ClocksBid (1).pdf

PDF 608 KB Posted

Attached to
Clock System Replacement
Solicitation number
RFP-RVS-190000001400-1
Issued by
Berrien County, Michigan

About this file

This is a Request for Bid (RFB) document from River Valley School District in Three Oaks, Michigan, seeking a comprehensive clock system installation across three district buildings: River Valley Middle High School, Chikaming Elementary, and Three Oaks Elementary. The project involves supplying and installing a total of 98 clocks, including 49 11.00" single-sided brushed aluminum analog clocks with lithium batteries at the middle high school, 21 similar clocks at Chikaming Elementary, 20 at Three Oaks Elementary, and 10 digital LED clocks across the three locations. Additionally, the bid requires a master clock system to synchronize all clocks. The bid was released on 3/14/19, with a pre-bid meeting scheduled for 3/20/19 at 1:30 PM and proposals due on 3/28/19 at 3:00 PM local time.

The bid does not specify a specific budget or funding source, and no bid security or performance bond is required. Bidders must provide a Certificate of Insurance with specific liability coverage requirements, including worker's compensation, automobile liability, and commercial general liability insurance. The district reserves the right to award the contract based on factors beyond price, such as delivery time, quality, past performance, and references. Contractors must comply with safety regulations, wear shirts on district property, avoid smoking on school grounds, and provide immediate communication contact information. The bid emphasizes the need for skilled personnel and proper workmanship, with the district maintaining the right to terminate the contract if performance standards are not met.

View the file

Other files

File Type Posted
ClocksBid.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Request for Bid

Clock System

Public Bid

River Valley School District

Bid Release Date: 3/14/19

Pre-Bid Meeting Date:

3/20/19 – 1:30 PM, local time.

Proposal Due Date:

3/28/19 – 3:00 PM, local time.

Return to:

Brian Brown

Business Manager

River Valley School District

15480 Three Oaks Road

Three Oaks, MI 49128

(269) 756-7611

Late Proposals will be Rejected

INFORMATION TO BIDDERS

1. Authority

2. Receipt and Opening of Bids

3. Qualification of Bidder

4. Sole Bidder

5. Discrepancies, Omissions or Interpretations

6. Inspection of Contract Documents

7. Bid Security

8. Performance and Payment Bond

9. Certificate of Insurance

10. Examination of Site

11. Pre-Bid Conference

12. Post-Bid Information

13. Acceptance and Rejection of Bid Proposals

14. Sales Tax

15. Payment

16. Scheduling and Hours of Work

17. Safety and Condition of Site

18. Indemnify and Hold Harmless Agreement

19. Workmanship/Inspection

20. Termination of Contract to Purchase

21. Specification of Services

22. Bid Proposal Form

23. District Site Map

24. School Site Plans

TENTATIVE TIME LINE

3/14/19 Bids Released

3/20/19 Pre Bid Meeting at 1:30 p.m., local time

Central Office

3/28/19 Bid Opening at 3:10 p.m., local time

INFORMATION TO BIDDERS

1. AUTHORITY

River Valley School District, hereby referred to as Owner, has the authority to obtain the best possible proposal for specified services. The Owner expects a complete service, as defined in the specifications. Owner will accept partially completed bids.

2. RECEIPT AND OPENING OF BID PROPOSALS

A. Bid Proposals will be opened and read aloud on 3/28/19 at 3:10 PM at the following location:

15480 Three Oaks Road

B. Bids received after designated bid receipt deadline will be returned unopened.

C. Proposal must be sealed with bidder’s name on the outside of the envelope and designated as follows:

Sealed Proposal

Attn.: Brian Brown, Business Manager

Clock Bid

Bidder Name, Address, Phone Number

D. Bids shall be submitted on the Bid Proposal Form furnished with all blank spaces filled in. All blanks on the bid form shall be filled in by typewriter or manually in ink. All alterations or erasures shall be initialed by the bid signer

E. The Owner shall have the right to waive any informality or irregularity in any bid received and to accept bids which, in his/her judgment, are in his/her own best interest.

