Coefficient Breakdown Form with profit language.pdf
PDF 125 KB Posted
- Solicitation number
- N4008022R9543
About this file
This document contains a coefficient breakdown form and details of a related federal contract opportunity. The coefficient breakdown form provides examples of cost breakdown structures for pre-priced and non-pre-priced work, including materials, labor, equipment, overhead, and proposed maximum profit rates. These examples are intended to demonstrate the level of detail required in proposals but are not representative of actual rates. The related solicitation is for a general construction IDIQ Job Order Contract for the Naval Research Laboratory, Naval Research Laboratory Chesapeake Bay Detachment, and Naval Warfare Center Carderock. The contract has a maximum value of $50 million over a one-year base period and four one-year options. The procurement is set aside for 8(a) small businesses and utilizes Lowest Price Technically Acceptable source selection. The period of performance for task orders is expected to range from $2,000 to $1,000,000.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 2 Coefficient Contractor Estimate Worksheet.xlsx | XLSX spreadsheet | |
| N4008022R9543 NRDE Gen Construction RFP NRL-CARD 17May22.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
COEFFICIENT BREAKDOWN FORM
PRE‐PRICED COEFFICIENT
PRE-PRICED COSTS MATERIALS LABOR EQUIPMENT AMOUNT
PRE-PRICED COEFFICIENT
RS MEANS BARE COST
(PRESUMED ANNUAL
AMOUNT)
$6,300,000.00 $3,500,000.00 $200,000.00 $10,000,000.00
WORKER'S COMP
INSURANCE
AVERAGE FIXED LABOR
OVERHEAD
PROJECT OVERHEAD
PRE-PRICED
MATERIAL MARKUP
EQUIPMENT MARKUP
SUBTOTAL
GENERAL AND
ADMINISTRATIVE
PROFIT
TOTAL
COEFFICIENT FACTOR
(TOTAL DIVIDED BY
PRESUMED ANNUAL
AMOUNT)
RS MEANS BARE COST
ADJUSTMENT
(PRODUCTION/DISCOUNT
- FACTOR)
0.9
PRE-PRICED
COEFFICIENT
NON‐PREPRICED COEFFICIENT
PRE-PRICED COSTS MATERIALS LABOR EQUIPMENT AMOUNT
NON PRE-PRICED COEFFICIENT
NON PRE-PRICED BARE
COSTS (PRESUMED
ANNUAL AMOUNT)
$630,000.00 $350,000.00 $20,000.00 $1,000,000.00
WORKER'S COMP
INSURANCE
AVERAGE FIXED LABOR
OVERHEAD
PROJECT OVERHEAD
NON PRE-PRICED
MATERIAL MARKUP
EQUIPMENT MARKUP
SUBTOTAL
GENERAL AND
ADMINISTRATIVE
PROFIT
TOTAL
COEFFICIENT FACTOR
(TOTAL DIVIDED BY BARE
COST)
NON-PRE-PRICED BARE
COST ADJUSTMENT
(PRODUCTION/DISCOUNT
- FACTOR)
NON PRE-PRICED
COEFFICIENT
Offerors should fully understand "at a minimum" what is to be included in the coefficient. Section B of the RFP, and more specifically paragraphs B.2 OFFEROR'S COEFFICIENT AND PRE‐PRICED WORK (and its subparagraphs) and B.3 NON PRE‐PRICED WORK (and its subparagraphs) define the requirements for the pre‐priced and non‐pre‐priced coefficients.
The amounts shown above are based on the presumption that the Contractor has an annual billing amount of $10,000,000 and up. The amounts listed herein are fictitious as are the cost items. These examples should not be construed to be minimum or maximum, or even normal, amounts. Cost items should be added, removed, or separated as the Offeror deems necessary to demonstrate a detailed breakdown of coefficient cost. Any Offeror edits to the form must be explained in detail in the
Offeror’s proposal.
NOTE: The profit percentage proposed by the contractor on this form to be included in its pre‐priced and non‐pre‐priced coefficients shall be binding and shall be the maximum profit rate the Contractor will be allowed to propose for all task orders and/or subsequent modifications issued under this contract.
The Contractor may propose a lower profit rate when responding to an individual task order request
(or subsequent modifications) based on the tasks identified in the request. Profit will be negotiated on an individual Task Order and modification basis, but shall never exceed the maximum profit rate proposed by the Contractor on this form. The maximum profit rate shall be binding even if the DFARS
215.404‐73 ALTERNATE STRUCTURED APPROACH PROFIT WORKSHEET would result in a higher profit.
The maximum profit rate shall not be construed as a “fixed” profit percentage for all Task Orders or
Modification actions issued under this contract. If DFARS 215.404‐73 ALTERNATE STRUCTURED
APPROACH PROFIT WORKSHEET calculations indicate a lower profit rate is merited, the lower profit percentage shall be applied.
File details come from the government source that posted it. Updated .