CKI Bridge PWS 20260521.docx
DOCX document 313 KB Posted
- Solicitation number
- FA8604_C130J_CKI_SpecialNotice
- Issued by
-
Department of Defense
About this file
This is a Performance Work Statement (PWS) for the C-130J Contractor Kit Installation (CKI) Bridge contract. The document outlines requirements for Block Upgrade (BU) 7.0/8.1 Group A and B kit and delta kit installations onto various USAF C-130J and HC-130J aircraft. The work is to be performed by Canadian Commercial Corporation (CCC) under a sole-source, Firm-Fixed Price bridge contract awarded by Air Force Materiel Command (AFMC) at Wright-Patterson Air Force Base, Ohio. The contract is structured in accordance with the Defence Production Sharing Agreement (DPSA) Memorandum of Understanding between the U.S. Department of Defense and Canada's Department of National Defence. CCC is selected as the sole source contractor based on its current performance under the existing CKI contract and its possession of requisite technical knowledge and expertise necessary to continue operations without disruption or delay.
The PWS establishes the technical and operational specifications for kit installation procedures, quality assurance standards, and compliance requirements for the upgrade program. The contract supports ongoing modernization efforts for the C-130J and HC-130J aircraft fleets by implementing approved block upgrades and associated delta kits. The solicitation notice indicated a response deadline of 1:00 PM EST on June 18, 2026, for any parties wishing to submit capability statements challenging the sole-source determination, with submissions directed to casey.murphy@us.af.mil and ashley.crawford.12@us.af.mil.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PERFORMANCE WORK STATEMENT (PWS)
FOR THE
C-130J BLOCK UPGRADE (BU) 7.0/8.1 CONTRACTOR KIT INSTALLATION (CKI) BRIDGE
BASIC PWS
May 2026
PREPARING ORGANIZATION:
AFLCMC/MOBILITY DIRECTORATE
C-130 HERCULES DIVISION
C-130J RETROFIT PROGRAM BRANCH
WRIGHT-PATTERSON AFB OH 45433-7233
TABLE OF CONTENTS
| 1.0 | INTRODUCTION | 5 |
| 2.0 | SCOPE | 5 |
| 3.0 | PRE-EXECUTION REQUIREMENTS | 6 |
| 3.1 | Scheduling | 6 |
| 3.2 | Program Planning and General Requirements | 7 |
| 3.3 | Communications/Status Reports | 9 |
| 4.0 | AIRCRAFT PRE-ARRIVAL REQUIREMENTS | 9 |
| 4.1 | Deliveries, Inventory, and Inspection | 9 |
| 4.2 | Contractor Furnished Equipment (CFE) | 10 |
| 5.0 | EXECUTION: AIRCRAFT ARRIVAL AND INSTALLATION | 11 |
| 5.1 | Preparation for Aircraft Arrival | 11 |
| 5.2 | Kit Installation | 13 |
| 6.0 | MAINTENANCE ACTIONS | 15 |
| 6.1 | Maintenance Records, Forms and Publications | 15 |
| 6.2 | Repair and Replenish | 16 |
| 6.3 | Reporting Maintenance Actions | 17 |
| 6.4 | Non-BU 7.0/8.1 Aircraft Maintenance Actions and Discrepancies | 18 |
| 6.5 | Loss, Damage, and Destruction (LDD) | 20 |
| 7.0 | ACCEPTANCE TEST PROCEDURES (ATP) THROUGH COMPLETION | 21 |
| 7.1 | Test Plan/Checklist and Acceptance Test Report | 21 |
| 7.2 | Record Review | 21 |
| 7.3 | Test, Inspections, and Completion | 21 |
| 7.4 | Aircraft Transfer and Post-Install Ferry Support | 22 |
| 8.0 | SECURITY | 22 |
| 8.1 | General | 22 |
| 8.2 | Communication Security (COMSEC) | 23 |
| 8.3 | Physical Security | 23 |
| 8.4 | Controlled/Restricted Areas | 24 |
| 8.5 | Operations Security (OPSEC) | 24 |
| 8.6 | Program Protection Plan (PPP). | 25 |
| 8.7 | Safeguarding Covered Defense Information and Cyber Incident Reporting. | 25 |
| 8.8 | Access to Government Systems and Facilities. | 25 |
| 8.9 | Information Security (INFOSEC). | 26 |
| 8.10 | Security Clearances. | 27 |
| 9.0 | OTHER GENERAL REQUIREMENTS | 30 |
| 9.1 | Government Furnished Property (GFP) Management | 30 |
| 9.2 | Support from Outside Entities | 31 |
| 9.3 | Transfer/Transportation Requirements for Foreign Contractors | 32 |
| 9.4 | Non-Personal Services | 33 |
| 10.0 | QUALITY REQUIREMENTS | 34 |
| 10.1 | Contractor Point of Contact (POC) | 34 |
| 10.2 | Services Summary | 34 |
| 10.3 | Quality Management System | 36 |
| 11.0 | DATA | 37 |
| 11.1 | Contract Data Requirement List (CDRL) Deliveries | 37 |
| 11.2 | Data Accession List (DAL) | 38 |
| 12.0 | PWS Applicable Clauses | 38 |
| 12.1 | DAFFARS 5352.201-9101 Ombudsman (Jul 2013) | 38 |
| 13.0 | ATTACHMENT 1: TENTATIVE SCHEDULE | 40 |
| 14.0 | ATTACHMENT 2: ACRONYM LIST | 41 |
| 15.0 | ATTACHMENT 3: DATA DICTIONARY | 43 |
| 16.0 | ATTACHMENT 4: GFE LIST, a/o May 2025 | 45 |
| 17.0 | ATTACHMENT 5: O&A PROCEDURES | 46 |
| 18.0 | ATTACHMENT 6: CKI AIRCRAFT GENERAL MAINTENANCE | 64 |
1.0 INTRODUCTION
This Performance Work Statement (PWS) defines the requirements for Contractor services to complete Block Upgrade (BU) 7.0/8.1 kit, and delta kit, installations onto United States Air Force (USAF) C-130J aircraft. The Contractor shall successfully install Group A and Group B BU 7.0/8.1 on up to 15 aircraft in accordance with (IAW) TCTOs and associated Technical Orders (TO); successfully accomplish the Acceptance Test Procedures (ATP) with Defense Contracts Management Agency’s (DCMA) sign-off of the DD250 within the contract schedule; and DD1149 transfer back to the owning USAF Major Command (MAJCOM). On five (5) applicable C-130J-30 (Stretch) aircraft, the Contractor shall also accomplish the Time Compliance Technical Orders (TCTO) for Dynamic Re-tasking Capability (DRC) De-confliction in parallel with the BU kit installation. For actions completed under this contract, “Work Scope” shall refer to provisions of the Basic contract. The owning MAJCOMs are Air Mobility Command (AMC) and Pacific Air Forces (PACAF)
2.0 SCOPE
The work scope shall consist of the installation of Government-furnished BU 7.0/8.1 modification kits on the C-130J-30 (Stretch) aircraft IAW TCTOs and associated TOs. The Contractor shall receive, inspect, and preserve the aircraft in preparation of the installation. The Contractor shall complete the installation, employing Government-furnished installation kits and identified support equipment. The Contractor shall return the aircraft to flyable status IAW established practices, procedures, and instructions documented in approved USAF C-130J TOs and this Basic PWS.
