edge of the park. These are to be completed to the Engineer’s standards provided in the plan set. All work to be in compliance with state, federal, and local regulations.
20.02.2 MATERIALS
Processed Aggregate Base and Pavement: The materials for this work shall meet the following requirements:
1. Gradation: Coarse and fine aggregates shall be combined and mixed by approved methods so that the resulting material shall meet the following gradation requirements:
TABLE M.05.01-1
SQUARE MESH SIEVES PERCENT PASSING BY WEIGHT
PASS 2 ½ INCHES 100
PASS 2 INCHES 95-100
PASS ¾ INCHES 50-75
PASS ¼ INCHES 25-45
PASS NO. 40 5-20
PASS NO. 100 2-12
2. Coarse Aggregate: Coarse aggregate shall be either gravel, broken stone or reclaimed miscellaneous aggregate containing no more than 2% by weight of asphalt cement, at the option of the Contractor. When tested by means of the Los Angeles Machine, using AASHTO Method T 96, the coarse aggregate shall not have a loss of more than 50%.
a. If gravel is used for the coarse aggregate, it shall consist of sound, tough, durable particles of crushed or uncrushed gravel or a mixture thereof, free from soft, thin, elongated or laminated pieces, lumps of clay, loam and vegetable or other deleterious substances.
b. If broken stone is used for the coarse aggregate, it shall consist of sound, tough, durable fragments of rock of uniform quality throughout. It shall be free from soft disintegrated pieces, mud, dirt, organic or other injurious material.
c. If the reclaimed miscellaneous aggregate is used for the coarse aggregate, it shall consist of sound, tough, durable fragments of uniform quality throughout. It shall be free from soft disintegrated pieces, mud, dirt, glass, organic or other injurious material.
d. Soundness for Gravel, Broken Stone and Reclaimed Miscellaneous Aggregate: When tested by magnesium sulfate solution for soundness using AASHTO Method T 104, the coarse aggregate shall show a loss of not more than 15% at the end of 5 cycles.
3. Fine Aggregate: The fine aggregate shall be natural sand, stone sand, screenings or any combination thereof. The fine aggregate shall be limited to material 95% of which passes a No. 4 sieve having square openings and not more than 8% of which passes a No. 200 sieve. The material shall be free from clay, loam and deleterious materials.
a. Plasticity: When natural sand is used, the fine aggregate shall conform to the requirements of M.02.06-2.
b. Plasticity: When screenings or any combination of screenings and natural sand or any combination of stone sand and natural sand are used, the following requirements shall apply:
1. When the fraction of the dry sample passing the No. 100 mesh sieve is 6% or less by weight, no plastic limit test will be made.
2. When the fraction of the dry sample passing the No. 100 mesh sieve is greater than 6% and not greater than 10% by mass, that fraction shall not have sufficient plasticity to permit the performing of the plastic limit test, using AASHTO Method T 90.
3. When the fraction of the dry sample passing the No. 100 mesh sieve is greater than 10% by weight, the sample shall be washed; and additional material passing the No. 100 mesh sieve shall be determined by AASHTO Method T 146, except that the No. 100 mesh sieve shall be substituted for the No. 40 mesh sieve where the latter is specified in AASHTO Method T 146. The combined materials that have passed the No. 100 mesh sieve shall not have sufficient plasticity to permit the performing of the plastic limit test using AASHTO Method T 90.
20.02.3 CONSTRUCTION METHODS
Paving Walking Pathway:
8’’ aggregate subbase in accordance with CTDOT Form 818 M.05. Installation of bituminous concrete pavement HMA S0.5 minimum of 2’’ thickness in accordance with CTDOT Form 818 M.04.
20.02.4 METHOD OF MEASUREMENT
Measurement shall be made by the Engineer for the subbase and shall be the area in cubic yards. The area to be measured shall be the actual length times the width as shown on the drawings time the required 8” thickness, within the pay limits as shown on the plans.
Measurement shall be made by the Engineer for the walking loop path pavement and shall be in tons.
The area to be measured shall be the actual length times the width as shown on the drawings times the required 2” thickness, converted to tons, within the pay limits as shown on the plans.
20.02.5 BASIS OF PAYMENT
Payment for the installation of subbase for new walking loop path will be made at the contract unit price per Cubic Yard for "Installation of processed aggregate subbase" which price shall include all equipment, tools and labor necessary for installation of all subbase.
Payment for the installation of pavement for new walking loop path will be made at the contract unit price per ton for "Installation of bituminous concrete pavement HMA S0.5" which price shall include all equipment, tools, and labor necessary for installation of all pavements.
