CMS Site Reno Addendum No. 4 - 260512-01.pdf
PDF 944 KB Posted
- Solicitation number
- S-P26028-00016709
- Issued by
- Oregon
About this file
This is Addendum No. 4 to the contract documents for the Centennial Middle School Site Renovations Project #260512-01 in Oregon, issued by the Centennial School District on May 6, 2026. The addendum clarifies design specifications and construction requirements for site improvements including asphalt paving (20,372 SF of AC area plus 436 SF of additional AC area), concrete sidewalks and pedestrian pavements, curbing, drainage systems, landscaping, and fencing. The bid due date remains unchanged at Tuesday, May 12, 2026, at 2:00 PM. The addendum includes a revised drawing (Sheet C4.0 - Paving and Horizontal Control Plan, dated 5/6/2026) and provides responses to eight contractor questions regarding material specifications, concrete reinforcement requirements, expansion joint details, tree maintenance responsibilities, drainage specifications, seeding scope, and temporary fencing requirements.
Key clarifications include establishing that civil drawings govern over landscape drawings for pedestrian sidewalk specifications; requiring reinforcement of the mower travel area (315 SF) with #3 rebar spaced every 12 inches on center with control joints every 6 feet; mandating 12-inch expansion joints with silicone sealant between existing curbing and proposed sidewalk and between existing building foundation and proposed asphalt; confirming trees are included in the contract scope with contractor-provided watering bags until project turnover; limiting seeding to disturbed areas only; and requiring full site fencing that can combine temporary and permanent components. All subcontractors affected by this addendum must be notified of these changes.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CENTENNIAL MIDDLE SCHOOL SITE RENOVATIONS
PROJECT #260512-01
May 6, 2026
ADDENDUM NO. FOUR (4)
THE FOLLOWING CHANGES, ADDITIONS, AND DELETIONS TO THE CONTRACT DOCUMENTS
DATED MAY 6, 2026, HEREBY BECOME A PART OF THE CONTRACT DOCUMENTS, PER THE
ORIGINAL CONTRACT DOCUMENTS DATED APRIL 22, 2026.
NOTIFY ALL SUBCONTRACTORS AFFECTED BY THIS ADDENDUM.
BID DUE UNCHANGED: Tuesday, May 12, 2026, 2:00 PM
SPECIFICATIONS
N/A
DRAWINGS
C4.0 Revised Attached
GENERAL INFORMATION
Item 2. QUESTION: Landscape Drawings call for reinforced with thickened edge concrete sidewalk, but civil legend says “unreinforced” 4” ped sidewalk. Which one should we follow?
ANSWER:
A. Civil shall govern. The existing extruded curb along the parking lot to remain.
B. A callout has been added to the back edge of existing curb as follows: “Construct ½”
Expansion Joint with silicone sealant at top between back of existing curb and proposed sidewalk.” Refer to revised Sheet C4.0, attached.
C. A callout to reinforce an area of concrete where mower will travel has been added, as follows:
“Reinforce mower travel area, 315 SF, with #3 Rebar spaced every 12” on mid slab. Construct control joints every 6’ in this area”. Refer to revised Sheet C4.0, attached.
Item 3. QUESTION: 1A/L5.1 shows no base rock below sidewalk, but civil legend on C4.1 calls for 6” rock over geotextile. Which detail should we follow?
ANSWER:
A. Civil shall govern. Refer to Paving Legend on C4.0.
Item 4. QUESTION: Can you provide a detail for asphalt paving, or should we just use the legend on
C4.0 as a guideline?
ANSWER:
A. Refer to Paving Legend on C4.0 for paving section.
B. A callout has been added at the existing building foundation and new asphalt interface as follows: “Construct ½” Expansion Joint with silicone sealant at top between existing building foundation and proposed asphalt paving.” Refer to revised Sheet C4.0, attached.
Item 5. QUESTION: Are the trees on L3.1 in this contract? If so, how will they get watered?
A. Yes, trees are in the contract.
CENTENNIAL MIDDLE SCHOOL SITE RENOVATIONS
PROJECT #260512-01
May 6, 2026
ADDENDUM NO. FOUR (4)
B. Trees shall be provided with watering bags and filled till project turnover, at which point the district will maintain those.
