This is a Task Assignment Notification Form for an indefinite delivery contract between the Florida Department of Environmental Protection (FDEP) and Ecology and Environment, Inc. (E&E), a contracted environmental consulting firm. The task assignment, numbered DC004K under Contract HW553, pertains to groundwater monitoring services at the Blue Ribbon Cleaners site in Tallahassee, Leon County, Florida (Facility ID 37-9500612; ERIC_4859). The document was executed on November 22, 2019, with Ben Grubbs serving as the FDEP Contract Manager and Perry Kelso as the contractor representative.
The task assignment authorizes E&E to conduct annual groundwater monitoring activities comprising two subtasks: Project Management (calculated at 12.5% of direct labor costs) and Annual Groundwater Sampling and Report. The scope includes collection of groundwater samples from eight monitoring wells (MW001-MW008) using passive diffusion bags (PDBs), analysis for chlorinated volatile organic compounds (VOCs) via EPA Method 8260, and preparation of an Annual Groundwater Monitoring Report with professional engineering certification. The total fixed-price task assignment value is $7,949.96, encompassing 61.6 labor hours, laboratory analysis costs of $1,350.00, sample shipping costs of $40.00, equipment costs of $283.84, and travel costs of $194.00. The deliverable—the Annual Groundwater Monitoring Report—is due October 15, 2020, with task completion scheduled for December 31, 2020. Invoicing occurs upon submittal and FDEP approval of the final report, with no retainage applied.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
11/26/2019
Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment
Contract Number: HW553 Task Assignment #: DC004K
Deliverables:
Deliverable Deliverable Due Date Subtask 2: Annual Groundwater Monitoring Report 15-Oct-20
Invoice Schedule:
Requirements for Invoice Submittal Amount to be Invoiced
Subtasks 1 & 2: Submittal and FDEP approval of the Annual Groundwater Monitoring Report
$7,949.96
TOTAL COST $7,949.96
BWC TAFORM 01/18
Printed on recycled paper.
FLORIDA DEPARTMENT OF
Environmental Protection
Bob Martinez Center
2600 Blair Stone Road Tallahassee, FL 32399-2400
Ron DeSantis Governor
Jeanette Nuñez
Lt. Governor
Noah Valenstein Secretary
To: HW553 Contract Negotiation File Blue Ribbon Cleaners
Tallahassee, Leon County
ERIC_ 4859
From: Ben Grubbs, Project Manager Date: November 22, 2019 Subject: Negotiation Summary
HW553 DC004K
This Task Assignment authorizes E&E to conduct groundwater monitoring activities in accordance with the November 22, 2019, Scope of Work and Cost Estimate.
Subtask 1: Project Management An automatic calculation based upon total direct labor hours determines the labor hours within this subtask.
Subtask 2: Annual Groundwater Sampling and Report E&E will collect groundwater samples from monitoring wells MW001-MW008. Prior to sampling, depth-to-water will be measured. The groundwater samples will be collected using passive diffusion bags (PDBs) and analyzed for chlorinated volatile organic compounds (VOCs).
E&E will submit the Annual Groundwater Monitoring Report to FDEP.
The FDEP Project Manager agrees to the scope of work and final cost associated with this Task Assignment. The final cost for this Task Assignment is $7,949.96 with 61.6 labor hours.
E&E may invoice following the schedule established in the Deliverables and Invoice Schedule Attachment, which accompanies the Task Assignment Notification Form.
