About this file
This is a comprehensive bid document for the City of Stone Mountain's Fiscal Year 2025 SPLOST (Special Purpose Local Option Sales Tax) Resurfacing Project located in Stone Mountain, Georgia. The project involves road repair, patching, and resurfacing on multiple city streets, including Redwood Court, Zachary Court, Rosewood Drive, Ridgemont Court, VFW Drive, Veal Street, Leon Street, Cemetery Circle, San Pablo Drive, and various Rockborough Courts. The bid is scheduled for opening on Thursday, April 24, 2025, at 2:00 p.m. local time, with an optional virtual pre-bid meeting on Wednesday, April 16, 2025. The contract term is 150 consecutive calendar days from the commencement date, with work including asphalt milling, pavement replacement, subgrade repairs, traffic maintenance, and associated road improvements.
The project is funded through the city's SPLOST program, with a bid bond or certified check requirement of 5% of the total bid amount. Contractors must provide a performance and payment bond for 100% of the contract value and maintain specific insurance coverages. The bidding process allows for unit price submissions, with an estimated quantity of work including various asphalt and concrete applications, traffic control, excavation, graded aggregate base, and road markings. The bid includes an alternate option for full-depth pavement replacement on Zachary Court, with potential adjustments to the contract scope and price based on the city's selection. Contractors must be licensed to do business in Georgia and comply with E-Verify employment verification requirements.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CITY OF STONE MOUNTAIN FY 2024 SPLOST RESURFACING PROJECT
CPL R.23.00937.02 PROJECT DIRECTORY SECTION 00 001-1
OWNER CITY OF STONE MOUNTAIN (770) 498-8984
875 Main Street FAX (770) 498-8609
Stone Mountain, Georgia 30083
Shawntez �Shawn� Edmondson City Manager
PRIMARY CONSULTANT:
ARCHITECT &
ENGINEER CPL (770) 831-9000
3011 Sutton Gate Drive, Suite 130 FAX (770) 831-9243
Suwanee, Georgia 30024
Richard B. Henry, PE
CPL President
CITY OF STONE MOUNTAIN FY 2025 SPLOST RESURFACING PROJECT
CPL R.23.00937.02 TABLE OF CONTENTS SECTION 00 002-1
TECHNICAL PROVISIONS
DIVISION 0 - BIDDING/CONTRACT REQUIREMENTS
Section Title
00 001 Project Directory
00 002 Table of Contents
00 010 Invitation to Bid
00 100 Instructions to Bidders
00 200 Project Description
00 300 Bid Form
00 500 Form of Agreement
00 701 General Conditions
DIVISION 1 - GENERAL REQUIREMENTS
Section Title
01 010 Summary of Work
01 230 Alternates
01 630 Product Options and Substitutions
01 740 Contractor Warranty Form
01 741 Subcontractor Warranty Form
01 742 E-Verify Contractor Affidavit
END OF SECTION 00 002
CPL R.23.00937.02 INVITATION TO BID SECTION 00 010-1
INVITATION TO BID ON THE
City of Stone Mountain - FY 2025 SPLOST RESURFACING PROJECT
PROJECT BID NO. CIP 2025-001
The City of Stone Mountain is soliciting competitive sealed bids from qualified contractors for STREET REPAIR, PATCHING, AND PAVING. Sealed bids will be received by the City of Stone Mountain at the Stone Mountain
City Hall, 875 Main Street, Stone Mountain, Georgia 30083, until 2:00 p.m. local time on Thursday, April 24, 2025. The bids will be opened by staff and the results will be posted later that day via email to the bid submitters.
Any bid received after 2:00 p.m. will not be accepted. Bid envelopes must be marked on the outside with Bid
Number, Name of Bidder, date and time of opening and Contractor�s License Number. Failure to display
Contractor�s License Number may result in the bid being returned.
Work required under the contract will include asphalt milling and paving, replacement of distress pavement areas, subgrade repairs as necessary, all traffic maintenance and safe movement of emergency vehicles during construction on the following city streets:
Redwood Court from Pepperwood Trail to cul-de-sac
Zachary Court from Zachary Court to cul-de-sac
Rosewood Drive from Lucille Ave to Pepperwood Trail
Ridgemont Court from Ridge Forest Drive to cul-de-sac
VFW Drive Mimosa to Cloud, Cloud to dead end
Veal Street from JB Rivers to Central
Leon Street from Mimosa to Manor
W. Rockborough Court from Rockborough Drive to cul-de-sac
E. Rockborough Court from Rockborough Drive to cul-de-sac
N. Rockborough Court from Rockborough Drive to cul-de-sac
Cemetery Circle from Silver Hill Road to PoncedeLeon Ave
San Pablo Drive from Ridge Ave to Shappard Road
An optional virtual pre-bid meeting will be held Wednesday, April 16, 2025 at 2:00pm.
Interested parties should contact Lori Brothers at lbrothers@cplteam.com (678-318-1001) to request a bid package.
Bids shall be entered as a lump sum price. The bidder shall provide a lump sum price based on unit prices for estimated quantities as described in the project manual and outlined on the bid form.
One complete set of drawings and specifications shall be provided in an electronic format. No partial sets of working drawings or specifications shall be issued. Questions shall be emailed to Thomas McElheny at CPL, Attention: Stone Mountain City Engineer Bid No. 2025-001 at TMcElheny@cplteam.com. Questions will be received up to Friday, April 18, 2025 at 5:00 pm. Responses will be made through an addendum. Contractor shall provide email address on facsimile and/or at time of bid package request and/or pick up.
Bids in the case of Corporations not chartered in Georgia, must be accompanied by proper certification stating that said Corporation is authorized to do business in the State of Georgia. No Bidder may withdraw his Bid within ninety (90) days after the actual date of the opening thereof.