Item 6. QUESTION: What detail are we to follow for the EWF area? 1E/L5.1, or 9/C5.0?
A. Both apply. Refer to Landscape drawings for elevations and edge details for EWF, per Addendum 3. Refer to Civil for drain rock and perforated pipe below EWF, per Addendum 3.
Item 7. QUESTION: L3.1 shows seeding that’s outside of the work zone area. Should we bid to seed this area even though we’re not disturbing it? Are we supposed to bid to strip/haul-off the sod in this area and re-seed?
ANSWER:
A. Only in areas disturbed.
B. Refer to note in Legend on L3.1.
Item 8. QUESTION: Is temp fencing required surrounding the entire site?
A. Yes, the construction zone must be fully fenced but can be a combination of temporary and permanent components.
END OF ADDENDUM FOUR (4)
Attachments: C4.0 dated 5/6/2026
DW
CB
CB
CB
CO CO
CO
COCO
CO
CO
CO
PAVING AND
HORIZONTAL
CONTROL PLAN
C4.0
PLAN SCALE
N
PAVING AND HORIZONTAL CONTROL PLAN
SCALE: 1" = 10'
74-23118-00
03/20/2026
C
EN
TE
N
N
IA
L M
ID
D
LE
S
C H
O O
L
- P
LA
Y
AR
EA
BID & PERMIT SET
REVISIONS
A B C D E F
C4.0
SO
U
TH
EA
ST
B R
O O
KL
YN
S
TR
EE
T
CE
NT
EN
NI
AL
S
CH
OO
L
DI
ST
RI
CT
EXPIRATION DATE: 06/30/26
91653PE
OREGON
ENG INEER
SEPT 13 , 20 16
A N
DREA W . STANCL
I F
F
RE
G I S
TERED PROFESS IONAL
1498 E. Main Street, Suite 103, #345
Cottage Grove, Oregon 97424 www.gaia-engineering.com
503-830-3635
PO
R
TL
AN
D , O
R
EG
O N
CONST PCC
CONCRETE AREA,
40 SF
CONSTRUCTION NOTES
1. CONSTRUCT FULL DEPTH CURB PER DETAIL 6, SHEET C5.0.
2. CONSTRUCT AT GRADE CURB PER DETAIL 6, SHEET C5.0.
3. CONSTRUCT VALLEY GUTTER PER DETAIL 7, SHEET C5.0.
4. CONSTRUCT MOUNTABLE CURB PER DETAIL 8, SHEET C5.0.
PAVING LEGEND
PLAY AREA ASPHALT PAVEMENT
3" COMPACTED LIFT, ASPHALT PAVEMENT, OVER
6" COMPACTED DEPTH, 1 1/2"-0 CRUSHED ROCK, OVER
GEOTEXTILE FABRIC, OVER
APPROVED SUBGRADE
PEDESTRIAN CONCRETE PAVEMENTS
4" DEPTH 3,000 PSI PCC PAVEMENT (NON-REINFORCED) OVER
6" MINIMUM DEPTH 34"-0 CRUSHED ROCK BASE OVER
GEOTEXTILE FABRIC OVER
APPROVED SUBGRADE.
CHANGE OF CURB TYPE
290 LF2
REFER TO LANDSCAPE PLANS
AND SPECIFICATIONS FOR
PROPOSED PLAY AREA
STRIPING LAYOUT AND
INSTALLATION REQUIREMENTS
EXISTING SCHOOL
FFE=262.43'
EXISTING
PARKING
LOT
EXISTING ASPHALT
TRACK AREA
EXISTING
PROPERTY LINE,
TYP.
PROPOSED CONCRETE
AREA, REFER TO
LANDSCAPE
ARCHITECT PLANS
FOR JOINTING PLAN
PROPOSED ASHALT
CONCRETE (AC) AREA,
20,372 SF
5' CURB
TRANSITION
16 LF 1
4 LF 1
2' CURB TRANSITION
2' CURB TRANSITION
12" WIDE CONCRETE FENCE
FOUNDATION, TYP.
SEE LANDSCAPE ARCHITECT
PLANS
SWING SET AREA EDGING, TYP.
SEE LANDSCAPE ARCHITECT
PLANS
10 LF 4
3' CURB TRANSITION
3' CURB TRANSITION
100 LF 3
CHAINLNK FENCE
AND POSTS, TYP.