F. The Owner shall award bids based upon Site Grouping and reserves the right to award these groups in such a manner as it deems is in the best interest of the District. Multiple contractors may be selected.

G. The bidder, by making his/her bid, represents that he/she has read and understood the contract and bid documents, and that his/her bid is made in accordance therewith.

H. Bid prices shall include all applicable taxes, bonds, overhead, profit and other pertinent costs. Bid prices provided on the Bid Proposal Form shall be binding for the duration of the mowing season. No additional costs to this contract will be authorized during the contract period without written authorization from the Owner.

I. Oral, telephone, facsimile or telegraphic bids are invalid and will not receive consideration.

J. Any bid may be withdrawn prior to the scheduled time for opening of bid proposals.

K. A bid may not be modified, withdrawn or canceled by the bidder for sixty (60) calendar days following the time and date designated for the opening of bids, and bidder so agrees in submitting his/her bid.

L. The bid proposal form will be considered a portion of the contract document.

3. QUALIFICATION OF BIDDER

A. The Owner reserves the right to request qualification information from any bidder before issuing documents, receiving bids or awarding a contract. The Owner may, at his/her sole discretion, accept or reject bidders as qualified. The right to waive any informality in qualification materials is reserved by the Owner. The Bidder, in submitting his/her bid, agrees to accept the decision of the Owner as final.

B. To enable the Owner to evaluate the competency and financial responsibility of the bidder, the bidder shall furnish the following information:

1) A list of similar projects completed during the previous five years, including the name and phone number of a contact person. All school contracts shall be listed.

2) A statement regarding any past, present, or pending litigation with an owner. Such additional information may be required to satisfy the Owner that the bidder is adequately prepared, in technical experience, or otherwise, to fulfill the contract.

C. The submitters shall provide full familial disclosure of all existing client relationships with any River Valley employee or board member.

4. SOLE BIDDER

If only one bid is received in response to the Invitation to Bid, a detailed cost proposal will be requested of the single bidder. A cost/price analysis and evaluation and/or audit shall be performed of the cost proposal in order to determine if the price is fair and reasonable. The Owner reserves the right to cancel the bid if there is only one bid received. The

Owner’s decision will be final.

5. DISCREPANCIES, OMISSIONS OR INTERPRETATIONS

A. Bidder shall promptly notify the Owner of any ambiguity, inconsistency, or errors which they may discover upon examination of the contract documents or of the site and local conditions. Bidders requesting clarification or interpretation of the bid documents contact the Owner. Direct all questions to:

Curtis Newton, Technology Director

Brian Brown, Business Manager

River Valley School District

15480 Three Oaks Road

Three Oaks, MI 49128

Phone: (269) 756-7611

FAX: (269) 756-6631

6. INSPECTION OF CONTRACT DOCUMENTS

A. Bid documents are located and may be obtained at:

15480 Three Oaks Road

Three Oaks, MI 49128

FAX: (269) 756-6631

B. The Owner does not assume any responsibility for errors, omissions or misinterpretations resulting from the use of incomplete sets of contract documents.

C. The Owner, in making copies of the contract documents available, does so only for the purpose of obtaining bids on construction of the work, and does not confer a license or grant for any other use, therefore does not warrant its completeness and adequacy.

7. BID SECURITY

Bid security will not be required for this project.

8. PERFORMANCE AND PAYMENT BOND

Performance and payment bonds will not be required on this project.

9. CERTIFICATE OF INSURANCE

A. Before commencement of any work, a Certificate of Insurance executed by bidder’s insurance agent or carrier showing required insurance coverage shall be submitted. A Thirty Day Cancellation Clause is required on all policies. Failure to provide the Certificate may be considered material breach of the agreement and may be grounds for terminating the agreement.

B. As a condition of performing work for the Owner as a Contractor, the Contractor must provide Owner with satisfactory evidence of its insurance coverage as follows:

1) Worker’s Compensation and Employers’ Liability Insurance covering your statutory obligations in the State of Michigan.