CPL R.23.00937.02 INVITATION TO BID SECTION 00 010-2
All Bidders are required to submit a Bid Bond or a certified check made payable to the City of Stone Mountain in the amount of five percent (5%) of the total amount bid. The successful bidder will be required to furnish a contract performance bond and payment bond in the amount of one hundred percent (100%) of the total amount bid and provide insurance coverage as required by the contract documents. The Bid Bond or certified check must be enclosed in the envelope with the sealed bid.
Bonding Company must be licensed to do business in Georgia, licensed to do business by the Georgia Secretary of
State, authorized to do business in Georgia by the Georgia Insurance Department, listed in the Department of the
Treasury's Publication of Companies Holding Certificates of Authority as Acceptable Surety on Federal Bonds and as Acceptable Reinsuring Companies and have an A.M. Best rating of A-, Class V or higher.
The Owner will award the Contract to the lowest qualified bidder, subject with the Owner's right to reject any or all bids, to waive technicalities, and to make an award deemed in its best interests.
CPL R.23.00937.02 INSTRUCTIONS TO BIDDERS SECTION 00 100-1
SECTION I
INSTRUCTIONS TO BIDDERS
1. DEFINED TERMS:
1.1 The terms used in Instructions to Bidders and defined in General Conditions
(Section G) shall have meanings assigned to them in General Conditions.
1.2 The term �Successful Bidder� means the Bidder to whom the Owner awards or expects to award the contract.
2. COPIES OF BID DOCUMENTS:
2.1 Bid Document Package may be available in advance to contractors and other interested parties at the cost and location stipulated in the INVITATION TO BID.
2.2 Complete sets of Bid Documents shall be used in preparing Bids. The Owner assumes no responsibility for errors or misinterpretations resulting from using incomplete sets of Bid Documents.
2.3 The Owner, in making Bid Documents available on the above terms, does so only to obtain Bids on Work and does not confer license or grant for any other use.
2.4 Any part of the Bid Documents may be modified by Addenda.
Where forms are provided, THEY MUST BE USED WITHOUT SUBSTITUTION!
Use of forms other than those provided by the City shall constitute a non-responsive Bid and shall be rejected.
NOTE: Bidder must submit one original and one copy of Bid Documents to include: Bid
Form; Instructions to Bidders; Bidder�s Affidavit; Non-Collusion Affidavit; and Bid Bond.
3. QUALIFICATIONS OF BIDDERS:
3.1 The City may make any investigations deemed necessary to determine Bidder�s ability to perform the Work, and Bidder shall furnish all information and data requested by the City. The City reserves right to reject any bid from any Bidder that the City considers not properly qualified to carry out Contract obligations or able to satisfactorily complete the Work on schedule.
3.2 If Bidder does not have offices in the State of Georgia, such Bidder shall designate a proper agent in the State of Georgia on whom service can be made in the event of litigation.
CPL R.23.00937.02 INSTRUCTIONS TO BIDDERS SECTION 00 100-2
4. EXAMINATION OF BID DOCUMENTS AND SITE:
4.1 Before submitting Bid, each Bidder shall: (a) examine the Bid Document Package thoroughly; (b) visit the site to become familiar with local conditions affecting cost or Work progress or performance; (c) become familiar with federal, state, and local laws, ordinances, rules, and regulations affecting cost or Work progress or performance; (d) study and carefully correlate Bidder�s observations with the Bid
Document Package; and, (e) notify The Architect concerning conflicts, errors, or discrepancies in Bid Document Package.
4.2 On request, The Architect may provide each Bidder access to the site to conduct investigations and tests that Bidder deems necessary in order to submit Bid subject to easement acquisitions and existing conditions.
4.3 Bid submission will constitute incontrovertible representation that Bidder understands and has complied with requirements contained in this Article 4, and that Bidder has read and understood the Bid Document Package and hereby stipulates that the documents are sufficient in scope and detail to indicate and convey understanding for terms and conditions in order to perform Work.
5. ADDENDA AND INTERPRETATIONS:
5.1 Questions concerning meaning or intent of Bid Document Package shall be directed in Thomas McElheny at tmcelheny@cplteam.com. Replies will be issued by Addenda mail or delivered to parties recorded by the Department as having received Bid Document Package. Questions after the end of questions date and time will not be answered. Only questions answered by formal written Addenda will be binding. Oral and other interpretations or clarifications will be without legal effect.
5.2 Addenda may be issued to modify Bid Document Package as deemed necessary by the City.
6. BID SECURITY:
6.1 Each bid shall be accompanied by Bid Security made payable to Owner in the amount equal to five percent (5%) of the Bidder�s maximum Bid Price. Bid
Security shall be cashier's check or Bid Bond issued by Surety meeting requirements contained in paragraph 24 below. Bid bond must be on City provided form found in bid package. Failure to use City forms may constitute a non-responsive bid and may be rejected.
6.2 Bid Security for Successful Bidder will be retained until Bidder has executed
Agreement and furnished required payment and performance bonds. If Successful
Bidder fails to furnish the qualifications submittals or fails to execute and deliver
Agreement and furnish required Payment and Performance Bonds within fifteen
(15) calendar days after Notice of Award, Owner may annul Notice of Award and
Bidder�s Bid Security will be forfeited.
CPL R.23.00937.02 INSTRUCTIONS TO BIDDERS SECTION 00 100-3
Bid Security, for any Bidder that the City believes to have reasonable chance to receive award, may be retained by Owner until the ninety-first (91st) day after Bid opening. If Notice of Award is issued within ninety (90) calendar days after Bid opening, Bid Security for Bidder receiving Notice of Award may be retained by
Owner up to ninety (90) calendar days after Notice of Award.
6.3 Bid Bond shall be issued by company having a registered agent in State of Georgia and shall comply with the additional requirements of paragraph 23 below.
7. CONTRACT TIME:
The Work shall be completed within one hundred fifty (150) consecutive calendar days.