FDEP Contract HW553 Cost Estimate
Contractor:
Date:
Task #: HW553 DC004K SubTask 1 Project Management (12.5% of direct labor costs) Site: SubTask 2 Annual Groundwater Monitoring and Report
Site ID #: Fac. ID:37-9500612; ERIC_4859 SubTask 3 Activity/Phase: SubTask 4
Project Manager: SubTask 5
10BP20E.0056.01
Labor Rate Category Totals 1 2 $47.79 PM 12.5% of direct labor costs 4.6 4.589
Principal $60.47 Kelso 2.0 2.0 $63.94 Brown 0.0 0.0
Chief $45.65 Werth 0.0 0.0 $45.11 Elliott 0.0 0.0 $43.01 Ringo 0.0 0.0 $31.25 Gebhart 0.0 0.0 $48.10 Moore 0.0 0.0
Senior $36.37 Krajewski 0.0 0.0 $34.46 Murak 0.0 0.0 $33.75 Chappell 16.5 16.5 $36.06 Anders 10.0 10.0 $39.09 Dillon 0.0 0.0 $39.09 Eucogno 0.0 0.0 $39.09 Guerrero 0.0 0.0 $39.09 Percifull 0.0 0.0
Associate $24.78 Oien 25.5 25.5 $28.09 Witherington 0.0 0.0 $28.09 Brighton 0.0 0.0 $28.09 Fowler 3.0 3.0 $28.09 Hammond 0.0 0.0
Junior $22.05 Kuhn 0.0 0.0 $22.73 Clapsaddle 0.0 0.0 $24.47 Beck 0.0 0.0 $24.47 Cooper 0.0 0.0 $24.47 Kowal 0.0 0.0 $24.47 Slabaugh 0.0 0.0
Technician $18.72 N/A 0.0 0.0
Clerical $16.40 Williams 0.0 0.0 $22.28 Rodriguez 0.0 0.0
Total Hours 61.6 4.6 57.0
1) Direct Labor $1,973.90 $219.32 $1,754.58
2) Fringe (33.44% of Lines 1 ) $660.07 $73.34 $586.73
3) Overhead (49.90% of Lines 1 + 2) $1,314.35 $146.04 $1,168.31
4) Gen & Admin (36.27% of Lines 1 + 2 + 3) $1,432.06 $159.12 $1,272.94
5) Total Labor (Sum Lines 1 thru 4) $5,380.38 $597.82 $4,782.56
6) Other Direct Costs (5.0% of Line 1) $98.70 $10.97 $87.73 Travel
7a) Vehicle Rental $194.00 $0.00 $194.00 7b) Mileage Costs $0.00 $0.00 $0.00 7c) Air Fare $0.00 $0.00 $0.00 7d) Per diem + Hotel $0.00 $0.00 $0.00 7e) Total Travel $194.00 $0.00 $194.00
Subcontractor (Equipment Procurement) 8a) Provider - Task # $0.00 $0.00 $0.00 8b) Provider - Task # $0.00 $0.00 $0.00 8c) Provider - Task # $0.00 $0.00 $0.00 8d) Subcontractor Subtotal $0.00 $0.00 $0.00 8e) Procurement Fee $0.00 $0.00 $0.00 8f) Total Subcontractor Cost $0.00 $0.00 $0.00
Subcontractor (Services Procurement) 9a) Drilling (Conventional) $0.00 $0.00 $0.00 9b) Drilling (Non-conventional) $0.00 $0.00 $0.00 9c) Mobile Laboratory $0.00 $0.00 $0.00 9d) Surveying $0.00 $0.00 $0.00 9e) IDW $0.00 $0.00 $0.00 9f) Utilities $0.00 $0.00 $0.00 9g) Other Sub 1 - Task # $0.00 $0.00 $0.00 9h) Other Sub 2- Task # $0.00 $0.00 $0.00 9i) Other Sub 3 - Task # $0.00 $0.00 $0.00 9j) Subcontractor Subtotal $0.00 $0.00 $0.00 9k) Handling Fee $0.00 $0.00 $0.00 9l) Total Subcontractor Cost $0.00 $0.00 $0.00
Laboratory 10a) Analytical Costs (Fixed Lab) $1,350.00 $0.00 $1,350.00 10b) Fast Turnaround Rate (%) (Fixed Lab) 0% 100% 10c) Fast Turnaround Charges (Fixed Lab) $0.00 $0.00 $0.00 10d) Sample Shipping $40.00 $0.00 $40.00 10e) Total Laboratory $1,390.00 $0.00 $1,390.00
Field Expenses 11a) Personal Protection $0.00 $0.00 $0.00 11b) Expendables $65.00 $0.00 $65.00 11c) Equipment (Drilling Related) $0.00 $0.00 $0.00 11d) Equipment (Analytical Related) $0.00 $0.00 $0.00 11e) Equipment (IDW Related) $0.00 $0.00 $0.00 11f) Equipment (Other) $283.84 $0.00 $283.84 11g) Total Field Expenses $348.84 $0.00 $348.84
Subtotal $7,411.92 $608.79 $6,803.13 Completion Fee 12) (10.0% of Line 5) $538.04 $59.78 $478.26
13) Total Estimated Cost $7,949.96 $668.57 $7,281.39
November 22, 2019
* Equipment Procurement - 10.0% Per Subcontractor, maximum $2,500 per Subcontractor.