2) Automobile Liability Insurance with a limit of $1,000,000 per accident covering your owned, non owned and hired automobiles.

3) Commercial Liability Insurance written on an OCCURRENCE policy form that includes coverage for your operations, personal injury, XCU (explosion, collapse and underground), independent contractors, contractual, and products-completed operations with limits of liability as follows:

a. If your policy is written on the 1986 ISO Simplified form:

$1,000,000 Occurrence

$2,000,000 General Aggregate

$2,000,000 Product- Completed Operations Aggregate

b. If your policy’s general aggregate is per job, then a $1 million limit of liability is acceptable for the general aggregate and the products-completed operations aggregate.

c. If your policy is written on a form other than the 1986 ISO Simplified form:

$1,000,000 Occurrence (bodily injury and property damage combined)

$1,000,000 Aggregate (applicable to products-completed operations only)

4) That Owner is an additional insured on the General Liability and Umbrella Liability policies certified.

10. EXAMINATION OF SITE

The bidder shall be held to have examined the premises and to have satisfied themselves as to the condition of the premises, obstructions, the actual levels, and other factors necessary for carrying out the work before the delivery of their proposal. The bidders shall also acquaint themselves with the character and extent of the Owner’s operations in the area of the work, so that they may plan their services accordingly. No allowances or extra payment will be made to a Contractor for or on account of costs or expenses occasioned by failure to comply with the provisions of this paragraph, or by reason of error or oversight on the part of the bidder, or on account of interference by the Owner’s or other Contractor’s activities. It shall be expressly understood that the Owner’s operations will take precedence over any other activity.

11. PRE-BID CONFERENCE

A. A pre-bid meeting is scheduled as follows to review the specifications and expectations of the contracted services:

3/20/19, 1:30 PM, local time

River Valley School District

Central Office

15480 Three Oaks Road

B. Attendance at the pre-bid conference is not required in order to submit a bid proposal for these services.

However, all bidders are responsible for knowing the information disseminated at the pre-bid conference.

C. Responses to questions and requests for clarifications will be made by addenda only after the pre-bid conference if required. Any representations and/or oral discussions not confirmed by addenda will not be binding upon the

Owner.

12. POST-BID INFORMATION

A. After the bids are received, tabulated, and evaluated by the Owner, the apparent lowest bidder (s) shall meet with the Owner at a post-bid meeting, if requested by Owner, for the purpose of determining any contract overlaps or omissions, and shall provide the following information:

1) Designation of the work to be performed by the bidder with his/her own forces, and that to be contracted.

2) Complete detailed cost breakdown including manpower requirements and costs associated with work activities.

13. ACCEPTANCE AND REJECTION OF BID PROPOSALS

A. Low bid price is not always the determining factor in the awarding of the bid. Other factors considered may include, but not be limited to, delivery and/or completion time, quality, past performance, and references.

B. The contract shall be awarded in the form of a Purchase Order mailed or facsimiled to the Contractor(s) selected.

C. The Owner shall have the right to accept combination bids received from a bidder for more than one bid category.

D. Bids are considered irregular and may be rejected for any of the following reasons unless otherwise provided by law:

1) If bid proposal form furnished is not used, altered, or incomplete.

2) If there are unauthorized additions, qualifications, conditions, or irregularities of any kind which may make the bid incomplete, indefinite or ambiguous as to its meaning.

3) If bidder adds any provisions reserving right to accept or reject any awards of contract.

4) If unit or lump sum prices or alternates contained in the bid schedule are obviously unbalanced either in excess of, or below, reasonable costs analysis values.

5) If bid security does not accompany bid proposal form.

6) Failure of the bidder to inspect the proposed sites.

7) Bidder’s lack of expertise as shown by past work and judged from the standpoint of workmanship and performance history or past references.

8) If any pertinent instructions to bidders are not fully complied with.

14. SALES TAX

Owner is exempt from all taxes. A tax exemption certificate will be issued upon request.

15. PAYMENT

A. Payment will be processed within thirty (30) days of receipt of invoice, assuming no discrepancies exist, after approval of request for payment. All invoices shall have invoice numbers printed on them.