Pay Item Pay Unit
Installation of processed aggregate subbase Cubic Yard Installation of bituminous concrete pavement HMA S0.5 Ton
SECTION 05 52 00 – STAINLESS STEEL HANDRAILS
1.0 GENERAL
1.1 SUMMARY
This section covers the materials, fabrication, and installation requirements for stainless steel handrails, including posts, brackets, fittings, fasteners, and anchorage systems.
1.2 REFERENCES
Handrails shall comply with the most current editions of the following standards:
• ASTM A240 – Standard Specification for Chromium and Chromium-Nickel Stainless Steel Plate, Sheet, and Strip
• ASTM A276 – Stainless Steel Bars and Shapes
• ASTM A312 – Seamless and Welded Austenitic Stainless Steel Pipe
• ASTM A554 – Welded Stainless Steel Mechanical Tubing
• AWS D1.6 – Structural Welding Code – Stainless Steel
• ADA Standards for Accessible Design
• IBC – International Building Code (handrail height, clearance, and load requirements)
1.3 SUBMITTALS
Provide the following:
• Product Data: Manufacturer’s data for tubing, fittings, fasteners, and accessories
• Shop Drawings: Fully dimensioned drawings showing profiles, connections, anchorage, and interface with adjacent construction
• Samples: 6-inch sample of tubing showing finish
• Welding Certificates: Qualifications of welders per AWS D1.6
• Maintenance Data: Cleaning and care instructions
1.4 QUALITY ASSURANCE
• Fabricator shall have a minimum of 5 years experience producing architectural stainless steel railings.
• All welding shall be performed by certified welders.
• Mock-up may be required to verify appearance and workmanship.
1.5 DELIVERY, STORAGE, AND HANDLING
• Deliver materials wrapped to prevent scratching.
• Store off the ground in a dry, covered location.
• Protect finished surfaces from damage during installation.
2.0 PRODUCTS
2.1 MATERIALS
• Tubing: ASTM A554, Grade 304 for interior applications; 316 for exterior or corrosive environments
• Handrail Diameter: 1.5 in. or 1.75 in. round (unless otherwise noted)
• Wall Thickness: Minimum 0.065 in. (16 gauge)
• Posts: 1.5–2.0 in. diameter round or square tubing
• Fittings: Stainless steel, welded or mechanically secured
• Fasteners: Stainless steel, Type 304 or 316 to match rail material
• Anchors: Stainless steel or manufacturer-approved structural anchors suitable for substrate
2.2 FABRICATION
• Fabricate handrails to dimensions shown on drawings.
• Bends shall be smooth, uniform, and free of deformation.
• Welds shall be TIG welded, ground smooth, and blended to match adjacent surfaces.
• Provide continuous rail segments between posts unless otherwise indicated.
• Provide expansion joints where required by length or temperature conditions.
2.3 FINISHES
• Standard finish: No. 4 brushed satin
• Optional finish (if specified):
o No. 8 mirror polish o Bead-blasted matte
• All exposed surfaces shall be free of scratches, pits, and fabrication marks.
3.0 EXECUTION
3.1 EXAMINATION
• Verify field conditions and dimensions prior to fabrication.
• Confirm substrate strength is adequate for required loads (per IBC: 200 lb point load and 50 lb/ft uniform load).
3.2 INSTALLATION
• Install handrails plumb, level, and aligned.
• Provide continuous clearance of 1.5 inches minimum between handrail and adjacent wall.
• Secure posts and brackets using approved anchors appropriate for substrate.
• Isolate dissimilar metals to prevent galvanic corrosion.
• Field welds shall be ground smooth and finished to match shop finish.
3.3 CLEANING AND PROTECTION
• Clean stainless steel with non-chloride cleaners.
• Remove all labels, adhesives, and residue.
• Protect installed work from damage until project completion.
3.4 FINAL ACCEPTANCE
• Handrails shall be free of dents, scratches, weld discoloration, and visible defects.
• All joints shall be tight and uniform.
• Finish shall be consistent across entire installation.
Purchase, delivery, installation of handrail Lump Sum
SECTION 12 93 13 — BICYCLE RACKS
1.0 DESCRIPTION
Provide and install bicycle racks at the locations shown on the Drawings and as specified herein. Work includes furnishing all materials, hardware, anchors, labor, equipment, and incidentals necessary for a complete and functional installation.
2.0 REFERENCES
The following standards form part of this specification:
• ASTM A53/A53M — Standard Specification for Pipe, Steel, Black and Hot-Dipped, Zinc-Coated, Welded and Seamless
• ASTM A123/A123M — Zinc (Hot-Dip Galvanized) Coatings on Iron and Steel Products
• ASTM A153/A153M — Zinc Coating (Hot-Dip) on Iron and Steel Hardware
• Manufacturer’s published installation instructions
3.0 PRODUCTS
3.1 Manufacturer
• Approved Model: 1-Loop Wave Style Bike Rack – 3 Bike Capacity, Galvanized
• Manufacturer: ULine
• Or approved equal
3.2 Designation
• Bicycle Rack Type: BR-1
• Use this designation to identify each bicycle rack location.
