CO700_26050701_JP3423904_SampleProposalRevised.pdf

PDF 11 MB Posted

Attached to
Widen, Resurface & Bridge, SH-152
Solicitation number
260114 CO 700
Issued by
Atoka County, Oklahoma

About this file

Summary of SH-152 Widening, Resurfacing, and Bridge Project

This is a sample proposal document from the Oklahoma Department of Transportation (ODOT) for a federal aid construction contract to widen, resurface, and construct bridge work on State Highway 152 in Beckham County, Oklahoma. The project extends 5.859 miles from the junction of SH-6 westward near Sayre and involves multiple construction sections including roadway work, two bridge replacements, traffic control, and traffic signing and striping. The project consists of over 60 line items with quantities including 121,463 cubic yards of unclassified excavation, 20,968 tons of Superpave Type S3 asphalt, 15,625 tons of Superpave Type S4 asphalt, and various culvert and drainage structures. Bidding proposals were available beginning April 16, 2026, with a proposal cost of $50.00 plus tax. The bid opening was scheduled for May 7, 2026, at 10:30 a.m. Standard time, with proposals submitted electronically through Bid Express or in written form prior to the bid opening deadline of May 6, 2026, at 10:30 a.m. All bids required a proposal guaranty equal to 5% of the bid total. The estimated contract time is 340 calendar days with flexible start provisions allowing work to begin anytime after Notice to Proceed but no later than October 5, 2026. Questions and comments regarding the bid opening were accepted until April 24, 2026, through the ODOT pre-bid email address.

The contract requires compliance with Buy America and Build America, Buy America requirements, as specified in Special Provision 106-5, with all applicable materials, steel, iron products, and manufactured goods required to be produced or manufactured in the United States. The Disadvantaged Business Enterprise (DBE) goal for this proposal is zero. Liquidated damages are assessed based on contract amounts, with daily rates ranging from $300 for contracts under $200,000 to $1,800 for contracts exceeding $10,000,000. An internal milestone provision requires completion of the critical closure phase of SH-152 (Station 654+00 to 709+00) within 150 calendar days at an incentive/disincentive rate of $5,000 per calendar day. The contract includes provisions for fuel price adjustments on applicable earthwork items, with a 3% threshold before adjustments apply. Contractors must perform at least 30% of the contract amount using their own organization, with the remaining 70% allowable for subcontracting. Upon contract award, the successful bidder must execute and return the contract within ten working days, with ODOT completing its execution within fourteen working days. Davis-Bacon prevailing wage requirements apply to all workers on the project, with rates varying by county and trade classification as established in General Decision Number OK20260018.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

BID RIGGING IS A SERIOUS CRIME. IF YOU HAVE ANY INFORMATION CONCERNING COLLUSIVE BIDDING, EVEN A REQUEST TO SUBMIT A COMPLIMENTARY BID, PLEASE CALL THE OKLAHOMA ATTORNEY GENERAL'S OFFICE AT TELEPHONE NO. 405-521-3921.

PROPOSAL 260114

CALL ORDER 700

TO BE LET ON

THURSDAY, MAY 07, 2026 AT 10:30 A.M.

STANDARD PROPOSAL

BIDX WILL BE ACCEPTED.

BECKHAM COUNTY

FEDERAL AID PROJECT

WIDEN, RESURFACE AND BRIDGE

SH-152: FROM THE JUNCTION OF SH-6, EXTEND WEST NEAR SAYRE.

PROJECT LENGTH = 5.859 MILES

STP-205C(121)PM, 34239(04)

BUY AMERICA AND BUILD AMERICA, BUY AMERICA REQUIREMENTS APPLY, HOWEVER,

FOR ANY APPLICABLE WAIVERS PLEASE REVIEW SPECIAL PROVISION 106-5 (8-20-25)

CONTRACT TIME ESTIMATED FOR PROPOSAL IS 340 CALENDAR DAYS

FLEX START - SEE SPECIAL PROVISION 108-23

THE DBE GOAL IS ZERO FOR THIS PROPOSAL.

CREATION OF THIS DOCUMENT WAS ON THURSDAY, APRIL 30, 2026 AT 9:10 AM.

CREATED: 4/30/2026 9:10 AM

S T A T E O F O K L A H O M A D E P A R T M E N T O F T R A N S P O R T A T I O N

Advertisement to Contractors – May 07, 2026 10:30 A.M. Bid Opening

SHEET 1 OF 1

Plans and proposals for this bid opening will be available on April 16, 2026. No bidding proposals will be issued to any Contractor after May 06, 2026 10:30 A.M.. The cost for each bidding proposal is $ 50.00 + tax. State Standard Specifications may be purchased by contacting ODOT Business Services Center Branch (405) 521-4509. No refunds will be made for bidding documents or specification books purchased.

Sample proposals, preliminary plans, long form and short form notices, order forms, bid tabs and awards, can be accessed on ODOT's Web site: https://oklahoma.gov/odot/business-center/contracts-and-proposals.html

Bids must be prepared in accordance with the State Standard Specifications. Unless otherwise specified, bids for all projects must be submitted over the internet to Bid Express(https://www.bidx.com) using AASHTOware Project Bids.

Instructions for using Bid Express, Project Bids, and the electronicbidding process are available from the Office Engineer Division. When written bids are allowed, sealed proposals may be delivered directly to the Office Engineer Division prior to the scheduled bid opening. For written bids, do not disassemble the bidding proposal in any way.

Any firm bidding a project as a joint venture, that has not been previously approved by the department, must complete the ‘Request for Joint Venture’ form, which is posted on the ODOT website, prior to bidding.

Unless otherwise specified in the proposal, all bids must be submitted with a proposal guaranty equal to 5 % of the bid total.

Questions and comments regarding the May 07, 2026 bid opening will be accepted until April 24, 2026. Please submit your questions through the ODOT pre-bid email address: ODOT-Prebid.Question@odot.org. Responses will be posted to the “Pre-bid Questions and Answers” section of the ODOT Contracts & Proposals webpage as they are received. It is recommended that interested contractors visit the “Pre-Bid Questions and Answers” link regularly in order to stay informed of the latest information: https://oklahoma.gov/odot/business-center/contracts-and-proposals.html.

Unless otherwise noted in the proposal, upon award of the contract to the successful bidder, the contract will be completely and correctly executed by the contractor and returned to the Department within ten(10) working days from the date of award. The Department will have fourteen(14) working days from the date of award to complete it's execution of the contract.