For 5 C-130J aircraft that have DRC included on the aircraft, the work scope shall also consist of removing DRC conflicting hardware and components, installing Government-furnished DRC de-confliction kits, and manufacturing cargo compartment insulation blankets concurrent with the BU 7.0/8.1 modification. The Contractor shall manufacture the cargo compartment insulation blankets on site, to include all necessary snaps, buttons, fasteners, and details required to return the aircraft to its original configuration.
As a complement to the installation, per the TCTOs, the work scope shall include kit management and integrity, change management, and aircraft knowledge and maintenance to include but not limited to:
· kit receipt, inspection, inventory and warehousing
· aircraft receipt and aircraft induction (DD1149)
· aircraft arrival inspection and preservation tasks
· technical data management
· installation scheduling
· execution of preservation kits
· identification and resolution of aircraft maintenance actions and issues (will include non-BU 7.0/8.1 actions and issues)
· quality assurance checks
· successful completion of prescribed Acceptance Test Procedures (ATP) (culminating in Government acceptance and DD250 signature)
· aircraft return to USAF via DD1149
· maintaining security requirements for the aircraft, its components, testing, and personnel
PRE-EXECUTION REQUIREMENTS
Scheduling
2.1.1 Integrated Master Schedule (IMS). Using Attachment 1, Aircraft Schedule, as a reference, the Contractor shall develop, coordinate, and execute an IMS for all assigned installations. The standard installation IMS shall be delivered to the C-130 PMO NLT thirty (30) calendar days after contract award. At a minimum, this schedule shall define the sequencing of planned aircraft inductions, the details of the installation cycle (from aircraft DD1149 through DD250) by tail number, and pre-defined touch points (defined by Contractor and approved by the USG) to support quality assurance inspections, and planned contract deliverables. (A004, DI-MGMT-81861C/T, INTEGRATED MASTER SCHEDULE)
2.1.2 Integrated Master Schedule (IMS) Maintenance. The Contractor shall update and maintain the USG-approved IMS to manage, report, and forecast program activities for each aircraft. The Contractor shall update the IMS regularly with changes, out-of-cycle actions, additions of Over and Above (O&A) activities, actual start/finish dates, and rationale and impacts to the installation cycle. The updated IMS will be delivered monthly for an accurate accounting of program installation activities and their schedules to give an accounting of each aircraft’s activities while at the installation location. (A004, DI-MGMT-81861C/T, INTEGRATED MASTER SCHEDULE) Program Planning and General Requirements
2.1.3 TCTO Instructions. The Contractor shall complete installation IAW applicable TCTOs, TOs, and related publications, instructions, and procedures. As a complement, all applicable technical manuals, forms, publications, bulletins, specifications, standards, and field procedures guides shall be utilized. When/if a document provided by the USG is revised, supplemented, replaced or rescinded, the Contractor, upon notification or receipt of it, shall comply with the change(s). The Contractor shall review and provide potential impacts and rationale for non-compliance to the USG NLT three (3) business days.
2.1.4 Contractor Risk Management Status Reporting. The Contractor shall use the current Risk Management Plan developed in support of the CKI 1 effort. The Contractor shall provide a current summary of risks and watch items that identify: the risk item number, title, description, risk levels, and mitigation/reduction steps for each risk. (A006, DI-MGMT-81809, RISK MANAGEMENT STATUS REPORT (RMSR))
2.1.5 Engineering Support. The Contractor shall provide engineering support. The Contractor shall assess drawings and TOs/TCTOs to prepare for the modification, maintenance, and O&A work on their aircraft. The Contractor shall evaluate any discrepancies in work, the aircraft, documentation, and issues with the aircraft (to include both mod and non-mod related). The Contractor shall suggest proper resolution of the issues according to the descriptions in this document. The Contractor shall assess work changes as updated guidance is received from the USG (i.e. TOs/TCTOs) when software or engineering changes result in a directional change. If necessary, the Contractor shall propose technical changes as an Engineering Change Proposal (ECP). (A007, DI-SESS-80639E/T, ENGINEERING CHANGE PROPOSALS)
2.1.6 Configuration Management (CM). The Contractor shall implement, utilize, maintain, and fully comply with fundamental configuration management practices and procedures as part of this modification for the C-130J Program. At a minimum, the Contractor shall use the processes documented in the Configuration Management Plan (CMP) approved under FA8625-20-D-2016. In particular, the Contractor shall follow the approved processes for change management and configuration status accounting that pertain to the Standardized Issue Reporting Form (SIRF).
