CN-370000-CN205-T7CO3.pdf
PDF 1 MB Posted
- Contract number
- CN205
- Issued by
- Florida
About this file
Summary
This is a Task Assignment Change Order (Change Order No. 03) issued by the Florida Department of Environmental Protection (FDEP) to Ayres Associates, Inc. for engineering inspection services at Weeki Wachee Springs State Park. The contract is identified as FDEP Contract No. CN205, Task Assignment No. TA07, and Project No. 61253. The FDEP Contract Manager is Donald Finkbeiner, and the consultant representative is Rick Maslyn, CBI, Supervisor of Structural Inspection at Ayres Associates.
The change order authorizes Ayres Associates to provide two separate field inspections and reports for the water slide infrastructure at Weeki Wachee Springs State Park, specifically the slide tower, Pirates Revenge slide, and Cannonball slide. Task 1 involves a preliminary inspection conducted between October 2-14, 2022, with a report due October 28, 2022, to establish a bidding scope of work for repairs. Task 2 requires a follow-up inspection between January 30-February 3, 2023, to confirm completion of repairs and includes a signed and sealed Affidavit of Compliance for submission to the Department of Agriculture. The total contract value is $2,525.72, comprised of $2,440.28 in fixed-price costs (labor from Ayres Associates personnel including Project Manager, Senior Structural Engineer, and Structural Inspector at respective hourly rates) and $85.44 in reimbursable costs (mileage at $0.445 per mile for a 96-mile round trip). The new task end date is July 31, 2023, representing a net extension of 365 days from the original end date. Payment will be made upon FDEP approval of deliverables for each subtask.
View the file
Other files
Show all 28
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Florida Department of Environmental Protection
TASK ASSIGNMENT CHANGE ORDER FORM
(Revised 9-26-2018) Page 1 of 1
Required Signatures: Adobe Signature
FDEP Contract No.: Task Assignment No.: Change Order No.: Project No.:
Project Location: Project Name:
Consultant Name:
Consultant Representative: Phone: Email:
FDEP Contract Manager: Phone: Email:
Description and Justification of Change:
Change in Task Amount:
Item Reimbursement Fixed Fee Total
Original Task Amount:
Task amount including all previous Change Orders:
Net increase/decrease in task amount for this Change Order:
Total Amounts with all Change Orders:
Change in Task Time:
Original Task Execution Date:
Original Task End Date:
Present Task End Date:
Net Change in Days:
New Task End Date:
Approval Signatures:
Budget Representative, FDEP Signature Date
Project Manager, FDEP Signature Date
Contract Manager, FDEP Signature Date
Consultant Signature Date
Contract Authority, FDEP Signature Date
Project # Grant # Org Code Cat/Year Fund Module Object Code EO Amount
29 Digit FLAIR Code: Total:
CN205 TA07 03 61253
Weeki Wachee Springs State Park Waterslide Engineering Inspections
Ayres Associates, Inc.
Rick Maslyn, CBI 813-318-1577 MaslynR@AyresAssociates.com
Donald Finkbeiner 850-245-2587 Donald.Finkbeiner@FloridaDEP. gov
Provide yearly engineering report on the condition of the waterslides at Weeki Wachee Springs per proposal dated May 16, 2022 .
$ 42.72 $ 1,220.14 $ 1,262.86 $ 256.32 $ 10,914.56 $ 11,170.88 $ 85.44 $ 2,440.28 $ 2,525.72 $ 341.76 $ 13,354.84 $ 13,696.60
08/14/2019
07/31/2020
07/31/2022
07/31/2023
Diane Langston Diane Langston Digitally signed by Diane Langston Date: 2022.05.17 15:55:13 -04'00'
Donald Finkbeiner Donald J. Finkbeiner Digitally signed by Donald J.
Finkbeiner Date: 2022.05.17 16:22:03 -04'00'
Jeffrey Whitfield Jeffrey Whitfield Digitally signed by Jeffrey Whitfield Date: 2022.05.17 16:27:34 -04'00'
Rick Maslyn, CBI Hisham N Sunna Digitally signed by Hisham N Sunna Date: 2022.05.23 10:20:51 -04'00'
Michael W. Foster Jr., P.E. Michael W. Foster Jr., P.E.
Digitally signed by Michael W.