The Oklahoma Department of Transportation(ODOT) and the Oklahoma Turnpike Authority(OTA) ensures that no person or groups of persons shall, on the grounds of race, color, sex, religion, national origin,age, disability, retaliation or genetic information, be excluded from participation in, be denied the benefits of, or be otherwise subjected to discrimination underany and all programs, services, or activities administered by ODOT or OTA, their recipients, sub -recipients, and contractors. To request an accommodation please contact the ADA Coordinator at (405)521-4140 or the Oklahoma Relay Service at 1-800-722-0353. If you have any ADA or Title VI questions email ODOT-ada-titlevi@odot.org

Description of work and location of project: Call Order: 700 STP-205C(121)PM SH-152 BECKHAM JP No.34239(04)

WIDEN, RESURFACE AND BRIDGE

SH-152: FROM THE JUNCTION OF SH-6, EXTEND WEST NEAR SAYRE.

STATE OF OKLAHOMA, OKLAHOMA DEPARTMENT OF TRANSPORTATION - By: TIM J. GATZ, Director.

PAGE 1 OF 176PROPOSAL ID : 260114

https://oklahoma.gov/odot/business-center/contracts-and-proposals.html https://www.bidx.com mailto:ODOT-Prebid.Question@odot.org https://oklahoma.gov/odot/business-center/contracts-and-proposals.html mailto:ODOT-ada-titlevi@odot.org mailto:ODOT-ada-titlevi@odot.org

S U M M A R Y O F T I M E

SHEET 1 OF 1

CONTRACT TIME

CONTRACT TIME ESTIMATED FOR PROPOSAL IS 340 CALENDAR DAYS

NOTICE

THE DEPARTMENT WILL CONSIDER A PROPOSAL NONRESPONSIVE AND REJECT IT IN ACCORDANCE

WITH SUBSECTIONS 102.08 AND/OR 102.14 OF THE CURRENT OKLAHOMA DEPARTMENT OF

TRANSPORTATION STANDARD SPECIFICATIONS.

PAGE 2 OF 176PROPOSAL ID : 260114

S U M M A R Y O F I T E M S

SHEET 1 OF 6

LINE ITEM DESCRIPTION APPROX. QTY UNIT PRICE BID AMOUNT

UNITS DOLLARS CTS DOLLARS CTS

SECTION 0001 ROADWAY

0010 201(A)1200

CLEARING AND GRUBBING

1.000 LSUM

0020 202(A)2200

UNCLASSIFIED EXCAVATION

121,463.000 CY

0030 205(A)6200

TYPE A-SALVAGED TOPSOIL

1.000 LSUM

0040 221(B)2300

TEMPORARY SILT FENCE

14,065.000 LF

0050 221(E)2600

TEMPORARY SILT DIKE

1,484.000 LF

0060 230(A)7200

SOLID SLAB SODDING

168,102.000 SY

0070 241 3100

MOWING

105.000 AC

0080 402(E)2600

TRAFFIC BOUND SURFACE COURSE

TYPE E

2,327.000 TON

0090 407(B)7300

TACK COAT

39,695.000 GAL

0100 408 8100

PRIME COAT

49,196.000 GAL

0110 411(B)1330

SUPERPAVE, TYPE S3(PG 64-22 OK)

20,968.000 TON

0120 411(C)1400

SUPERPAVE, TYPE S4(PG 76-28 OK)

15,625.000 TON

0130 411(J)2100

(SP) RICH INTERMEDIATE LAYER

7,794.000 TON

0140 412 3100

COLD MILLING PAVEMENT

81,081.000 SY

0150 501(A)1200

STRUCTURAL EXCAVATION

UNCLASSIFIED

59.000 CY

0160 509(A)0200

CLASS AA CONCRETE

972.000 CY

PAGE 3 OF 176PROPOSAL ID : 260114

SHEET 2 OF 6

UNITS DOLLARS CTS DOLLARS CTS

0170 509(D)0500

CLASS C CONCRETE

2,755.000 CY

0180 511(A)2200

REINFORCING STEEL

136,391.000 LB

0190 601(A)1100

TYPE I PLAIN RIPRAP

1,720.000 TON

0200 601(B)1200

TYPE I PLAIN RIPRAP WITH FILTER

BLANKET

5,002.000 TON

0210 613(A)5216

24" R.C.PIPE CLASS III

178.000 LF

0220 613(A)5350

22" X 13" R.C.PIPE ARCH CLASS A-III

112.000 LF

0230 613(B)5536

48" CORR. GALV. STEEL PIPE

140.000 LF

0240 613(B)5604

21" X 15" CORR. GALV. STEEL PIPE

ARCH

1,806.000 LF

0250 613(B)5612

28" X 20" CORR. GALV. STEEL PIPE

ARCH

294.000 LF

0260 613(M)6960

TYPE A4 CULVERT END TREATMENT

9.000 EA

0270 613(M)6964

TYPE B4 CULVERT END TREATMENT

6.000 EA

0280 613(M)6980

TYPE AA4 CULVERT END TREATMENT

14.000 EA

0290 613(M)6984

TYPE BB4 CULVERT END TREATMENT

3.000 EA

0300 613(M)6996

TYPE EE4 CULVERT END TREATMENT

1.000 EA

0310 613(M)7004

TYPE A6 CULVERT END TREATMENT

9.000 EA

0320 613(M)7008

TYPE B6 CULVERT END TREATMENT

4.000 EA

PAGE 4 OF 176PROPOSAL ID : 260114

SHEET 3 OF 6

UNITS DOLLARS CTS DOLLARS CTS

0330 613(M)7024

TYPE AA6 CULVERT END TREATMENT

14.000 EA

0340 613(M)7028

TYPE BB6 CULVERT END TREATMENT

1.000 EA

0350 613(M)7040

TYPE EE6 CULVERT END TREATMENT

1.000 EA

0360 619(A)6200

REMOVAL OF STRUCTURES &

OBSTRUCTIONS

1.000 LSUM

0370 619(B)6352

REMOVAL OF FENCE

41,867.000 LF

0380 619(B)6364

REMOVAL OF ASPHALT PAVEMENT

15,333.000 SY

0390 619(B)6384

REMOVAL OF ASPHALT DRIVEWAY

1,055.000 SY

0400 624 3100

(PL) ORNAMENTAL FENCE

259.000 LF

0410 624(C)3410

FENCE-STYLE SWF (6 BARBED WIRE)

42,447.000 LF

0420 629(D)7500

REMOVE AND RESET MAILBOX

2.000 EA

SECTION 0001 SUB TOTAL

SECTION 0002 BRIDGE 'A'

0430 501(A)1210

STRUCTURAL EXCAVATION

UNCLASSIFIED

305.000 CY

0440 509(A)0210

CLASS AA CONCRETE

493.500 CY

0450 511(A)2210

REINFORCING STEEL

66,775.000 LB

0460 619(D)6700

REMOVAL OF EXISTING BRIDGE

STRUCTURE

1.000 LSUM

SECTION 0002 SUB TOTAL

PAGE 5 OF 176PROPOSAL ID : 260114

SHEET 4 OF 6

UNITS DOLLARS CTS DOLLARS CTS

SECTION 0003 BRIDGE 'B'