3.3 Construction
• Frame Material: Steel
• Tubing Outside Diameter: Not less than 2.375 inches (Schedule 40 pipe recommended for heavy-duty applications)
• Style: Wave-style, single-loop configuration
• Overall Height: 36 inches
• Overall Width: As required for 1-loop wave rack
• Overall Depth: As required for 1-loop wave rack
• Capacity: Accommodates no fewer than 3 bicycles
3.4 Finish
• Finish Type: Hot-dip galvanized steel o Coating shall comply with ASTM A123/A123M o Hardware shall comply with ASTM A153/A153M
• Color: Natural galvanized finish
3.5 Installation Method
• Surface Mount o Rack shall be factory-prepared for surface mounting. Install per manufacturer’s specifications.
4.0 SUBMITTALS
Provide the following:
1. Product Data: Manufacturer’s catalog sheets, dimensions, materials, finishes, and installation instructions.
2. Shop Drawings: Indicate rack layout, mounting details, spacing, and clearances.
3. Samples: One sample of galvanized finish (if required).
4. Certificates: Manufacturer’s certification that products meet the requirements of this specification.
5.0 DELIVERY, STORAGE, AND HANDLING
• Deliver products in manufacturer’s original packaging with labels intact.
• Store racks off the ground, protected from moisture, dirt, and damage.
• Do not install damaged components; replace at no cost to the Owner.
6.0 INSTALLATION
6.1 General
Install bicycle racks in accordance with manufacturer’s instructions and as shown on the Drawings.
6.2 Location and Orientation
• Install racks at locations indicated.
• Maintain required clearances from walls, walkways, and other site furnishings.
• Align racks uniformly and plumb.
6.3 Surface-Mount Installation
• Drill holes to manufacturer-recommended depth and diameter.
• Set rack on concrete meeting Section 03 30 00 requirements.
• Ensure racks are plumb, level, and aligned before concrete sets.
• Secure per manufacturer’s instructions.
6.4 Protection
• Protect installed racks from damage during construction.
• Touch up minor finish damage with manufacturer-approved galvanizing repair compound.
• Replace components with significant damage.
7.0 FIELD QUALITY CONTROL
• Engineer may inspect installation for alignment, finish quality, and compliance with specifications.
• Non-conforming work shall be corrected or replaced at Contractor’s expense.
8.0 CLEANING AND CLOSEOUT
• Clean racks of construction debris and surface contaminants.
• Remove protective coverings.
• Leave installation in clean, ready-for-use condition.
9.0 MEASUREMENT AND PAYMENT
• Bicycle racks shall be measured per each installed and accepted.
• Payment includes furnishing, installation, concrete footings, hardware, and all incidentals required for a complete installation.
Section 20.08
UNCLASSIFIED EXCAVATION
20.01.01 DESCRIPTION
Unclassified excavation shall consist of the removal and satisfactory disposal, in the manner herein required, of all material other than water taken from within the limits of the work contracted for, the removal of which is necessary for the construction of the embankment, subgrade, shoulders, slopes, entrances, gutters and other miscellaneous construction, to the dimensions and limits shown on the plans or as ordered by the Engineer. It shall also include the disposal of surplus or unsuitable material.
20.08.2 MATERIALS
NOT APPLICABLE
20.08.3 CONSTRUCTION METHODS
Unclassified excavation shall be made in conformity with the requirements of the plans. The slopes of earth cuts shall be smooth, neat and true to the lines given or as directed.
Stumps, trees, sod, weeds and material that will not compact under rolling shall not be placed in embankments, but shall be disposed of as directed by the Engineer.
Placement of Excavated Material: Except as specifically provided elsewhere herein, suitable material removed from the excavation shall be used as directed in the formation of embankments, subgrade, shoulders, etc., and at such other places as may be required.
When embankments are to be constructed on existing slopes steeper than 1 vertical to 3 horizontal, the slope of the existing ground on which the embankment is to be placed shall be plowed deeply or cut into steps before the filling is begun.
Embankments are to be constructed of earth, rock or a mixture of earth and rocks, deposited in successive layers for the full width of the embankment. Except, as herein after permitted, the depth of each layer shall not be more than 12 inches before compaction. Each layer shall be leveled off by the use of blade graders or bulldozers with adequate power for the work involved. The entire area of each layer shall be compacted by distributing the hauling over the area, by the use of tread type equipment, by power rollers weighing not less than 10 tons, or by other mechanical means satisfactory to the Engineer.
Compactions shall be continued until each layer is thoroughly consolidated for its full width. The dry density of each layer after compaction shall not be less than 90 percent of the dry density achieved by the A.A.S.H.O. Method T-99 for that soil. Depending on the material and weather conditions, it may be necessary to supplement mechanical compaction methods by control of moisture in the material.