8. EXAMINATION OF BID PLANS AND SPECIFICATIONS:
Bidders are advised to carefully examine the Bid Plans and Specifications for the proposed
Work. The Bid Plans indicate the surface and underground structures likely to affect the prosecution of the Work insofar as they have been determined, but the information indicated is not guaranteed as being correct and complete. Bidders are expected to examine the Bid Plans and the location of the Work, verify all information with authorities concerned, and judge for themselves all the circumstances affecting the cost of the Work and the time required for its completion, and shall assume all patent and latent risks in connection therewith.
9. BID BOND FORFEITURE:
The Successful Bidder, upon his failure or refusal to execute and deliver the Contract and
Bonds required within fifteen (15) calendar days after receipt of Notice of Award, shall forfeit to the Owner, as penalty for such failure or refusal, the security deposited with Bid.
Provisions for penalty are set forth in the Advertisement for Bid, Bid Documents, and Specifications (including General Conditions).
10. SUBSTITUTE OR �OR EQUAL� TERMS:
10.1 The Contract, if awarded, will be based on material and equipment described in
Plans or specified in Specifications without consideration for possible substitute or
�or equal� items. Where indicated in Plans or specified in Specifications, substitute or �or equal� material or equipment may be furnished or used by
Contractor, if acceptable to the Engineer. Application for substitute or �or equal� items will be considered by the Owner until seven (7) calendar days prior to date for opening Bids.
Procedure for submitting application and consideration by the Architect is set forth in General Conditions and may be supplemented in Paragraphs 11.2 and 11.3 following.
CPL R.23.00937.02 INSTRUCTIONS TO BIDDERS SECTION 00 100-4
10.2 Materials or equipment specified or described in Bid Document Package by proprietary name or by naming a particular supplier are intended to establish type, function, and quality required. Unless name is followed by words indicating no substitution is permitted, materials or equipment from other suppliers may be accepted by the Architect if sufficient information is submitted by Bidder to allow the Architect to determine material or equipment proposed is equivalent or equal to named material or equipment. Bidders shall make written application to the Architect for proposed substitute material or equipment and shall certify that the proposed substitute material or equipment will perform adequate functions and achieve results called for by general design, be similar and equal substance to item specified, and be suited to same use as specified material or equipment.
Application shall state that the Architect�s acceptance of proposed substitute will not prejudice Contractor�s achieving Substantial Completion on time, will or will not require changes to Contract Documents to adapt design to proposed substitute, and will or will not require payment for license fee or royalty. Bidder shall indicate acceptance of responsibility for all costs of redesign, which will be required through approval of Bidder�s application.
Variations for proposed substitute from item specified will be identified in application and available maintenance, repair, and replacement service will be indicated.
10.3 Bidders may propose substitute construction means, methods, sequences, techniques, or procedures for specific construction means, methods, techniques, sequences, or procedures indicated in or required by Bid Document Package.
Bidders shall submit sufficient information to allow the Architect to determine substitute proposed is equivalent to means, method, sequence, technique, or procedure indicated or required by Bid Document Package. Procedure for review by the Architect will be similar to method provided in Paragraph 11.2 above.
10.4 The Architect will be allowed reasonable time to evaluate each proposed substitute. No application for substitute will be considered later than seven (7) calendar days prior to bid opening date. The Architect will be sole judge concerning proposed substitute acceptability.
11. SUBCONTRACTORS, SUPPLIERS AND OTHERS:
11.1 Each Bid shall identify names and addresses for subcontractors, suppliers, and other persons and organizations furnishing material and equipment, or Bid will be considered non-responsive. The Bidder is cautioned that any person, firm or other party to whom it is proposed to award a subcontract under this Contract must meet the same conditions of experience, competent personnel and workman�s compensation insurance as the Bidder.
If requested by the Engineer, the Successful Bidder and any other Bidder shall, within seven (7) calendar days after request, submit to the Architect experience statement with pertinent information for similar projects and other qualifications
CPL R.23.00937.02 INSTRUCTIONS TO BIDDERS SECTION 00 100-5
for each subcontractor, supplier, person, and organization. If the Architect, after due investigation has reasonable objection to any proposed subcontractor, supplier, person, or organization, the Engineer may, before giving Notice of Award, request
Successful Bidder to submit acceptable substitute without increase in Contract
Price or Contract Time. If Successful Bidder declines to make substitution, the
Engineer may elect not to award contract to Bidder. Bidder�s declining to make substitution will not constitute grounds for sacrificing Bid Security.
11.2 Procedures for approving Subcontractors after executing Agreement are described in the General Conditions. No subcontractors may be employed without the specific written authorization of the Engineer.
11.3 No Contractor will be required to employ subcontractor, supplier, person, or organization against whom Contractor has reasonable objection.
12. NOTICE OF SPECIAL CONDITIONS:
Attention is particularly called to those parts of the Specifications (including General
Conditions) which deal with the following:
a. Insurance Requirements
13. BID FORM:
13.1 Bid Form is included in the Bid Document package purchased by the Bidders.
13.2 Bid Forms shall be completed and submitted in duplicate.
13.3 Bids by corporations shall be executed in corporate name by president or vice-president (or other corporate officer accompanied by evidence indicating officer has authority to sign) and corporate seal shall be affixed and attested by secretary or assistant secretary. Corporate address and state of incorporation shall be shown below signature. If Bid is executed by someone other than president or vice-president, attach to Bid certified corporate resolution by board of directors authorizing person to execute Bid for Corporation.
13.4 Bids by partnerships shall be executed in partnership name and signed by partner, whose title shall appear under signature and official partnership address shall be shown below signature.
13.5 If requested, person signing Bid for corporation or partnership shall produce evidence satisfactory to Owner indicating person�s authority to bind corporation of partnership.