0470 501(A)1210

STRUCTURAL EXCAVATION

UNCLASSIFIED

215.000 CY

0480 502 3100

TEMPORARY EARTH RETAINAGE

1.000 LSUM

0490 509(A)0210

CLASS AA CONCRETE

353.300 CY

0500 511(A)2210

REINFORCING STEEL

46,300.000 LB

0510 619(B)6304

REMOVAL OF BRIDGE ITEMS

1.000 LSUM

SECTION 0003 SUB TOTAL

SECTION 0004 TRAFFIC CONTROL

0520 823 6100

(SP)PORTABLE TRAFFIC SIGNAL

SYSTEM

960.000 SD

0530 857(A)9205

CONSTRUCTION TRAFFIC

STR.(PAINT)(6" WIDE)

422,188.000 LF

0540 857(F)9700

PAVEMENT

MRKNG.REMOVAL(TRAF.STRP)

109,616.000 LF

0550 858(A)0212

PAVE.MARKERS CLASS A TYPE 2

10,873.000 EA

0560 858(A)0284

PAVE.MARKERS CLASS D TYPE 2

10,873.000 EA

0570 880(B)6300

CONSTRUCTION SIGNS 0 TO 6.25 SF

16,560.000 SD

0580 880(B)6310

CONSTRUCTION SIGNS 6.26 SF TO 15.99

SF

4,000.000 SD

PAGE 6 OF 176PROPOSAL ID : 260114

SHEET 5 OF 6

UNITS DOLLARS CTS DOLLARS CTS

0590 880(B)6320

CONSTRUCTION SIGNS 16.0 SF TO 32.99

SF

5,980.000 SD

0600 880(C)6410

CONSTRUCTION BARRICADES(TYPE III)

7,760.000 SD

0610 880(E)6607

WARNING LIGHTS(TYPE B)

4,820.000 SD

0620 880(E)6610

WARNING LIGHTS(TYPE C)

13,720.000 SD

0630 880(F)6700

DRUMS

13,720.000 SD

0640 882(A)8210

PORT.CHANGEABLE MESSAGE SIGN

2,866.000 SD

SECTION 0004 SUB TOTAL

SECTION 0005 TRAFFIC SIGNING AND STRIPING

0650 413(A)4200

RUMBLE STRIP-METHOD HMA-CON

61,400.000 LF

0660 413(A)4210

RUMBLE STRIP-CENTERLINE HMA-CON

30,675.000 LF

0670 850(A)1200

SHEET ALUMINUM SIGNS

261.000 SF

0680 851(C)2430

2 1/2" SQUARE TUBE POST

342.000 LF

0690 856(A)8207

(SP) TRAFFIC STRIPE(PLURAL-

COMPONENT)(6" WIDE)

117,325.000 LF

0700 856(A)8215

(SP) TRAFFIC STRIPE(PLURAL-

COMPONENT)(12" WIDE)

730.000 LF

0710 856(A)8219

(SP) TRAFFIC STRIPE(PLURAL-

COMPONENT)(24" WIDE)

24.000 LF

SECTION 0005 SUB TOTAL

PAGE 7 OF 176PROPOSAL ID : 260114

SHEET 6 OF 6

UNITS DOLLARS CTS DOLLARS CTS

SECTION 0006 STAKING

0720 642(B)3300

CONSTRUCTION STAKING LEVEL II

1.000 LSUM

SECTION 0006 SUB TOTAL

SECTION 0007 CONSTRUCTION

0730 220 1100

SWPPP DOCUMENTATION AND

MANAGEMENT

1.000 LSUM

0740 641 2110

MOBILIZATION

1.000 LSUM

SECTION 0007 SUB TOTAL

TOTAL

PAGE 8 OF 176PROPOSAL ID : 260114

D E P A R T M E N T O F T R A N S P O R T A T I O N

I N D E X O F P R O V I S I O N S FOR JPN(s) : STP-205C(121)PM, 34239(04)

BECKHAM COUNTY

SHEET 1 OF 2

PROPOSAL DOCUMENTS

OK20260018 WAGE DECISION

PROPOSAL PROVISIONS

102-013(a-b)19 BIDDING PROCEDURES 103-003(a)19 SUBCONTRACTS 104-004(a-b)19 UTILITY PROPERTY AND SERVICES 106-005(a-e)19 BUY AMERICA AND BUILD AMERICA, BUY AMERICA 108-023(a)19 FLEXIBLE NOTICE TO PROCEED 108-080(a)19 LIQUIDATED DAMAGES 108-081(a)19 DISINCENTIVE FOR EXPOSED COLD-MILLED PAVEMENT 108-182(a)19 SUBLETTING OF CONTRACT (70%) 108-415(a)19 INTERNAL MILESTONE 109-003(a-c)19 PRICE ADJUSTMENT FOR FUEL 109-014(a)19 MATERIAL ON HAND 109-015(a-c)19 PROMPT PAYMENT FOR SUBCONTRACTORS 411-015(a-f)19 RICH INTERMEDIATE LAYER (RIL) 411-025(a)19 HOT MIX ASPHALT/WARM MIX ASPHALT 430-2QA(a-j)19 PAVEMENT AND BRIDGE DECK SMOOTHNESS 430-4QA(a-j)19 PAVEMENT AND BRIDGE DECK SMOOTHNESS USING IRI 441-001(a-c)19 ELECTRONIC TICKETING FOR BITUMINOUS MATERIALS 703-001(a-b)19 RECYCLED CONCRETE AGGREGATE 708-024(a-b)19 PERFORMANCE-GRADED ASPHALT BINDER USING MULTIPLE STRESS

CREEP RECOVERY (MSCR) TEST

711-003(a-h)19 TRAFFIC STRIPE 823-001(a)19 TEMPORARY TRAFFIC SIGNALS 856-003(a-j)19 TRAFFIC STRIPE (PLURAL-COMPONENT)

CORPS OF ENGINEERS PERMIT

CF000050 REPORTING OF BID RIGGING

CF000101 TITLE VI - NON-DISCRIMINATION CLAUSE

CF000200 RESIDENCE REQUIREMENTS FOR LABOR ON FEDERAL AID PROJECTS

PROJECTS

CF000501 CERTIFICATION FOR FEDERAL-AID CONTRACTS

CF000800 NOTICE OF REQUIREMENTS FOR AFFIRMATIVE ACTION

CF000900 STANDARD FEDERAL EQUAL EMPLOYMENT OPPORTUNITY

SPECIFICATIONS

CF001000 ON-THE-JOB TRAINING (OJT) PROGRAM

CF001700 CONTRACTORS AFFIDAVIT

CX00210B DISADVANTAGED BUSINESS ENTERPRISE PROGRAM

CZ002300 CONTRACT DISPUTE RESOLUTION PROCEDURE

CZ002850 NO.2 PROPOSAL SHEET

CZ002975 * BIDDER'S AFFIDAVIT - STATEMENT UNDER PENALTY OF PERJURY

FHWA1273 REQUIRED CONTRACT PROVISIONS FEDERAL-AID CONSTRUCTION

CONTRACTS

PAGE 9 OF 176PROPOSAL ID : 260114

D E P A R T M E N T O F T R A N S P O R T A T I O N

I N D E X O F P R O V I S I O N S FOR JPN(s) : STP-205C(121)PM, 34239(04)

BECKHAM COUNTY

SHEET 2 OF 2

PAGE 10 OF 176PROPOSAL ID : 260114

"General Decision Number: OK20260018 01/02/2026

Superseded General Decision Number: OK20250018

State: Oklahoma

Construction Type: Highway

Counties: Beckham, Caddo, Cotton, Custer, Greer, Harmon, Jackson, Jefferson, Kiowa, Roger Mills, Stephens, Tillman and Washita Counties in Oklahoma.

