CMAR_106232_ECG_Renovations_-_Project_Info_and_Scope.pdf

PDF 263 KB Posted

Attached to
RFQ CMAR 106232 ECG Renovations
Solicitation number
106232
Issued by
Maricopa County, Tucson City, Arizona

About this file

This Project Information and Scope document outlines Construction Manager at Risk (CMAR) services for Arizona State University's Engineering Center G-Wing (ECG) renovation project located at 501 E Tyler Mall, Tempe, Arizona. The project involves renovating the 2nd and 3rd floors of the ECG building, including window replacements, audio-visual and lighting systems, classroom and office renovations, fire sprinkler and alarm systems, mechanical and plumbing upgrades, restroom improvements, and associated work. The work will be executed in phases to minimize disruption to building operations, with no more than one floor out of commission during any academic semester unless otherwise approved. The CMAR selection is scheduled for December 2026, followed by permitting in January 2027 and guaranteed maximum price (GMP) establishment in February 2027. Arizona Board of Regents (ABOR) Individual Project Approval is required in April 2027 before construction begins. The 3rd floor construction is projected to start in May 2027 with substantial completion in December 2027, while 2nd floor construction begins in January 2028 with substantial completion in August 2028. The project includes a two-year warranty period following substantial completion, extending through August 2030.

The estimated project budget ranges from $18,000,000 to $21,000,000, with final fees to be established using a Progressive Fee Schedule based on a Project Complexity Coefficient considering delivery method, renovation scope, project location, and schedule. Pre-construction fees are intentionally set higher than market benchmarks to ensure adequate planning and resource allocation, while construction phase fees align with prevailing market standards. General Conditions/General Requirements may be reviewed and refined on a project-specific basis subject to owner approval. The CMAR's pre-construction responsibilities include attending meetings, preparing Critical Path Method schedules, conducting constructability reviews and value engineering, providing conceptual cost estimates, pre-selecting subcontractors using a qualifications-based process, and negotiating the final GMP. The project requires LEED Silver certification compliance, close coordination with a separate Design Professional and Owner's Commissioning Provider, and adherence to ASU Project Guidelines and Arizona Board of Regents Construction Cost Control guidelines. ASU retains the right to cancel agreements at its discretion and reserves the right to contract with separate entities for future phases.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Project Information and Scope of Services

NOTE: ASU reserves the right to cancel all agreements at their discretion.

The selected CMAR will provide effective management of the project’s schedule, cost, quality, safety, scope, and functionality as outlined below, throughout the project and for the duration of the two-year warranty period following substantial completion.

1. Site Description

A. ECG is located at 501 E Tyler Mall, Tempe, AZ 85281, and highlighted in blue below:

2. Project Description

A. This project will renovate the 2nd and 3rd floors of the Engineering Center G-Wing (ECG) building. The work will include, but is not limited to,

● aesthetically similar window replacements and finishes

● audio visual, ceiling, and lighting systems

● classroom and office renovations

● fire sprinkler and alarm

● mechanical, plumbing, and electrical

● restroom upgrades

● and other associated improvements required to support the renovated spaces.

B. The contractor will be required to coordinate closely with other ASU departments and project stakeholders.

C. This project is planned to be completed in phases to minimize impacts to building operations and occupancy. Phasing shall be developed so that no more than one floor is out of commission during any academic semester, unless otherwise approved by the Owner. Phasing may lengthen the typical construction schedule as the priority is to minimize disruption to the learning environment.

D. This project will be built in accordance with:

● ASU Project Guidelines

● ABOR Construction Cost Control and Professional Fee Guidelines

● Applicable state and local codes

● ASU Comprehensive Development Plan

● ASU is the Authority Having Jurisdiction (AHJ)

E. ASU intends to award this contract to a single firm. ASU, at its sole discretion, reserves the right to terminate this contract in full, without any further obligation, if officials determine that it is an unsatisfactory instrument to move the project forward. ASU also reserves the right to contract with a separate entity.

3. Project Budget

Estimated Project Budget: $18,000,000 - $21,000,000

An approved construction budget will be developed by ASU together with the selected DP and CMAR.

4. Progressive Fee Schedule

A. ASU has implemented a fee schedule to establish consistency, transparency, and alignment with market conditions across all project delivery methods.

B. Preconstruction and Construction phase fees, as well as General Conditions/ General

Requirements (GC/GRs) are calculated with a Progressive Fee Schedule.

C. ASU intends to apply fees within the ranges shown below.

D. Final project fees will be established using a Project Complexity Coefficient, considering the factors listed below.

i) Delivery Method

ii) New vs Renovation

iii) Project Scope

iv) Project Location

v) Project Schedule https://cfo.asu.edu/design-professionals http://www.azregents.edu/sites/default/files/reports/Cost-Control-Guidelines-ALL.pdf https://cfo.asu.edu/campus-planning

● Preconstruction Fees have been intentionally set higher than typical market benchmarks to ensure the contractor devotes the appropriate resources, expertise, and time necessary to rigorously plan, schedule, and budget the project. ASU views this investment as critical to achieving cost certainty at GMP and minimizing risk during construction.