2.1.7 Contract Change Proposals (CCPs). Non-technical contract changes shall be prepared as CCPs. (A008, DI-ADMN-81401C/T, CONTRACT CHANGE PROPOSALS)
2.1.8 Request for Shortfall/Variance. The Contractor shall propose and document all non-conformances from the specified modification requirements via a Shortfall/Variance (a.k.a. Request for Deviation/Waiver) for approval by the USG. The USG may require monetary withholds against the Contractor for any Shortfall/Variance until the issue is corrected. Shortfalls and Variances shall be tracked and made available to USG. (A009, DI-SESS-80640E/T, REQUEST FOR VARIANCE)
2.1.9 Continuous Shortfall/Variance. There are known shortfalls in the C-130J kit installations that are expected with each aircraft modified. The Contractor will not be able to complete operational checks due to unavailable MIDS LVDT BU2 test procedures, lack of MIDS and RPS equipment, lack of VHF/UHF/HF 1 and 2 (ANDVT for HF) secure voice testing. There is also a lack of testing equipment and incomplete test procedures for AN/ARC-222 VHF communication data fill test, and operational check of SKE-2000 due to incoming deferral of SKE Directional Antenna fail. Until complete test equipment, procedures, voice tests, and operational checks are available, the USG will conduct these tests upon return to the unit.
Communications/Status Reports
2.1.10 Program Management Review (PMR). The Contractor shall plan for delivery of CDRLs, one (1) PMR per year, and at least two (2) weekly meetings for aircraft status (1 with the C-130J PMO and 1 with mod sites, MAJCOMs and C-130J PMO). The Contractor may supplement this information with other content that affords USG insight into the installation progress (by tail number), and proactive coordination and mitigation of issues impacting the installation schedule. Events that occur impacting the program (schedule, performance) must be brought to the C-130J PMO attention NLT one (1) business day by either email or telecom. In such events, the Contractor shall document the event and provide a get-well plan to include a schedule for corrective action NLT three (3) business days after notification. The Contractor shall respond to all USG requests for information NLT three (3) business days of USG inquiry. The Contractor shall develop and deliver a meeting agenda, briefing slides, and minutes for the PMR (held either on line or at the Contractor’s Facilities). (A001, DI-ADMN-81249C, CONFERENCE AGENDA; A002, DI-ADMN-81373, PRESENTATION MATERIALS; A003, DI-ADMN-81250C, CONFERENCE MINUTES)
2.1.11 Monthly Status Report (MSR). The Contractor shall generate and provide a MSR which includes the overall project status, milestones, accomplishments, issues, deliveries, and any changes from the previous month. The MSR shall include the technical activities accomplished for the month; objectives, changes, and results of efforts; identification of major problems/deficiencies with impact and recommended solutions. (A005, DI-MGMT-80368A/T, MONTHLY STATUS REPORT)
AIRCRAFT PRE-ARRIVAL REQUIREMENTS
Deliveries, Inventory, and Inspection
2.1.12 Installation Kit Deliveries. Installation kit deliveries will occur NLT thirty (30) calendar days in advance of aircraft arrival. Aircraft specific kits will include all components and technical documentation required to complete TCTO installations. Kits will be provided as Government Furnished Property (GFP) to include the DRC Kits and necessary delta kits specific to the C-130J aircraft.
2.1.13 Peculiar Support Equipment and Tooling Deliveries. Installation support equipment is in place at the Contractor’s facility. Installation support equipment consists of the peculiar assets (test articles and tooling) required to support BU 7.0/8.1 kit installations per the TCTOs and TOs. This equipment shall be handled and accounted for as GFP. If required, the Contractor shall ensure timely calibration of the equipment in accordance with the National Institute of Standards and Technology (NIST) or host nation equivalent standards.
2.1.14 Installation Kit Inventory and Inspection. Upon each installation kit delivery, the Contractor shall complete a full inventory and inspection of all contents, to include any peculiar support equipment, tooling, and drawings IAW with the attached Bill of Materials and Harness Assembly Drawings. Kit content shortfalls, if any, shall be immediately brought to the attention of the C-130J PMO and DCMA. Once the inventory is complete, the Contractor shall be responsible for warehousing, accounting, securing, and making inventory available (per the Contractor-defined installation schedule) across the installation cycle. The Contractor shall provide storage, warehouse, and inventory control for stored kits in support of active installation lines. Installation kits will arrive NLT thirty (30) calendar days prior to aircraft induction.
For each installation kit and support equipment, the Contractor’s acceptance shall be documented on a DD Form 1149 (signed by an authorized Contractor representative). Copies shall be forwarded to the cognizant DCMA office and PMO. (A010, DI-MGMT-80441D, GOVERNMENT PROPERTY INVENTORY REPORT) Contractor Furnished Equipment (CFE)
The Contractor shall be responsible for obtaining Contractor furnished items, which includes Common Support Equipment (CSE) as well as standard tooling and test equipment required to support Block Upgrade 7.0/8.1 kit installations per the TCTOs and TOs and general maintenance of the C-130J aircraft and its variances. Items include but are not limited to ground support equipment, structural tooling, jacks/engine propeller change kits, etc. CFE shall be in place NLT thirty (30) calendar days in advance of the first aircraft arrival.
EXECUTION: AIRCRAFT ARRIVAL AND INSTALLATION
Preparation for Aircraft Arrival
2.1.15 Personnel. The Contractor shall establish required personnel and security verifications (Section 8.0) needed to execute Contract requirements. The Contractor shall have qualified and certified maintenance technicians complete the modification and Over & Above work on USG Aircraft, to include avionics and general maintenance activities. Qualified C-130J maintenance technicians should have recent and relevant experience on the C-130J aircraft that enables them to: install, test and troubleshoot TCTO modifications; inspect, diagnose and solve maintenance problems; maintain, service, and inspect aircraft and aerospace support equipment (SE); interpret and advise on maintenance procedures and policies to repair aircraft and SE; and troubleshoot and maintain aircraft structures, systems, components, and SE. Additional qualifications can be found in the Data Dictionary, Attachment 3. Certified C-130J maintenance technicians possess current FAA Airframe and Propulsion certifications. Certified maintenance technicians shall be responsible for, and provide oversite and quality checks of, qualified maintenance technicians during authorized installation and avionics and maintenance work.
