Summary
This Request for Qualifications (RFQ) document is issued by the Successor Coeur d'Alene Custodial and Work Trust for remedial action construction projects within the Canyon Creek Basin in Shoshone County, Idaho, conducted under EPA oversight at the Bunker Hill Mining and Metallurgical Complex Superfund Site. The RFQ solicits qualified construction contractors for three separate projects: Standard-Mammoth Reach Remedial Action Construction Project, Frisco Black Bear Reach Remedial Action Construction Project, and Canyon Creek Garbage Dump Remedial Action Construction Project. Work includes excavating and hauling mine waste materials, regrading and consolidating mine waste, stream diversion, construction dewatering, stream reconstruction, bank stabilization, Redi-Rock retaining wall installation, liner installation, storm water construction, adit closures, revegetation, and coordination with utility companies in steep mountainous terrain. The Standard-Mammoth Reach and Frisco Black Bear Reach projects are anticipated to be completed within two construction seasons, while Canyon Creek Garbage Dump is expected to be completed within one construction season. The RFQ deadline for submittal is 12:00 p.m. PDT on September 16, 2026, with interviews tentatively scheduled for the week of September 21, 2026. A mandatory pre-bid site walk for prequalified contractors is tentatively scheduled for the week of October 5, 2026, and successful contractors will be asked to submit bids during the first quarter of 2027. The Trust's objective is to prequalify four to six contractors for each project based on submitted Statements of Qualifications. Questions must be submitted by August 28, 2026, with answers provided by September 4, 2026. Selected contractors will execute a Master Services Agreement with project-specific work orders detailing scope and costs.
Respondents must demonstrate relevant experience with mine waste excavation and hauling, construction dewatering, hazardous waste site safety (including HAZWOPER training and Site Safety and Health Officer qualification with minimum two years of experience), quality assurance/quality control program implementation, and detailed document management capabilities required for EPA compliance. The Coeur d'Alene Trust requires prevailing wages for all projects and implementation of a Diesel Emissions Reduction Implementation Plan. The Trust has established a local labor objective of 50% for field and office personnel, defined as the area east of the Idaho/Washington border and west of Lookout Pass, with contractors required to explain their plan to meet this objective or justify why it cannot be attained. Respondents must submit electronically via the CivCast website a Statement of Qualifications not exceeding 20 pages (excluding resumes and cover page) in searchable PDF format, including company capacity information, subcontracting approach, relevant work experience (maximum 10 project profiles), health and safety program details, QAPP implementation experience, and demonstrated document management experience.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Coeur d’Alene Trust Request for Qualifications: 2027 Remedial Action Construction Projects Page 1
COEUR D’ ALENE TRUST REQUEST FOR QUALIFICATIONS:
2027 REMEDIAL ACTION CONSTRUCTION PROJECTS:
STANDARD-MAMMOTH REACH
FRISCO BLACK BEAR REACH
CANYON CREEK GARBAGE DUMP
1.0 INFORMATION AND OVERVIEW
Request for Qualifications (RFQ) Managers: Kyle Allen, Troy Colvin, Zach Archibald
Contact Information/Trust Representative:
Kyle Allen – kallen@pioneer-technical.com, (208) 596-1374 (Standard-Mammoth Reach)
Troy Colvin – tcolvin@pioneer-technical.com, (406) 490-0151 (Frisco Black Bear Reach)
Zach Archibald – zarchibald@pioneer-technical.com, (406) 565-0180 (Canyon Creek Garbage
Dump)
RFQ Website: www.civcastusa.com – Coeur d’Alene Trust 2027 Remedial Action Construction
Projects RFQ
Project Names: Standard-Mammoth Reach Remedial Action Construction Project RFQ, Frisco
Black Bear Reach Remedial Action Construction Project RFQ, and Canyon Creek Garbage Dump
Remedial Action Construction Project RFQ
Through this RFQ, the Successor Coeur d’Alene Custodial and Work Trust (Coeur d’Alene Trust) is soliciting information from qualified construction contractors (Respondents) to perform the
Standard-Mammoth Reach Remedial Action (RA) Construction Project, the Frisco Black Bear Reach
RA Construction Project, and the Canyon Creek Garbage Dump RA Construction Project in the
Canyon Creek Basin in Shoshone County, Idaho.