● Construction Phase Fees are aligned with prevailing market benchmarks and are applied consistently to ensure equitable treatment of all proposers.

● General Conditions/General Requirements (GC/GRs) may be reviewed and refined on a project-specific basis, subject to Owner approval. While the maximum GC/GRs percentage remains in effect, ASU may consider adjustments to the composition of GC/GRs where appropriate.

● Certain high-cost items may be evaluated to determine whether they are more appropriately a direct cost line item within the Schedule of Values rather than embedded within GC/GRs.

E. Fees may be recalculated if there is a significant change order as required by the Owner.

5. Estimated Project Schedule

A. Capital projects with an estimated total project cost of $10 million or more require approval from the Arizona Board of Regents (ABOR). This approval is required on projects for new construction, renovations, and major infrastructure improvements at ASU, NAU, and UA. Projects with an estimated total cost under $10 million require only university level approval.

B. Before the construction phase on this project may begin, an Individual Project Approval

(IPA) from ABOR will be required. The project may be delayed due to this approval process.

DP Selection Completed

CxP Selection October 2026

CMAR Selection December 2026

Permitting January 2027

GMP @ Permitted Design February 2027

ABOR IPA April 2027

3rd Floor

Construction Start May 2027

Commissioning Complete December 2027

Substantial Completion December 2027

Client Move-in Complete January 2028

2nd Floor

Construction Start January 2028

Commissioning Complete July 2028

Substantial Completion August 2028

Client Move-in Complete August 2028

Project Closeout October 2028

Two-Year Warranty Term Complete August 2030

6. Scope of Services

A. Proposed services include Construction Manager at Risk (CMAR) services during both the Pre-Construction and Construction phases of the project. Under the conditions outlined below, ASU will enter into separate contracts for the design and construction phase of the Project. Design services will be provided by a separate awarded Design Professional under a separate design phase services agreement.

B. Pre-Construction services are anticipated to begin at Schematic Design Phase of the project or potentially earlier in some cases. Pre-Construction services will include, among others:

● Attend and assist at all meetings and CMAR-designated activities.

● Prepare and maintain a Critical Path Method (CPM) schedule, including phasing if applicable.

● Conduct constructability reviews, system evaluations, and value engineering.

● Provide conceptual cost estimates throughout design to accurately forecast the

GMP.

● Collaborate with ASU, Design Professionals, Cx Provider, consultants, and subcontractors.

● Pre-select subcontractors using a qualifications-based process.

● Prepare and negotiate the final GMP with necessary documentation.

C. Sustainability is a very important aspect of the program and this project is expected to comply with the new sustainability guidelines that have been incorporated into the ASU Project Guidelines. In addition, ASU has its own Sustainable Advisory Committee, and the Design Team and CMAR may meet with this committee to address compliance with the guidelines. If the project meets the minimum program requirements set by the U.S. Green Building Council, it will achieve LEED Silver certification at a minimum, with LEED Silver https://www.asu.edu/fm/documents/project_guidelines/Project-Guidelines.pdf https://www.asu.edu/fm/documents/project_guidelines/Project-Guidelines.pdf as the project’s goal. The CMAR will work directly with the Owner, Commissioning Provider (CxP), and Design Professional (DP) to meet the established LEED targets. LEED certification must be obtained within 12 months following substantial completion.

D. Engineering Center G-Wing (ECG) meets the requirement to be on the Historic

Preservation List but doesn’t have a formal designation. (Facilities that are at least 50 years old, demonstrate historical significance and possess historic integrity may qualify.)

E. Commissioning. The CMAR shall coordinate closely with the Owner's Commissioning

Provider (CxP) to ensure proper commissioning of all equipment and systems. While the Owner’s CxP will oversee the process, this does not absolve the CMAR of the responsibility to deliver a fully functional and operational system(s). The Owner expects the CxP to be engaged from the development of the Owner’s Project Requirements (OPR) through design and submittal reviews, construction activities (including startup and commissioning), and final functional testing.

F. The CMAR must collaborate with the CxP to ensure that the systems perform as required under all conditions and continue to operate consistently year-round and into the foreseeable future. Additionally, follow-up reviews involving the CMAR, their subcontractors, and the CxP will be conducted one year after commissioning completion and again two years after substantial completion.

G. Additional phases may be released in separate drawing packages if, during the development of the project's scope, schedule, and budget, it is determined that phasing is necessary for optimal execution. It is important to note that the CMAR awarded the first phase is not guaranteed future phases. The awarded CMAR's performance will be continuously evaluated throughout both the preconstruction and construction phases and discussed during weekly meetings with ASU’s Project Manager.

H. If ASU and the CMAR agree on a guaranteed maximum price, and ASU receives the required approvals, ASU and CMAR will enter into an agreement that will cover preconstruction, construction, commissioning support, and warranty services for the project.

I. The above description of the proposed services provides a brief overview and is not a comprehensive outline of the project’s full scope of work. Prospective proposers are strongly encouraged to submit questions to Procurement through the Questions and Answer Board within this SunRISE/Jaggaer electronic bidding portal and attend the scheduled Pre-Submittal for more detailed information.