Clarification 1.pdf
PDF 75 KB Posted
- Attached to
- WWTP Dechlorination and Ammonia removal Project
- Solicitation number
- S-R29138-00011397
- Issued by
- Tillamook County, Oregon
About this file
This document is a clarification to the Plans and Contract Bid Documents for the Port of Tillamook Bay WWTP Dechlorination and Ammonia Removal project. The project consists of upgrades to the existing Port of Tillamook Bay Wastewater Treatment Plant, including treatment for chlorine residual using chemical dechlorination, treatment to meet ammonia limits, converting a gravity sewer line to a pressure sewer, replacing 635 LF of 2" PVC pipe and installing 575 LF of 1-1/4" PVC pipe, and replacing existing meters. This clarification notes that Specification Section 16010 contains items that are not part of this project and should be ignored when bidding. The electrical work should only include work pertinent to the items listed on the plans and bid schedule.
The project is located in Tillamook County, Oregon. No additional details are provided regarding pricing terms, set asides, incumbents, funding requirements and sources, or the contract term and renewal options.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| NOITA_WWTP Improvements_Signed.pdf | ||
| Notice of Award_WWTP Dechlorination and Ammonia Removal_Signed.pdf | ||
| 00100 - Invitation For Bids.docx | DOCX document | |
| Addendum 2.pdf | ||
| Addendum 3.pdf | ||
| Addendum 4.pdf | ||
| Notice of Award.pdf | ||
| Bid Comparison10-25-24 WWTP ~1.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Port of Tillamook Bay – WWTP Dechlorination and Ammonia Removal Clarification No. 1 – October 23, 2024
Port of Tillamook Bay WWTP Dechlorination and Ammonia Removal
Clarification No. 1 October 23, 2024
Clarifications to Plans and Contract Documents
This is a clarification of the Plans and Contract Bid Documents. This clarification does not change the bid time or date.
CLARIFICATIONS TO CONTRACT DOCUMENTS:
Specification Section 16010 – GENERAL PROVISIONS AND TESTING, Sections 1.1 and 1.2 contain items listed that are not a part of this project and should be ignored when bidding. The electrical work for this project should only include work pertinent to the items listed on the plans and bid schedule.