B. The Contractor is responsible for submitting all invoices within thirty days of the date for which services are rendered. Invoices for services rendered during the month of June must be submitted by June 30, 2019.

16. SCHEDULING AND HOURS OF WORK

A. Services shall be performed at times mutually agreed upon between Owner and Contractor. Contractor shall be responsible for complying with all local ordinance regarding working times. Contractor assumes all liability for complying with local ordinances. Any changes to the established schedule must have prior approval of the

Owner, and scheduled at the least disruptive time possible.

B. Scheduling of work must be coordinated with the individual facilities’ operational needs in order to avoid disruption or unsafe conditions.

C. The Contractor shall contact Curtis Newton by 5/1/19 to discuss schedules, site activities and expectations. A list of contact names and numbers will be provided.

17. SAFETY AND PROTECTION OF SITE

A. All work must be performed within the codes, standards and municipal ordinances of the community within which the property is located and must meet all federal, state and local regulations.

B. The Contractor shall be responsible for providing and for the placement of barricades, tarps, plastic, flag tape and other safety/traffic control equipment required to protect its employees, the public, surrounding areas, equipment and vehicles. The flow of vehicular traffic shall not be impeded at any time during this project. The safety of the

Contractor’s employees and the public is of prime concern to the Owner, and the Contractor must take all necessary steps to assure proper safety during the performance of the contract. Any bidders that have a history of safety problems or a high incidence of accidents will not be considered for award of a contract.

C. All machinery shall be operated by trained and qualified personnel.

D. The work area shall be cleaned at the end of each work day. All waste, tools, equipment, etc., shall be removed or safety stored. The Owner is not responsible for theft, damage or loss of materials to the Contractor’s property.

All possible safety hazards to workers or the public shall be corrected immediately and left in a safe condition at the end of each work day.

E. Contractor shall perform all work so that no damage to the building, grounds or finished materials result.

Contractor shall be responsible for all damages to the Owner’s property caused by either equipment or operator error and shall repair any damage to the satisfaction of the Owner. The Owner reserves the right to repair all damages with other sources if the Contractor fails to do so. The Contractor shall then be back-charged for all costs required to complete these repairs.

F. The Contractor shall be responsible and liable for any and all damages caused by any action or inaction of an employee or subcontractor working for the Contractor.

G. In the event that the Contractor causes building damage which compromises the security of the building, the

Contractor is responsible for immediately contacting the Owner’s representative.

18. INDEMNIFY AND HOLD HARMLESS AGREEMENT

Contractor agrees to accept responsibility for loss or damage to any person or entity, and to defend, indemnify, hold harmless and release the Owner, its officers, and employees, from actions, claims, damages, disabilities or the cost of litigation that are asserted by any person or entity to the extent arising out of the negligent acts or omissions or willful misconduct in the performance by the seller hereunder, whether or not there is concurrent negligence on the part of the

Owner, but excluding liability due to the active negligence or willful misconduct of the Owner. This indemnification obligation is not limited in any way by any limitation on the amount or type of damages or compensation payable to or for seller or its agents, under workmen’s compensation acts, disability benefits acts or other employees’ benefits acts.

19. WORKMANSHIP/INSPECTION

A. Where not more specifically described in any of the various sections of these specifications, workmanship shall conform to all of the methods and operations of best standards and accepted practices of the trade or trades involved, and shall include all items required for completion of the services. All work shall be executed by personnel skilled in their respective lines of work.

B. The Owner may request a meeting with the Contractor at any time for the purpose of evaluating the Contractor’s performance. Items not completed to the satisfaction of the Owner will be corrected by the Contractor within a mutually agreed timeframe. Failure by the Contractor to remedy concerns of the Owner may result in the termination of this contract.

20. TERMINATION OF CONTRACT

A. The Owner reserves the right to review and/or terminate the contract if at any time the Contractor fails to conform to the requirements of this contract, seeks relief under any law for the benefit of insolvents or is adjudicated bankrupt, if any legal proceedings are commenced against Contractor which may interfere with the performance of the contract or if the Contractor has failed to supply an adequate working force, or material or proper quality, or has failed in any other respect to prosecute the work with the diligence and force specified and intended by the terms of the contract.