SEE LANDSCAPE
ARCHITECT PLANS
FOR DETAILS
CAUTION! EX LIGHT
POLE AND ELECTRICAL
CONDUIT TO REMAIN
AND BE PROTECTED IN
PLACE DURING
CONSTRUCTION
CAUTION! EX LIGHT
POLE AND ELECTRICAL
CONDUIT TO REMAIN
AND BE PROTECTED IN
PLACE DURING
CONSTRUCTION
POINT NORTHING EASTING DESCRIPTION
ASPHALT/CURB
POINT TABLE - ASPHALT AND CURBS
165024.05 397319.751
ASPHALT/CURB
ASPHALT/CURB
ASPHALT/CURB
ASPHALT
ASPHALT
ASPHALT
CURB TRANSITION
CURB
CURB
VALLEY GUTTER
33 34
43 44
165024.07 397322.25
165024.08 397323.72
165024.10 397325.72
165030.05 397320.18
165030.10 397325.68
165024.27 397347.77
165034.11 397347.77
165034.05 397336.71
165048.76 397325.56
165048.79 397319.75
ASPHALT/CURB
ASPHALT/CURB
ASPHALT
ASPHALT
165042.14 397320.03
165042.14 397314.54
165042.14 397229.63
165031.97 397319.47
164999.95 397219.48
ASPHALT/CURB
CURB
CURB
CURB
CURB
164990.12 397209.96
164990.12 397193.00
164979.95 397182.84
164890.51 397182.83
164880.44 397192.99
164880.96 397196.15
164878.59 397198.03
164857.92 397196.24
164848.16 397116.64
CURB
CURB
CURB
CURB
CURB
164848.01 397084.52 CURB
164847.13 397114.34 CURB
164844.21 397117.34 CURB
164859.57 397211.78 CURB TRANSITION
164861.01 397214.43 MOUNTABLE CURB
164865.77 397223.23
164867.20 397225.86 CURB TRANSITION
MOUNTABLE CURB
164878.59 397296.62 VALLEY GUTTER
164876.70 397323.17 CONCRETE WALK
164876.73 397326.73 CONCRETE WALK
164880.95 397321.76 CURB
164882.53 397326.70 CONCRETE WALK
164886.33 397326.67 CONCRETE WALK
164890.53 397326.66 CONCRETE WALK
164900.33 397321.61 CURB
165014.86 397194.86 EDGING
165014.86 397102.20 EDGING
165048.53 397102.20 EDGING
165048.53 397194.86 EDGING
NOTE: REFER TO SURVEY DRAWING FOR CONTROL POINTS
PROPOSED ASHALT
CONCRETE (AC) AREA,
436 SF
PROPOSED ROOF STRUCTURE
AND CONCRETE FOOTINGS.
REFER TO SEPARATE PLANS AND
SPECIFICATIONS FOR DETAILS
2 04/21/2026 ADDENDUM #2
REINFORCE MOWER
TRAVEL AREA, 315 SF,
WITH #3 REBAR
INSTALLED EVERY 12"
ON CENTER, MID SLAB.
CONSTRUCT CONTROL
JOINTS EVERY 6' IN
THIS AREA.
CONSTRUCT 12" EXPANSION JOINT
WITH SILICONE SEALANT AT TOP,
BETWEEN BACK OF EXISTING CURB
AND PROPOSED SIDEWALK, TYP.
CONSTRUCT 12" EXPANSION JOINT
WITH SILICONE SEALANT AT TOP,
BETWEEN EXISTING BUILDING
FOUNDATION AND PROPOSED
ASPHALT PAVING, TYP.
CONSTRUCT 10 LF
THICKENED EDGE ON
SIDEWALK PER DETAIL
1A, SHEET L5.1
4 05/06/2026 ADDENDUM #4
C4.0
ISOLATION JOINT
NOT TO SCALE
AutoCAD SHX Text
1 INCH = FT.
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text 2 C4.0
AutoCAD SHX Text 2 C4.0
| Addendum No. 4 - 260512-01 |
| C4.0 - PAVING AND HORIZONTAL CONTROL PLAN - ADD-04 |
| Sheets and Views |
| C4.0 |
File details come from the government source that posted it. Updated .