No stone over 5 inches in its greatest dimensions shall be placed within 12 inches of the subgrade. The subgrade shall be the bottom of the pavement base course.
Surplus Excavated Material: All surplus excavated material shall be used as required to uniformly widen embankments, to flatten slopes, to fill low places in the right-of-way, or for such other purposes as the Engineer may direct. Any surplus or unsuitable material not required, or permitted to be used for such purposes shall be removed from the limits of the work and deposited at such point or points as the Engineer may direct on other property owned by the City of New Haven or disposed of in a manner approved by the Engineer. Material shall be deposited and spread uniformly as directed by the Engineer, within the limits of the area designated by him to receive the surplus material.
20.08.4 METHOD OF MEASUREMENT
Payment lines for "Unclassified Excavation" shall coincide with the slope and subgrade lines as shown on the plans or as ordered.
The amount of unclassified excavation will be determined by the method of average end areas.
20.08.5 BASIS OF PAYMENT
Unclassified excavation will be paid for at the contract unit price per cubic yard for "Unclassified Excavation", which price shall include all equipment, tools, transportation and labor incidental to the completion of the excavation, the formation and compaction of embankments and the disposal of surplus or unsuitable material in accordance with provisions of the plans and of these specifications.
Unclassified Excavation Cubic Yard
32 11 23 — WELL-GRADED #8 ANGULAR CRUSHED STONE (6" DEPTH) PATH WITH NON-WOVEN
GEOTEXTILE FABRIC
1.0 DESCRIPTION
Provide and install a 6-inch thick layer of well-graded #8 (3/8") angular crushed stone placed over non-woven geotextile fabric (Mirafi 140NL or approved equal) at the locations shown on the Drawings and as specified herein. Work includes furnishing materials, delivery, placement, compaction, grading, and all incidentals necessary for a complete installation.
2.0 REFERENCES
The following standards form part of this specification:
Aggregates
• ASTM D448 — Classification for Sizes of Aggregate for Road and Bridge Construction
• AASHTO M43 — Standard Specification for Aggregate Sizes
• ASTM C33 — Concrete Aggregates
• ASTM C136 — Sieve Analysis of Fine and Coarse Aggregates
• ASTM C117 — Materials Finer Than No. 200 Sieve
• ASTM D75 — Sampling Aggregates
Geotextile Fabric
• AASHTO M288 — Geotextile Specification for Highway Applications
• ASTM D4491 — Water Permeability (Permittivity)
• ASTM D4751 — Apparent Opening Size (AOS)
• ASTM D4632 — Grab Tensile Strength
• ASTM D4833 — Puncture Resistance
• ASTM D5261 — Mass per Unit Area
• ASTM D6241 — CBR Puncture Strength
• ASTM D4355 — UV Resistance
3.0 MATERIALS
3.1 Non-Woven Geotextile Fabric
• Type: Non-woven, needle-punched polypropylene
• Approved Product: Mirafi 140NL or approved equal
• Minimum Properties:
o Grab Tensile Strength (ASTM D4632): ≥ 205 lb o Elongation: ≥ 50% o CBR Puncture Strength (ASTM D6241): ≥ 500 lb o AOS (ASTM D4751): No. 70 sieve (0.212 mm) o Permittivity (ASTM D4491): ≥ 1.0 sec⁻¹ o UV Resistance (ASTM D4355): ≥ 70% retained at 500 hr
• Packaging: Rolls shall be wrapped to protect against moisture, dirt, and UV exposure.
3.2 Well-Graded #8 Angular Crushed Stone
• Material: Clean, hard, durable, angular crushed rock (granite, limestone, or trap rock)
• Size: #8 aggregate per AASHTO M43 or ASTM D448
• Gradation Requirements:
Sieve Size Percent Passing
1/2 in (12.5 mm) 85–100%
3/8 in (9.5 mm) 10–30%
No. 4 (4.75 mm) 0–10%
No. 8 (2.36 mm) 0–5%
• Quality Requirements:
o Los Angeles Abrasion (ASTM C131/C535): ≤ 45% o Soundness (ASTM C88): ≤ 12% loss o Fines (ASTM C117): ≤ 1.0% o Flat/Elongated Particles: ≤ 10% at 5:1 ratio
4.0 SUBMITTALS
Contractor shall provide:
1. Geotextile product data and certification of compliance
2. Aggregate source certification
3. Gradation test results (ASTM C136)
4. Quality test results (abrasion, soundness, deleterious materials)
5. Delivery tickets for each load of stone
5.0 DELIVERY, STORAGE, AND HANDLING
Geotextile
• Store rolls off the ground on pallets.
• Protect from sunlight, moisture, and physical damage.