The Coeur d’Alene Trust’s objective is to identify four to six qualified contractors to bid on each of the three RA Projects. The work associated with each project is described in Section 4.0 of this document. Respondents may be prequalified for one or multiple projects based on information provided in response to this RFQ. Prequalified Respondents will participate in a mandatory pre-bid site walk to be held in the fall of 2026 (tentatively the week of October 5, 2026). Prequalified
Respondents will also be asked to provide bids during the first quarter of 2027. The Respondent(s) ultimately selected to complete work for each project will execute a Master Services Agreement with the Coeur d’Alene Trust, with the specific scope and costs identified through a Project-specific work order.
mailto:kallen@pioneer-technical.com mailto:tcolvin@pioneer-technical.com mailto:zarchibald@pioneer-technical.com http://www.civcastusa.com/
Coeur d’Alene Trust Request for Qualifications: 2027 Remedial Action Construction Projects Page 2
Interested Respondents must use the CivCast website to respond to this RFQ and complete their
Respondent Information and Statement of Qualifications (SOQ). All submittals must be in accordance with the instructions provided in Section 5.0 and 7.0 of this document.
2.0 SCHEDULE
Questions: Questions from Respondents regarding the RFQ are due by August 28, 2026, at 5:00 p.m.
(Pacific Daylight Savings Time [PDT]).
Answers: Questions from Respondents will be answered by 5:00 p.m. PDT on Friday, September 4, 2026, as described in Section 6.0.
Submittals: Submittals must be completed on the website by 12:00 p.m. (NOON) PDT on
Wednesday, September 16, 2026, as described in Section 7.0.
Interviews: Interviews, if necessary, will follow during the week of September 21, 2026, at the
Coeur d’Alene Trust’s office in Kellogg, Idaho. A pre-qualified contractor’s mandatory bid walk is tentatively scheduled for the week of October 5, 2026.
3.0 BACKGROUND INFORMATION
The Coeur d’Alene Trust is undertaking a variety of environmental cleanup-related actions at the
Bunker Hill Mining and Metallurgical Complex Superfund Site located in the Silver Valley of north
Idaho, as required by the Coeur d’Alene Trust Agreement with the U.S. Environmental Protection
Agency (EPA). The Coeur d’Alene Trust will implement this work in cooperation with and under the oversight of the EPA. The overall objective for the Coeur d’Alene Trust is to initiate and complete priority work identified in the EPA decision documents, such as the Record of Decision (ROD) and
ROD Amendments. EPA has identified the cleanup of mine and mill sites within the Canyon Creek basin as one of the Coeur d’Alene Trust activities.
Construction of the Canyon Complex Repository (CCR)/Waste Consolidation Area (WCA) and infrastructure improvements have been ongoing and adequate space is available at the CCR/WCA for mine waste disposal from the Standard-Mammoth Reach RA Construction Project and the Frisco
Black Bear Reach RA Construction Project. It is anticipated that all mine waste at the Canyon Creek
Garbage Dump RA Construction Project will be regraded and consolidated on-site and waste removal is not necessary. State Highway 4 will be used for hauling mine waste and backfill materials to and from the Standard-Mammoth Reach, Frisco Black Bear Reach, and Canyon Creek Garbage
Dump projects to/from the CCR/WCA. This RFQ is for the work associated with the Standard-
Mammoth Reach RA Construction Project, the Frisco Black Bear Reach RA Construction Project, and the Canyon Creek Garbage Dump RA Construction Project as described in Section 4.0 of this document.
4.0 SCOPES OF WORK
4.1 Standard-Mammoth Reach RA Construction Project
The Standard-Mammoth Reach RA Construction Project is adjacent to State Highway 4 and is comprised of mine waste associated with old mining operations. The majority of the work is located
Coeur d’Alene Trust Request for Qualifications: 2027 Remedial Action Construction Projects Page 3 in steep mountainous terrain. The project is anticipated to be completed within two construction seasons and work will include the following major components:
• Establishing traffic controls throughout the Site and along the haul route.