13.6 Names shall be typed or printed below signature.
13.7 Bid shall contain acknowledgement Bidder has received Addenda (Addenda numbers shall be filled in on Bid Form).
CPL R.23.00937.02 INSTRUCTIONS TO BIDDERS SECTION 00 100-6
13.8 Address and telephone number for communications regarding Bid shall be shown.
13.9 Bidder must furnish, in his Bid (if not furnished with Pre-Qualification Package), summary information relative to the facilities, ability, and financial resources available for the fulfillment of the Contract.
14. QUANTITIES OF WORK:
The quantities of Work shown on the drawings are approximate and are assumed solely for comparison of the proposals. They are not guaranteed to be accurate statements or estimates of quantities of Work that are to be performed under the Contract, and any departure, therefrom will not be accepted as valid grounds for any claim for damages, for extension of time or for loss of profits; nor will any additional payments other than that bid, be made regardless of the actual quantities required or ordered to complete the Work.
15. SUBMISSION OF BIDS:
15.1 Bids shall be submitted before time and at place indicated in Advertisement for
Bid and shall be submitted in sealed envelope with the following notation on the face:
BID NUMBER: CIP 2025-001
CITY OF STONE MOUNTAIN � FY 2025 SPLOST RESURFACING PROJECT
NAME OF BIDDER
DATE AND TIME OF OPENING: Thursday, April 24th, 2025, 2:00 PM
If Bid is sent through mail or other delivery system, sealed envelope shall be enclosed in separate envelope with same notations as above on face.
15.2 Each Bid shall contain following documents in completed form (City forms must be used without substitution):
1. Bid Form
2. Bidder�s Affidavit
3. Non-Collusion Affidavit
4. Bid Security (Surety Bond on City provided Form or Certified or
Cashier�s Check)
5. Power of Attorney (Surety Bonds only)
6. Corporate authority to execute Bid (required for any corporate officer other than president or vice-president)
7. E-Verify Contractor Affidavit under O.C.G.A
15.3 More than one Bid received for same work from individual, firm, partnership, corporation, or association under same or different names will not be considered.
Reasonable grounds for believing any Bidder is interested in more than one Bid for same work will cause Owner to reject all Bids from Bidder. If Owner believes collusion exists among Bidders, Bids from participants in collusion will not be considered.
CPL R.23.00937.02 INSTRUCTIONS TO BIDDERS SECTION 00 100-7
15.4 Conditions, limitations, or provisions attached by the Bidder to the Bid Forms may cause its rejection. Bids containing Items not included in the form of Bid will be considered irregular.
16. MODIFICATION AND WITHDRAWAL OF BIDS:
16.1 Withdrawal Prior to Time for Receiving Bids: Bids may be modified or withdrawn by appropriate document duly executed (in manner Bid must be executed) and delivered to place where Bids are to be submitted at any time prior to deadline for submitting Bids. Bid Withdrawal will not prejudice Bidder�s rights to submit new Bid prior to Bid Date and Time.
16.2 Withdrawal After Time for Receiving Bids: After period for receiving Bids has expired, no Bid may be withdrawn, modified, or explained except as provided for in paragraph 18 below.
17. OPENING OF BIDS:
Bids will be opened publicly at the time and place set forth in the INVITATION TO BID and read aloud. Abstract listing amount for Base Bids and major alternates will be made available after Bid opening.
17.1 After Bid opening Bidder has up to twenty-four (24) hours to notify the City that
Bidder made an obvious error in Bid calculation. Bid Bond withdrawal for this reason shall be requested in writing within this same twenty-four (24) hour period.
Said written request shall be accompanied by sufficient documentation to demonstrate the origin and composition of the �obvious error.� Bid Bond may not be withdrawn for any other reason.
18. BIDS TO REMAIN OPEN:
Bids shall remain open for acceptance by Owner for ninety (90) calendar days after Bid opening. Owner may, at its sole discretion, release any Bid prior to that date.
19. AWARD OF CONTRACT:
19.1 To extent permitted by applicable state and federal laws and regulations, Owner reserves the right to reject any and all Bids, to waive any and all informalities, and to disregard nonconforming, non-responsive, or conditional Bids. Bids may be considered irregular and subject to rejection if they show serious omission, unauthorized form alterations, use unauthorized forms, unauthorized alternate bids, incomplete or unbalanced unit prices, or other irregularities. Discrepancies between words and figures will be resolved in favor of correct sum. Any mistake which is obviously a clerical one, such as an error in price extension, or in placement of decimal points, reversal of prices, FOB destination, FOB point of origin, etc., may be corrected by the purchasing authority after verification is made by the bidder. However, under no circumstances can unit prices be changed.
CPL R.23.00937.02 INSTRUCTIONS TO BIDDERS SECTION 00 100-8
19.2 Contract will be awarded by Owner pursuant to applicable law. Nothing contained herein shall place duty upon Owner to reject bids or award contract based upon anything other than Owner�s sole discretion as described herein.
19.3 The Department may consider qualifications and experience for subcontractors, suppliers, persons, and organizations proposed for Work.
19.4 The Department may conduct investigations deemed necessary to assist in evaluating Bids and to establish responsibility, qualifications, and financial ability for Bidders, proposed Subcontractors, persons, and organizations to do Work.
Owner reserves right to reject Bid from any Bidder not passing evaluation to
Owner�s satisfaction.
19.5 One contract for Work will be awarded, if award is made, based upon Base Bid to lowest responsible, responsive Bidder. Alternate Bids will not be considered as basis for award unless specifically stated on the Bid Form. Successful Bidder will be required to perform Work as Prime Contractor. Work performed by Contractor shall be 50% minimum. No Contract assignment or subcontracting will be allowed without written permission from the Architect.
19.6 The Successful Bidder will be required to furnish a Performance and Payment
Bond, Each in a sum not less than one hundred percent (100%) of the amount of the Contract. The Bonds shall be that of an approved surety meeting the requirements as noted in paragraphs 6 and 24 herein.
