CN-370000-CN205-T7CO1.pdf
PDF 287 KB Posted
- Contract number
- CN205
- Issued by
- Florida
About this file
This is a Task Assignment Change Order Form (Change Order No. 01) issued by the Florida Department of Environmental Protection (FDEP) for Contract CN205 with Ayres Associates, Inc. The document modifies Task Assignment TA 07 for engineering inspection services at Weeki Wachee Springs State Park. The contract is managed by FDEP Project Manager Donald Finkbeiner, with Rick Maslyn, CBI serving as the Consultant Representative for Ayres Associates. The change order was executed on July 22, 2020 and signed by authorized representatives from both FDEP and the consultant.
The change order authorizes three subtasks totaling $7,382.30 in compensation: Subtask 1 ($4,856.58) provides removal process documentation and shed roof design for water slide equipment due by October 16, 2020; Subtask 2 ($1,262.86) requires field inspection and a detailed report on the Tower, Pirates Revenge, and Cannonball slides due by October 16, 2020; and Subtask 3 ($1,262.86) mandates post-repair inspection and compliance documentation due by February 14, 2021. Costs are structured as fixed fees ($7,254.14) covering professional labor from Project Managers, Senior Structural Engineers, and Structural Inspectors, plus reimbursable expenses totaling $128.16 primarily for mileage. Payment is contingent upon FDEP approval of deliverables for each subtask. The task execution period extends from August 14, 2019 through July 31, 2021, with this change order adding 365 days to the original timeline.
View the file
Other files
Show all 28
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Florida Department of Environmental Protection
TASK ASSIGNMENT CHANGE ORDER FORM
( ) Page 1 of 1
Required Signatures: Adobe Signature
FDEP Contract No.: Task Assignment No.: Change Order No.: Project No.:
Project Location: Project Name:
Consultant Name:
Consultant Representative: Phone: Email:
FDEP Contract Manager: Phone: Email:
Description and Justification of Change:
Change in Task Amount:
Item Reimbursement Fixed Fee Total
Original Task Amount:
Task amount including all previous Change Orders:
Net increase/decrease in task amount for this Change Order:
Total Amounts with all Change Orders:
Change in Task Time:
Original Task Execution Date:
Original Task End Date:
Present Task End Date:
Net Change in Days:
New Task End Date:
Approval Signatures:
Budget Representative, FDEP Signature Date
Project Manager, FDEP Signature Date
Contract Manager, FDEP Signature Date
Consultant Signature Date
Contract Authority, FDEP Signature Date
Project # Grant # Org Code Cat/Year Fund Module Object Code EO Amount
29 Digit FLAIR Code: Total:
CN205 TA 07 01 61253
Weeki Wachee Springs State Park Waterslide Engineering Inspections
Ayres Associates, Inc.
Rick Maslyn, CBI 813-318-1577 MaslynR@AyresAssociates.com
Donald Finkbeiner 850-245-2587 Donald.FInkbeiner@FloridaDEP.gov
Provide yearly engineering report on the condition of the waterslides at Weeki Wachee Springs per proposal dated July 20, 2020.
$ 42.72 $ 1,220.14 $ 1,262.86 $ 42.72 $ 1,220.14 $ 1,262.86 $ 128.16 $ 7,254.14 $ 7,382.30 $ 170.88 $ 8,474.28 $ 8,645.16
08/14/2019
07/31/2020
07/31/2020
07/31/2021
Greg Turral Gregory Turral Digitally signed by Gregory Turral Date: 2020.07.22 16:47:33 -04'00'
Donald Finkbeiner Donald J. Finkbeiner Digitally signed by Donald J.
Finkbeiner Date: 2020.07.27 21:30:35 -04'00'
Philip Stone P.T. Stone Digitally signed by P.T. Stone Date: 2020.07.28 08:59:17 -04'00'
Hisham Sunna, PE Digitally signed by Hisham N Sunna Date: 2020.07.28 10:25:07 -04'00'
Michael W. Foster Jr., P.E. Michael W. Foster Jr.
Digitally signed by Michael W.
Foster Jr.
Date: 2020.07.28 16:21:08 -04'00'
61253 37504000281 080039/20 000286 U3200 131545 AD $ 7,382.30
$ 7,382.30
July 20, 2020
Don Finkbeiner Construction Project Consultant II Bureau of Design and Construction Florida Department of Environmental Protection 3900 Commonwealth Boulevard, MS 520 Tallahassee, FL 32399
RE: CN205
Weeki Wachee Springs State Park Water Slide Inspection
Dear Mr. Finkbeiner;
For your review, Ayres Associates, has provided a proposal summary and man‐hour documentation for the services tasks identified below:
Schedule:
1. Ayres Associates will provide a scope of work and process of removal of the Thunderbolt slide from the tower. This includes closure of the original entrance to the straight slides. This scope will be completed within (2) weeks of execution of this change order. A shed roof design is needed to cover the pump and electric panels between bents 6 and 7. This will be due by October 16, 2020.
2. Ayres Associates will provide an inspection of the slide tower, Pirates Revenge slide and the Cannonball slide after Labor Day, September 7, 2020 and before October 1, 2020. The report will be due by October 16, 2020 and used as the bidding scope of work.
3. Ayres Associates will provide inspection of slide structure between January 1, 2021 and January 31, 2021 to confirm completion of the repairs. The Affidavit of Compliance and will be completed and forwarded to the Department of Agriculture by February 14, 2021. Department of Agriculture inspection will be completed in the last (2) weeks of February 2021.