Aggregate
• Stockpile on clean, stable, well-drained surface.
• Prevent segregation and contamination.
• Keep different aggregate sizes separated.
6.0 INSTALLATION
6.1 Subgrade Preparation
• Grade and compact subgrade to lines and elevations shown.
• Remove soft, unstable, or unsuitable material.
• Proof-roll if required by the Engineer.
• Subgrade shall be smooth and free of sharp objects.
6.2 Geotextile Placement
• Unroll fabric directly onto prepared subgrade without wrinkles or folds.
• Overlap adjacent sheets:
o 18 inches minimum on flat ground o 36 inches minimum on slopes
• Secure fabric with pins, staples, or soil cover to prevent movement.
• Do not allow construction traffic directly on exposed fabric.
6.3 Placement of #8 Stone
• Place stone carefully to avoid damaging geotextile.
• Minimum compacted thickness: 6 inches
• Place in a single lift or multiple lifts as required to achieve compaction.
• Avoid segregation by minimizing pushing with equipment.
6.4 Compaction
• Compact using vibratory roller or plate compactor until stone is stable and interlocked.
• Continue compaction until no visible movement occurs under equipment.
6.5 Tolerances
• Finished compacted thickness: ± ½ inch
• Surface shall be smooth, stable, and free of ruts or depressions.
7.0 QUALITY CONTROL
7.1 Field Testing
Engineer may perform:
• Verification of geotextile type and placement
• Aggregate gradation testing
• Thickness measurements
• Compaction verification (visual or proof-roll)
7.2 Rejection
Material or installation may be rejected for:
• Contamination with soil or debris
• Excess fines
• Damage to geotextile
• Failure to meet gradation or thickness requirements
8.0 MEASUREMENT AND PAYMENT
Unless otherwise specified:
• Geotextile fabric to be included in CY cost of crushed stone.
• #8 stone measured by cubic yard placed and accepted.
• Payment includes all labor, materials, equipment, overlaps, waste, and incidentals.
SECTION 32 31 19 – POST-AND-ROPE FENCE (PRESSURE-TREATED POSTS WITH MANILA JUTE
ROPE)
PART 1 – GENERAL
1.1 SUMMARY
This section includes labor, materials, equipment, and services necessary to furnish and install a post-and-rope fence consisting of 6-inch diameter pressure-treated wood posts and manila jute rope.
1.2 REFERENCES
• AWPA (American Wood Protection Association) Standards for pressure-treated lumber
• ASTM D3909 – Standard Specification for Manila Rope
• OSHA requirements for safe installation practices
1.3 SUBMITTALS
• Product data for pressure-treated posts
• Product data for manila jute rope
• Post layout plan if required by drawings
• Sample of rope knotting/attachment method upon request
1.4 QUALITY ASSURANCE
• All posts shall be treated to AWPA UC4A or UC4B (ground contact) standards.
• All rope shall be new, uniform in appearance, and free of fraying or defects.
• Installation shall be performed by personnel experienced in fence construction.
PART 2 – PRODUCTS
2.1 WOOD POSTS
• Material: Southern Yellow Pine or approved equivalent
• Diameter: Minimum 6 inches measured at the small end
• Treatment: Pressure-treated for ground contact (AWPA UC4A or UC4B)
• Finish: Natural; no paint or stain unless noted
• Top: Flat or chamfered; tops shall be smooth and free of splinters
2.2 ROPE
• Material: 100% natural manila jute rope
• Diameter: 1" to 1½" (as shown on drawings or specified by owner)
• Construction: 3-strand twisted
• Color: Natural tan
• Weather Treatment: Optional clear preservative or marine-grade oil if specified
2.3 HARDWARE
• Eye bolts, rope brackets, or through-post holes as indicated on drawings
• Material: Hot-dip galvanized or stainless steel
• Fasteners: Galvanized spikes, screws, or bolts suitable for exterior use
PART 3 – EXECUTION
3.1 EXAMINATION
• Verify locations of underground utilities before excavation.
• Confirm fence alignment and post spacing with site plans.
3.2 INSTALLATION OF POSTS
• Spacing: Typically 6'–10' on center unless otherwise shown.
• Depth: Set posts a minimum of 30"–36" into the ground or ⅓ of total post length, whichever is greater.
• Hole Diameter: Minimum 10" or 2× post diameter.
• Backfill:
o Compact native soil in 6" lifts or o Use concrete footing where required (12" diameter minimum).
• Posts shall be plumb within ¼" over full height.
3.3 ROPE INSTALLATION
• Install rope in continuous runs between posts.
• Thread rope through pre-drilled holes or attach using approved hardware.
• Maintain a consistent sag or tension as shown on drawings (typically 3"–6" sag between posts for aesthetic fences).