19.7 If at any time after the execution and approval of the Contract and of the Surety
Bonds as required in the Bid Advertisement, the Owner shall deem any of the
Sureties upon such Bonds to be unsatisfactory, or such Bonds to be inadequate security for the Owner, the Contractor shall, within five (5) calendar days after notice from Owner to do so, furnish new or additional Contract Bonds, in form and sum, and signed by such Sureties who all shall be satisfactory to the Owner. No further payment will be deemed due nor will any further payment be made to the
Contractor unless such new or additional Bonds are furnished and approved. The premium on such Bonds shall be paid by the Contractor.
Failure of the Contractor to submit approved Performance and Payment Bonds within the required five (5) calendar days shall, at the discretion of the Owner, constitute a forfeiture of the Bid Bond.
20. SUBMITTALS BY SUCCESSFUL BIDDER:
20.1 Owner intends to award contract to Bidder competent to perform and complete
Work in satisfactory manner. Owner will require Successful Bidder to submit, within seven (7) calendar days after receiving written request from the Architect and prior to contract award, Preliminary Progress Schedule and Schedule of
Values, as set forth below.
20.2 Preliminary Progress Schedule shall be submitted in triplicate and include time-scaled schedule and narrative in accordance with appropriate formats established in the Architects� written request for schedules. Activities in schedule shall show order Successful Bidder proposes to perform Work within constraints and
CPL R.23.00937.02 INSTRUCTIONS TO BIDDERS SECTION 00 100-9
sequencing conditions set forth in Specification (including General Conditions) and shall indicate starting and completion dates for key milestones and Work pertaining to each Specifications division within each major structure or geographical area on site. Activities shall identify significant submittals and approvals, major equipment deliveries, equipment testing, Owner�s responsibilities, affected utilities, and other similarly involved third parties.
20.3 Schedule of Values shall include Bid itemization by major structures or Work areas.
20.4 Successful Bidder and surety, if any, agree any delays within Bidder�s control in delivering submittals shall constitute request by Bidder for time extension and Bid shall remain open for Owner�s acceptance. If Owner agrees to time extension, Bidder shall comply with Submittal Requirement within five (5) additional calendar days. At Owner�s option, failure by Successful Bidder to deliver submittals within extended period will void Bid evaluation and will constitute proof Successful Bidder has abandoned Bid, Bid Security may be declared forfeited to Owner as liquidated damages, and Work may be awarded to Another
Bidder.
21. BUSINESS LICENSE:
Successful Bidder�s submittals shall include a copy of Bidder�s business license.
22. TAXES:
Contractor shall pay applicable sales, consumer, use, and other similar taxes required by law. Contractor is responsible for reviewing pertinent state statutes involving sales tax and complying with requirements.
The Contract prices for articles, materials, or equipment names herein are subject to increase by the amount of any additional tax or taxes affecting the articles, materials or equipment involved in the Contract imposed by or under the authority of the Federal or
State Government and passed or taking effect after the receipt of Bids, and shall continue in effect during such time as such tax or taxes are lawfully collectible; provided, however, that in the event of such increase in cost, the claim shall be presented within thirty (30) days and supported by evidence of such additional tax, satisfactory to the City Attorney.
23. QUALIFICATIONS OF SURETY COMPANIES:
In order to be acceptable to Owner, surety company issuing Bid Guaranty Bonds or 100%
Performance/Payment bonds as required in Bid Advertisement shall meet and comply with following minimum standards:
23.1 Bonding Company must be licensed to do business in Georgia by the Georgia
Secretary of State, authorized to do business in Georgia by the Georgia Insurance
Department, listed in the Department of the Treasury's Publication of Companies
Holding Certificates of Authority as Acceptable Surety on Federal Bonds and as
Acceptable Reinsuring Companies and have an A.M. Best rating of A-, Class VI or higher.
CPL R.23.00937.02 INSTRUCTIONS TO BIDDERS SECTION 00 100-10
23.2 All bonds must be submitted on forms provided by the City and agencies providing bonds and insurance must provide proof that they meet the criteria outlined in the bid and contract documents.
23.3 Surety shall be admitted to do business in State of Georgia and shall be registered to provide such surety the State of Georgia Insurance Commissioner.
23.4 Attorneys-in-fact who sign bid bonds or performance/payment Bonds shall file with bond certified power of attorney to sign bond.
23.5 Surety company agents shall list name, address, and telephone number on bonds.
23.6 Performance and payment Bonds shall extend twelve (12) months beyond date of final payment and shall contain waiver for alteration to Contract terms, time extensions, or forbearance on Owner�s part.
24. EXECUTION OF WRITTEN CONTRACT
Successful Bidder will be required to sign written contract identified in bid package as
Agreement. Unsigned Agreement will be submitted to Successful Bidder either prior to or along with the Notice of Award. The Contractor shall sign and deliver the fully executed
Agreements to Owner with all required bonds within ten (10) calendar days following receipt of Agreement forms, (unless otherwise stipulated by the Owner).
25. AREA OFFICE:
If required by the Architect, the Contractor will be required to establish an office and an equipment and spare parts storage yard within Gwinnett County to conduct this work and must arrange to cope with any emergency that may arise in connection with the Work on a twenty-four (24) hour per day, seven (7) day per week basis.
26. PROTESTS:
Owner is responsible for resolving protests concerning contract award, claims, disputes, alleged license fees, and other related procurement matters in accordance with sound business judgment and good administrative practice. Following procedures shall be used for this purpose:
26.1 Any party with direct financial interest adversely affected by Owner�s procurement decision shall file protest under this article, or be barred further relief.
26.2 Protest shall: (a) be made in writing, oral protests will not be permitted; (b) adequately state basis for protest and relief requested; and (c) be received by
Owner within seven (7) calendar days from date basis for protest was, or should have been, known.