The Scope includes:
1. Provide a signed and sealed letter of the process of removal for the Thunderbolt straight slides, closure of the original entrance to the straight slides, and termination of the piping to the slide, to the Department of Agriculture and DEP. Provide a shed roof design between bents 6 and 7 over the pump and electric panels.
DEP will provide a fence enclosure. No other design or permitting is included with this scope.
2. Provide complete inspection of Tower, Pirates Revenge slide, Cannonball slide and structure and provide an inspection report in a pdf and excel format to DEP.
3. Provide a signed and sealed Affidavit of Compliance to the Department of Agriculture and DEP.
Please review the attached Proposal Summary and deliverables.
Sincerely, Rick Maslyn, CBI Supervisor‐ Structural Inspection 813.318.1577 8875 Hidden River Parkway, Suite 200 Tampa, FL 33637
Project Description
Weeki Wachee Springs State Park
CN205, Task Assignment Number 08
Task 1: Design and Removal Process.
Description: Provide a removal process for Thunderbolt straight slide, closure to the original slide entrance and termination of slide piping. Provide shed roof design for water slide equipment between existing Bents 6 & 7.
Deliverable:
1 – Signed and sealed letter for Thunderbolt removal process will be delivered electronically in pdf format, along with specifications for closure of slide entrance and piping. Signed and sealed plans and specifications will be delivered electronically in pdf format for the shed roof.
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language)
Fixed Price Cost:
Subtask 1
Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost
Ayres Associates Project Manager 150.34 9 1,353.06
Ayres Associates Sr. Structural Engineer (PE) 144.20 24 3,460.80
Ayres Associates Structural Inspector (CBI) 100.89 0 0
Reimbursable Cost: (if applicable – provide for each task in which reimbursables are required)
Postage $0
Printing $0
Overnight Travel (if applicable)
$0
Mileage (@ $0.445 per mile) Provide the calculation and number for trips and provide total estimated cost 48 mile trip from office to park and back (96 miles)
Reimbursable Total Cost $42.72
Total for Subtask 1: (Fixed Price Cost + Reimbursable)
Project Schedule:
Activity Duration (Calendar Days)
Subtask 1 The signed and sealed letter will be provided within (2) weeks of execution of this change order. The shed roof design will be due by October 16, 2020.
Task 2: Slide Inspection and Report Deliverable
Description: Perform field inspection of Weeki Wachee Springs State Park Water Slide Tower, Pirate’s Revenge Slide and
Cannonball Slide and provide inspection report to be used as basis for contractor bid repairs.
2 – Inspect structure and provide one pdf, 8 ½ x 11, report deliverable to include list of defects, corrective actions taken since the prior inspection, and repair recommendations with photos and slide layout sketches. Report will also include a signed and sealed Affidavit of Compliance and an Excel Spreadsheet of repair recommendations, submitted by February 14, 2020
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language)
Fixed Price Cost:
Subtask 2
Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost
Ayres Associates Project Manager 150.34 1.5 225.51
Ayres Associates Sr. Structural Engineer (PE) 144.20 2 288.40
Ayres Associates Structural Inspector (CBI) 100.89 7 706.23
Printing $0
Overnight Travel (if applicable)
$0
Mileage (@ $0.445 per mile) Provide the calculation and number for trips and provide total estimated cost 48 mile trip from office to park and back (96 miles)
Subtask 2 23 days. After Labor Day, September 7, 2020 and before October 1, 2020. The report will be due by October 16, 2020.
Task 3: Slide Inspection and Report Deliverable
Description: Perform field inspection of Weeki Wachee Springs State Park Water Slide Tower, Pirate’s Revenge Slide and
Cannonball Slide and provide inspection report to be used as basis for documentation/confirmation of contractor repairs.
3 – Inspect structure and provide one pdf, 8 ½ x 11, report deliverable to include list of defects, corrective actions taken since the prior inspection, and repair recommendations with photos and slide layout sketches. Report will also include a signed and sealed Affidavit of Compliance and an Excel Spreadsheet of repair recommendations, submitted by February 14, 2021.
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language)
Fixed Price Cost:
Subtask 3
Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost
Ayres Associates Project Manager 150.34 1.5 225.51
Ayres Associates Sr. Structural Engineer (PE) 144.20 2 288.40
Ayres Associates Structural Inspector (CBI) 100.89 7 706.23
Printing $0
Overnight Travel (if applicable)
$0
Mileage (@ $0.445 per mile) Provide the calculation and number for trips and provide total estimated cost 48 mile trip from office to park and back (96 miles)
Subtask 3 31 days. Between January 1, 2021 and January 31, 2021.The Affidavit of Compliance and will be completed and forwarded to the Department of Agriculture by February 14, 2021.
Summary of Fees:
Subtask Subtask Fixed Price Cost Subtask Reimbursable
Subtask 1 $4,813.86 $42.72
Subtask 2 $1,220.14 $42.72
Subtask 3 $1,220.14 $42.72
Total Fixed Price Cost: $7,254.14
Total Reimbursable Cost: $128.16
Overall Total Cost: $7,382.30
Payment will be made upon approval of deliverables for each subtask by the FDEP in the amount specified. (Please do not alter this language)
File details come from the government source that posted it. Updated .