• Secure rope ends with knots, clamps, or splices to prevent unraveling.
• Trim excess rope neatly.
3.4 FINISHING
• Remove all debris, cuttings, and packaging from site.
• Touch up any damaged treatment on posts with approved preservative.
3.5 PROTECTION
• Protect installed fence from damage until final acceptance.
• Replace any posts or rope sections damaged prior to project completion.
3.6 MEASUREMENT AND PAYMENT
• Item shall be measured by linear foot installed and accepted.
• Payment includes furnishing, installation, hardware, and all incidentals required for a complete installation.
SECTION 32 33 23 — TRASH RECEPTACLES
1.0 DESCRIPTION
Provide and install trash receptacles at the locations determined by the Landscape Architect and as specified herein. Work includes furnishing all materials, hardware, anchors, labor, equipment, and incidentals necessary for a complete and functional installation.
2.0 REFERENCES
The following standards form part of this specification:
• ASTM A240/A240M — Chromium and Chromium-Nickel Stainless Steel Plate, Sheet, and Strip
• ASTM A653/A653M — Steel Sheet, Zinc-Coated (Galvanized)
• ASTM A123/A123M — Zinc (Hot-Dip Galvanized) Coatings on Iron and Steel Products
• ASTM A153/A153M — Zinc Coating on Iron and Steel Hardware
• Manufacturer’s published installation instructions
3.0 PRODUCTS
3.1 Manufacturer
• Product: 1-Module MEDIUM Citibins with Basket Top and Stainless Steel Door Handle
• Dimensions: 29.5 inches (W) × 34.75 inches (D) × 54 inches (H)
• Manufacturer: Citibin (or approved equal)
3.2 Designation
• Trash Receptacle Type: TR-1. Coordinate with City of New Haven.
• Use this designation to identify each receptacle location.
3.3 Construction
• Module Type: Single-module, medium-size enclosure
• Body Material: Steel panels
• Door: Hinged front-access door with stainless steel handle
• Top: Basket-style top for refuse insertion
• Internal Bin: Manufacturer’s standard removable liner or bin
• Ventilation: Integrated ventilation slots or perforations (if provided by manufacturer)
• Fasteners: Stainless steel, tamper-resistant where exposed
• Structural Frame: Welded or mechanically fastened steel frame designed to resist deformation under normal public use
3.4 Finish
• Exterior Panels: Factory-applied powder-coat finish or galvanized finish per manufacturer’s standard
• Hardware: Stainless steel
• Color: Manufacturer’s standard color (insert color if project-specific)
3.5 Capacity
• Unit shall be sized to accommodate standard municipal toter for a single-module medium enclosure.
3.6 Installation Method
• Surface-mounted installation
• Anchored to concrete pad or pavement using stainless steel or galvanized anchors per manufacturer’s recommendations.
4.0 SUBMITTALS
Provide the following:
1. Product Data: Manufacturer’s catalog sheets, dimensions, materials, finishes, and installation instructions.
2. Shop Drawings: Indicate mounting details, clearances, and anchorage.
3. Samples: Finish sample for exterior panels (if required).
4. Certificates: Manufacturer’s certification that products meet this specification.
5.0 DELIVERY, STORAGE, AND HANDLING
• Deliver products in manufacturer’s original packaging with labels intact.
• Store receptacles off the ground, protected from moisture, dirt, and damage.
• Do not install damaged components; replace at no cost to the Owner.
6.0 INSTALLATION
6.1 General
Install trash receptacles in accordance with manufacturer’s instructions.
6.2 Location and Orientation
• Install receptacles at locations indicated by Landscape Architect.
• Maintain required clearances from walkways, benches, bicycle racks, and other site furnishings.
• Ensure units are level, plumb, and aligned.
6.3 Mounting
• Install on a level concrete pad or pavement surface.
• Secure receptacle using manufacturer-recommended anchors.
• Ensure door operation is unobstructed and smooth.
6.4 Protection
• Protect installed receptacles from damage during construction.
• Replace components with significant damage.
• Touch up minor finish damage with manufacturer-approved coating.
7.0 FIELD QUALITY CONTROL
• Landscape Architect may inspect installation for alignment, finish quality, anchorage, and compliance with specifications.
• Non-conforming work shall be corrected or replaced at Contractor’s expense.
8.0 CLEANING AND CLOSEOUT
• Clean receptacles of construction debris, fingerprints, and surface contaminants.
• Remove protective coverings.
• Leave installation in clean, ready-for-use condition.
9.0 MEASUREMENT AND PAYMENT
• Trash receptacles shall be measured per each installed and accepted.
• Payment includes furnishing, installation, anchorage, hardware, and all incidentals required for a complete installation.
SECTION 32 93 00 – PLANTING
PART 1 – GENERAL
1.1 SUMMARY
• Furnish and install all trees, shrubs, perennials, groundcovers, grasses, and seed shown on the drawings and specified herein.