26.3 Owner may defer protested procurement upon receiving procedurally adequate protests, provided in any even awarding contract, subcontract, or procurement for sub item may be permitted, at Owner�s sole discretion, where award will not materially affect resolving protest.
CPL R.23.00937.02 INSTRUCTIONS TO BIDDERS SECTION 00 100-11
26.4 Protest shall be limited to: (a) issues arising from procurement provisions contained in Specifications; and (b) state or local law. No protest may be filed with respect to basic project design.
26.5 City Attorney will establish procedures for resolving protests. Owner will rely for protest resolution on decisions issued under Georgia law, as well as decisions issued under Georgia law, as well as decisions issued by other states, Federal courts, U.S. Comptroller General, or other Federal agencies with extensive procurement expertise, if state law is not clearly established.
27. BIDDER�S ACKNOWLEDGEMENT:
The undersigned bidder acknowledges all requirements outlined in the above �Instructions to Bidders Package� and all documents referred to therein. This signed form must accompany the completed bid form submitted at the time of bid.
SIGNATURE: ______________________ DATE: ___________________________
(President, Vice President or
Corporate Officer)
PRINTED NAME: __________________ TITLE: ___________________________
ATTESTED BY: ___________________ DATE: ___________________________
(Secretary of Corporation)
PRINTED NAME: __________________ TITLE: ___________________________
SEAL
(Corporate Seal Required if Bidder is a Corporation)
COMPANY NAME:
ADDRESS:
CITY: _________________________________ STATE: ________ ZIP: ___________
TELEPHONE NO: _______________________________________________________
END OF SECTION 00 100
CPL R.23.00937.02 PROJECT DESCRIPTION SECTION 00 200-1
ROADWAY IMPROVEMENTS ON VARIOUS CITY ROADS
This project consists of milling, patching, asphaltic crack filling, resurfacing, and marking on various City roads and parking lots.
This section provides a description of the project, the diagrams and exhibits necessary to understand the scope and work of the project, and technical descriptions of how the work is to be conducted.
BIDDERS ARE ADVISED TO THOROUGHLY UNDERSTAND THE GENERAL
CONDITIONS AND SPECIAL PROVISIONS OF THIS SECTION, PRIOR TO
SUBMITTING THEIR BID.
I. GENERAL CONDITIONS
A. AWARD OF CONTRACT
The Contract will be an "Open End" type to provide for the requirements of City of S t o n e
M o u n t a i n on an as needed basis. As it is impossible to determine the exact quantities of items and the roads, parking areas, etc., to receive these items, either for resurfacing or new roads, the quantities of items may be increased or decreased as required to satisfy the needs of the City. It is anticipated that the quantities referenced in these bid documents are approximate and subject to change.
B. LOCATION AND SITE
1. The site of the proposed work is at the stated location(s) within the City of Stone
Mountain, Georgia. A list of proposed roads is included in these specifications.
2. All auxiliary lanes located in the corridor are included in the milling and resurfacing limits of this contract. The city has established an estimated quantity to structure bid determination. The bidder is advised to confirm the quantities presented in Section F.
2. The Contractor shall accept the site in its present condition and carry out all work in accordance with the requirements of the specifications, as indicated on the drawings or as directed by the engineer.
3. The Contractor, before submitting a bid, is advised to visit the site, and acquaint themselves with the actual conditions and the location of any or all obstructions that may exist on the site.
4. The Contract Documents contain the provisions required for the completion of the work to be performed pursuant to this Contract. Information obtained from an Officer, agent, or employee of City of Stone Mountain or any other person shall not affect the risks or obligations assumed by the Contractor or relieve the Contractor from fulfilling any of the conditions of the Contract. Each Bidder is responsible for inspecting the site and for reading and being thoroughly familiar with the Contract Documents. The failure or omission of any Bidder to so familiarize themselves shall in no way relieve any Bidder from any obligation in respect to their Bid.
5. The Contractor is responsible for the location of above and below ground utilities and structures, which may be affected by the work.
CPL R.23.00937.02 PROJECT DESCRIPTION SECTION 00 200-2
II. SPECIAL PROVISIONS
A. GENERAL CONSTRUCTION GUIDELINES
1. All driveways and intersections shall be tied-in with surface mix at the time of paving for a sufficient distance to provide a smooth transition from the new pavement to the existing surface.
2. City of Stone Mountain does not commit to furnishing full-time inspection or testing of the work in progress, or at material sources. Lack of inspection and/or testing by the City will in no way relieve the Contractor of their responsibility to provide quality workmanship in accordance with the Specifications.
3. On roads to be resurfaced the contractor shall furnish, install, maintain and remove all necessary traffic signs, barricades, lights, signals, cones and other traffic control devices, and all flagging and other means of traffic protection and guidance as required by the Standard
Specifications of the Georgia Department of Transportation. Such work shall be considered incidental to the overall contract, and no additional compensation will be made.
4. On roads without curb and gutter the contractor shall be required to knock down any windrows created by the clipping operation. This work shall be done following resurfacing, at such time that the mix has sufficiently cured to prevent damage. Such work shall be incidental to the cost of the resurfacing work being performed and no additional payment shall be made.
5. All surface utility and drainage structure covers shall be adjusted as.
6. The final road cross section as a minimum shall in accord with Dekalb County Std 700, Type
III Industrial Street.
B. ROAD PATCHING
1. Road Patching, as described herein, shall apply to the removal and replacement of failed areas, as indicated by the Engineer, on roads scheduled for resurfacing.
2. The City has pre-marked the areas to be patched with white paint. The city has established an estimated quantity to structure bid determination.