2.1.16 Pre-Arrival Procedures. The Contractor shall develop and coordinate an incoming package/checklist for aircraft arrival crews. The Contractor shall articulate everything they require from the crew upon arrival to include but is not limited to: arrival time, names/position of the crew, contact numbers of the crew, and any additional documentation needed prior to or upon arrival. The Contractor shall also include 2-3 layers of Contractor contact information for the incoming crew as well for simplified transitions in/out of the Contractor location(s).
2.1.17 Pre-Induction Meeting. Approximately two (2) weeks prior to each aircraft arrival, the Contractor shall attend a pre-induction meeting via telecom with the USG unit providing the aircraft to be modified and the program office to ensure everything is prepared for the arrival of the aircraft and any pre-existing issues with the aircraft are understood. Also at this time, the Contractor shall disseminate pre-arrival procedures and the PMO will articulate any required Communications Security (COMSEC) documentation required prior to aircraft arrival.
2.1.18 Aircraft Arrival Procedures. The Contractor shall develop, coordinate, and execute aircraft arrival procedures specific to their installation location. At a minimum, the locations and procedures shall provide for safe arrival, landing, ground transit of the aircraft to a defined parking location, and relocation of the USG ferry crew to a central location for their return to base. The procedures shall not be modified without prior coordination with the C-130J PMO.
5.1.4.1 Contractor Acceptance. For each aircraft, the Contractor’s acceptance shall be documented on a DD Form 1149 (signed by an authorized Contractor representative). Copies shall be forwarded to the cognizant DCMA office and the C-130J PMO. (A010, DI-MGMT-80441D, GOVERNMENT PROPERTY INVENTORY REPORT)
5.1.4.2 Updating and Maintaining Aircraft Forms. The Contractor shall update and maintain the aircraft forms documented in Table 1 (Section 6.1 Maintenance Forms and Publications of this PWS) for all aircraft at all Contractor install facilities.
5.1.4.3 Foreign Object Debris (FOD). Upon receipt of the aircraft, during the inspection, induction, preservation, kit modification, and testing, until the aircraft leaves the Contractor’s facilities, the Contractor shall ensure the aircraft is free of FOD.
2.1.19 Aircraft Arrival/Inspections/Induction. The USG ferry pilots will be responsible for delivering the aircraft to the Contractor’s facility. At the point of aircraft arrival, the Contractor shall perform post flight aircraft inventory check with the USG (Flight-Crew/DCMA/PMO). The Contractor shall document missing, damaged items using the AFTO Form 781. The Contractor shall conduct inspection baseline checks (Acceptance Inspection). The Contractor shall develop, coordinate, and execute procedures for aircraft arrival inspections of the aircraft. The inspection shall encompass Contractor-defined procedures, accomplished IAW approved USAF C-130J TO’s, to validate the aircraft’s physical and maintenance condition as well as readiness for induction into the installation line. At a minimum, the Contractor shall include an inspection of all lights, interior and exterior, for operation and aircraft bleed air checks for minimum bleed down upon arrival. The procedures shall not be modified without prior coordination with the PMO. Should aircraft issues be identified during inspections, the Contractor shall implement the procedures outlined in Section 6.4.1 Over and Above of this PWS.
2.1.20 Preservation Requirements. The Contractor shall execute procedures and preservation requirements (per TO 1C-130J-17, Long Term Storage USAF C-130J Series Aircraft) within seven (7) days of aircraft arrival.
Kit Installation
2.1.21 The USG will provide TOs required for the Contractor to perform duties in support of the contract NLT sixty (60) calendar days after contract award. Contractor personnel will not remove TOs from the work area at any time.
2.1.22 The Contractor shall execute the C-130J BU 7.0/8.1 kit installations and DRC effort consistent with the applicable TCTOs and referenced TOs—to include referenced engineering drawings, wiring diagrams, and functional and operational checkout procedures:
1) 1C-130J-1062, Installation of Block Upgrade 7.0/8.1 Modification Kits, Forward Fuselage Stations 0.0 to 245.0, C-130J Aircraft
2) 1C-130J-1063, Installation of Block Upgrade 7.0/8.1 Modification Kits, Mid Fuselage Stations 245.0 to 537.0, C-130J Aircraft
3) 1C-130J-1064, Installation of Block Upgrade 7.0/8.1 Modification Kits, Aft Fuselage Stations 537.0 to 1202.1, C-130J Aircraft
4) 1C-130J-1065, Installation of Block Upgrade 7.0/8.1 Wiring Modification Kits, C-130J Aircraft
5) 1C-130J-1096, Block Upgrade (BU) 7.0/8.1 and Dynamic Re-tasking Capability (DRC) De-confliction, C130J Aircraft if applicable
6) 1C-130J-1180, Issuance Of Air Vehicle Software (AVS) Card Part Number 3370252-9, Software Version Block 8.1.1-4 On Select C-130J Aircraft
Installation Cycle. The Contractor shall complete the steady state installation cycle (DD1149 to DD250) NTE one-hundred twenty (120) calendar days. Seven (7) additional days shall be allocated for the removal of DRC on the C-130J-30 (Stretch) DRC configured aircraft and installation of the de-confliction kits.
2.1.23 Aircraft Non-Conformances. Any non-conformances discovered that could negatively affect the modification installs and potential aircraft acceptance, to include factors that may cause damage to equipment or injury to personnel and cannot be resolved immediately by the on-site engineering staff, the Contractor shall notify the C-130J PMO/DCMA NLT twenty-four (24) hours after discovery for resolution. All Major Non-conformances shall be reported and dispositioned by the Program Office.
2.1.24 Technical Issues, Engineering Disposition Requests. Technical issues, engineering disposition requests or questions shall be presented to the C-130J PMO as soon as possible for disposition. Engineering disposition requests shall (1) describe the request in detail and (2) provide a recommended disposition for consideration. Contractor-generated delays in submitting requests shall not be reason to extend the installation period.