• Work includes plant materials, soil preparation, planting mixes, fertilizers, mulch, staking, guying, edging, and maintenance during establishment.
1.2 RELATED DOCUMENTS
• Drawings and general provisions of the Contract, including General and Supplementary Conditions.
• Section 32 91 00 – Topsoil and Soil Preparation.
• Section 32 92 00 – Turf and Seed.
1.3 REFERENCES
• American Standard for Nursery Stock (ANSI Z60.1).
• ASTM D5268 – Standard Specification for Topsoil.
• ANSI A300 – Standards for Tree Care Operations.
1.4 SUBMITTALS
• Plant Material Sources: List of nurseries supplying each species.
• Soil Amendments: Manufacturer data for compost, fertilizers, and mulch.
• Planting Schedule: Proposed delivery and installation timeline.
• Samples: Mulch, staking materials, and any decorative stone.
1.5 QUALITY ASSURANCE
• Plant materials shall conform to ANSI Z60.1 and be nursery-grown, true to name, vigorous, and free of pests, disease, and mechanical injury.
• Installer shall have a minimum of 3 years of documented experience in landscape installation.
• All substitutions must be approved by the Landscape Architect prior to ordering.
1.6 DELIVERY, STORAGE, AND HANDLING
• Dig, transport, and handle plants to prevent injury to roots, branches, or trunks.
• Protect root balls from drying out; cover with burlap or tarps during transport.
• Do not prune plants before delivery unless approved.
1.7 PROJECT CONDITIONS
• Do not plant when soil is frozen, waterlogged, or excessively dry.
• Coordinate planting with site grading and preparation.
• Protect existing vegetation and site features from damage.
1.8 WARRANTY
• Provide a one-year warranty from date of substantial completion.
• Replace dead, declining, or unacceptable plants at no cost to the Owner.
PART 2 – PRODUCTS
2.1 PLANT MATERIALS
• Trees: Nursery-grown, balled-and-burlapped (B&B) unless otherwise noted. Straight trunks, full crowns, and well-developed root systems.
• Shrubs: Container-grown or B&B as specified; full, well-branched, and typical of species.
• Perennials & Grasses: Container-grown, vigorous, with healthy root systems and no signs of stress.
• Groundcovers: Plugs or containers as specified.
2.2 TOPSOIL & PLANTING MIX
• Topsoil meeting ASTM D5268, free of debris, stones >1", weeds, and contaminants.
• Planting mix:
o 60% screened topsoil o 30% compost (STA-certified) o 10% sand or per project soils report
2.3 FERTILIZER
• Slow-release, organic-based fertilizer (e.g., 5-3-2 or similar).
• Mycorrhizal inoculant for trees and shrubs where specified.
2.4 MULCH
• Medium nugget pine bark mulch, aged, dark brown, free of dyes and contaminants.
• Depth: 2–3 inches after settlement.
2.5 STAKING AND GUYING MATERIALS
• Two 2"x2"x8' hardwood stakes for small trees; three-point guying for larger trees.
• Non-abrasive, wide tree straps; no wire in hose.
PART 3 – EXECUTION
3.1 EXAMINATION
• Verify finish grades, soil preparation, and irrigation installation prior to planting.
• Report unsuitable conditions to the Landscape Architect.
3.2 PLANTING BED PREPARATION
• Loosen subgrade to 6".
• Incorporate planting mix uniformly to a depth of 12".
• Remove stones >1" and debris.
3.3 TREE PLANTING
• Excavate pits 2–3 times the root ball width and equal to root ball depth.
• Set tree so root flare is visible and 1–2" above finished grade.
• Remove all twine, burlap from top 1/3 of root ball, and wire baskets from top 8–12".
• Backfill with planting mix in lifts, watering to eliminate air pockets.
• Create a 3–4" high berm outside root ball edge unless irrigation is provided.
• Stake only if required by drawings or site conditions.
3.4 SHRUB PLANTING
• Excavate pits twice the container width.
• Set shrubs at or slightly above finished grade.
• Backfill with planting mix; water thoroughly.
• Space shrubs as shown on drawings; adjust for natural appearance in mass plantings.
3.5 PERENNIALS, GRASSES, AND GROUNDCOVERS
• Loosen planting bed to 6".
• Install plants at same depth as grown in container.
• Water immediately after planting.
• Arrange perennials in informal drifts unless otherwise shown.
3.6 MULCHING
• Apply mulch to 2–3" depth.
• Keep mulch 3–4" away from tree trunks and shrub crowns.
3.7 WATERING
• Water all plants immediately after installation.
• Maintain adequate soil moisture throughout establishment period.
3.8 CLEANING AND PROTECTION
• Remove excess soil, debris, and unused materials.
