This document is a Change Order Notice for a contract between the Illinois Department of Natural Resources (DNR) and a contractor for the Yorkville Dam Erosion Repair project (FR-444). The change order adds quantities to pay items in the bid schedule to allow the contractor to satisfactorily complete the project. The original contract amount was $402,540.62, and the estimated increase is $76,000. The contract term remains June 9, 2022 through March 31, 2023. The circumstances necessitating the change order were not reasonably foreseeable at the time the contract was signed, and the change order is germane to the original contract.
The increased quantities provided through this change order are estimated to be required to complete the work on the project. If this change order is not approved, the intent of the contract to repair the eroded areas will not be fulfilled. The Contract Completion Date remains the same.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Please wait...
If this message is not eventually replaced by the proper contents of the document, your PDF viewer may not be able to display this type of document.
You can upgrade to the latest version of Adobe Reader for Windows®, Mac, or Linux® by visiting http://www.adobe.com/go/reader_download.
For more assistance with Adobe Reader visit http://www.adobe.com/go/acrreader.
Windows is either a registered trademark or a trademark of Microsoft Corporation in the United States and/or other countries. Mac is a trademark of Apple Inc., registered in the United States and other countries. Linux is the registered trademark of Linus Torvalds in the U.S. and other countries.
Change Order Notice Chief Procurement Office General Services v.21.1
44 Ill. Adm. Code 1.1525(h) requires notice of renegotiated contracts and change orders that increase the cost of a contract by more than $10,000 or the time of completion by a total of 30 days or more to be posted on the Bulletin/BidBuy for 14 days.
This Change Order Notice provides detail as to why the change order is needed and, pursuant to Section 33E-9 of the Criminal Code, that the circumstances said to necessitate the change in performance were not reasonably foreseeable at the time the contract was signed or the change is germane to the original contract as signed. Change orders are defined by Section 1-15.12 of the Procurement Code and Section 1.2067 of the CPO-GS' Administrative Rules.
Detailed explanation for this change order:
11.0.0.20130303.1.892433.887364
| BBREFNO.: B-32392 |
| ProcurementTitle: FR-444: Yorkville Dam Erosion Repair |
| DropDownList1: DNR - Natural Resources |
| thedetails: Change Order #1 adds quantities to pay items in the bid schedule allowing the Contractor to satisfactorily complete the project. |
Original Contract Amount: $402,540.62: Estimated increase of $76,000.
Contract Term: June 9, 2022 thru March 31, 2023: No Change
The quantities in the bid schedule were estimated for the establishment of pay item prices.
The Contractor is paid based on measurements of the actual quantity of work completed.
In the table below, the increased quantities are estimated to complete the work.
The circumstances which necessitate these costs provided through this Change Order were not foreseeable at the time the contract was signed.