B. In the event of termination of the contract, any excess of the cost arising there from will be charged against the

Contractor and his sureties, who will be liable thereof. All monies due the Contractor or retained under terms of the contract shall be forfeited to the Owner.

21. SPECIFICATION OF SERVICES

A. SCOPE OF WORK

1) River Valley Middle High School, Chikaming Elementary and Three Oaks Elementary (3 buildings) – Master

Clocks with synchronized clocks for classrooms/hallways and offices

1) MHS – 49 11.00” Dial Single Sided Brushed Aluminum Analog Clocks with Lithium Batteries

2) MHS – 8 4-digit 4.0 inch Double-Sided LED Digital Clocks

3) Chikaming – 21 11.00” Dial Single Sided Brushed Aluminum Analog Clocks with Lithium Batteries

4) Chikaming – 1 4-digit 4.0 inch Double-Sided LED Digital Clocks

5) Three Oaks – 20 11.00” Dial Single Sided Brushed Aluminum Analog Clocks with Lithium

Batteries

6) Three Oaks – 1 4-digit 4.0 inch Double-Sided LED Digital Clocks

7) Master Clock for all three buildings

B. GENERAL CONDITIONS

1) All employees working for the Contractor must wear shirts at all times while on district property unless granted an exception by the Owner’s representative.

2) Smoking is illegal and not permitted on school grounds. The Contractor shall ensure all employees observe this law.

3) The Contractor shall provide the Owner with a means of immediate communication regarding site completion, emergencies or any other occasion that may arise. A cellular phone number or pager number of the person responsible for managing this contract must be provided on the bid proposal form.

4) Non-approved work will not be paid for. Bid prices for some of these services shall be provided as requested on the Bid Proposal Form.

22. BID PROPOSAL FORM

BID PACKAGE: Clock System

DUE DATE: Wednesday, 3/28/19, 3:00 PM, local time.

TO: River Valley School District

15480 Three Oaks Road

Three Oaks, MI 49128

Attn: Brian Brown

Business Manager

NAME OF BIDDER

Firm Name:

Address:

Telephone: Fax:

AGREEMENTS

The undersigned understands that the Owner reserves the right to reject any and all bids and to waive informalities and irregularities in bidding.

Owner also reserves the right to withhold bids for a period of time (60 days) from bid opening date.

The Owner reserves the right to accept or reject any or all bids in whole or in part, or to waive any informalities therein.

If in the Owner’s opinion it is in his/her best interest, the contract may be awarded to other than the lowest bidder, for reason of establishing uniformity, delivery time, etc.

If award is made to us under this proposal, we agree to enter into an Agreement with River Valley School District to furnish products and/or services, in strict accordance with this proposal, bid documents and all pertinent portions of plans, drawings and specifications.

LEGAL STATUS OF BIDDER

1. A Corporation organized and existing under the laws of the State of

2. Name, title, and signature of individual duly authorized to execute contracts:

Name:

Title:

Signature:

REFERENCES: Attach the names of five references to your bid, preferably school districts.

Name Of Company/District:

Contact Person: Phone No:

BID PROPOSAL

Clock System for all three (3) buildings as presented

GROUP LOCATION COST

Combined Schools COMBINED TOTAL $

My signature certifies that the proposal as submitted complies with all Terms and Conditions as set forth in this RFB.

My signature also certifies that the accompanying proposal is not the result of, or affected by, any unlawful act of collusion with another person or company engaged in the same line of business or commerce, or any act of fraud.

Furthermore, I understand that fraud and unlawful collusion are crimes under Federal Law, and can result in fines, prison sentences and civil damages awards.

I hereby certify that I am authorized to sign as a representative for the following firm:

Address:

Telephone: Fax:

Cellular Phone: Pager No.:

Name:

Position:

Signature:

File details come from the government source that posted it. Updated .