HIGHWAY CONSTRUCTION PROJECTS (excluding tunnels, building structures in rest area projects & railroad construction;

bascule, suspension & spandrel arch bridges designed for commercial navigation, bridges involving marine construction;

and other major bridges).

Modification Number Publication Date 0 01/02/2026

SUOK2011‐005 04/18/2011

Rates Fringes

CARPENTER (Excludes Form Work) Caddo County................$ 12.18 Custer County...............$ 12.39 Remaining Counties..........$ 12.57

CEMENT MASON/CONCRETE FINISHER

Caddo County................$ 11.04 Custer County...............$ 13.38 Remaining Counties..........$ 12.53 Washita County..............$ 12.95

FORM WORKER

Remaining Counties..........$ 11.46 Washita County..............$ 11.13

GUARDRAIL INSTALLER (Includes Guardrail/Post Driver Work)......$ 9.70

IRONWORKER, REINFORCING..........$ 13.63

LABORER

Air/Power Tool Operator (Includes Handheld

PAGE 11 OF 176PROPOSAL ID : 260114

Concrete Saws and Chipping Guns).......................$ 12.79 Asphalt Raker and Shoveler..$ 10.49 Common or General Beckham County.............$ 10.47 Caddo County...............$ 10.30 Custer County..............$ 10.60 Greer County...............$ 10.05 Jefferson County...........$ 10.07 Kiowa County...............$ 9.54 Remaining Counties.........$ 10.29 Roger Mills County.........$ 10.08 Stephens County............$ 10.31 Washita County.............$ 10.27 Pipelayer...................$ 11.83 Traffic Control (Includes Flagger, Setting Up and Moving Cones/Barrels).......$ 10.39 Vibrating Plate.............$ 12.70

POWER EQUIPMENT OPERATOR:

Asphalt Paver Screed........$ 13.19 Asphalt Paving Machine......$ 12.32 Asphalt Plant...............$ 14.70 Backhoe/Trackhoe Caddo County...............$ 13.46 Remaining Counties.........$ 13.71 Bobcat/Skid Loader..........$ 12.06 Broom.......................$ 11.02 Bulldozer...................$ 13.69 Concrete Paving Machine.....$ 14.42 Concrete Saw................$ 12.46 Crane.......................$ 16.61 Distributor Truck...........$ 12.24 Excavator...................$ 15.45 Grader/Blade Caddo County...............$ 13.18 Remaining Counties.........$ 13.30 Loader (Front End)..........$ 12.21 Mechanic....................$ 16.89 Milling Machine.............$ 11.81 Mixer.......................$ 14.56 Oiler.......................$ 13.84 Roller (Asphalt) Caddo County...............$ 12.73 Remaining Counties.........$ 12.61 Roller (Dirt Compaction)....$ 10.22 Rotomill....................$ 17.33 Scraper.....................$ 12.82 Striping Machine............$ 12.11

PAGE 12 OF 176PROPOSAL ID : 260114

Tractor/Box Blade...........$ 9.79 Transfer Material Machine...$ 12.38 0.75 Trencher....................$ 14.66

TRUCK DRIVER

Concrete Truck..............$ 14.22 Dump Truck..................$ 12.84 Flatbed Truck...............$ 15.30 Lowboy/Float................$ 16.02 Off the Road Truck..........$ 11.84 Single Axle Truck (Includes Pilot Car)........$ 12.30 Straight Truck..............$ 15.92 Tandem Axle/Semi Trailer....$ 13.53 Water Truck.................$ 12.00

WELDERS ‐ Receive rate prescribed for craft performing operation to which welding is incidental.

Note: Executive Order (EO) 13706, Establishing Paid Sick Leave for Federal Contractors applies to all contracts subject to the Davis‐Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2017. If this contract is covered by the EO, the contractor must provide employees with 1 hour of paid sick leave for every 30 hours they work, up to 56 hours of paid sick leave each year.

Employees must be permitted to use paid sick leave for their own illness, injury or other health‐related needs, including preventive care; to assist a family member (or person who is like family to the employee) who is ill, injured, or has other health‐related needs, including preventive care; or for reasons resulting from, or to assist a family member (or person who is like family to the employee) who is a victim of, domestic violence, sexual assault, or stalking. Additional information on contractor requirements and worker protections under the EO is available at https://www.dol.gov/agencies/whd/government‐contracts.

Note: Executive Order 13658 generally applies to contracts subject to the Davis‐Bacon Act that were awarded on or between January 1, 2015 and January 29, 2022, and that have not been renewed or extended on or after January 30, 2022. Executive Order 13658 does not apply to contracts subject only to the Davis‐Bacon Related Acts regardless of when they were awarded.

If a contract is subject to Executive Order 13658, the contractor must pay all covered workers at least $13.30 per hour (or the applicable wage rate listed on this wage

PAGE 13 OF 176PROPOSAL ID : 260114

determination, if it is higher) for all hours spent performing on the contract in 2025. The applicable Executive Order minimum wage rate will be adjusted annually. Additional information on contractor requirements and worker protections under Executive Order 13658 is available at www.dol.gov/whd/govcontracts.

Unlisted classifications needed for work not included within the scope of the classifications listed may be added after award only as provided in the labor standards contract clauses (29CFR 5.5 (a) (1) (iii)).

The body of each wage determination lists the classifications and wage rates that have been found to be prevailing for the type(s) of construction and geographic area covered by the wage determination. The classifications are listed in alphabetical order under rate identifiers indicating whether the particular rate is a union rate (current union negotiated rate), a survey rate, a weighted union average rate, a state adopted rate, or a supplemental classification rate.

Union Rate Identifiers

A four‐letter identifier beginning with characters other than ""SU"", ""UAVG"", "SA", or "SC" denotes that a union rate was prevailing for that classification in the survey. Example:

PLUM0198‐005 07/01/2024. PLUM is an identifier of the union whose collectively bargained rate prevailed in the survey for this classification, which in this example would be Plumbers.

0198 indicates the local union number or district council number where applicable, i.e., Plumbers Local 0198. The next number, 005 in the example, is an internal number used in processing the wage determination. The date, 07/01/2024 in the example, is the effective date of the most current negotiated rate.