2.1.25 Aircraft Non-Essential Equipment. The Contractor shall remove and disposition non-essential equipment (e.g., cables, connectors, circuit breakers, racks, panels, structural components, and associated equipment) in accordance with the TCTOs.
2.1.26 Support DCMA Quality Assurance. Per each installation schedule, the Contractor shall support installation line quality assurance inspections by DCMA personnel. Any DCMA-identified discrepancies or findings shall be corrected within the installation cycle.
MAINTENANCE ACTIONS
Maintenance Records, Forms and Publications
2.1.27 General. The Contractor shall update and maintain the forms and publications listed in Table 1, as required. The Contractor shall seek clarification from the C-130J PMO if the records are illegible at point of aircraft delivery. All forms, publications, and records listed shall be updated and maintained from the date of the DD1149 until the aircraft is accepted by the signed DD250 and departs the Contractor’s facility. The Contractor shall ensure forms and records that arrived with the aircraft or generated during the modification (i.e. General Information Grid (GIG) sheets, DD-250 modification records) shall be returned with the aircraft. Documentation that is proprietary or belongs to the Contractor, will be retained by the Contractor.
Table 1: Summary of Aircraft Forms
| Form Number |
| Form Title |
| Applicable Directive |
| AF 2692 |
| Aircraft/Missile Equipment Transfer/Shipping Listing |
| AFI 21-103 |
| AFTO 95 |
| Significant Historical Data |
| TO 00-20-1 |
| AFTO 781 |
| Aircrew Mission Flight Data Document |
| TO 00-20-1 |
| AFTO 781A |
| Maintenance Discrepancy and Work Document |
| TO 00-20-1 |
| AFTO 781H |
| Aerospace Vehicle-Flight Status and Maintenance |
| TO 00-20-1 |
| AFTO 781J |
| Aerospace Vehicle-Engine Flight Document |
| TO 00-20-1 |
| AFTO 781K |
| Aerospace Vehicle Inspection, Engine Data, Calendar Inspection and Delayed Discrepancy Document |
| TO 00-20-1 |
2.1.28 AF Form 2692. The Contractor shall review aircraft equipment transfers and shipping information on the AF 2692. If the aircraft does not have an AF 2692 available, the Contractor shall use an equivalent form to annotate loose equipment inventory upon aircraft arrival and departure.
2.1.29 AFTO Form 95. The Contractor shall annotate TCTO compliance and completion on the AFTO Form 95 IAW TO 00-20-1.
2.1.30 AFTO Form 781. The Contractor shall annotate flight hours conducted during the TCTO installation and verification checks on the AFTO Form 781 IAW TO 00-20-1.
2.1.31 AFTO Form 781A. The Contractor shall annotate maintenance discrepancies during the TCTO installation on the AFTO Form 781A IAW TO 00-20-1. In addition, the Contractor shall periodically review the Form 781A for any upcoming maintenance inspections.
2.1.32 AFTO Form 781H. The Contractor shall annotate the aircraft flight and maintenance status, fuel servicing, engine oil servicing, liquid oxygen (LOX) servicing, and flight hours on the AFTO Form 781H IAW TO 00-20-1.
2.1.33 AFTO Form 781J. The Contractor shall annotate the aircraft accumulated engine run hours, flight hours, and landing gear retractions conducted during TCTO installation and verification checks on the AFTO 781J IAW TO 00-20-1.
2.1.34 AFTO Form 781K. The Contractor shall annotate the aircraft engine data, calendar inspections, and delayed discrepancies during the TCTO installation and verification checks on the AFTO 781K IAW TO 00-20-1. In addition, the Contractor shall periodically review the Form 781K for any upcoming maintenance inspections.
Repair and Replenish
2.1.35 Kit Content Repairs and Replenishing Requisitioning Process. If kit contents require repairs and/or replenishing at any point prior to or during installation, then the Contractor shall notify the C-130J PMO NLT two (2) business days and assign a Supply Liaison to order, track, ship, receive, inspect, and provide status on all requisitions, repairs and assets ordered under contract through the USG. The Contractor shall NLT two (2) business days of receipt of the requisitions, act as a liaison for the USG, process, and fill requisitions, generate material release orders, provide requisition status using standard Military Standard Requisitioning and Issue Procedures (MILSTRIP) supply status codes via electronic means, reconcile/validate backorders, and perform cataloging actions as applicable. The Contractor shall be responsible for managing and ordering/replenishing stock (i.e., consumables) using the Inventory Control Point for source of supply spares at Little Rock AFB, AR. .
2.1.36 Packaging, Handling, Storage and Transportation (PHS&T). The Contractor shall be responsible for the Packaging, Handling, Storage and Transportation of installation items in accordance with MIL-STD 2073-1E (1), Standard Practice for Military Packaging, when military packaging is specified. The Contractor shall comply with the American Society for Testing and Materials (ASTM) D3951-10 when commercial packaging is specified. The Contractor shall be responsible for shipping and tracking items to the designated installation receiving point(s) or to other locations as directed by the Procuring Contracting Officer (PCO). For shipments outside the Continental United States (OCONUS), the Contractor shall use USG provided World Wide Express (WWX) carrier services. When OCONUS shipments are directed by the USG, the Contractor shall request use of WWX services through DCMA.
Reporting Maintenance Actions
The Contractor is responsible for care, upkeep, and general maintenance actions associated with the aircraft while it is in residence at the Contractor’s facilities (for examples, see Attachment 6 General Maintenance). The Contractor shall report maintenance data IAW TO 00-20-2 upon completion of each aircraft installation. The Contractor shall document all maintenance activities/items, not associated with the TCTO modification installation, to include servicing and inspections, and over and above findings and associated approved maintenance actions in the aircraft AFTO 781 forms. The Contractor shall submit copies of the AFTO 781 forms twice per Aircraft: 1) 15 days prior to the Scheduled Acceptance Check Flight (ACF) date and 2) approximately 1 week prior to the aircraft returning to the MAJCOM. (A012, DI-MISC-80508B/T, TECHNICAL REPORT-STUDY/SERVICES (AFTO 781 SUBMISSIONS))
The Contractor shall document all maintenance activities related to installation of the modification separately in the Contractor’s work package. Upon return/release of the aircraft to the MAJCOM, the Contractor shall submit electronic copies of the work package to the MAJCOM by secure file transfer within 30 days of aircraft departure. The Contractor shall document each TCTO completion separately such as: “Block Upgrade (BU) 7.0/8.1 Time Compliance Technical Order (TCTO) 1C-130J-10XX required” and with a basic sign off “TCTO 1C-130J-10XX Complied With, see Contractor work package for maintenance break down”. All items authorized by the USG to include time change and inspection requirements and/or safety of flight inspections due during the bailment period to the Contractor shall be completed and signed off prior to aircraft delivery to the USG (DD250).
Non-BU 7.0/8.1 Aircraft Maintenance Actions and Discrepancies
2.1.37 Over and Above (O&A). “Over and above work” means work discovered during the course of performing overhaul, maintenance, and repair efforts that is—
(i) Within the general scope of the contract;
(ii) Not covered by the line item(s) for the basic work under the contract; and
(iii) Necessary in order to satisfactorily complete the contract.
O&A issues are NOT related to the actual physical installation of the BU 7.0/8.1 TCTOs nor any maintenance actions included with general movement or upkeep of the aircraft during the time it is in residence at the Contractor’s facility. For example, towing, inspections, records maintenance, movement of other aircraft, ACF preparation, ground servicing, etc. is not considered O&A as it is considered part of the modification and general upkeep of the aircraft while in residence and included in the CLIN for the modification itself. O&A are issues identified during the pre-induction inspection, the installation effort, final inspections, ACF preparation, during ACF, or identified and directed by the USG.
Aircraft actions and discrepancies shall be resolved under the O&A provisions included in Attachment 5 and must be completed by certified and/or qualified maintenance technicians and (like the modification) overseen by certified maintenance technicians. Certified and qualified maintenance technicians shall have the qualifications described in the Data Dictionary, Attachment 3. Certified maintenance technicians shall be responsible for, and provide oversite and quality checks of, qualified maintenance technicians during authorized installation and avionics and maintenance work.
2.1.38 Repairs and Corrective Actions. The Contractor shall identify needed repairs and recommended corrective action for non-modification-related, aircraft discrepancies identified during the installation. The Contractor shall also advise if the corrective action must be accomplished to continue the install (i.e., a prerequisite to maintenance or safety of flight and execution of the ATP cycle) and anticipated duration of the corrective action, or if the work can be deferred until after DD250. The Contractor shall notify the C-130 PMO/DCMA via telephone and in writing NLT 0800 local time the next business day. The Contractor shall follow up in writing NLT four (4) hours as to the scope of the maintenance concern, required TOs and support equipment (if any), and shall request disposition guidance. If a maintenance action is approved and not covered by an existing TO, then the Contractor shall notify the C-130J PMO to obtain the required engineering or maintenance assistance for proper disposition and procedures or approaches to correct the identified discrepancy. The Contractor shall document all discrepancies requiring aircraft maintenance in the aircraft forms.
2.1.39 Discrepancy Authorizations. The USG will decide on a case-by-case basis if each discrepancy shall be worked by the Contractor, USG team at the Contractor's facility, or left unresolved. The Contractor shall not perform any work until authorization for that work is received from the Administrative Contracting Officer (ACO). Support equipment (if any) and applicable TOs for that work will be authorized by the PCO. "CANN" (Cannibalization): A cannibalization request is for the movement of parts from one aircraft to another, in the event that the supply system cannot provide the part. Cannibalization will only be used as a last resort and must be approved and executed according to the attached O&A procedures. The C-130J Retrofit Logistics Manager will coordinate with the USAF Command and provide guidance to DCMA Quality Assurance Specialist (QAS) regarding cannibalization requests.
2.1.40 Maintenance Notifications. For O&A requirements, Contractor shall follow O&A direction included in Attachment 5 and notify DCMA of the scope of the maintenance issue, required TOs and support equipment (if any). The Contractor’s O&A request shall include the estimated maintenance labor categories, to include engineering, and labor-hours required; and total project cost (labor and material). The Contractor shall continue the installation on a noninterference basis for the O&A while waiting for direction. The USG will notify the Contractor the USG’s preferred disposition (i.e., Contractor repair, delay repair, Field team repair, etc.) of the maintenance issue. If the maintenance issue is approved for Contractor repair, then the Contractor repair shall require USG acceptance given by the PCO through the ACO. Any O&A issue that results in a delay to the installation being completed shall not prevent the Contractor from receiving the next aircraft IAW the agreed upon schedule.
2.1.41 Maintenance Contractual Direction. Once contractual direction is received, the Contractor shall execute the maintenance action IAW the referenced TO(s). If the maintenance action falls within the CKI Mandatory Government Inspection (MGI) list, it shall conclude with the completion of a physical inspection—specific to the requirement and IAW the referenced TO, to include documentation of the corrective action and clearing of the discrepancy in the applicable aircraft forms after USG inspection and acceptance.
Loss, Damage, and Destruction (LDD) The Contractor shall document LDD items and notify the USG upon discovery of LDD items. The Contractor shall submit LDD item documentation to the C-130J PMO/DCMA for review and disposition NLT twenty-four (24) hours from when the LDD is identified. The Contractor shall, when authorized by the USG, complete repair or replacement.
ACCEPTANCE TEST PROCEDURES (ATP) THROUGH COMPLETION
Test Plan/Checklist and Acceptance Test Report The Contractor shall generate and submit Acceptance Test Reports documenting the results of each acceptance test for each aircraft. The Contractor shall document and notify the USG of non-conformances noted during these TCTO checks and review for safety of flight issues. Any non-conformances requiring changes to the technical drawings or TCTOs shall employ the procedures in the Engineering Technical Assistance Request (ETAR) Policy, AFMCMAN 63-1202. The Contractor shall reconcile reported discrepancies, following the ACF, attributable to the installation of the kit. (A011, DI-QCIC-81891, ACCEPTANCE TEST REPORT) Record Review The Contractor shall conduct a record review prior to any flight or delivery. The Contractor shall update aircraft records (e.g., AFTO Form 95, AFTO Form 781, USAF Form 2692, etc.) The Contractor shall include post-Line Replacement Unit (LRU) installation information onto the AFTO Form 781 aircraft record and provide upon aircraft delivery. The LRU information shall include part number, position, serial number, and any pertinent software information including the identification number. The Contractor shall provide updated records with delivery of modified aircraft.
Test, Inspections, and Completion
2.1.42 Acceptance Test. The Contractor shall operationally and functionally test the final installation IAW the TCTOs to verify readiness for flight.
2.1.43 Pre-Flight/Safety-of-Flight Inspections. Pre-flights are due every 72 hours prior to flight, regardless of possible delays, and are included as part of this contract. The Contractor shall develop, coordinate, and execute the sequence of pre-flight inspections IAW approved USAF C-130J TO’s and additional activities on the C-130J for ACF (including but not limited to: DCMA Inspections, LOX servicing, emergency response support, towing of vehicles). The pre-flight inspections shall be accomplished in advance of every flight readiness determination: in preparation for USG ACFs as well as before ferry flights home. Once the Acceptance Test Plan is approved, the procedures shall not be modified without USG approval. All pre-flight inspections will be overseen by the cognizant DCMA office and/or USG program office personnel.
2.1.44 Acceptance Check Flight (ACF) Completion. After completion of the Contractor’s ATP, the Contractor shall prepare the necessary aircraft forms and records for the USG’s acceptance of the aircraft. The Contractor shall submit a DD250 after the successful completion of the USG ACF IAW applicable contract provisions; and shall support, as required, the cognizant DCMA office’s sign-off of the DD250. The ACF process shall not be completed until DD250 sign-off. NOTE: Sign-off will not be delayed by any aircraft issue that was identified by the Contractor, if deferred for execution by the USG.
Aircraft Transfer and Post-Install Ferry Support The Contractor shall develop, coordinate, and execute aircraft transfer and post-ACF ferry procedures specific to their installation location. At a minimum, the Contractor shall ensure ferry crew receipt and transit to the aircraft, support for pre-flight inspections, turn-over of applicable aircraft documentation to the USG flight crews, and aircraft departure. These procedures shall not be updated without USG concurrence.
SECURITY
General The Contractor shall comply with and execute security requirements as identified in the security documentation. The Contractor shall ensure that only properly cleared personnel, with appropriate clearances, will handle classified material under the contract. The USG will provide subsets for security classification guides for all COMSEC equipment. The Contractor shall obtain requisite clearance eligibility on all employees prior to contract award. To reduce program vulnerabilities and to protect controlled unclassified information technologies from inadvertent disclosure, the Contractor shall designate the Site Lead/Manager, Deputy Site Lead/Manager, or a program-specific/Site-located Security Manager to be the focal point for program security issues and Operations Security (OPSEC). The Contractor shall ensure compliance with DoDD 5205.02E, DoDM 5205.02-M, and/or other applicable USG security regulations including procedures to protect classified and/or controlled unclassified information, USG projects and/or programs (contract clauses).
Communication Security (COMSEC) The Contractor shall be responsible for removing, storing, installing, maintaining, operating, inventorying, and shipping and receiving of cryptographic equipment/information management. The Contractor shall have a designated COMSEC Manager and COMSEC Account. All classified material shall be stored in a General Services Administration Approved, Class “B” vault which meets the standards for classified storage as outlined in DoDM 5200.01- V3.
The Contractor shall ensure that employees have the appropriate security clearance for the level of classification involved and background investigation are current. The handling, documentation, and shipment of COMSEC will follow the COMSEC Transportation Plan and security guidance. If required, the Contractor shall assist the USG in developing the COMSEC Transportation Plan. The release of any related COMSEC information by any means without prior written approval from the USG is strictly prohibited.
The contractor shall ensure all personnel adhere to the security provisions of this PWS for all aspects of information handling and dissemination.
Physical Security The Contractor shall safeguard GFP provided for Contractor use and adhere to the GFP requirements contained in this PWS and contract. At the end of each workday, GFP related to this program shall be controlled and secured. Contractors shall perform end-of-day/end of shift security checks. Security cameras may be used in lieu of security personnel during install location down times and must maintain full coverage of GFP.
Controlled/Restricted Areas The Contractor shall provide establish security procedures and protocols for entry to controlled or restricted areas where Contractor personnel will access to perform required tasks and to the maintenance and storage areas. At a minimum the Contractor shall protect aircraft IAW PL-4 standards. The Contractor shall ensure an aggregation of aircraft, engines, parts and/or industrial equipment are provided additional protection; the Contractor shall designate maintenance areas as controlled areas IAW AFI 31-101, OPSEC direction (Section 8.5), and protected IAW PL-4 standards. The Contractor shall be responsible for ensuring that all employees adhere to approved access procedures and according to established Security Protocols. The Contractor shall document the security level arrangements in support agreements, contract requirements documents (i.e., sub-contracts), and other appropriate documents (i.e., access roster). The Contractor will maintain an access roster which shall be made available to the USG upon request.
Operations Security (OPSEC) OPSEC reduces the vulnerability of USAF missions to adversary collection and exploitation of critical information. Critical Information is defined as information about missions or activities the adversary needs to achieve their goals. OPSEC shall be maintained per the provisions of this PWS. The Contractor shall ensure personnel who perform work at geographically separated locations comply with standardized OPSEC procedures. The Contractor shall include OPSEC as part of its ongoing security awareness program. The Contractor shall protect critical and sensitive unclassified information and activities, which could compromise classified information or operations, or degrade the planning and execution of military operations performed by the Contractor in support of the mission in accordance with the Company information protection program. Items of critical information are the facts, which individually, or in the aggregate, reveal sensitive details about the Contractor's security operations, and thus require protection from adversarial collection or exploitation. Reference the Program Protection Plan (PPP) for identified critical information and the PPP Appendix F for more information on OPSEC.