** Utilities fees are calculated based on $20 per utility bill per month.
*** Except for utilities fees, 10% of first $50,000, 7% of next $50,000, 5% over $100,000 per Subcontractor.
Ecology and Environment, Inc.
FDEP: B. Grubbs / E & E: B. Anders
Blue Ribbon Cleaners
Annual Groundwater Monitoring
CEFLOE_HW553_DC004K 11/22/2019 Page 1
SITE: Blue Ribbon Cleaners
SUBTASK NO.: 2 DESCRIPTION:
DATE: November 22, 2019 FACILITY ID NO.: 37-9500612; ERIC_4859
TASK NO: HW553 DC004K
LABOR HOURS
Labor Category Work Description Hours
Principal Kelso Senior Review 2
Senior
Chappell 16.5
Anders Document preparation, Hydrogeologic evaluation, Recommendations / Conclusions, PG Sealing 10 Associate
Oien 25.5 Fowler Publications and Editing 3
57.00
VEHICLE RENTAL
ITEM RATE UNIT USAGE TOTAL
Equipment Truck/Van $97.00 Day 2 $194.00
$194.00
MILEAGE AND AIRFARE
$0.00
MEALS AND LODGING
$0.00
EQUIPMENT PROCUREMENT
$0.00
SUBCONTRACTOR
$0.00 LABORATORY and SAMPLE SHIPMENTS
ANALYSIS/PARAMETER
FAST TURNAROUND
RATE (%)
No. for Fast
Turnaround Rate RATE Media No. of
Samples No. of
QA/QC
Fast Turn- Around Charges TOTAL
EPA 8260 VOCs 100% 0 $135.00 Water 8 2 $0.00 $1,350.00 *Rate negotiated. Subtotal-Lab Analyses 8 2 $0.00 $1,350.00
SAMPLE SHIPMENTS
CONTAINER SIZE
Shipment Method
24 hr No. of
Containers Shipment Method
2 day No. of
Containers Ice No. of
Containers TOTAL Small (<50 lbs.) $63.00 0 $35.00 1 $5.00 1 $40.00
Subtotal-Sample Shipments $40.00 $1,390.00
FIELD EXPENSES
Personal Protection
SUBTOTAL - PERSONAL PROTECTION $0.00
Expendables
ITEM RATE UNIT USAGE TOTAL ITEM TOTAL
Expendables $32.50 Day 2 $65.00
SUBTOTAL - EXPENDABLES $65.00
Drilling Related Equipment
SUBTOTAL - DRILLING RELATED EQUIPMENT $0.00
Analytical Related Equipment
SUBTOTAL - ANALYTICAL RELATED EQUIPMENT $0.00
IDW Related Equipment
SUBTOTAL - IDW RELATED EQUIPMENT $0.00
Other Equipment
RATE ITEM UNIT NO OF ITEMS USAGE TOTAL ITEM
Water Level Indicator $19.40 day 1 2 $38.80 Passive Diffusion Bags $30.63 ea 1 8 $245.04
*Rate negotiated. SUBTOTAL - OTHER EQUIPMENT $283.84
$348.84FIELD EXPENSES
Annual Groundwater Monitoring and Report
TOTAL LABOR HOURS
TOTAL VEHICLE RENTAL
TOTAL MILEAGE AND AIRFARE
TOTAL MEALS AND LODGING
TOTAL LABORATORY and SHIPMENTS
TOTAL EQUIPMENT PROCUREMENT
TOTAL SUBCONTRACTOR
Travel time (TLH to site; 30 mins; 4 visits); DTW measurements (2 hours), installation of PDBs in 7 wells (3 hours), retrievel of PDBs and sample shipment (3 hours), warehouse mob/demob (1.5 hours), CAD Figure Development (3 hours)
Travel time (TLH to site; 30 mins; 4 visits); DTW measurements (2 hours), installation of PDBs in 7 wells (3 hours), retrievel of PDBs and sample shipment (3 hours), warehouse mob/demob (1.5 hours), Table & figure development, GIS data tables, Submittals (12 hours)
CEFLOE_HW553_DC004K/2 Page 6
November 22, 2019
Mr. Benjamin Grubbs Florida Department of Environmental Protection 2600 Blair Stone Road Tallahassee, Florida 32399-2400
Re: 2020 Annual Groundwater Monitoring Cost Proposal for the Blue Ribbon Cleaners Site, Tallahassee, Leon County, Florida (ERIC_4859; Task Assignment HW553-
DC004K)
Dear Benjamin:
Ecology and Environment, Inc. (E & E) is submitting to the Florida Department of Environmental Protection (FDEP) this annual groundwater monitoring cost proposal package the above-referenced site.
This cost proposal package includes a monitoring schedule (Table 1), site plan (Figure 1), a proposed field work and reporting schedule for the completion of subtasks, and a cost estimate form / level of effort (Attached Separately). A brief summary of the scope of work is provided below:
Subtask 1: Project Management This subtask consists of project management hours only and is automatically calculated based upon 12.5% of the direct labor costs.
Subtask 2: Annual Groundwater Sampling and Report The annual groundwater sampling event will include installation of passive diffusive bags (PDBs) and subsequent collection of groundwater samples as outlined in Table 1 for laboratory analysis.
E & E personnel will mobilize to the site and install the PDBs into the screen intervals of the monitoring wells as indicated on Table 1. Following installation, and due to low aquifer permeability, the passive diffusive bags will be left for approximately one month prior to removal and collection of samples. E & E recommends using the previously acquired passive diffusive bag assemblies (hangers) as they were custom fitted for each well. Costs for passive diffusive bags were requested from ALS Life Sciences Division (ALS), (Attachment A).
The groundwater samples, a duplicate sample, and a trip blank will be delivered to the Advanced Environmental Laboratories Tallahassee, Florida, (AEL Tallahassee) facility and analyzed for volatile organic compounds using United States Environmental Protection Agency (USEPA) Method 8260. Well locations are provided on Figure 1.
Prior to the installation of the passive diffusion bags, depth-to-water will be gauged and recorded in the monitoring wells to determine groundwater flow direction(s) across the site and to ensure the passive diffusive bag is placed within the water table.
Mr. Benjamin Grubbs November 22, 2019
Upon receipt of the analytical data from AEL Tallahassee for the annual sampling event, E & E will prepare an Annual Groundwater Monitoring Report. The Annual Groundwater Monitoring Report will include a PG/PE certification, analytical results, groundwater contaminant concentration figures, groundwater elevation isopleth maps, summary of the sampling event, conclusions, and recommendations.
Upon FDEP approval of the Annual Groundwater Monitoring Report, an electronic copy of the report and updated GIS data tables will be submitted to FDEP via the FDEP FTP site or by e-mail.
Schedule The proposed project task schedule for completion of this work is as follows:
Place PDB Bags: July 15, 2020 Completion of Sampling: August 31, 2020 Completion of Annual Groundwater Monitoring Report: October 15, 2020 Task Assignment End Date: December 31, 2020
Cost The cost estimate to complete the above-described work plan/cost is provided in the associated Excel worksheet (Blue Ribbon Cost). E & E estimates the work will cost $7,949.96 to complete.
If you have any questions please give me (banders@ene.com) a call at (850) 523-0954.
Sincerely, ECOLOGY AND ENVIRONMENT, INC.