CPL R.23.00937.02 PROJECT DESCRIPTION SECTION 00 200-3
3. The Contractor will give the City at least 24 hours notice before proceeding on patching a particular road.
4. The required procedures for patching Bituminous Asphaltic Concrete roads shall be as follows:
a) Areas to be patched shall be milled using an approved machine.
b) Where pavement repair areas are located, the Contractor shall saw cut the perimeter of the area, excavate the full depth of existing asphalt or concrete plus an additional six
(6) inches for placement of six (6) inches of compacted GAB, covered with 19mm asphalt binder backup to match the existing asphalt or concrete surface.
c) The base and edges around the patch shall be tack coated using approved material.
d) Patch material, Bituminous Asphaltic Concrete, shall be compacted using approved equipment. Prior to starting any work, the City shall approve the job mix design.
e) The existing pavement surface shall be cleaned to remove all loose patching related materials, upon completion of the day�s work, using suitable equipment.
5. The above patching operations shall be paid for as follows:
a) Bituminous Asphaltic C o n c r e t e o r C o n c r e t e d r i v e s : Will be paid at the
Unit price bid for Asphalt Concrete Patching, 19mm Superpave, and shall cover all
CPL R.23.00937.02 PROJECT DESCRIPTION SECTION 00 200-4
work required; including milling, removal and disposal of all existing material disturbed during the patching operation and any new loose material not incorporated into the patching on the same day; applying tack coat; placing and compacting new material and all required traffic control.
b) The placing and leveling of Graded Aggregate Base, where necessary, will be paid for at the bid unit price per ton of "Graded Aggregate Base".
c) The required excavation, saw cut and preparation to be paid as unclassified excavation.
C. ASPHALTIC CONCRETE PAVEMENT EDGE FILLET
� This work shall consist of constructing a 45-degree asphaltic concrete fillet along the pavement edge
(see diagram below), on each road being resurfaced, where curb and gutter is not present or residential road posted
25 mph. This fillet wedge shall be mechanically constructed at the time each pavement course is placed, by an attachment to the spreader or other method approved by the Engineer. The wedge should extend at a 45- degree (or flatter) angle from the top edge of each paving course to the existing earth shoulder grade.
� Any additional labor or equipment necessary to place this asphalt fillet shall be considered incidental to the resurfacing operation, and no additional compensation will be made with the exception of the extra asphalt material being paid for at the bid unit price for the particular material being used.
ASPHALTIC CONCRETE PAVEMENT FILLET WEDGE
TAKEN FROM: The Elimination or Mitigation of Hazards Associated with Pavement Edge Drop Off's
During Roadway Resurfacing.
BY: Jack B. Humphreys
CPL R.23.00937.02 PROJECT DESCRIPTION SECTION 00 200-5
D. ASPHALT-RUBBER CRACK FILL (Not Required in the Contract)
1 This work shall consist of cleaning and filling cracks in existing asphaltic concrete pavement with rubber asphalt after milling and in advance of resurfacing, at locations designated by the Engineer.
2 All work shall be performed in accordance with the Georgia Department of Transportation
Standard Specifications-Section 407 for type M crack filling.
3 The contractor will give the City a minimum of 24 hours� notice before proceeding on crack filling a particular road.
4 This process is intended for use on roadways in advance of overlay, on cracks at least 1/4" in width. It is estimated that there is approximately 15000 linear feet of cracking to be filled per mile of roadway (1500 lin. ft. per 0.1 mile).
5 Payment will be per mile for all two-lane roads regardless of their width. Any multi-lane road will be paid per lane mile multiplied by the numbers of every two lanes.
Payment shall include cleaning and filling of the cracks, as well as required traffic control and other items incidental to the crack-filling operation. Example � A two lane road one mile long would be paid at ONE MILE.
6 If necessary to prevent the Asphalt-Rubber Fill from being picked up; clean, dry sand shall be spread by hand or mechanically over the filled areas. Sand shall only be applied to those areas that are tacky, and the amount shall be the least needed to prevent picking up. No extra payment for this work or material will be made.
E. HOT MIX RECYCLED ASPHALTIC CONCRETE
1. All work shall be performed in accordance with the Georgia Department of Transportation
Standard Specifications-Section 402 except where otherwise noted herein:
2. References to "The Department" shall be taken to mean City of Stone Mountain or its representative.
3. References to "The Laboratory" shall be taken to mean either the Georgia Department of
Transportation's Materials Lab, or a private testing consultant firm approved by City of
Stone Mountain.
4. It shall be the responsibility of the Contractor to determine the actual composition of the RAP material and to fabricate from that the final asphaltic concrete design(s) and grade of asphalt cement necessary to meet the performance requirements of these
Specifications. The contractor shall be responsible for performing daily testing on plant produced asphalt mixes as described in the 2013
Edition of the Georgia Department of Transportation Standard Specifications section
400.3.06. The contractor shall provide these results to inspecting contractor designated by City of Stone Mountain by noon of the day following production. Any deficiencies in the material characteristics or performance will be corrected by the Contractor, as provided for in the Specifications, at no additional cost to the City.
5. References to "The Plans" shall be taken to mean the contents of the contract and bid documents, or written supplements to these documents.
CPL R.23.00937.02 PROJECT DESCRIPTION SECTION 00 200-6
6. The City will not provide a stockpile of RAP material for the contractor to draw. If
RAP material removed from City roads is insufficient or out of tolerance, the contractor shall provide materials. (NOTE: See paragraph in the General Construction Guidelines
Section of the Special Provisions, regarding the City's right to reclaim material).
7. The work performed and materials furnished, as prescribed by these specifications, will be paid for at Contract Unit Price per ton for the type of mix being placed. This payment shall be full compensation for providing all materials, hauling and necessary crushing, processing, placing, rolling, and finishing of the recycled mixture, and labor, tools, equipment, and incidentals necessary to complete the work, including hauling and stockpiling of any surplus RAP material. Any milling of existing asphaltic concrete pavements required by the City, prior to placement of the RAP material, will be performed as per the Specifications for Mill Asphaltic Concrete Pavement, and paid for at the unit price for that item.