• Installing and maintaining temporary fencing, gates, concrete barriers, and signage to control
Site access.
• Installing a permanent gate.
• Installing permanent signage.
• Clearing and grubbing vegetated areas within the excavation boundary.
• Controlling fugitive dust raised during construction activities and controlling tracking of soils off-Site during construction activities.
• Providing and installing temporary and long-term Best Management Practices (BMPs).
• Coordinating with the existing utility owners prior to waste excavation and during removal and replacement of poles, anchor rods, and guy wire lines (Avista Utilities and Ziply Fiber).
• Coordinating the shutoff of the Star Tailings Line with Trust Representative.
• Diverting the Star Tailings Line.
• Potential removal and disposal of asbestos concrete pipe.
• Installing the required piping, pumps, power, instrumentation, and controls for the dewatering system.
• Diverting surface waters from Canyon Creek.
• Diverting adit flows from the Anchor Mine Adit (CC-373A).
• Excavating, loading, and hauling mine waste and impacted soil from the Project Site to the
CCR/WCA or LBCR.
• Excavating, loading, hauling, and consolidating mine waste and impacted soil on Site at select locations.
• Loading, hauling, and placing general fill material.
• Removing and disposing of various concrete and wood debris (timbers, rail ties, etc.)
encountered during excavation to the CCR/WCA or LBCR.
• Reconstructing Canyon Creek.
• Installing grade control step structures as part of Canyon Creek stream reconstruction.
• Implementing bank stabilization along designated sections of Canyon Creek.
• Installing a Redi-Rock retaining wall.
• Installing a chain link fence behind the Redi-Rock retaining wall.
• Providing and installing three bat friendly adit closures.
• Constructing an adit conveyance channel.
• Constructing storm water conveyance channels.
• Constructing a channel to convey water from BUR143-PIPEOUTLET-001 to Canyon Creek.
• Installing HDPE culverts.
• Installing HDPE pipe, elbows, and an anchor block.
• Installing LLDPE liner and geotextile.
• Removing, salvaging, and reinstalling the salvaged HDPE pipe sections of the existing Star
Tailings Line.
• Providing and installing new HDPE pipe to the extent necessary to complete the installation of the Star Tailings Line.
• Incorporating organic amendment and lime into cover soil from the LBCR stockpile location.
• Placing amended steep slope cover soil.
Coeur d’Alene Trust Request for Qualifications: 2027 Remedial Action Construction Projects Page 4
• Placing amended cover soil.
• Placing 3-inch minus gravel along the Omaha Portal Road, Anchor Mine Adit Road, and other assorted areas throughout the Project.
• Placing 3-inch minus gravel along the road shoulder of State Highway 4 at select areas.
• Placing stockpiled woody debris for use as erosion control.
• Procuring and placing fertilizer and seeds for upland and riparian soils.
• Procuring and planting conifer tubelings.
• Procuring and planting riparian tubelings.
• Applying FlexTerra HP-FGM hydromulch to all disturbed areas.
• Applying ProGanicsTM Biotic soil to the Anchor Mine slope.
• Installing and maintaining trust provided trackout control devices.
• Handling and properly disposing of petroleum-impacted soils
• Documenting and reporting to meet Coeur d’Alene Trust and EPA quality assurance/quality control requirements.
4.2 Frisco Black Bear Reach RA Construction Project
The Frisco Black Bear Reach RA Construction Project is adjacent to State Highway 4 and is comprised of mine waste associated with old mining operations. The majority of the work is located in steep mountainous terrain. The project is anticipated to be completed within two construction seasons and work will include the following major components:
• Establishing traffic controls throughout the Site and along the haul route.
• Installing and maintaining gates, concrete barriers, and signage to control Site access.
• Installing two permanent gates.
• Installing permanent signage.
• Clearing and grubbing vegetated areas within the excavation boundary.
• Controlling fugitive dust raised during construction activities and controlling tracking of soils off-Site during construction activities.
• Providing and installing temporary and long-term BMPs.
• Coordinating with the existing utility owners prior to waste excavation and during removal and replacement of anchor rods, and guy wire lines (Avista Utilities and Ziply Fiber).
• Installing the required piping, pumps, power, instrumentation, and controls for the dewatering system.
• Diverting surface waters from Canyon Creek.
• Excavating, loading, and hauling mine waste and impacted soil from the Project Site to the
CCR/WCA or LBCR.
• Excavating, loading, hauling, and consolidating mine waste and impacted soil on Site at select locations.
• Loading, hauling, and placing general fill material.
• Removing and disposing of various concrete and wood debris (timbers, rail ties, etc.)
encountered during excavation to the CCR/WCA or LBCR.
• Reconstructing Canyon Creek.
• Installing grade control step structures as part of Canyon Creek stream reconstruction.
• Providing and installing a bat friendly adit closure.
• Constructing storm water conveyance channels.
Coeur d’Alene Trust Request for Qualifications: 2027 Remedial Action Construction Projects Page 5
• Constructing an artesian well channel to convey water to Canyon Creek.
• Installing a HDPE culvert.
• Installing LLDPE liner and geotextile.
• Incorporating organic amendment and lime into cover soil from the LBCR stockpile location.
• Incorporating organic amendment and lime into cover soil from the LBCR stockpile location for the Canyon Creek Garbage Dump Project.
• Placing amended steep slope cover soil.
• Placing amended cover soil.
• Placing 3-inch minus gravel along the on site access road.
• Placing 3-inch minus gravel along the road shoulder of State Highway 4 at select areas.
• Placing stockpiled woody debris for use as erosion control.
• Procuring and placing fertilizer and seeds for upland and riparian soils.
• Procuring and planting conifer tubelings.
• Procuring and planting riparian tubelings.
• Applying FlexTerra HP-FGM hydromulch to all disturbed areas.
• Installing and maintaining trust provided trackout control devices.
• Documenting and reporting to meet Coeur d’Alene Trust and EPA quality assurance/quality control requirements.
4.3 Canyon Creek Garbage Dump RA Construction Project
The Canyon Creek Garbage Dump RA Construction Project is adjacent to Burke Canyon Creek Road and is comprised of mine waste associated with old mining operations. The majority of the work is located in steep mountainous terrain. The project is anticipated to be completed within one construction season and work will include the following major components:
• Establishing traffic controls throughout the Site and along the haul route.
• Installing and maintaining temporary signage to control Site access.
• Clearing and grubbing vegetated areas within the project boundary.
• Controlling fugitive dust raised during construction activities and controlling tracking of soils off-Site during construction activities.
• Providing and installing temporary and long-term BMPs.
• Coordinating with the existing utility owners prior to waste excavation/consolidation (Avista
Utilities).
• Removing and replacing one utility anchor rod (Avista Utilities).
• Potentially removing and disposing of asbestos containing material.
• Potentially removing and disposing of polycyclic aromatic hydrocarbons and phenols.
• Diverting surface waters in Canyon Creek through the site.
• Excavating, loading, and hauling mine waste and impacted soil from the Project Site to the
CCR/WCA or LBCR, if necessary.
• Excavating, loading, hauling, grading, and consolidating mine waste and impacted soil on
Site.
• Removing and disposing of various debris (concrete, timbers, rail ties, etc.) encountered during waste consolidation to the CCR/WCA or LBCR.
• Implement bank stabilization along designated sections of Canyon Creek.
Coeur d’Alene Trust Request for Qualifications: 2027 Remedial Action Construction Projects Page 6
• Loading, hauling, and placing Type 1 (36-inch minus) riprap from the Ninemile riprap stockpile.
• Incorporating Type 3 (12-inch minus) riprap into amended cover soil from the LBCR stockpile location.
• Loading, hauling, and placing amended steep slope cover soil.
• Loading, hauling, and placing 3-inch minus gravel at designated areas of the Project.
• Placing stockpiled woody debris for use as erosion control.
• Procuring and placing fertilizer and seeds for upland soils.
• Procuring and planting conifer tubelings.
• Applying FlexTerra HP-FGM hydromulch to all disturbed areas.
• Installing and maintaining Coeur d’Alene Trust provided trackout control devices.
• Documenting and reporting to meet Coeur d’Alene Trust and EPA quality assurance/quality control requirements.
5.0 SUBMITTAL INFORMATION
Respondents must submit an SOQ summarizing relevant experience with the anticipated tasks identified in Section 4.0 as well as all other required information described below in Section 5.2.
5.1 Respondent Information
Respondents will be required to create a username/password to access the project on the CivCast website. All sections of Respondent Statement of Qualifications in Section 5.2 must be included in the response in order for the submittal to be considered complete.
5.2 Respondent’s Statement of Qualifications
The Respondent’s SOQ should briefly summarize the history, experience, and qualifications of the
Respondent. The SOQ should also include brief resumes or bios of key supervisory personnel and descriptions of relevant projects completed by key supervisory personnel, including years of experience completing the types of work outlined in Section 4.0. Additionally, the following topics should be addressed.
• Company Capacity: The three projects discussed in this RFQ will be bid separately;
however, the successful bidder(s) may be awarded more than 1 project bid. The SOQ should provide information that demonstrates the respondent’s capacity to perform multiple projects for the Coeur d’Alene Trust within the same construction year. If the respondent has the capacity to perform multiple projects per year, please provide management, subcontracting, or teaming plan to perform multiple projects. At a minimum, provide organizational charts and resumes for key staff down to project superintendents.
• Subcontracting Approach: The SOQ should provide information on all key subcontractors that the Respondent anticipates using for the RA Construction Projects. Include resumes or bios of key subcontractor employees to be used for the RA Construction Projects.
• Local Labor Requirement: The Coeur d’Alene Trust’s objective is to have 50% local labor and subcontractors for field and office personnel; however, if it is anticipated that this objective cannot be attained by the Respondent, the SOQ should discuss the reasoning. The
Coeur d’Alene Trust Request for Qualifications: 2027 Remedial Action Construction Projects Page 7 percent local labor will be calculated based on average utilization by the hour for Respondent and subcontractor employees. For the Coeur d’Alene Trust RA Construction Projects, local encompasses the area east of the Idaho/Washington border and west of Lookout Pass. The
SOQ must describe the Respondent’s proposed plan to achieve this local labor objective (i.e., subcontracting, hiring local, etc.) or the reasons why this objective may not be achieved.
• Relevant Work Experience: The SOQ should describe work completed by the Respondent that is similar in scope and site conditions to the work described in Section 4.0. Respondent shall include any relevant work experience pertaining specifically to the excavation and hauling of mine waste materials, regrading and consolidating mine waste, stream diversion, construction dewatering, stream reconstruction, bank stabilization, Redi-Rock retaining wall installation, liner installation, storm water construction, adit work, asbestos abatement, traffic control, coordinating with utility companies, working in steep terrain, revegetating, etc.
Respondent shall provide no more than 10 project work experience profiles as part of this section. Each project work experience profile shall include, at a minimum, reference contact information for owner/agency, original bid cost, final cost, project description, Respondent’s role in project, and days completed ahead of or behind schedule.
• Health and Safety: These sites are part of the Bunker Hill Superfund Site and appropriate
Hazardous Waste Operations and Emergency Response Training is required to complete the work. The Project contracts will require a Site Safety and Health Officer (SSHO) with a minimum of 2 years of experience in implementing safety and health programs at hazardous waste sites where Level C personal protective equipment is potentially required, and with a working knowledge of federal and state occupational safety and health regulations. The
Project contracts will also require that the Respondent prepare and implement an exposure monitoring/air sampling program to identify and quantify safety and health hazards and airborne levels of hazardous substances. The SOQ should describe the Respondent’s health and safety program and experience working on hazardous waste sites. The SOQ must include a resume or abbreviated biography for an individual qualified to fill the SSHO position.
• QAPP Implementation Experience: The SOQ should describe the Respondent’s experience with collecting and tracking field samples, collecting and tracking quality control samples
(e.g., field duplicates and rinsate blanks), managing stockpiled materials awaiting sample results, subcontracting analytical laboratories, and performing data validation.
• Demonstrated Document Management Experience: The SOQ should provide information that demonstrates the Respondent’s ability to comply with rigorous administrative requirements for submittals, document management, and reporting. EPA is the ultimate approving agency for the work, and EPA standard administrative requirements are incorporated into Coeur d’Alene Trust projects. Examples of administrative requirements include very thorough and detailed preconstruction submittals such as Health and Safety
Plans, Quality Control Plans (e.g., submittal management, testing procedures, and tracking systems for deficiencies), Environmental Protection Plans (e.g., Spill Prevention, Control, and Countermeasures Plan; non-hazardous solid waste disposal plan; air pollution control plan; contaminant prevention plan; wastewater management plan; and biological resources plan), as-built field data, and as-built Computer-Aided Design and Drafting (CADD) drawings.
Coeur d’Alene Trust Request for Qualifications: 2027 Remedial Action Construction Projects Page 8
The Respondent shall include any other additional information they feel is necessary to show reasonable experience completing this type of work.
The SOQ is to be provided electronically in a Portable Document Format (PDF) format that is text searchable (with Optical Character Recognition [OCR]). The filename format for the SOQ document is SOQ_Companyname.pdf, where “Company name” is the name of the Respondent. The SOQs shall not exceed 20 pages. The 20-page limit does not include resumes or a cover page/introductory letter and table of contents. Only one SOQ per Respondent will be reviewed. The SOQ should be submitted as described in Section 7.0 of this document.
6.0 QUESTIONS
Questions regarding this RFQ should be submitted via the “RFQ Questions” forum on the RFQ website (www.civcastusa.com – Coeur d’Alene Trust 2027 Remedial Action Construction
Projects RFQ). Questions must be posted to the website by 5:00 p.m. PDT on Friday, August 28, 2026. Please note that posted questions will be immediately available for other Respondents to view.
The Coeur d’Alene Trust may answer some questions prior to the deadline. If so, these will be posted as comments by a Trust Representative. A comprehensive summary of all questions and responses will be posted to the website by 5:00 p.m. PDT on Friday, September 4, 2026. The Coeur d’Alene
Trust may not respond to questions posted after Friday, August 28, 2026.
7.0 SUBMITTALS
To prepare a complete submittal to this RFQ, Respondents must create a CivCast username and password and upload an SOQ electronically to the RFQ website at www.civcastusa.com – Coeur d’Alene Trust 2027 Remedial Action Construction Projects RFQ. If you have any questions about the RFQ process or submittals, please contact the Trust Representative listed in Section 1.0 of this document.
8.0 OTHER INFORMATION
Please note that the Coeur d’Alene Trust is a private entity and that the Coeur d’Alene Trust requires prevailing wages for all its projects. The Coeur d’Alene Trust requires prevailing wages to ensure that Respondents completing work for the Coeur d’Alene Trust are of the highest quality available.
The Coeur d’Alene Trust has implemented a Diesel Emissions Reduction Implementation Plan for all
Coeur d’Alene Trust projects. The successful contractor(s) will be required to comply with all aspects of the diesel emissions reduction plan. All requirements will be provided to the pre-qualified contractors at the time of bidding.
http://www.civcastusa.com/ http://www.civcastusa.com/
| 1.0 Information and Overview |
| 2.0 Schedule |
| 3.0 Background Information |
| 4.0 Scopes of Work |
| 4.1 Standard-Mammoth Reach RA Construction Project |
| 4.2 Frisco Black Bear Reach RA Construction Project |
| 4.3 Canyon Creek Garbage Dump RA Construction Project |
| 5.0 Submittal Information |
| 5.1 Respondent Information |
| 5.2 Respondent’s Statement of Qualifications |
| 6.0 Questions |
| 7.0 Submittals |
| 8.0 Other Information |