Union prevailing wage rates are updated to reflect all changes over time that are reported to WHD in the rates in the collective bargaining agreement (CBA) governing the classification.

Union Average Rate Identifiers

The UAVG identifier indicates that no single rate prevailed for those classifications, but that 100% of the data reported for the classifications reflected union rates. EXAMPLE:

UAVG‐OH‐0010 01/01/2024. UAVG indicates that the rate is a

PAGE 14 OF 176PROPOSAL ID : 260114

weighted union average rate. OH indicates the State of Ohio.

The next number, 0010 in the example, is an internal number used in producing the wage determination. The date, 01/01/2024 in the example, indicates the date the wage determination was updated to reflect the most current union average rate.

A UAVG rate will be updated once a year, usually in January, to reflect a weighted average of the current rates in the collective bargaining agreements on which the rate is based.

Survey Rate Identifiers

The ""SU"" identifier indicates that either a single non‐union rate prevailed (as defined in 29 CFR 1.2) for this classification in the survey or that the rate was derived by computing a weighted average rate based on all the rates reported in the survey for that classification. As a weighted average rate includes all rates reported in the survey, it may include both union and non‐union rates. Example: SUFL2022‐007 6/27/2024. SU indicates the rate is a single non‐union prevailing rate or a weighted average of survey data for that classification. FL indicates the State of Florida. 2022 is the year of the survey on which these classifications and rates are based. The next number, 007 in the example, is an internal number used in producing the wage determination. The date, 6/27/2024 in the example, indicates the survey completion date for the classifications and rates under that identifier.

"SU" wage rates typically remain in effect until a new survey is conducted. However, the Wage and Hour Division (WHD) has the discretion to update such rates under 29 CFR 1.6(c)(1).

State Adopted Rate Identifiers

The ""SA"" identifier indicates that the classifications and prevailing wage rates set by a state (or local) government were adopted under 29 C.F.R 1.3(g)‐(h). Example: SAME2023‐007 01/03/2024. SA reflects that the rates are state adopted. ME refers to the State of Maine. 2023 is the year during which the state completed the survey on which the listed classifications and rates are based. The next number, 007 in the example, is an internal number used in producing the wage determination.

The date, 01/03/2024 in the example, reflects the date on which the classifications and rates under the "SA" identifier took effect under state law in the state from which the rates were adopted.

WAGE DETERMINATION APPEALS PROCESS

PAGE 15 OF 176PROPOSAL ID : 260114

1) Has there been an initial decision in the matter? This can be:

a) a survey underlying a wage determination

b) an existing published wage determination

c) an initial WHD letter setting forth a position on a wage determination matter

d) an initial conformance (additional classification and rate) determination

On survey related matters, initial contact, including requests for summaries of surveys, should be directed to the WHD Branch of Wage Surveys. Requests can be submitted via email to davisbaconinfo@dol.gov or by mail to:

Branch of Wage Surveys Wage and Hour Division U.S. Department of Labor 200 Constitution Avenue, N.W.

Washington, DC 20210

Regarding any other wage determination matter such as conformance decisions, requests for initial decisions should be directed to the WHD Branch of Construction Wage Determinations.

Requests can be submitted via email to BCWD‐Office@dol.gov or by mail to:

Branch of Construction Wage Determinations Wage and Hour Division U.S. Department of Labor 200 Constitution Avenue, N.W.

Washington, DC 20210

2) If an initial decision has been issued, then any interested party (those affected by the action) that disagrees with the decision can request review and reconsideration from the Wage and Hour Administrator (See 29 CFR Part 1.8 and 29 CFR Part 7).

Requests for review and reconsideration can be submitted via email to dba.reconsideration@dol.gov or by mail to:

Wage and Hour Administrator U.S. Department of Labor 200 Constitution Avenue, N.W.

Washington, DC 20210

The request should be accompanied by a full statement of the interested party's position and any information (wage payment data, project description, area practice material, etc.) that the requestor considers relevant to the issue.

PAGE 16 OF 176PROPOSAL ID : 260114

3) If the decision of the Administrator is not favorable, an interested party may appeal directly to the Administrative Review Board (formerly the Wage Appeals Board). Write to:

Administrative Review Board U.S. Department of Labor 200 Constitution Avenue, N.W.

Washington, DC 20210.

END OF GENERAL DECISION

PAGE 17 OF 176PROPOSAL ID : 260114

102-13(a-b)19 11/20/2020

OKLAHOMA DEPARTMENT OF TRANSPORTATION

SPECIAL PROVISION

FOR

BIDDING PROCEDURES

These special provisions amend and where in conflict, supersede applicable sections of the 2019 Standard Specifications for Highway Construction, English and Metric.

102.07 PREPARATION OF PROPOSAL (Revise to amend as follows:)

Submit the Proposal in the format required by the Bid Notice. For each item on the Proposal Forms, type or write (in ink) the unit price and the product of the unit price and estimated quantity on the Proposal Forms in the space provided. Show the total Proposal amount by adding the products of the unit prices and the estimated quantities. Acknowledge any change to a unit price, the product of a unit price and quantity, or the total Proposal amount with the initials of the person signing the Proposal, adjacent to each change.

If a discrepancy occurs on the Proposal, between the unit price and the product of the unit price and quantity, the Department will use the unit price. If a unit price or the product of a unit price and quantity is omitted or is entered as zero ($0) for any item listed on the Proposal Forms, the Department will consider the Proposal non-responsive and will reject the Proposal. If there is a discrepancy between the submitted electronic media and written Proposal, the Department will use the written Proposal. If the Department requires a printout of electronic media and a discrepancy occurs between the printout and the electronic media, the Department will use the printout.

An individual, all members of a partnership, a duly authorized officer of a corporation, or all members of a joint venture shall sign the Proposal in black or blue ink. For Proposals submitted by a corporation, show the name of the corporation and business address. For Proposals submitted by the internet bidding process, the Department will require an electronic signature only. Include a Non-Collusive Bidding Certification with the Proposal in accordance with Subsection 102.16, “Non- Collusive Bidding Certification.”

102.08 NONRESPONSIVE PROPOSALS (Revise to amend as follows:)

The Department will consider a proposal nonresponsive and may reject it for any of the following reasons:

• The bidder submits a Proposal on an unapproved form (or format, if computer-generated), or the form is altered, incomplete, or disassembled.

• The bidder submits a Proposal using a form other than the latest approved Proposal Form.

• The Department determines that Proposal irregularities (such as unauthorized additions and

PAGE 18 OF 176PROPOSAL ID : 260114

102-13(b-b)19 11/20/2020 conditional or alternate bids) may tend to make the Proposal incomplete, indefinite, or ambiguous.

• The Proposal does not contain a unit price for each item listed, except for authorized alternate items.

• The Proposal is materially unbalanced in accordance with Subsection 101.05.CT.2

• The Proposal is not properly signed.

• The Proposal is not typed or completed in ink.

• The bidder fails to provide a properly executed Proposal Guaranty, or irrevocable Letter of

Credit.

• The bidder fails to sign the unsworn statement made under penalty of perjury.

• The Proposal fails to comply with any material requirement of the Bid Notice.

• The bidder fails to properly comply with Disadvantaged Business Enterprise Requirements or to properly list eligible disadvantaged businesses if participation in accordance with the Proposal Forms.

PAGE 19 OF 176PROPOSAL ID : 260114

103-3(a) 19

6-8-20

OKLAHOMA DEPARTMENT OF TRANSPORTATION

SPECIAL PROVISIONS

FOR

SUBCONTRACTS

These Special Provisions revise, amend, and where in conflict, supersede applicable sections of the 2019

Standard Specifications for Highway Construction.

(Add the following:)

103.10 SUBCONTRACTS

Subcontracts and/or sub-agreements must be submitted for review and approval by the Department prior to the subcontractor performing contract work. Ensure all subcontracts conform to the requirements of

Subsection 108.01, “Subletting of Contract,” and are executed in accordance with the Contract requirements and the provisions specified herein.

As a minimum, the following information must be included in all subcontracts:

• Full description of the contract work to be performed by the subcontractor

• Contractor Equal Employment Opportunity (EEO) Policy Statement (see ODOT General Contractor

Requirements – Development and Dissemination of EEO Policy)

• Form FHWA-1273 (must be physically attached verbatim to subcontracts, excluding purchase orders, rental agreements and other agreements for supplies or services)

• ODOT Title VI Assurances Appendices A and E (must be physically attached verbatim)

• Prompt Payment/Return of Retainage provisions (from the ODOT DBE Program Manual)

• Signature(s) of the prime contractor and subcontractor

If the subcontract is with a subcontractor performing work as an ODOT certified DBE, then the following additional information must be included in the submitted subcontract:

• Full description of the contract work that the certified DBE will perform based upon their NAICS code

• DBE Termination/Substitution/Replacement Clause (from the ODOT DBE Program Manual)

The aforementioned subcontract documents can be downloaded from the ODOT website, and are available for the Contractors’ use: http://www.odot.org/subcontracts.

Purchase orders, rental agreements and other agreements for supplies or services related to a construction contract are excluded from this requirement only if the purchase order or other agreement is not with a DBE.

However, Prompt Payment/Return of Retainage provisions must still be included.

Submit executed subcontracts and/or sub-agreements in pdf format to the Department using the following email address: constructionsubcontracts@odot.org. Submit all additional and/or modified subcontracts or sub-agreements to the Department via the same email address. To prevent delays in the approval of the subcontract, include the following information in all correspondence: contract I.D., project number, prime contractor, and subcontractor.

Subcontracts and sub-agreements may be submitted prior to the receipt of the signed Contract by the

Department.

PAGE 20 OF 176PROPOSAL ID : 260114

https://www.ok.gov/odot/Doing_Business/Civil_Rights/Contractor_Compliance_-_Construction.html mailto:

104-4(a-b) 19 3-24-26

OKLAHOMA DEPARTMENT OF TRANSPORTATION

SPECIAL PROVISIONS

FOR

UTILITY PROPERTY AND SERVICES

STP-205C(121)PM, JP NO. 34239(04), BECKHAM COUNTY

These Special Provisions revise, amend, and where conflict, supersede applicable Sections of the 2019 Sta.ndard Specifications for Highway Construction.

(Add the following:)

104.19 UTILITY RELOCATION INFORMATION

Utility facilities will be removed, relocated, adjusted and/or abandoned in place in accordance with separate agreements between the Department and the respective utility owners at the herein designated locations.

The Contractor is forewarned that a portion of such work will be under way concurrently with the Contractor's work under this Contract.

The following utility forces will be working within the construction limits covered by this Contract:

1. OWNER: KINDER MORGAN

UTILITY INVOLVED AND LOCATION: There is a 16” and 26” gas line crossing within the extent of the project.

PROPOSED REARRANGEMENTS: The crossings will need the casings and vents extended.

REMARKS: Based on available information at this time, it is anticipated that relocations can be completed by May 15, 2026.

2. OWNER: ENERGY TRANSFER

UTILITY INVOLVED AND LOCATION: There is a 6” gas line crossing within the extent of the project.

PROPOSED REARRANGEMENTS: The facility conflicts with the new drainage structure and riprap. The new crossing will need to be relocated to Sta. 530+66 and have a minimum depth of 30” below the finished grade.

REMARKS: Based on available information at this time, it is anticipated that relocations can be completed May 15, 2026.

3. OWNER: SPARKLIGHT

UTILITY INVOLVED AND LOCATION: There is an underground 12 strand fiber optic line crossing at 501+55.

PAGE 21 OF 176PROPOSAL ID : 260114

104-4(b-b) 19 3-24-26

PROPOSED REARRANGEMENTS: The fiber optic line will need to be relocated to 502+17 with a minimum depth of 30” below finished grade.

REMARKS: Based on available information at this time, it is anticipated that relocations can be completed by May 15, 2026.

PAGE 22 OF 176PROPOSAL ID : 260114

106-5(a-e) 19 8-20-25

OKLAHOMA DEPARTMENT OF TRANSPORTATION

SPECIAL PROVISIONS

FOR

BUY AMERICA AND BUILD AMERICA, BUY AMERICA

These Special Provisions revise, amend, and where in conflict, supersede applicable sections of the 2019 Standard Specifications for Highway Construction.

106.01 SOURCE OF SUPPLY AND QUALITY REQUIREMENTS (Replace with the following :)

B. Buy America and Build America, Buy America

Buy America (BA) and Build America, Buy America (BABA) requirements are in effect only on projects with federal aid risk, as identified in the contract documents. The Contractor is responsible for submitting completed Material Data Testing (MDT-1) form in accordance with Section 106.01(B)(1) regardless of the BA/BABA requirements.

An article, material, or supply should only be classified into one of the following categories: (1) iron or steel products, (2) construction material, (3) manufactured products, or (4) excluded material. An article, material, or supply should not be considered to fall into multiple categories, except as otherwise provided in Subsection 106.01.B(4)(b)(2). A material is solely classified based on its status at the time it is brought to the worksite.

Except as otherwise provided in Subsection 106.01.B(4)(b)(2) of this special provision, an article, material, or supply shall not be considered to fall into multiple categories. In some cases, an article, material, or supply may not fall under any of the above-listed categories. The classification of an article, material, or supply as falling into one of the categories listed in this paragraph must be made based on its status at the time it is brought to the work site for incorporation into an infrastructure project. In general, the work site is the location of the infrastructure project at which the iron or steel product or manufactured product will be incorporated.

(1) Iron and/or Steel Products

Comply with the Buy America provisions of 23 CFR 635.410 which states that all manufacturing processes, including the application of a coating, for all steel or iron products permanently incorporated into the project shall have occurred in the United States (U.S.).

“All manufacturing processes” are defined as any process required to change the raw ore or scrap metal into the finished steel or iron product (e.g. smelting, rolling, extruding, bending, etc.).

“Coating” is defined as any process which protects or enhances the value of the steel or iron product to which the coating is applied (e.g. epoxy, galvanizing, painting, etc.).

The Contractor is responsible for submitting completed Material Testing Data (MDT-1) for the iron and steel in following items for all projects, regardless of the BA/BABA requirements:

• Precast box culverts

• Reinforced concrete pipe and precast end sections

• Precast inlets and catch basins

• Precast manholes

• Structural steel (girders, diaphragms, anchor bolts, high-strength bolts, sealed expansion joints, etc.)

• Reinforcing steel (all types)

• Welded wire fabric

• Steel spiral wire (drilled shaft cages, bridge rail, etc.)

• Steel piling

PAGE 23 OF 176PROPOSAL ID : 260114

106-5(b-e) 19

• Drill shaft casing (permanent)

• Dowel bars and baskets for paving

• Steel sheet piling (permanent)

• Bridge bearing assemblies (fixed and expansion)

• Post-tensioning steel (strands, wedges, anchor plates, etc.)

• Steel monotube structures

• Galvanized steel supports for overhead and cantilevered sign structures

• Sign posts and bases (all sizes)

• Guardrail, guardrail posts, end sections, terminals, impact attenuators

• Intelligent transportation system or other electronic hardware system cabinets

(2) Waiver for Iron and Steel Raw Materials

The BA/BABA requirements for the following raw materials are waived in accordance with the FHWA nationwide waiver (dated March 24, 1995) for pig iron and processed, pelletized, and reduced iron ore, unless processed or refined to include substantial amounts of steel or iron material, and may be used regardless of source in the domestic manufacturing process for steel or iron material:

• Raw materials (iron ore or alloys)

• Scrap

• Pig iron

• Processed, pelletized, and reduced iron ore material

For recycled steel, only the manufacturing processes to produce steel products must occur domestically, beginning at the point where the recycled steel is melted.

(3) Minimal Use Request for Steel and Iron

Federal regulations allow a minimal use of foreign steel or iron if the cost of the steel and iron products as they are delivered to the project does not exceed 0.1 percent of the total Contract amount, or $2,500, whichever is greater. This threshold applies to the cumulative amount of all foreign steel and iron used on the project. The Contractor must track the amount of incorporated foreign steel and iron throughout the life of a project to ensure the minimal use threshold amount is not exceeded.

(4) Construction Materials

Comply with the Build America, Buy America (BABA) Act of 2 CFR 184. The following construction materials as defined in 2 CFR 184.3 must be manufactured in the United States of America. This means that all manufacturing processes for the construction material occurred in the United States of America.

• Non-ferrous metals

• Plastic and polymer-based products (including polyvinylchloride, composite building materials, and polymers used in fiber optic cables)

• Glass (including optic glass)

• Fiber optic cable (including drop cable)

• Optical fiber

• Lumber

• Engineered wood

• Drywall

For non-ferrous metals, certification requires all manufacturing processes, from initial smelting or melting through final shaping, coating, and assembly, occurred in the United States.

PAGE 24 OF 176PROPOSAL ID : 260114

106-5(c-e) 19

For plastic and polymer-based products, certification requires all manufacturing processes, from initial combination of constituent plastic or polymer-based inputs, or, where applicable, constituent composite materials, until the item is in its final form, occurred in the United States.

For glass, certification requires all manufacturing processes, from initial batching and melting of raw materials through annealing, cooling, and cutting, occurred in the United States.

For fiber optic cable (including drop cable), certification requires all manufacturing processes, from the initial ribboning (if applicable), through buffering, fiber stranding and jacketing, occurred in the United States. All manufacturing processes also include the standards for glass and optical fiber, but not for non-ferrous metals, plastic and polymer-based products, or any others.

For optical fiber, certification requires all manufacturing processes, from the initial preform fabrication stage through the completion of the draw, occurred in the United States.

For lumber, certification requires all manufacturing processes, from initial debarking through treatment and planning, occurred in the United States.

For engineered wood, certification requires all manufacturing processes from the initial combination of constituent materials until the wood product is in its final form, occurred in the United States.

For drywall, certification requires all manufacturing processes, from initial blending of mined or synthetic gypsum plaster and additives through cutting and drying of sandwiched panels, occurred in the United States.

(5) Manufactured Products

Manufactured products used and permanently incorporated in this project must be produced in the United States. Manufactured products will comply with the Buy America requirements of 23 CFR 635.410 with the following modifications:

(a) Produced in the United States, in the case of manufactured products, means the product was manufactured in the United States. FHWA further clarifies that this means the final assembly must occur in the United States.

(b) Classification of Precast Concrete Products and Electronics Cabinets

(1) With respect to precast concrete products that are classified as manufactured products, components of precast concrete products that consist wholly or predominantly of iron or steel, or a combination of both, shall also meet the requirements of Subsection 106.01.B(1), “Iron and/or Steel Products.” The cost of such components shall be included in the applicable calculation for purposes of determining whether the precast concrete product is produced in the United States.

(2) With respect to intelligent transportation systems and other electronic hardware systems that are installed in the highway right of way or other real property and classified as manufactured products, the cabinets or other enclosures of such systems that consist wholly or predominantly of iron or steel, or a combination of both, shall also meet the requirements of Subsection 106.01.B(1), “Iron and/or Steel Products.” The cost of cabinets or other enclosures shall be included in the applicable calculation for purposes of determining whether systems referred to in the preceding sentence are produced in the United States.

PAGE 25 OF 176PROPOSAL ID : 260114

106-5(d-e) 19

(6) Application of BA/BABA Requirements

BA/BABA requirements only apply to steel, iron, construction materials and manufactured products that are consumed in, incorporated into, or affixed to an infrastructure project. As such, it does not apply to tools, equipment, and supplies, such as temporary scaffolding, removed at or before completion of the project. BA/BABA does not apply to equipment and furnishings, such as movable chairs, desks, and portable computer equipment, that are used at or within the finished project, but are not an integral part of or permanently affixed to the structure.

(7) USDOT de Minimis Costs and Small Grant Waiver for Construction Materials and Manufactured Products

If the total value of the non-compliant construction materials and manufactured products is no more than the lesser of $1,000,000 or 5% of total applicable project costs, BA/BABA does not apply for those products. Iron and steel are still subject to minimal use in accordance with 23 CFR 635.410(b)(4) and 106.01.B(3), “Minimal Use Request for Steel and Iron.” The total applicable project costs are defined as the cost of all materials, including iron, steel, manufactured products, and construction materials subject to BA/BABA requirements. The Contractor assumes the responsibility of tracking the costs of the materials and providing the certification for the waiver if applicable.

For projects identified by the Department as small grants with federal awards less than $500,000, BA/BABA requirement is waived for all materials.

(8) Compliance with BA/BABA Requirements

The Contractor assumes the risk of including any foreign materials including iron, steel, construction materials, and manufactured products that are not exempt in the Contractor's bid.

The Contractor has the obligation to remove and replace non-Buy America complaint material that exceeds minimal threshold, unless a waiver is granted for the use. No claims for contract adjustment (additional time, money, or both) will be made because of the non-complaint material.

After work is completed on the project, submit a list of items in compliance with the Buy America (BA) Act and the Build America, Buy America (BABA) Act. The list shall include all materials permanently incorporated into the project, with a designation indicating whether the item is an iron or steel product, a construction material, a manufactured product, or an excluded other product. In addition to the list, submit a notarized or electronically verified certification signed by the Contractor's authorized agent to the Engineer, with the following information:

“I hereby certify that all construction materials furnished to the Oklahoma Department of Transportation for the construction of the above referenced project that are required to be compliant with the the Build America, Buy America (BABA) Act provision of 2 CFR 184 have been manufactured in the United States of America. I further certify that all supporting documentation is on file and will be maintained for a period of three (3) years after project completion.”

“I also hereby certify that all manufacturing processes of all steel and iron products permanently incorporated into this Oklahoma Department of Transportation referenced project, including protective coating, occurred in the USA and are in accordance with 23 CFR 635.410.”

"I also hereby certify that all manufactured products permanently incorporated into this Oklahoma Department of Transportation reference project were produced in the United States of America, in accordance with 23 CFR Part 635.410( c). I further certify that all supporting documentation is on file and will be maintained for a period of three (3) years after project completion.”

PAGE 26 OF 176PROPOSAL ID : 260114

106-5(e-e) 19

The Contractor may maintain this documentation electronically or in paper format. Upon request, the Department, or FHWA, may review the Contractor's supporting documentation to verify compliance with the Buy America provisions at any time. The Contractor shall provide the supporting documentation within five (5) business days of the request. The burden of proof to meet the Buy America provisions rests on the Contractor. If the supporting documentation does not undeniably demonstrate to the Department, or FHWA, that the iron or steel, manufactured products, or construction materials identified in the Certificates of Compliance were produced in the United States of America, then such iron, steel, manufactured products, or construction materials will be considered unacceptable and must be replaced at no cost to the Department.

The Contractor shall not anticipate that any Buy America Preference provisions will be waived.

PAGE 27 OF 176PROPOSAL ID : 260114

108-23(a) 19 1-10-20

OKLAHOMA DEPARTMENT OF TRANSPORTATION

SPECIAL PROVISIONS

FOR

FLEXIBLE NOTICE TO PROCEED

These Special Provisions revise, amend, and where in conflict, supersede applicable sections of the 2019 Standard Specifications for Highway Construction, English and Metric.

108.03 PROSECUTION AND PROGRESS (Add the following:)

The Notice to Proceed for this project will be issued in the normal time period (approximately 30 days after the award). The Contractor may begin work any time after the issuance of the Notice to Proceed, but no later than October 5, 2026. Time charges will begin on the date the Contractor begins work, or at the date specified in the Notice to Proceed, and will continue until the project is completed.

Once the work begins, construction is expected to continue at an optimum rate until the work is done.

Notify the Resident Engineer, and when applicable the County Commissioner, at least 14 calendar days prior to beginning work.

There will be no additional compensation for any increased costs due to beginning work at or near the end of the flexible period.

PAGE 28 OF 176PROPOSAL ID : 260114

108-80(a) 19 1-19-23

OKLAHOMA DEPARTMENT OF TRANSPORTATION

SPECIAL PROVISIONS

FOR

LIQUIDATED DAMAGES

These Special Provisions revise, amend, and where in conflict, supersede applicable sections of the 2019 Standard Specifications for Highway Construction.

108.09 FAILURE TO COMPLETE ON TIME (Revise Table 108:1 as follows:)

Table 108:1 Schedule of Liquidated Damages

Contract Amount, $ Daily Assessment Rate, $

# $200,000 $300 >$200,000 and #$1,000,000 $800

>$1,000,000 and #$5,000,000 $1,000 > $5,000,000 and #$10,000,000 $1,300

> $10,000,000 $1,800

PAGE 29 OF 176PROPOSAL ID : 260114

108-81(a) 19

OKLAHOMA DEPARTMENT OF TRANSPORTATION

SPECIAL PROVISIONS

FOR

DISINCENTIVE FOR EXPOSED COLD-MILLED PAVEMENT

These Special Provisions revise, amend, and where in conflict, supersede applicable sections of the 2019

Standard Specifications for Highway Construction.

(Add the following:)

108.14 DISINCENTIVE FOR EXPOSED COLD-MILLED PAVEMENT

The intent of this provision is to minimize the time of exposure of milled paving surfaces. The following items set forth the Contract requirements for this portion of work, and disincentive(s) for non-compliance with these specifications.

A disincentive of $0.02 per square yard per hour will be assessed for all cold-milled surfaces not overlayed within 48 hours of being exposed by cold-milling operations. The disincentive will be assessed each hour after the 48 hours, and continue until the cold-milled surfaces are no longer exposed to the elements as determined by the Engineer. (Fog sealing cold-milled surfaces will not exempt the Contractor from this disincentive.)

The Engineer may allow cold-milled surfaces to remain exposed for up to 96 hours if the Contractor, at no additional cost to the Department, covers the exposed cold-milled surfaces with an approved trackless tack coat meeting the requirements of Special Provision 708-25 within 48 hours of being exposed by cold-milling operations. The trackless tack coat layer must be maintained, ensuring that the trackless tack is of sufficient adhesion or tack coat must be reapplied prior to overlaying the cold-milled surface(s). In the event that trackless tack is used, the above disincentive will be assessed each hour after the 96 hours, and continue until the cold-milled surfaces are overlayed.

Extents of cold-milling required to provide a smooth transition to bridge approaches or to existing pavements will be exempt from this provision. However, if these extents are to be left exposed for more than

48 hours, they must be fog sealed or the disincentive set forth in this provision will apply for each hour in excess of the 48 hours until the fog seal or surfacing is placed.

PAGE 30 OF 176PROPOSAL ID : 260114

108-182(a) 19

OKLAHOMA DEPARTMENT OF TRANSPORTATION

SPECIAL PROVISIONS

FOR

70% SUBLETTING OF CONTRACT

These Special Provisions revise, amend, and where in conflict, supersede applicable sections of the 2019

Standard Specifications for Highway Construction.

108.01 SUBLETTING OF CONTRACT (Replace paragraph one with the following:)

The Department will not allow the Contractor to sublet, sell, assign, or otherwise dispose of the Contract, or any…