Foster Jr., P.E.
Date: 2022.05.26 16:49:12 -04'00'
61253 37504000281 080039/22 408001 u3200 131545 PF $ 2,525.72
$ 2,525.72
May 16, 2022
Don Finkbeiner Construction Project Consultant II Bureau of Design and Construction Florida Department of Environmental Protection 3900 Commonwealth Boulevard, MS 520 Tallahassee, FL 32399
RE: CN205, Task Assignment Number 07, Change Order 03
Weeki Wachee Springs State Park Water Slide Inspection
Dear Mr. Finkbeiner;
For your review, Ayres Associates, has provided a proposal summary and man-hour documentation for the services tasks identified below:
Schedule:
1. Ayres Associates will provide an inspection of the slide tower, Pirates Revenge slide and the Cannonball slide between October 2, 2022, and October 14, 2022. The report will be due by October 28, 2022 and used as the bidding scope of work.
2. Ayres Associates will provide inspection of slide structure between January 30, 2023, and February 3, 2023, to confirm completion of the repairs. The Affidavit of Compliance and will be completed and forwarded to the Department of Agriculture by February 17, 2023. Department of Agriculture inspection will be completed in the last (2) weeks of February 2023.
The Scope includes:
1. Provide complete inspection of Tower, Pirates Revenge slide, Cannonball slide and structure and provide an inspection report in a pdf and excel format.
2. Provide a signed and sealed Affidavit of Compliance to the Department of Agriculture and DEP.
Please review the attached Proposal Summary and deliverables.
Sincerely, Rick Maslyn, CBI Supervisor- Structural Inspection 813.318.1577 8875 Hidden River Parkway, Suite 200 Tampa, FL 33637
Project Description Weeki Wachee Springs State Park
CN205, Task Assignment Number 07, Change Order 03
Task 1: Slide Inspection and Report Deliverable Description: Perform field inspection of Weeki Wachee Springs State Park Water Slide Tower, Pirate’s Revenge Slide and Cannonball Slide and provide inspection report to be used as basis for contractor bid repairs.
Deliverable:
• 1 – Inspect structure and provide one pdf, 8 ½ x 11, report deliverable to include list of defects, corrective actions taken since the prior inspection, and repair recommendations with photos and slide layout sketches. Report will also include an Excel Spreadsheet of repair recommendations, submitted by October 28, 2022.
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language)
Fixed Price Cost:
Subtask 1 Firm Name Position Classification Hourly Rate Hours Total Fixed
Price Cost Ayres Associates Project Manager 150.34 1.5 225.51 Ayres Associates Sr. Structural Engineer (PE) 144.20 2 288.40 Ayres Associates Structural Inspector (CBI) 100.89 7 706.23
Reimbursable Cost: (if applicable – provide for each task in which reimbursables are required)
Postage $0 Printing $0 Overnight Travel (if applicable)
$0
Mileage (@ $0.445 per mile) Provide the calculation and number for trips and provide total estimated cost 48 mile trip from office to park and back (96 miles)
Reimbursable Total Cost $42.72 Total for Subtask 1: (Fixed Price Cost + Reimbursable)
Project Schedule:
Activity Duration (Calendar Days) Subtask 1 12 days. Between October 3, 2022, and October 14, 2022. The report will be due by October 28, 2022.
Task 2: Slide Inspection and Report Deliverable Description: Perform field inspection of Weeki Wachee Springs State Park Water Slide Tower, Pirate’s Revenge Slide and Cannonball Slide and provide inspection report to be used as basis for documentation/confirmation of contractor repairs.
Deliverable:
• 2 – Inspect structure and provide one pdf, 8 ½ x 11, report deliverable to include list of defects, corrective actions taken since the prior inspection, and repair recommendations with photos and slide layout sketches. Report will also include a signed and sealed Affidavit of Compliance and an Excel Spreadsheet of repair recommendations, submitted by February 17, 2023.