Program Protection Plan (PPP).
A PPP and supporting annexes shall be provided as Government Furnished Information (GFI). The Contractor shall follow guidance in the PPP and annexes for protection of Critical Program Information (CPI) identified in the PPP. Any modifications or deviations to the PPP or annexes shall be made in writing by the USG Program Manager. Requests for clarification of the PPP or annexes shall be made by the Contractor to the C-130J PMO not later than thirty (30) days from receipt of the PPP, its annexes, or updates thereof. The Contractor shall plan for and execute program protection in accordance with the PPP and program guidance.
Safeguarding Covered Defense Information and Cyber Incident Reporting.
The Contractor shall perform all necessary tasks to ensure Information Security is in compliance with the PWS. The Contractor shall certify all required Automated Information Systems are implemented IAW DoD Instruction 8500.1, Cybersecurity.
The Contractor shall provide adequate security to safeguard unclassified controlled technical information from compromise throughout the life of the contract. The Contractor shall comply with the clauses of this contract to ensure adequate security. If required, the Contractor will obtain access to USG data management systems and databases through the C-130J PMO. Security clearance and training of all personnel accessing these USG systems, and the resulting protection of information shall comply related provisions of this contract.
Access to Government Systems and Facilities.
Trustworthiness determinations and other Personnel and Cyberspace requirements are necessary for access to unclassified and classified Government IT systems. If required, the Contractor shall submit personnel security investigative paperwork for trustworthiness determinations, initial and/or continuous, IAW DoDMAN5200.02_DAFMAN16-1405, DoD Common Access Card (CAC) IAW DAFI36-3026V2 or Alternate Login Token (ALT) issuance, and Cyberspace requirements (e.g. user rules of behavior, statement of understanding/responsibilities, privileged user agreement, operating environment training, and/or qualifications/certifications IAW DoDM 8140.03, AFMAN17-1301, AFMAN17-1303, and DAFMAN17-1304. The Contractor shall ensure their personnel have appropriate requirements completed and approved prior to commencing work on this task order unless otherwise approved in writing by the PCO. The Contractor shall also ensure their personnel maintain the necessary requirements as a condition of continued task performance. All costs associated with obtaining necessary systems and facility access shall be borne by the Contractor. The information below summarizes the requirements:
2.1.45 Privileged (IT Level I) Access - Investigative requirement: favorable Tier 5 personnel security investigation; CAC & ALT; user rules of behavior; statement of understanding and responsibilities; privileged user agreement; Annual DAF Cyber Awareness Training; operating environment training; and qualifications and certifications.
2.1.46 Limited Privileged (IT Level II) Access - Investigative requirement: favorable Tier 3 personnel security investigation; CAC & ALT; user rules of behavior; statement of understanding and responsibilities; privileged user agreement; Annual DAF Cyber Awareness Training; operating environment training; and qualifications and certifications.
2.1.47 Non-Privileged (IT Level III) Access - Investigative requirement: favorable Tier 1 personnel security investigation; CAC for unclassified and ALT for classified systems; Annual DAF Cyber Awareness Training; user rules of behavior.
Information Security (INFOSEC).
The Contractor shall comply with DoDI 8582.01, DoDI5200.48_DAFI16-1403, DoDM5200.01V1_AFMAN16-1404V1, DoDM5200.01V2_AFMAN16-1404V2, DoDM5200.01V3_DAFMAN16-1404V3, AFI16-1404_AFMCSUP, DAFI16-701, AFMAN14-403, DODM5205.07V3_AFMAN16-703V3, and the Special Security Agreement for the protection of unclassified, Controlled Unclassified Information (CUI), and classified information. The Contractor shall identify, consult, and comply with applicable Security Classification Guides (SCGs) for classified information.
CUI is any information that law, regulation, or Government-wide policy requires to have safeguarding or disseminating controls, excluding information that is classified under Executive Order 13526, Classified National Security Information, December 29, 2009, or any predecessor or successor order, or the Atomic Energy Act of 1954, as amended. The National Archives and Records Administration CUI Registry (http://www.archives.gov/cui/registry/category-list.html) identifies approved CUI categories and subcategories, provides general descriptions for each, identifies the basis for controls, and sets out procedures for the use of CUI. The Contractor shall comply with additional guidance for specific categories of CUI, such as DoD Scientific and Technical Information (STINFO), DAFI61-201; Personally Identifiable Information (PII), AFI33-332; and protect other contractors’ proprietary data (Conflict of Interest clauses, including FAR 52.203-16, Preventing Conflicts of Interest).
The Contractor shall protect unclassified DoD information not approved for public release on non-DoD Information Systems IAW DoDI 8582.01.
The Contractor shall comply with Air Force Records Management IAW AFI33-322 and Freedom of Information Act (FOIA) requirements IAW DODM5400.07_AFMAN33-302.
Security Clearances.
The Contractor shall ensure applicable Contractor personnel have security clearances at the appropriate level for proper accomplishment of the contract requirements. The security clearance shall be obtained in accordance with the Special Security Agreement. Contractor personnel whose clearances have been suspended or revoked shall immediately be denied access to classified information and/or CUI and classified items. The Contractor shall possess a current collateral Secret clearance (at a minimum), the highest clearance level required, as specified in the Special Security Agreement and this PWS. The Contractor shall submit personnel security investigative paperwork for security clearances IAW DoDMAN5200.02_DAFMAN16-1405. All costs associated with obtaining necessary clearances shall be borne by the Contractor. Regardless of clearance level, the Contractor shall maintain this clearance throughout the contract Period of Performance.
2.2 Reporting Requirements.
The Contractor…