J. Bradley Anders Project Manager
AndersB Stamp
Table
Table 1 2020 Annual Groundwater Monitoring Schedule
Blue Ribbon Cleaners Site, Tallahassee, Leon County, Florida ERIC_4859; Facility ID No. 37-9500612; Task Assignment HW553-DC004I
Sampling Point Method Frequency Justification Groundwater Samples
MW001 USEPA Method 8260 Annual 1,2 MW002 USEPA Method 8260 Annual 1,2 MW003 USEPA Method 8260 Annual 1,2 MW004 USEPA Method 8260 Annual 1,2 MW005 USEPA Method 8260 Annual 1,2 MW006 USEPA Method 8260 Annual 1,2 MW007 USEPA Method 8260 Annual 1,2 MW008 USEPA Method 8260 Annual 1,2
Justification: 1. Required by Rule 62-780;
2. Source area or downgradient well.
Figure
AutoCAD SHX Text
CONCRETE WALK
AutoCAD SHX Text
CONCRETE WALK
AutoCAD SHX Text
ASPHALT DRIVE AND PARKING
AutoCAD SHX Text
ASPHALT DRIVE AND PARKING
AutoCAD SHX Text
CONCRETE WALK
AutoCAD SHX Text
SERVICE ROAD
AutoCAD SHX Text
RAMP
AutoCAD SHX Text
ASPHALT PAVEMENT ACCESS ROAD
AutoCAD SHX Text
LAFAYETTE STREET
AutoCAD SHX Text
PARKWAY SHOPPING CENTER
AutoCAD SHX Text
LOADING RAMP
AutoCAD SHX Text
BLUE RIBBON CLEANER'S
AutoCAD SHX Text
ASPHALT DRIVE
AutoCAD SHX Text
FORMER ONE HOUR VALLET CLEANERS
AutoCAD SHX Text
CONCRETE
AutoCAD SHX Text
CONCRETE
AutoCAD SHX Text
LOADING RAMP
AutoCAD SHX Text
APALACHEE PARKWAY
AutoCAD SHX Text
MOTEL 6
AutoCAD SHX Text
OLIVE GARDEN
AutoCAD SHX Text
MW005
AutoCAD SHX Text
MW006
AutoCAD SHX Text
MW008
AutoCAD SHX Text
MW002
AutoCAD SHX Text
MW004
AutoCAD SHX Text
MW007
AutoCAD SHX Text E
AutoCAD SHX Text
MW001
AutoCAD SHX Text
CONCRETE PAD
AutoCAD SHX Text
WALL
AutoCAD SHX Text
WALL
AutoCAD SHX Text
DUMPSTER & GREASE TRAP
AutoCAD SHX Text
COVERED DRIVE-THRU
AutoCAD SHX Text
MW003
AutoCAD SHX Text
AND PARKING
AutoCAD SHX Text
SCALE IN FEET
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
MAGNETIC
AutoCAD SHX Text
LEGEND
AutoCAD SHX Text
MONITORING WELL LOCATION
AutoCAD SHX Text
APPROXIMATE RIGHT OF WAY
AutoCAD SHX Text
DRYCLEANING MACHINE
AutoCAD SHX Text
BUILDING
AutoCAD SHX Text Global Environmental Specialists
AutoCAD SHX Text
AutoCAD SHX Text
DATE ISSUED
AutoCAD SHX Text
C.A.D. FILE NO.
AutoCAD SHX Text ecology and environment, inc.
AutoCAD SHX Text
ERIC_4859
AutoCAD SHX Text
1003077.0168.01C.DWG
AutoCAD SHX Text
FIGURE 1
AutoCAD SHX Text
SITE MAP
AutoCAD SHX Text
BLUE RIBBON CLEANERS (LAFAYETTE)
AutoCAD SHX Text
TALLAHASSEE, LEON COUNTY, FLORIDA
Attachment A ALS Costs
AndersB Text Box $28.50 X 7.5% tax = 30.63 each
| Task Assignment Notification |
| Deliverable & Invoice Schedule |