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language)
Fixed Price Cost:
Subtask 2 Firm Name Position Classification Hourly Rate Hours Total Fixed
Price Cost Ayres Associates Project Manager 150.34 1.5 225.51 Ayres Associates Sr. Structural Engineer (PE) 144.20 2 288.40 Ayres Associates Structural Inspector (CBI) 100.89 7 706.23
Reimbursable Cost: (if applicable – provide for each task in which reimbursables are required)
Postage $0 Printing $0 Overnight Travel (if applicable)
$0
Mileage (@ $0.445 per mile) Provide the calculation and number for trips and provide total estimated cost 48 mile trip from office to park and back (96 miles)
Reimbursable Total Cost $42.72 Total for Subtask 2: (Fixed Price Cost + Reimbursable)
Project Schedule:
Activity Duration (Calendar Days) Subtask 2 4 days. Between January 30, 2023, and February 3, 2023, to confirm completion of the repairs. The Affidavit of Compliance and will be completed and forwarded to the Department of Agriculture by February 17, 2023.
Summary of Fees:
Subtask Subtask Fixed Price Cost Subtask Reimbursable Subtask 1 $1,220.14 $42.72 Subtask 2 $1,220.14 $42.72
Total Fixed Price Cost: $2,440.28 Total Reimbursable Cost: $85.44
Overall Total Cost: $2,525.72 Payment will be made upon approval of deliverables for each subtask by the FDEP in the amount specified.
(Please do not alter this language)
From: Givens, Ezell To: Finkbeiner, Donald; Felts, Tracy Cc: Rowe, Richard J.; Chang, Laura D; Belden, Adam; Anderson, Robyn; Faustini, Michael; Goss, John Subject: RE: Weeki Wachee - slide inspections, underwater inspections Date: Monday, May 16, 2022 4:16:47 PM Attachments: image001.png
Don Yes this is acceptable.
Adam Please budget for this inspection Thanks
From: Finkbeiner, Donald <Donald.Finkbeiner@FloridaDEP.gov> Sent: Monday, May 16, 2022 1:22 PM To: Givens, Ezell <Ezell.Givens@dep.state.fl.us>; Felts, Tracy <Tracy.Felts@dep.state.fl.us> Cc: Rowe, Richard J. <Richard.J.Rowe@dep.state.fl.us>; Chang, Laura D <Laura.D.Chang@FloridaDEP.gov>; Belden, Adam <Adam.Belden@dep.state.fl.us>; Anderson, Robyn <Robyn.Anderson@FloridaDEP.gov>; Faustini, Michael <Michael.Faustini@dep.state.fl.us>; Goss, John <John.Goss@FloridaDEP.gov> Subject: Weeki Wachee - slide inspections, underwater inspections
Good afternoon BJ, Tracy, I have received the proposal from Ayres Associates for the slide inspections in October, 2022. The $2,525.72 will include an inspection to create the yearly repair scope of work and a final inspection report for the Department of Agriculture.
We will skip the underwater inspection of the Mermaid Theater and task that work for next year, unless there is an emergency request.
If this is acceptable, I will get the change order routed for signature.
Thank you Don
Donald Finkbeiner Construction Project Consultant II Bureau of Design and Construction Office of Operations Department of Environmental Protection Donald.Finkbeiner@dep.state.fl.us Office: 850.245.2587 Cell: 850.510.8028
This communication does not constitute an authorization for any increase in the scope of work, cost, or time for the project being discussed. All changes to services, cost, or time must be accomplished in accordance with the formal process outlined in the contract. The DEP objects to, and shall not be responsible for, any changes to services, costs, or additional time not mailto:Ezell.Givens@dep.state.fl.us mailto:Donald.Finkbeiner@FloridaDEP.gov mailto:Tracy.Felts@dep.state.fl.us mailto:Richard.J.Rowe@dep.state.fl.us mailto:Laura.D.Chang@FloridaDEP.gov mailto:Adam.Belden@dep.state.fl.us mailto:Robyn.Anderson@FloridaDEP.gov mailto:Michael.Faustini@dep.state.fl.us mailto:John.Goss@FloridaDEP.gov http://www.dep.state.fl.us/ mailto:Donald.Finkbeiner@dep.state.fl.us authorized by an executed Contract Amendment, Task Assignment Change Order, Construction Change Order, or Construction Change Directive, as appropriate for this contract.
| CN205 TA7 CO3 Weeki Wachee Springs State Park - Water Slide Inspection |
| CN205 TA7 CO3 Weeki Wachee Springs State Park - Waterslide Engineering Inspections |
| Ayres Associates_Task 07 Assignment_ Change Order 03_5.16.22 |