• Protect installed plantings from damage by construction activities.
3.9 MAINTENANCE
• Maintain plantings for 60 days after installation or until substantial completion.
• Maintenance includes watering, weeding, resetting plants, tightening stakes, and replacing mulch.
3.10 MEASUREMENT AND PAYMENT
• Plant material shall be measured per each installed and accepted.
• Payment includes furnishing, installation, warranty, and all incidentals required for a complete installation.
Section 50.01
LOAMING, SEEDING AND SODDING
50.01.1 DESCRIPTION
The work under this section shall consist of furnishing all labor, materials, and equipment required to complete the loaming, seeding and/or sodding on areas indicated on the Drawings or directed by the Engineer.
50.01.2 MATERIALS
Grass: All grass seed shall be fresh, clean, of latest crop, and composed of the following varieties, mixed in proportions by weight testing to minimum percentages of purity and germination specified:
Botanical Name Common Name %Purity %Germination %by weight
Festuca ruba Creeping Red or
Chewing's Fescue 98 90 50
Poa pratensis Kentucky Bluegrass 85 75 25
Poa pratensis merion merion Kentucky Bluegrass 85 75 25
Seed shall be delivered pre-mixed to the Site in standard size sealed containers bearing the vendor's guaranteed statement attesting to the composition of the mixture and to the percentages of purity and germination of each variety. Seed shall be stored in such manner that its effectiveness is not impaired.
Samples of seed shall be taken as directed by the Engineer, and shall be submitted to the State Agricultural Station for analysis.
Sod: All sod shall be well-established, good quality, permanent lawn grass, grown on open ground in an approved area. It shall be strongly rooted, containing seventy-five (75) percent Merion Bluegrass (Poa pratensis merion) and twenty-five (25) percent Pennlawn Fescue, free of pernicious weeds and coarse, burned or bare spots.
The sod shall be in rectangular sections varying in length between 3 feet and 6 feet and shall be of uniform width not to exceed 18 inches. Sod shall have a uniform soil thickness of one and one-half (1-1/2) inches.
Grass shall have been mowed to a height of two (2) inches before lifting. Sections shall be of such size as to be lifted without breaking, tearing, or loss of soil.
The Contractor shall furnish the Engineer with an adequate sample for inspection and approval before any sod is delivered to the site.
Loam: The Contractor shall furnish soil samples to the Engineer as requested at no additional cost to the City. Generally, the Engineer shall submit a sample of loam material proposed to be used on the project to a U.S. State or Agricultural Station for analysis and corrective recommendations if necessary. The Engineer shall advise the Contractor as to the corrective recommendations required to make the loam acceptable for use on the project.
Loam material furnished from sources outside of the project limits shall consist of loose, friable, sandy loam or loam topsoil free of admixture of subsoil, refuse stumps, roots, rock, brush, weeds, and other material which will prevent the formulation of a suitable sod or seed bed. Loam shall be that portion of the soil profile defined technically as the "A" horizon by the Soil Science Society of America. It shall contain not less than 6 percent nor more than 20 percent organic matter as determined by loss-on-ignition of oven dried samples drawn by the Engineer. Loam shall be free of stone 1-1/4 inches and larger in over-all dimensions. The Contractor shall notify the Engineer of the location from which he proposes to furnish loam at least 15 calendar days prior to delivery of loam to the project site from that location.
The loam and its source shall be inspected and approved by the Engineer prior to delivery to the project site. Any loam delivered to the project which does not meet the above requirements will be rejected and shall be immediately removed from the project site and replaced by the Contractor with acceptable material at no additional cost to the City.
When loam is not furnished from outside sources, the material used shall be the loam stripped during the course of excavation on the project site. All roots, stumps, debris, pavement, brush sods and other objectionable materials shall be removed by the Contractor prior to its use.
Chlordane: Chlordane shall be a commercial product in dry powder form, of recent manufacture, delivered to the Site in original unopened containers bearing the manufacturer's guaranteed statement of analysis giving the percent of active ingredient.
Commercial Fertilizer Commercial fertilizer shall be a complete fertilizer and a standard product complying with Federal and State Fertilizer laws. It shall be uniform in composition, dry, free flowing, and shall have been stored in a weatherproof place in such a manner that its effectiveness is not impaired. Fertilizer which becomes caked or otherwise damaged, making it unsuitable for use, shall not be accepted.
Commercial fertilizer shall be delivered to the Site in original, unopened containers showing weight, analyses, and name of manufacturer and shall contain the following percentages of weight, of which at least fifty (50) percent of the nitrogen will be derived from an organic material or a composition containing "uramite".
The Contractor shall submit to the Engineer, the manufacturer's guarantee statement of analysis or a manufacturer's certification of compliance covering analysis for the Engineer's written approval before delivery to the Site.