F. . PAVEMENT MARKING
1. The contractor will match all pavement marking as exists on the parking areas each side of Leon Street.
CPL R.23.00937.02 PROJECT DESCRIPTION SECTION 00 200-7
K. LOCATION MAP AND PROJECT DESCRIPTION DETAILS
Zachary Court
CPL R.23.00937.02 PROJECT DESCRIPTION SECTION 00 200-8
VFW Drive
CPL R.23.00937.02 PROJECT DESCRIPTION SECTION 00 200-9
San Pablo Drive
North Rockbridge Ct, Wesr Rockbridge Ct, East Rockbridge Ct.
CPL R.23.00937.02 PROJECT DESCRIPTION SECTION 00 200-10
Ridgemere Ct.
CPL R.23.00937.02 PROJECT DESCRIPTION SECTION 00 200-11
Leon Street
CPL R.23.00937.02 PROJECT DESCRIPTION SECTION 00 200-12
Cemetery Circle
CPL R.23.00937.02 PROJECT DESCRIPTION SECTION 00 200-13
Veal Street
CPL R.23.00937.02 PROJECT DESCRIPTION SECTION 00 200-14
Redwood Ct. and Rosewood Drive
CPL R.23.00937.02 PROJECT DESCRIPTION SECTION 00 200-15
I.
1. Zachary Court
a. 6� x 5� repair at turn in from Zachary Drive
b. 2050 sf of repairs in the Cul-de-Sac
2. VFW Drive
a. As shown on the plan, three (3) each pavement repair areas: 9� x 13�, 8� x
38�, 8�x 20�
3. San Pablo Drive
a. As shown on the plan, four (4) each pavement repair areas: 20�x96�, 20� x
46�, 10�x 69�, 20�x30�.
4. West Rockborough Court
a. No Pavement Repairs
5. North Rockborough Court
a. No Pavement Repairs
6. East Rockborough Court
a. As shown on the plan one (1) each pavement
7. Ridgemere Court
a. As shown on the plan six (6) each pavement. Repair areas: 10� x 23�, 3�x2�, 8�x25�, 35�x4�, 13�x6�, 6�x5�.
8. Leon Street
a. No pavement repairs
9. Cemetery Circle
a. As shown on the plan seven (7) each pavement repair areas: 10.5� x 63�, 10.5�x145�, 2�x25�, 10.5� x 68�, 11�x54�, 17�x 147�, 27x38�.
10. Veal Street
a. No pavement repairs
11. Redwood Court
a. No pavement repairs
12. Rosewood Drive
a. Replacement in full the existing 24 inch cross culvert near the intersection of
Lucille Street
J. Street Video
a. Prior to the start of any work, the contractor shall video each street to be reconstructed. The videos shall show pavement conditions the full length of the work area including a minimum of 10 feet back of curb and gutter each side of the street to show the existing conditions of adjacent private properties. The city to review the video prior to start of work to insure satisfactory area coverage.
K. United Consulting Report
END OF SECTION 00 200
CPL R.23.00937.02 BID FORM SECTION 00 300-1
BID FORM
CITY OF STONE MOUNTAIN � FY 2024 SPLOST RESURFACING PROJECT
BID NUMBER: CIP 2025-001 BID DATE: ___April 24, 2025
SUBMITTAL DATE:_________________________
BY: _______________________________________________________________
(Bidder)
PROJECT DESCRIPTION: The project consists of road milling, patching, placement of graded aggregate base, concrete infill, asphalt paving, manhole adjustment and parking lot striping.
THIS BID IS SUBMITTED TO: City of Stone Mountain, Georgia (hereinafter called Owner) acting through its City Council.
A. Undersigned Bidder offers and agrees to enter into Agreement with Owner, in accordance with the instructions, requirements and forms included in Bid Document Package (including the Invitation to Bid and Instructions to Bidders Package), and to complete all Work for the Bid Price and within required calendar days, all in accordance with the Bid Document Package.
Bidder accepts terms and conditions contained in Bid Document Package including without limitation those dealing with Owner�s time for accepting Bid and disposition of Bid Security.
In submitting this Bid, Bidder makes representations required by Instructions to Bidders and further warrants and represents:
Bidder has examined Bid Document Package, including Invitation for Bids and Instructions to Bidders, and following addenda:
No. Dated __ No. ________ Dated ________ No. ___ Dated __ No. ________ Dated ________ No. ________ Dated _______ No. ________ Dated ________ No. ________ Dated _______ No. ________ Dated ________
Bidder has examined site and locality where the Work is to be performed and legal requirements (federal, state, and local laws, ordinances, rules, and regulations) and conditions affecting Work cost, difficulty, progress, or performance and has made independent investigations as Bidder deems necessary.
B. Bidder has carefully studied reports and drawings indicating subsurface conditions and drawing depicting physical conditions as identified in General Conditions and accepts determination concerning technical data contained in reports and drawings on which Bidder is entitled to rely.
C. Bidder has obtained and carefully studied (or assumes responsibility for obtaining and carefully studying) examinations, investigations, explorations, tests, and studies (in addition to or to supplement those referred to in �B� above) pertaining to subsurface or physical conditions at site or otherwise affecting cost, progress, performance, or furnishing Work as Bidder considers necessary for performing or furnishing Work at Contract Price, within Contract Time, and in accordance with terms
CPL R.23.00937.02 BID FORM SECTION 00 300-2
and conditions contained in Bid Document Package, including specifically provisions stated in General Conditions and no additional examinations, investigations, explorations, tests, reports, or similar information or data are or will be required by Bidder.
D. Bidder has reviewed and checked Plans and data shown or indicated on Bid Document Package with respect to existing underground facilities at or contiguous to site and assumes responsibility for accurately locating underground facilities.
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .