J.24-D_NCC_Status_Report.docx

DOCX document 282 KB Posted

Attached to
2016 End Stage Renal Disease (ESRD) Networks Federal contract opportunity
Solicitation number
CMS-2016-ESRD-NETWORKS
Issued by
Department of Health and Human Services Centers for Medicare and Medicaid Services

About this file

ESRD National Coordinating Center (NCC) Status Report

View the file

Other files for this federal contract opportunity

Other files attached to 2016 End Stage Renal Disease (ESRD) Networks, newest first.
File Type Posted
Amendment_000009_SF30.pdf PDF
ESRD_NCC_Questions.pdf PDF
J.24-B_NCC_SOW.pdf PDF
ESRD_Amendment_000007_Cover_Letter_.pdf PDF
J.24-C_NCC_SOD.pdf PDF
J.24-A_NCC_SIP_Instructions.pdf PDF
KCER_Questions_ _Answers.pdf PDF
J.23-D_KCER_Monthly_Status_Report_Template.docx DOCX document
ESRD_Amendment_000006_Cover_Letter_.pdf PDF
ESRd_Amendment_000006_SF-30.pdf PDF
J.23-B_KCER_SOW_9.22.2015.pdf PDF
J.23-C_KCER_SOD_9.22.2015.pdf PDF
ESRD_Amendment_000005_Cover_Letter_.pdf PDF
J.23-B_KCER_SOW.pdf PDF
ESRD_Amendment_000004_Cover_Letter_.pdf PDF
ESRD_Amendment_000004.pdf PDF
J-22_ESRD_BP_Forms_-_ESRD_2016-20_07102015.xlsx XLSX spreadsheet
J-4_Reporting_Requirements_07102015_REDLINE.docx DOCX document
ESRD_Amendment_000003.pdf PDF
ESRD_Questions_and_Responses.xlsx XLSX spreadsheet
ESRD_Amendment_000003_Cover_Letter_.pdf PDF
J-9__Healthcare-Associated_Infections_and_the_National_Healthcare_Safety_Network_07102015.docx DOCX document
J-1_SOD_07102015.docx DOCX document
ESRD_Amendment_000002_Cover_Letter_.pdf PDF
J-2_Style_Guide.docx DOCX document
ESRD_Amendment_000001.pdf PDF
J-22a_ESRD_BP_Instructions.docx DOCX document
J-22_ESRD_BP_Forms_-ESRDFY2016-20.xlsx XLSX spreadsheet
J-9__Healthcare-Associated_Infections_and_the_National_Healthcare_Safety_Network.docx DOCX document
J-17_Small_Business_Subcontracting_Plan_Template.doc DOC document
J-20_Information_Security_Attestation.docx DOCX document
J-21_Question_Submission_Template.xlsx XLSX spreadsheet
J-2_Style_Guide.docx DOCX document
J-22_ESRD_BP_Forms_-_ESRD_2016-20.xlsx XLSX spreadsheet
J-8_Grievance_Overview.docx DOCX document
J-6_Learning_and_Action_Networks.docx DOCX document
J-1_SOD_06182015.docx DOCX document
ESRD_NETWORK_RFP.pdf PDF
J-15_HHS_565_Form.pdf PDF
J-14_Consent_to_Subcontract.docx DOCX document
J-4_Reporting_Requirements.docx DOCX document
J-7_Quality_Improvement_Activities.docx DOCX document
J-5_Recommendations_for_Sanctions_and_Alternative_Sanctions.docx DOCX document
J-12_CROWNWeb.docx DOCX document
J-3_Paperwork_Reduction_Act.docx DOCX document
Preproposal_conference.docx DOCX document
Synopsis_ESRD.docx DOCX document
UPDATED_2016_ESRD_Networks_SS.docx DOCX document
2016_ESRD_Networks_SS.docx DOCX document
ESRD_Network_Map.docx DOCX document
Show all 50

2016 End Stage Renal Disease (ESRD) Networks has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

<SPECIAL PROJECT LETTERHEAD>

<SPECIAL PROJECT LOGO>

ESRD NATIONAL COORDINATING CENTER (NCC)

MONTHLY STATUS REPORT – <MONTH> <YEAR>

Contract Name: <NAME>Reporting Period: <Month> <Year>
Project Director:<NAME>Date Submitted:<Month Date>, <Year>

CMS Contracting Officer Representative: <NAME>

Issues Needing Executive Intervention

· Ex. Currently, there are no items identified that need executive intervention.

Key Accomplishments Performed during the Period

· Ex. Grievance Satisfaction Survey: The pilot was completed with 9 administered initial tests and 8 administered re-test surveys on July 15, 2014.

Key Milestones for Next Period

· Ex. 07/24/14 Release 12.0 Pre-Release Distribution V

STATUS KEY
TREND FROM PREVIOUS MONTH
Controlled
Caution
Critical
Not Started
Complete
Improved
Stable
Declined
None/minor issues or risks; proceeding as planned
At risk; plan in place to avoid getting off track or pending a CMS decision
Off track; needs intervention
Project has not started as of yet; not applicable
All deliverables within the subtask have been completed
Improving and expected to remain so
No changes but not expected to need escalation outside of project team
Worsening and may need executive intervention to resolve

Overall Contract Performance Assessment

Topic
Status/ Trend
Comments and Concerns

Overall Status & Trending

Contract Management

Topic
Status/ Trend
Comments and Concerns

Overall Contract Management

Scope Adherence

Contract Team Communication

Contract Change Management

Contract Budget

Deliverables (list for reporting month)

Subtask
Deliverable #
Date Submitted
Date Approved by COR
Details/Comments

Individual Task Assessment

Task 1 – Support for Clinical AIM 1

Subtask 1.A Foster Patient and Family Engagement at the National Level

Status/Trend

Key Progress
·
Risks and Mitigation Actions
·
Next Month’s Action Items
·
90 Day Forecast
·
GTL/COR Hot List
·

Notes

Subtask 1.A.1 Develop and Recruit Members for a National Patient LAN

Status/Trend

Key Progress
·
Risks and Mitigation Actions
·
Next Month’s Action Items
·
90 Day Forecast
·
GTL/COR Hot List
·

Notes

Subtask 1.A.2 Enhance and Sustain the NPFE_LAN

Status/Trend

Key Progress
·
Risks and Mitigation Actions
·
Next Month’s Action Items
·
90 Day Forecast
·
GTL/COR Hot List
·

Notes

Subtask 1.A.3 Spread the Work of the NPFE_LAN

Status/Trend

Key Progress
·
Risks and Mitigation Actions
·
Next Month’s Action Items
·
90 Day Forecast
·
GTL/COR Hot List
·

Notes

Subtask 1.B – Improve Grievant Experience of Care and Evaluation and Resolution of Grievances

Status/Trend

Key Progress
·
Risks and Mitigation Actions
·
Next Month’s Action Items
·
90 Day Forecast
·
GTL/COR Hot List
·

Notes

Subtask 1.B.1 ESRD Grievant Satisfaction Survey

Status/Trend

Key Progress
·
Risks and Mitigation Actions
·
Next Month’s Action Items
·
90 Day Forecast
·
GTL/COR Hot List
·

Notes

Subtask 1.B.2 Administration of the Grievant Satisfaction Survey

Status/Trend

Key Progress
·
Risks and Mitigation Actions
·
Next Month’s Action Items
·
90 Day Forecast
·
GTL/COR Hot List
·

Notes

Subtask 1.B.3 Process for the Administration of the Grievant Satisfaction Survey including initial preparation for Survey administration; and actual Survey Administration

Status/Trend

Key Progress
·
Risks and Mitigation Actions
·
Next Month’s Action Items
·
90 Day Forecast
·
GTL/COR Hot List
·

Notes

Subtask 1.B.4 Analysis of National Grievance Data

Status/Trend

Key Progress
·
Risks and Mitigation Actions
·
Next Month’s Action Items
·
90 Day Forecast
·
GTL/COR Hot List
·

Notes

Subtask 1.B.5 Development of Grievance Related CMS Publications

Status/Trend

Key Progress
·
Risks and Mitigation Actions
·
Next Month’s Action Items
·
90 Day Forecast
·
GTL/COR Hot List
·

Notes

Subtask 1.C. ICH-CAHPS

Status/Trend

Key Progress
·
Risks and Mitigation Actions
·
Next Month’s Action Items
·
90 Day Forecast
·
GTL/COR Hot List
·

Notes

Subtask 1.C.1. Data Support for ICH-CHAPS

Status/Trend

Key Progress
·
Risks and Mitigation Actions
·
Next Month’s Action Items
·
90 Day Forecast
·
GTL/COR Hot List
·

Notes

Subtask 1.C.2 Clinical Support for ICH-CAHPS

Status/Trend

Key Progress
·
Risks and Mitigation Actions
·
Next Month’s Action Items
·
90 Day Forecast
·
GTL/COR Hot List
·

Notes

Subtask 1.D Supporting Facility Vascular Access Reporting, Spread of Best Practices, and Provision of Technical Support

Status/Trend

Key Progress
·
Risks and Mitigation Actions
·
Next Month’s Action Items
·
90 Day Forecast
·
GTL/COR Hot List
·

Notes

Subtask 1.D.1 Fistula First Catheter Last Workgroup Coalition

Status/Trend

Key Progress
·
Risks and Mitigation Actions
·
Next Month’s Action Items
·
90 Day Forecast
·
GTL/COR Hot List
·

Notes

Subtask 1.D.2 Data Support for the Increased use of AVFs and Decreased Use of Catheters

Status/Trend

Key Progress
·
Risks and Mitigation Actions
·
Next Month’s Action Items
·
90 Day Forecast
·
GTL/COR Hot List
·

Notes

Subtask 1.E.1 Reduce HAIs – Establish National HAI LAN

Status/Trend

Key Progress
·
Risks and Mitigation Actions
·
Next Month’s Action Items
·
90 Day Forecast
·
GTL/COR Hot List
·

Notes

Subtask 1.E.2 Data Support for HAI Vaccination QIA

Status/Trend

Key Progress
·
Risks and Mitigation Actions
·
Next Month’s Action Items
·
90 Day Forecast
·
GTL/COR Hot List
·

Notes

TASK 2

Support for Population Health Projects

Subtask 2.A Data Support for Network Population Health Projects

Status/Trend

Key Progress
·
Risks and Mitigation Actions
·
Next Month’s Action Items
·
90 Day Forecast
·
GTL/COR Hot List
·

Notes

Subtask 2.B Clinical Support for Network Population Health Projects

Status/Trend

Key Progress
·
Risks and Mitigation Actions
·
Next Month’s Action Items
·
90 Day Forecast
·
GTL/COR Hot List
·

Notes

TASK 3

Support for Clinical AIM 3

Subtask 3.A Support for the ESRD QIP, DFC, Star Ratings and DFR for Performance Improvement

Status/Trend

Key Progress
·
Risks and Mitigation Actions
·
Next Month’s Action Items
·
90 Day Forecast
·
GTL/COR Hot List
·

Notes

Subtask 3.B Clinical Support for the ESRD QIP Projects

Status/Trend

Key Progress
·
Risks and Mitigation Actions
·
Next Month’s Action Items
·
90 Day Forecast
·
GTL/COR Hot List
·

Notes

Task 4 Maintenance, Enhancement, Security of the ESRD Network Data Warehouse

Subtask 4. A Data Warehouse

Status/Trend

Key Progress
·
Risks and Mitigation Actions
·
Next Month’s Action Items
·
90 Day Forecast
·
GTL/COR Hot List
·

Notes

Next Month’s Action Items
·
90 Day Forecast
·
GTL/COR Hot List
·

Notes

Subtask 4.B Support for Crown Web

Status/Trend

Key Progress
·
Risks and Mitigation Actions
·
Next Month’s Action Items
·
90 Day Forecast
·
GTL/COR Hot List
·

Notes

Subtask 4.C Participation in CROWNWEB User Group Meetings

Status/Trend

Key Progress
·
Risks and Mitigation Actions
·
Next Month’s Action Items
·
90 Day Forecast
·
GTL/COR Hot List
·

Notes

Subtask 4.D ESRD Dashboard Support

Status/Trend

Key Progress
·
Risks and Mitigation Actions
·
Next Month’s Action Items
·
90 Day Forecast
·
GTL/COR Hot List
·

Notes

Subtask 4.E Support for Clinical AIM Data Analysis

Status/Trend

Key Progress
·
Risks and Mitigation Actions
·
Next Month’s Action Items
·
90 Day Forecast
·
GTL/COR Hot List
·

Notes

Subtask 4.F Clinical AIMs Data Extract, Reporting Business Requirements, and Development of Business Requirements

Status/Trend

Key Progress
·
Risks and Mitigation Actions
·
Next Month’s Action Items
·
90 Day Forecast
·
GTL/COR Hot List
·

Notes

Subtask 4.G Support for Change Management

Status/Trend

Key Progress
·
Risks and Mitigation Actions
·
Next Month’s Action Items
·
90 Day Forecast
·
GTL/COR Hot List
·

Notes

Subtask 4.H Infrastructure Operations Support

Status/Trend

Key Progress
·
Risks and Mitigation Actions
·
Next Month’s Action Items
·
90 Day Forecast
·
GTL/COR Hot List
·

Notes

Subtask 4.I ESRD Security Compliance

Status/Trend

Key Progress
·
Risks and Mitigation Actions
·
Next Month’s Action Items
·
90 Day Forecast
·
GTL/COR Hot List
·

Notes

Task 5 ESRD NCC Project Management and Communication

Subtask 5.A Strategic Plan

Status/Trend

Key Progress
·
Risks and Mitigation Actions
·
Next Month’s Action Items
·
90 Day Forecast
·
GTL/COR Hot List
·

Notes

Subtask 5.B Internal Quality Improvement Program

Status/Trend

Key Progress
·
Risks and Mitigation Actions
·
Next Month’s Action Items
·
90 Day Forecast
·
GTL/COR Hot List
·

Notes

Subtask 5.C Comprehensive Progress and Status Report

Status/Trend

Key Progress
·
Risks and Mitigation Actions
·
Next Month’s Action Items
·
90 Day Forecast
·

GTL/COR Hot List

Notes

Subtask 5.D Change of Key Personnel

Status/Trend

Key Progress
·
Risks and Mitigation Actions
·
Next Month’s Action Items
·
90 Day Forecast
·
GTL/COR Hot List
·

Notes

Task 6 End of Contract Transition

Status/Trend

Key Progress
·
Risks and Mitigation Actions
·
Next Month’s Action Items
·
90 Day Forecast
·
GTL/COR Hot List
·

Notes

Task 7 National Coordinating Role for the ESRD Network Program

Subtask 7.A Plan, Facilitate, Participate in National/Regional/Local Meetings

Status/Trend

Key Progress
·
Risks and Mitigation Actions
·
Next Month’s Action Items
·
90 Day Forecast
·
GTL/COR Hot List
·

Notes

Subtask 7.B Serve as Lead ESRD Program Planner/Organizer for the CMS Annual QualityNet Conference

Status/Trend

Key Progress
·
Risks and Mitigation Actions
·
Next Month’s Action Items
·
90 Day Forecast
·
GTL/COR Hot List
·

Notes

Subtask 7.C Actively Participate in and or attend National and Regional Meetings

Status/Trend

Key Progress
·
Risks and Mitigation Actions
·
Next Month’s Action Items
·
90 Day Forecast
·
GTL/COR Hot List
·

Notes

Subtask 7.D Support ESRD Network Refresh of Standard Computer hardware and Software

Status/Trend

Key Progress
·
Risks and Mitigation Actions
·
Next Month’s Action Items
·
90 Day Forecast
·
GTL/COR Hot List
·

Notes

Subtask 7.E Clinical Aim Resource Library – Facilitate and Exchange of ESRD Network and Patient Information, Tools, Resources, and other Materials

Status/Trend

Key Progress
·
Risks and Mitigation Actions
·
Next Month’s Action Items
·
90 Day Forecast
·
GTL/COR Hot List
·

Notes

Subtask 7.F Clinical AIMS Marketing and Social Media Responsibilities

Status/Trend

Key Progress
·
Risks and Mitigation Actions
·
Next Month’s Action Items
·
90 Day Forecast
·
GTL/COR Hot List
·

Notes

Task 8 Development and Lead Authorship, Limited Printing, and Distribution of the Directory of ESRD Network Organizations

Status/Trend

Key Progress
·
Risks and Mitigation Actions
·
Next Month’s Action Items
·
90 Day Forecast
·
GTL/COR Hot List
·

Notes

Task 9 Development, Lead Authorship, Printing and Distribution of the End Stage Renal Disease Network Organization Program Summary Annual Report

Status/Trend

Key Progress
·
Risks and Mitigation Actions
·
Next Month’s Action Items
·
90 Day Forecast
·
GTL/COR Hot List
·

Notes

Task 10 Maintenance and Ongoing Development/Enhancement of a Centralized Website for the ESRD Network Program, Including All ESRD – Related Special Projects

Status/Trend

Key Progress
·
Risks and Mitigation Actions
·
Next Month’s Action Items
·
90 Day Forecast
·
GTL/COR Hot List
·

Notes

Task 11 Maintain a System for the Identification of all New Dialysis Patients and Distribute New Patient Orientation packets (NEPOPs) Monthly to New Patients

Status/Trend

Key Progress
·
Risks and Mitigation Actions
·
Next Month’s Action Items
·
90 Day Forecast
·
GTL/COR Hot List
·

Notes

Task 12 Provide Administrative Support to CMS as Requested

Status/Trend

Key Progress
·
Risks and Mitigation Actions
·
Next Month’s Action Items
·
90 Day Forecast
·
GTL/COR Hot List
·

Notes

Scheduled Milestones

Milestone
Due Date(s)
Current Forecast
Status

Monthly Status Report Appendices

The CMS COR/GTL as well as the NCC Program Director shall be consulted as to what data and/or supplementary documentation should be included in each Monthly Status Report’s Appendix section.

Version 1.0 July 15, 2015

ESRD National Coordinating Center Monthly Status Report – <Month>

Version 3.0: 07-14-2015 image7.png image8.png image9.png image10.png image11.png image12.png

File details come from the government source that posted it. Updated .