This Invitation for Bid document is issued by the City of Alton, Illinois for the complete demolition and removal of the building located at 1606 Greenwood Street. The project scope includes demolition of all existing buildings, fences, and appurtenances on the premises; complete removal of foundations, footings, and basement floors; removal of any cisterns or similar reservoirs; and proper disposal of all materials at approved disposal sites. Asbestos removal by AC Environmental has already been completed. Sealed bids must be received by the Deputy Comptroller at 101 East Third Street, Alton, Illinois 62002 by 10:00 a.m. on Thursday, September 10, 2026, with public opening and reading immediately following. The project must be commenced as soon as possible after the Notice to Proceed and completed within thirty (30) calendar days, with late fees of $100 per day assessed thereafter up to forty (40) days. A three-hundred-dollar ($300.00) bond per address is required prior to project commencement, and all demolition permits will be waived by the City.
Award will be made on an "all or nothing" basis considering quality versus price and contractor responsibility as determined by City Council. Bidders must submit lists of previous demolition work and equipment/machinery to be used. This is a prevailing wage project subject to Illinois Prevailing Wage Act requirements, with contractors obligated to pay laborers and mechanics the current prevailing wage rates as published by the Illinois Department of Labor and submit certified monthly payroll records. Contractors must comply with multiple federal and state requirements including Davis-Bacon Act provisions, Section 3 of the Housing and Urban Development Act of 1968, Executive Order 11246 affirmative action obligations with minimum 10% minority business participation and 7% female utilization goals, and must provide a Certificate of Insurance naming the City of Alton as additional insured with minimum coverage limits including $1,000,000 Commercial General Liability per occurrence, $1,000,000 Automobile Liability, and Worker's Compensation per Illinois Statute. The successful contractor must submit all required paperwork within one week of award and will be paid within thirty (30) days after acceptance of project completion and submission of all required documentation, including lien waivers.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Department: Owner: City of Alton
101 East Third Street
Alton, IL 62002
Vendor Name and Address: Bid Number: 2026 - 18
Date: 8/28/2026
Bids will be received until:
at 10:00 am
Demolition per the Attached Specifications for the Following:
1606 Greenwood Street $
Asbestos removed by AC Environmental
THIS IS A PREVAILING WAGE PROJECT
Please Note: Our bid documents may have changed, please review carefully.
Quotation Submitted By:
(Print Name on this Line)
(Signature in this Box) (Print Title on this Line)
FEMALE AND MINORITY OWNED BUSINESS FIRMS ARE ENCOURAGED TO SUBMIT PROPOSALS AND THE SUCCESSFUL VENDOR IS ENCOURAGED
TO UTILIZE FEMALE AND MINORITY OWNED BUSINESSES AS SUBCONTRACTORS FOR SUPPLIES, EQUIPMENT, SERVICES AND CONSTRUCTION.
For further information, contact the Comptroller’s Office at 618.463.3545 or lbockholdt@cityofaltonil.gov.
Compliance with the Illinois Fair Employment Practice Commission Regulations required.
Building & Zoning
CITY OF ALTON, ILLINOIS
INVITATION FOR BID
September 10, 2026
Please sign your bid form and return, in a sealed envelope, to: Lori Bockholdt, 101 East Third Street, Alton, IL 62002. Bid number must be placed on the face of the envelope. All quotations must be FOB destination and include cost of packing and cartage. Do not include taxes in your prices. The City of Alton is exempt from Federal Excise Tax, State Sales Tax and Transportation Taxes.
BID PACKET SHOULD BE RETURNED IN ITS ENTIRETY
Return Page Bid # 2026 – 18 Demolition Bid Document Page 1 of 10
INVITATION FOR BIDS
CITY OF ALTON - DEMOLITION
The City of Alton, Illinois invites sealed bids for the demolition of buildings in accordance with the provisions, specifications, and bidding instructions set forth in this Invitation for Bid. Bids will be received by the Deputy Comptroller, Room 104, 101 East Third Street, Alton, IL 62002, until 10:00 a.m., Thursday, September 10, 2026; they will be publicly opened and read immediately following. Late bids will not be considered.
Responses must be submitted in a sealed envelope containing the original copy of the response, addressed to:
Lori Bockholdt Comptroller’s Office 101 East Third Street Alton, IL 62002
Each sealed envelope containing a response must be plainly marked on the outside of the envelope with the respondent’s name, proper address, and BID #2026 – 18 DEMOLITION.
All responses must be made on the forms provided. All blank spaces must be filled in, in ink or typewritten, and the bid forms must be fully completed and executed and signed by an authorized individual.
Any questions regarding this bid should be directed to Lori Bockholdt, Comptroller’s Office, City of Alton
(618) 463-3545. The City cannot accept your bid response via fax.
A copy of the bid tabulation will be available upon written request to the Comptroller’s Office or by email to lbockholdt@cityofaltonil.gov. Telephone requests will not be accepted. Each written request must contain a self-addressed, stamped envelope and must reference the bid title and number.
Contractor shall guarantee, in writing, that all work conforms to the requirements of the specifications.
Award of contract will be made on the most advantageous bid, on a quality versus price basis, taking into consideration the responsibility of the Contractor, as interpreted by the City Council. Award of contract will be made on an “all or nothing” basis. Proper consideration will be given to modern accepted practice, efficiency and workmanship. No award will be made for any service which does not adequately fulfill the requirements of the project.
If services offered differ from the provisions contained in the specifications, such differences must be explained in detail (see Exception Certificate).
The City of Alton reserves the right to reject any or all of the bids, or any part thereof, on any basis and without disclosure of a reason. The failure to make such a disclosure shall not result in accrual of any right, claim or cause of action by any unsuccessful bidder against the City of Alton, Illinois. The City further reserves the right to accept any bid or any part thereof, or to waive any informalities and to make an award in its best interest.
All paperwork (i.e., certificate of insurance and signed contract, etc.) must be received and in order before work may begin on project. Failure to do so could result in disqualification of the bidder.
Return Page Bid # 2026 – 18 Demolition Bid Document Page 2 of 10
CONTRACTOR/SUBCONTRACTOR CLAUSE
The contractor/subcontractor agrees, in performance of this contract, to observe and comply with all applicable federal, state and local safety rules and regulations including, but not limited to, the Occupational Safety and Health Act of 1970.
The contractor/subcontractor agrees to indemnify and hold the City of Alton, Illinois harmless for, or and from, any loss, including but not limited to any fines, penalties and corrective measures the City of Alton, Illinois may sustain by reason of contractor/subcontractor’s failure to comply with said laws, rules and regulations in connection with the performance of said contract.
All work that is unsatisfactory, in the judgment of the City, shall be redone properly at no additional expense to the City. Should the Respondent fail to do this within a reasonable time, the City may deny payment and perform the work itself in any manner it sees fit. At no time, shall the Respondent or any of the Respondent’s personnel, be considered an agent or employee of the City of Alton.
Where not more specifically described in any of the sections of these specifications, workmanship shall conform to all the methods and operations of the best standards and accepted practices of the trade or trades involved. All work shall be executed by personnel skilled in their respective lines of work. No portion of this project may be subcontracted unless authorized by the City prior to the award of the contract. The Contractor shall not assign his contract to any other party or parties without the official approval of the corporate authorities of the City.
Section 1
1.1 Contractor’s Performance
It is the intent of these specifications to provide for the City of Alton the materials, equipment, labor, transportation, supervision and insurance necessary to demolish the building(s) per the following specifications. Contractor shall guarantee, in writing, that all work conforms to the specifications. Copies of the Asbestos Abatement report(s) are available.
1.2 Requirements
a) Project Description The project consists of the complete demolition and removal and disposal of any existing buildings, fences and similar appurtenances located on the premises. The foundation, footing and basement floors shall be completely removed from the demolition site and disposed of at an approved disposal site. Any cisterns or similar reservoirs found on the premise are to be removed.
b) Deposits The Contractor who is the successful bidder shall post a three hundred-dollar bond ($300.00 per address) prior to commencement of project.
c) Permits – Per Each Address The Contractor shall obtain the necessary demolition permits from the City of Alton prior to beginning the project and shall perform all work in strict conformity therewith. As this project is contracted through the City, the fee for demolition permit will be waived.
Return Page Bid # 2026 – 18 Demolition Bid Document Page 3 of 10
d) Utilities The contractor shall be responsible for notifying all utility companies of the demolition prior to beginning the project. All rules and regulations of the utility companies and City Codes must be complied with before, during and after the demolition project. The Contractor shall seal all existing drains and open lines connected to a public sewer system. The Contractor shall either completely remove all septic tanks, cisterns and sewage disposal systems of any kind from the property or fill the systems with sand, at the option of the Contractor subject to approval by Alton. Prior to fill being placed, the Department of Public Works shall be notified (618- 463-3530), as well as Illinois-American Water Company to arrange inspection of the sewer for proper capping (required by ILAW to be at the property line). Contact information for ILAW will be provided at the meeting after the awarding of work. Contractor shall not fill any sewer excavation until approved by the sewer service provider, currently Illinois-American Water Co. or its designee. A Sewer Inspection Fee for each address may be charged as established from time to time.
e) Fill The Contractor shall fill only with clean dirt up to twelve (12”) inches below the level of grade of the existing surrounding area. The top layer of fill shall be a minimum of twelve (12”) inches of soil capable of encouraging vegetation. Prior to fill being placed, Contractor shall notify the Department of Building & Zoning to schedule an inspection for the approval of the fill material to be used. The Contractor shall rake smooth and apply grass seed and straw to the entire soil surface. Care shall be taken to prevent the occurrence of voids in the fill or undue settlement after the fill has been placed. Lumber, lath, siding, shingling, guttering and other building materials will not be permitted in the fill. All material which is not suitable for fill materials shall not be used and shall be removed from the site and disposed of at the Contractor’s expense.
f) Disposal Any and all materials to be disposed of shall be disposed of at a legally approved disposal area. Receipt of the disposal transaction with the approval of the disposal site (photocopies are not acceptable) shall be retained and presented to the City of Alton before final payment will be made. The burning of any materials will not be authorized or permitted. Any unauthorized materials remaining on the premises at the completion of the project will delay final acceptance until such time as said materials have been removed. The premises shall be left orderly and clean, free of debris and/or building materials.
g) Salvageable Materials There is no guarantee of salvable materials in any building involved in this project. No responsibility shall be assumed by any party for loss of salvable materials.
h) Complete Demolition All ancillary buildings on the lot with the principal structure shall likewise be demolished and removed unless specified otherwise in the bid specifications. Any trees not scheduled to be removed shall not be damaged, and if damaged, shall be removed at the Contractor’s expense. Dead trees located on the subject premises are to be removed by Contractor as a part of the bid project. The contractor shall inquire of the city as to whether any fencing or walls on the subject lot are to be removed as part of the demolition proceeding, if such issue is not addressed in the bid specifications. As a final step of the bid project, the Contractor shall clean the subject property by removal of all garbage, debris, scrub trees, and cutting of weeds and grass, including but not limited to the area between the subject property and the adjoining streets.
i) Time of Completion The Contractor shall commence the work required by the project as soon as possible after the date of the “Notice to Proceed” and shall complete the work within thirty (30) calendar days of said notice unless the period for completion is extended otherwise by the contract. Should Contractor fail to complete all aspects of
Return Page Bid # 2026 – 18 Demolition Bid Document Page 4 of 10 the bid project within forty (40) days after the date of the “Notice to Proceed”, the Contractor shall owe a late fee in the sum of One-Hundred Dollars ($100.00) for each day thereafter until the bid project is deemed complete by the City. Said sum may be withheld by City from the contract price otherwise payable to Contractor to cover the total late fee.
1.3 Additional Requirements
Respondents must familiarize themselves with any conditions which may affect performance and prices. It is the intent of these specifications to provide for the City the materials, equipment, labor, transportation and supervision necessary for the completion of the project, per the following specifications. Respondent shall guarantee, in writing, that all work conforms to the specifications.
The Respondent shall furnish all labor, equipment, materials, tools and all incidentals necessary to perform such services as are requested by this Invitation for Bid. The Respondent shall also remove all litter, rubbish, trash, debris, garbage and other matter generated during the performance of this project. All acts must be performed in accordance with all applicable Regulations, Statutes and Ordinances. All work shall be performed under the direction of the Department of Building & Zoning and shall be completed according to the standards of the industry, and to the complete satisfaction of the City.
Per State of Illinois Statute 625ILCS5/12-712; 713 Contractor shall be required to use trucks and equipment with their company name prominently and legibly displayed on the sides. Per State of Illinois Statute 720ILCS605 Contractor shall be required to use neon orange “construction” fencing around the perimeter of the demolition area.
Contractor shall, at all times, observe and comply with all Federal and State laws, local ordinances and regulations which affect the conduct of this work. Contractor shall be solely responsible for all claims and liabilities arising from or based upon the violation of any such laws, ordinances or regulations whether by himself or his employees
This contract calls for the construction of a “public work,” within the meaning of the Illinois Prevailing Wage Act, 820 ILCS 130/.01 et seq. (“the Act”). The Act requires contractors and subcontractors to pay laborers, workers and mechanics performing services on public works projects no less than the current “prevailing rate of wages” (hourly cash wages plus amount for fringe benefits) in the county where the work is performed.
The Department publishes the prevailing wage rates on its website at http//labor.illinois.gov/. The Department revises the prevailing wage rates and the contractor/subcontractor has an obligation to check the Department’s web site for revisions to prevailing wage rates. For information regarding current prevailing wage rates, please refer to the Illinois Department of Labor’s website. All contractors and subcontractors rendering services under this contract must comply with all requirements of the Act, including but not limited to, all wage requirements and notice and record keeping duties. Each contractor and subcontractor on public works projects must submit certified payroll records on a monthly basis to the City. The certified payroll records shall include, for every worker, the name, address and telephone number, social security number, job classification, hourly wages paid in each pay period, number of hours worked each day, and starting and ending time of work each day. The Grantee agrees by the acceptance of the funds from the City of Alton that the Grantee shall abide by all requirements of the Prevailing Wage Act of the State of Illinois to the extent required by law.
All work under this contract shall be coordinated with the Department of Code Enforcement, Department of Planning and Development or the Department of Public Works, whichever is found to be appropriate. Any changes to the established schedule must have prior Alton departmental approval.
Return Page Bid # 2026 – 18 Demolition Bid Document Page 5 of 10
1.4 Safety
The Contractor shall keep the premises clean of all rubbish and debris generated by the work involved and shall leave the premises neat and clean. All surplus material, rubbish and debris shall be properly disposed of by the Contractor at the Contractor’s expense. The work area shall be cleaned at the end of each workday. All material, tools, equipment, etc. shall be removed or safely stored. The City is not responsible for theft or damage to the Contractor’s property. All possible safety hazards to workers or the public shall be corrected immediately, and the project area left in a safe condition at the end of each workday. If there is a question in this area, the Department of Code Enforcement will be consulted.
The City does not assume responsibility, at any time, for the protection of or for loss of materials and/or personnel, from the time that the contract operations have commenced through the final acceptance of the work.
The Contractor shall perform all work so that no damage to the surrounding buildings, grounds or personal property results. The Contractor shall be responsible for any damage that does occur, to the satisfaction of Alton at no cost to the City.
Contractor will be responsible for proper set-up, usage and removal of all necessary safety/traffic control equipment required to protect its employees, the public, surrounding areas, equipment and vehicles. The free passage to and from adjacent buildings or the flow of vehicular traffic shall not be impeded at any time during this project. The safety of the Contractor’s employees and the public is of prime concern to the City, and the Contractor must take all necessary steps to assure proper safety during the performance of the contract. Any bidders that have a history of safety problems or a high incidence of accidents will not be considered for award of the contract. The Contractor shall, at all times, observe and comply with all Federal and State laws, local ordinances and regulations which affect the conduct of this work. The Contractor shall be solely responsible for all claims and liabilities arising from or based upon the violation of any such laws, ordinances or regulations whether by the Contractor or its employees.
Successful Contractor must submit a certificate of insurance naming the City of Alton as “additional named insured” per the attached minimum insurance requirements and sign the attached hold harmless agreement.
1.5 Submittals
On a separate sheet of paper, please submit the following with your bid response:
1. List of previous demolition work (include contract amount and location)
2. List of equipment/machinery to be used on the bid project
Section 2
2.1 Payment Terms
Bidder shall be paid within thirty (30) days after Alton’s acceptance of the completion of the bid project, including the submission of all documentation required.
2.2 Award of Contract
Award will be made on an “all or none” basis. In the event only one response is received, the City may require that the bidder submit a cost proposal in sufficient detail for the City to perform a cost/price analysis to determine if the bid price is fair and reasonable.
Return Page Bid # 2026 – 18 Demolition Bid Document Page 6 of 10
2.3a The undersigned Respondent declares Respondent has carefully examined the General Instructions/Conditions, Specifications and Forms for the City’s Invitation for Bid and the figures submitted are the lowest responsible cost for this work. The Respondent further understands that Respondent is responsible for any errors or omissions affecting coverage based on these specifications as submitted on the forms.
2.3b The undersigned Respondent further declares that this quotation is made without any connection with any person making another quotation for the same contract, that the quotation is in all respects fair and without collusion or fraud, that no member of the Alton City Council or City of Alton employee is directly or indirectly interested in this quotation, or in any portion of the profits thereof.
2.3c The undersigned Respondent certifies that it is not barred from being awarded a contract or subcontract under Section 10.1 of the Illinois Purchasing Act.
2.3d The undersigned Respondent certifies that it has not been barred from contracting with a unit of State or local government as a result of a violation of Section 33E-3 or 33E-4 of the Criminal Code of 1961.
Signature
Respondent’s Name
Section 3 Company Information The undersigned does hereby agree and certify that none of the work described above will be subcontracted to any City employee
Bidder certifies it is a: proprietorship ; partnership ; corporation
Length of time company has been in business
Illinois Sales Tax Number
Use Tax Number for Out-of-State Suppliers
Taxpayer’s Federal Identification Number
Federal SAM.gov Identification Number
Bidder certifies that bidder has read, understands and will fully and faithfully comply with this invitation for the bid, its attachments, addenda and any referenced documents. Bidder also certifies that the prices offered were independently developed without consultation with any of the other bidders or potential bidders.
All work items shall be performed in accordance with the City of Alton Demolition Specifications.
Company’s Legal Name
Address
City, State and Zip Code
Telephone Number
Company’s Fax Number
Email Address and Website
Return Page Bid # 2026 – 18 Demolition Bid Document Page 7 of 10
Signature of Authorized Agent
Printed Name and Title
Email Address:
Mailing Addresses:
Purchase Order Name
Address
City, State and Zip Code
Payment Address
Name
City, State and Zip Code
References Please list five (5) references that have contracted with your company for similar work.
Name/Contact Person Company/Entity
Address Telephone Number/Email
1.
2.
3.
4.
5.
Return Page Bid # 2026 – 18 Demolition Bid Document Page 8 of 10
Section 4 Paperwork
All paperwork (i.e., certificate of insurance, signed contract, hold harmless agreement and related documents) must be received and approved by Alton as “in order”, within one week from the date of award. Failure to do so could result in disqualification of the respondent.
Note: Successful respondent shall be responsible for providing lien waivers before final payment is made.
Section 5 Qualifications
5.1 The undersigned Respondent shall ensure that Respondent is appropriately licensed (when applicable) and qualified to perform the described work. Madison County requires the respondent be registered with www.SAM.gov, prior to award of any contract.
5.2 The undersigned Respondent agrees that Respondent is insured and shall provide a “Certificate of Insurance”, listing the City of Alton as additional insured in amounts per the attached minimum requirements shall be provided. Cost of compliance shall be included as an incidental expense in the project and shall not be paid for separately.
5.3 The undersigned Respondent agrees to save and keep the City of Alton, including it Officials, Agents and Employees, free and harmless from all liability including but not limited to, losses, damages, costs, attorney’s fees, expenses, causes of action, claims or judgments resulting from claimed injury, death, damage to property or loss of use of property or any person or legal entity arising out of or in any way connected with the performance of work or work to be performed under this Contract, except in the case of gross negligence of the City of Alton, Illinois or its employees as to which this Hold Harmless and Indemnity Agreement. The Respondent shall indemnify the City of Alton, Illinois, for any costs, expenses, judgments and attorneys’ fees paid or incurred, by or on behalf of the City of Alton, its Officials, Agents or Employees or by insurance purchased or self-insurance provided by the City of Alton, as this Hold Harmless and Indemnity Agreement requires.
5.4 The Respondent shall further hold harmless the City of Alton, its Officials, Agents and Employees from liability or claims for any injuries to or death of the Contractor’s employees or Subcontractor’s employees, arising out of, or in any way connected with, the work or work to be performed under this Contract, including protection against any claim of the Contractor or Subcontractor for any payments under any worker’s compensation law or any expenses of or any payments made by any worker’s compensation insurance carrier on behalf of said Contractor or Subcontractor and the Contractor shall indemnify the City of Alton for any costs, expenses, judgments and attorneys’ fees with respect to any above referenced worker’s compensation claim incurred or paid by the City of Alton or paid on its behalf or behalf of its Officials, Agents or Employees by insurance purchased or self-insurance provided by the City of Alton. Contractor agrees to waive subrogation in favor of the City of Alton, IL.
Section 6
6.1 Authorized Signature
By my signature, I hereby affirm that I have read, understood, and agree to comply with all of the instructions set forth in this invitation for bid. (Must be signed by an authorized agent of the Respondent.)
Signature
Printed Name
Title
Date
Return Page Bid # 2026 – 18 Demolition Bid Document Page 9 of 10
MINIMUM INSURANCE REQUIREMENTS AND INSURANCE CERTIFICATE
UPON AWARD OF CONTRACT
The City of Alton has developed insurance requirements in order to protect the municipality from suffering a financial loss that is not directly under its control.
A municipal contractor must file with the Deputy Comptroller the Certificate of Insurance naming the City of Alton as additional insured as required herein.
Please forward the signed the Certificate of Insurance with the named additional insured immediately upon the award of the bid. The Certificate Holder shall be shown as follows:
City of Alton, IL Attn: Lori Bockholdt 101 East Third Street Alton, IL 62002
Email: lbockholdt@cityofaltonil.gov Phone: 618-463-3545
The certificate must provide insurance coverage that meets the established minimum insurance requirements, as follows:
Coverage Limits
Commercial General Liability $1,000,000 per occurrence $2,000,000 aggregate
Professional Liability $1,000,000 per occurrence (Errors and Omissions) $1,000,000 annual aggregate
Automobile Liability $1,000,000 per occurrence Bodily Injury $1,000,000 per occurrence Property Damage $1,000,000 per occurrence
Employer’s Liability $1,000,000 per occurrence $1,000,000 each accident – policy limit $1,000,000 each disease – policy limit $1,000,000 disease – each employee
Worker’s Compensation Per State of Illinois Statutes, with Waiver of Subrogation in favor of City of Alton, IL
CONTRACT WORK SHALL NOT BEGIN NOR SHALL INVOICES BE PAID WITHOUT A CURRENT CERTIFICATE OF
INSURANCE ON FILE, PER THE ABOVE MINIMUM REQUIREMENTS.
Return Page Bid # 2026 – 18 Demolition Bid Document Page 10 of 10
EXCEPTION CERTIFICATION
INVITATION FOR BID/PROPOSAL
CITY OF ALTON, ILLINOIS
It is hereby certified, by the Respondent or by a legally authorized agent of the Respondent, that any and all exceptions (variations) from the specifications are noted and explained in detail as set forth in the invitation.
Signature
Printed Name and Title
Company
1606 Greenwood Street
Concrete path/sidewalk near house to be removed.
Dead trees to be removed.
All vegetation (shrubs, vines, etc.) within 20’ from house and inside property lines to be removed.
Making The World Beautiful Again
AC Environmental, Inc P.O. Box 27 Wilsonville, IL 62093 618-288-8960
7/31/2026
City of Alton Re: 1606 Greenwood Completion Of Work Certification
Dear Christine, All of the roofing material (388 SF) and glaze (50 LF) included in the Asbestos Building Inspection Report for the above referenced building has been removed according to Federal, State and Local regulations. You may use this letter to secure a renovation/demolition permit for this project.
Please call me if you have any questions and thank you for using AC Environmental, Inc. as your abatement contractor for this project.
Sincerely, Taylor Bailey Office Email: taylor@acenviro.com Direct Contact: 618-225-9091
MADISON COUNTY COMMUNITY DEVELOPMENT
COMPLIANCE PACKAGE
Project Name:
Demolition of 1606 Greenwood Street
Project Number:
2026 – 18
The contents of this package must be incorporated by attachment as a part of the contract between Owner and Contractor.
Updated May 23, 2012
Madison County Compliance Package- updated May 23, 2012 Page 2
NOTICE TO ALL CONTRACTORS
Minority Business Participation at a minimum level of ten percent (10%) is a requirement of this project. It may come from direct construction contracts, services, or goods supplied. Utilization of females in construction is also encouraged. However, the use of
F.B.E.s (female owned businesses) does not count towards your minority business requirement. Prime contractors who are not minority owned businesses themselves should have the name and address of their minority subcontractors proposed for participation on this project at the time of the preconstruction conference.
NOTE: A wage determination is a part of this bidders package. If it is not attached, please call Madison County Community
Development for the latest applicable wage determination. (618) 692-8940.
If you have any questions, please contact Madison County Community Development, 130 Hillsboro Avenue, Edwardsville, Illinois 62025 at (618) 692-8940.
SPECIAL CONDITIONS
SUMMARY EXPLANATION OF SPECIAL CONDITIONS
(1) The Copeland "Anti-Kick Back" Act (18 U.S.C. 874) as supplemented in Department of Labor regulations (29 CFR, Part 3). This
Act provided that each contractor or subcontractor shall be prohibited from inducing, by any means, any person employed in the construction, completion, or repair of public work, to give up any part of the compensation to which he is otherwise entitled.
(2) The Davis-Bacon Act (40 U.S.C. 276a to a-7) as supplemented by Department of Labor regulations (29 CFR, Part 5). Under this
Act, contractors and subcontractors shall be required to pay wages to laborers and mechanics at a rate not less than the minimum wages specified in a wage determination made by the Secretary of Labor. In addition, contractors shall be required to pay wages not less often than once a week.
For prime contracts for trucking services prevailing wages shall be required for al truck drivers operating under such contract.
For all other contracts, the Davis-Bacon Act shall be applied to truck drivers as follows:
Truck drivers are COVERED by the Davis-Bacon labor standards provisions in the following circumstances:
• Drivers of a contractor or subcontractor for the time spend working on the site of the work.
• Drivers of a contractor or subcontractor for the time spent loading and/or unloading materials and supplies on the site of work.
• Truck drivers transporting materials and supplies from a facility that is a part of the site of the work and the actual construction site.
Truck drivers are NOT COVERED in the following instances:
• Drivers of an independent trucking firm, or materialman hauling material to a Davis-Bacon job from a commercial supply facility which was not set up exclusively for the Davis-Bacon job or is not located adjacent or virtually adjacent to the site of work.
• Drivers of a contractor or subcontractor hauling materials to or from a Davis-Bacon job from a commercial facility when they are off the site of work.
In addition, the Department of Labor has an enforcement position with respect to bona fide owner-operators of trucks who are independent contractors (an owner operator is a person who owns and drives a truck). Certified payrolls including the names of such owner-operators do not need to show the hours worked or the rates paid, only the notation “owner-operator”. This position does not apply to owner-operators of other equipment such as bulldozers, backhoes, cranes, etc.
(3) The Contract Work Hours and Safety Standards Act (40 U.S.C. 327-330) as supplemented by Department of Labor regulations
(29 CFR, Part 5). Under Section 103 of the Act, each contractor shall be required to compute the wages of every mechanic and laborer on the basis of a standard work week of forty (40) hours. Work in excess of the standard work week is permissible provided that the worker is compensated at a rate of not less than 1 1/2 times the basic rate of pay for all hours worked in excess of forty (40) hours in the work week. Section 107 of the Act is applicable to construction work and provides that no laborer or mechanic shall be required to work in surroundings or under working conditions which are unsanitary, hazardous, or dangerous to
Madison County Compliance Package- updated May 23, 2012 Page 3 his health and safety as determined under construction, safety, and health standards promulgated by the Secretary of Labor.
These requirements do not apply to the purchases of materials or articles ordinarily available on the open market or contracts for transportation or transmission of intelligence.
(4) The Equal Opportunity Clause of Executive Order 11246. This Clause requires that the contractor will not discriminate against any employee or applicant for employment because of race, color, religion, sex, or national origin. The contractor will take affirmative action to ensure that applicants are employed and that employees are treated during employment without regard to their race, color, religion, sex, or national origin. Such action shall include, but not be limited to, the following: employment, upgrading, demotion or transfer, recruitment or recruitment advertising, layoff or termination, rates of pay or other forms of compensation and selection for training, including apprenticeship. The contractor agrees to post in conspicuous places, available to employees and applicants for employment, notices to be provided setting forth the provisions of this nondiscrimination clause.
(5) Section 3 of the Housing and Urban Development Act of 1968. Section 3 provides that to the greatest extent feasible opportunities for training and employment shall be given to lower income residents of HUD assisted project areas and that contracts for work in connection with such projects shall be awarded to business concerns which are located in or are owned in substantial part by project area residents.
(6) Women in construction. Regulations (41 CFR 60-4) published by the Department of Labor pursuant to Section 201, 202, 205, 211, 301, 302, and 303 of Executive Order 11246 are directed at reducing the exclusion of women from the construction industry.
These regulations have given the Director of the Office of Federal Contract Compliance Program the authority to issue goals and timetables for female utilization on federal or federally assisted construction projects. To meet the overall objectives of this program, a national goal has been established for women in construction trades as follows: seven percent (7%) after 1980. In order for Madison County to be in compliance with federal law, all contractors working on projects funded through the Community
Development Block Grant Program must certify that a full and good faith effort will be made to achieve the national goal for female utilization.
(7) Minority participation, Executive Order 11625. Executive Order 11625 authorizes the Secretary of Commerce to supervise the implementation of the Minority Business Enterprise Program. This program is designed to extend the opportunity for participation in the United States free enterprise system to socially and economically disadvantaged persons. The President has required all departments and agencies receiving federal funds to establish goals for improving minority participation efforts in 1978. In order to meet the interest and substance of Executive Order 11625, a ten percent (10%) level of minority business participation for programs funded with Community Development Block Grant monies has been established. In order for Madison County to be in compliance with Executive Order 11625, all contractors working on projects funded through Community Development must obtain a ten percent (10%) level of minority participation in contracts and subcontracts for goods and services.
(8) All prime contractors shall document and maintain a record of all subcontractors and suppliers. Such record shall be presented to
Madison County Community Development at the preconstruction conference, and no Notice to Proceed shall be provided until such record has been provided.
(9) Rehabilitation Act of 1973, Public Law 93-112 as amended. This act requires that no qualified handicapped person(s) shall on the basis of handicap be excluded from participation in, denied the benefits of, or otherwise be subject to discrimination under any program or activity which receives or benefits from federal financial assistance.
(10) HUD Lead Based Paint Regulations, 24 CFR Part 35. These regulations require that all interior surfaces and those exterior surfaces readily accessible to children be free of lead based paint.
(11) Insurance. Successful bidder, should the job be done, will be required to provide certificates of insurance naming Madison
County Government as additional insured and indicating the following coverage in the amount of one million dollars ($1,000,000) for each category of coverage except as noted herein:
1. Liability Insurance
Commercial General Liability
Products Completed Operations Liability
Contractual Liability
Comprehensive Automobile Liability
Madison County Compliance Package- updated May 23, 2012 Page 4
2. Worker’s Compensation & Employers Liability $500,000. Statutory limits required.
3. Property Damage Insurance - not less than $500,000 for each occurrence and not less than $1,000,000 in aggregate.
If the contractor should use any subcontractor, the contractor shall include all subcontractors as insured under its policies, or shall furnish to Madison County separate certificates and endorsements for each subcontractor. All coverage for subcontractors shall be subject to all of the requirements of the contractor.
Bidder shall submit, along with his proposal, a copy of his current “Certificate of Insurance”.
All prime contractors and subcontractors will be required to meet the insurance criteria.
Certificates evidencing the aforesaid insurance coverage shall be deposited with Madison County Community Development prior to commencement of any work called for under this Contract. Contractor and owner agree to hold Madison County Community
Development harmless and indemnify Madison County Community Development for any cost or loss, including, without limitation, cost of litigation resulting from any claim, demand, suit or loss, including personal injury, death or property damage, arising directly or indirectly from or in connection with the said work to be performed by the contractor, subcontractor, or any other person or firm under the direct or indirect authority of the contractor. Also, contractor shall, at its own expense, defend any and all actions based thereon, any claim with respect to any of the merchandise called for by this order or rising out of the use of such merchandise, or infringement on a patent, copyright, trademark, trade name, brand or slogan, or of unfair competition, or any adverse claim of statutory or non-statutory rights; any litigation based upon any claim referred to above; or, in the event scaffolding or other mechanical contrivance to the so called "Illinois Scaffolding Act" (Illinois Revised Statute, Chapter 48, Section
60-69) applies is furnished by contractor, or any claim or demand made pursuant to said statutes involving, directly or indirectly, said scaffolding and/or mechanical contrivances.
BONDING REQUIREMENTS
The minimum bond requirements shall be as follows:
(1) A bid guarantee from each bidder equivalent to five percent of the bid price. The "bid guarantee" shall consist of a firm commitment such as bid bond, certified check, or other negotiable instrument accompanying a bid as assurance that the bidder will, upon acceptance of his bid, execute such contractual documents as may be required within the time specified.
(2) A performance bond on the part of the contractor for 100 percent of the contract price. A "performance bond" is one executed in connection with a contract to secure fulfillment of all the contractor's obligations under such contract.
(3) A payment bond on the part of the contractor for 100 percent of the contract price. A "payment bond is one executed in connection with a contract to assure payment as required by law of all persons supplying labor and material in the execution of the work provided for in the contract.
CERTIFICATION OF COMPLIANCE WITH AIR AND WATER ACTS
(Applicable to federally assisted construction contracts and related subcontracts exceeding $100,000)
During the performance of this contract, the contractor and all subcontractors shall comply with the requirements of the Clean Air Act, as amended, 42 U.S.C. 1857 et seq., the Federal Water Pollution Control Act, as amended, 33 U.S.C. 1251 et seq., and the regulations of the Environmental Protection Agency with respect thereto, at 40 CFR Part 15, as amended.
In addition to the foregoing requirements, all non-exempt contractors and subcontractors shall furnish to the owner, the following:
(1) A stipulation by the contractor or subcontractor that any facility to be utilized in the performance of any non-exempt contract or subcontract is not listed on the List of Violating Facilities issued by the Environmental Protection Agency (EPA) pursuant to 40
CFR 15.20.
Madison County Compliance Package- updated May 23, 2012 Page 5
(2) Agreement by the contractor to comply with all the requirements of Section 114 of the Clean Air Act, as amended (42 U.S.C.
1857c-8), Section 308 of the Federal Water Pollution Control Act, as amended, information, as well as all other requirements specified in Section 114 and Section 308, and all regulations and guidelines issued thereunder.
(3) A stipulation that, as a condition for the award of the contract, prompt notice will be given of any notification received from the
Director, Office of Federal Activities, EPA, indicating that a facility utilized, or to be utilized, for the contract is under consideration to be listed on the EPA List of Violating Facilities.
(4) Agreement by the contractor that criteria and requirements in Paragraphs (1) through (4) of this section will be included in every nonexempt subcontract. The contractor will take any action needed as required by the U.S. Federal Government to enforce such provisions.
SPECIAL CONDITIONS PERTAINING TO HAZARDS,
SAFETY STANDARDS, AND ACCIDENT PREVENTION
(1) Lead-Based Paint Hazards (applicable to contracts for construction or rehabilitation of residential structures). The construction or rehabilitation of residential structures is subject to the HUD Lead-Based Paint Regulations, 24 CFR Part 35. The contractor and subcontractors shall comply with the provisions for the elimination of lead-based paint hazards under Sub-Part B of said regulations. The owner will be responsible for the inspections and certifications required under Section 35.14(f) thereof.
(2) Use of Explosives. When the use of explosives is necessary for the prosecution of the work, the contractor shall observe all local, state and federal laws in purchasing and handling explosives. The contractor shall take all necessary precaution to protect completed work, neighboring property, water lines, or other underground structures. Where there is danger to structures or property from blasting, the charges shall be reduced and the material shall be covered with suitable timber, steel or rope mats.
The contractor shall notify all owners of public utility property of intention to use explosives at least eight (8) hours before blasting is done close to such property. Any supervision or direction of use of explosives by the engineer does not in any way reduce the responsibility of the contractor or his or her surety for damages that may be caused by such use.
(3) Danger Signals and Safety Devices. The contractor shall make all necessary precautions to guard against damages to property and injury to persons. The contractor shall put up and maintain in good condition, sufficient red or warning lights at night, suitable barricades, and other devices necessary to protect the public. In case the contractor fails or neglects to take such precautions, the owner may have such lights and barricades installed and charge the cost of this work to the contractor. Such action by the owner does not relieve the contractor of any liability incurred under these specifications or contract.
EEO, SECTION 3, AFFIRMATIVE
ACTION PLAN, AND CERTIFICATION
Notice of Requirement for Affirmative Action to Ensure Equal Employment Opportunity (Executive Order 11246) (Applicable to contracts/subcontracts exceeding $10,000).
1. The contractor's attention is called to the "Equal Opportunity Clause" and the "Standard Federal Equal Employment Opportunity
Construction Contract Specifications" set forth herein.
2. The requirements and timetables for minority and female participation expressed in percentage terms for the contractor's aggregate work force in each trade on all construction work in the covered area are as follows:
Requirement for Minority Goals for Female
Timetables Participation For Each Trade Participation In Each Trade
10% 7%
These are applicable to all the contractor's construction work (whether or not it is federally assisted) performed in the covered
Madison County Compliance Package- updated May 23, 2012 Page 6 area.
The contractor's compliance with the Executive Order and the regulations in 41 CFR Part 60-4 shall be based on its implementation of the Equal Opportunity Clause, specific affirmative action obligations required by the specifications set forth in
41 CFR 60-4.3(a), and its efforts to meet the goals established for the geographical area where the contract resulting from this solicitation is to be performed. The hours of minority and female employment and training must be substantially uniform throughout the length of the contract, and in each trade, and the contractor shall make a good faith effort to employ minorities and women evenly on each of its projects. The transfer of minority or female employees or trainees from contractor to contractor or from project to project for the sole purpose of meeting the contractor's goals shall be a violation of the contract, the executive
Order and the regulations in 41 CFR Part 60-4. Compliance with the goals will be measured against the total work hours performed.
3. The contractor shall provide written notification to the Director of the Office of Federal Contract Compliance Programs within ten
(10) working days of award of any construction subcontract in excess of $10,000 at any tier for construction work under the contract resulting from this solicitation. The notification shall list the name, address, and telephone number of the subcontractor;
employer identification number; estimated dollar amount of the subcontract; and the geographical area in which the contract is to be performed.
4. As used in this notice and in the contract resulting from this solicitation, the "covered area" is the St. Louis Metropolitan area with a special emphasis on Madison County.
Standard Federal Employment Opportunity Construction Contract Specifications (Executive Order 11246)
1. As used in these specifications:
a. "Covered area" means the geographical area described in the solicitation from which this contract resulted;
b. "Director" means Director, Office of Federal Contract Compliance Programs, United States Department of Labor, or any person to whom the Director delegates authority;
c. "Employer identification number" means the Federal Social Security number used on the Employer's Quarterly Federal Tax
Return, U.S. Treasury Department Form 941.
d. "Minority" includes:
i. African American (all persons having origins in any of the Black African racial groups not of Hispanic origin);
ii. Asian and Pacific Islander (all persons having origins in any of the original peoples of the Far East, Southeast Asia, the Indian Subcontinent, or the Pacific Islands); and
iii. American Indian or Alaskan Native (all persons having origins in any of the original peoples of North America and maintaining identifiable tribal affiliations through membership and participation or community identification).
2. Whenever the contractor, or any subcontractor at any tier, subcontracts a portion of the work involving any construction trade, it shall physically include in each subcontract in excess of $10,000 the provisions of these specifications and the notice which contains the applicable goals for minority and female participation and which is set forth in the solicitations from which this contract resulted.
3. If the contractor is participating (pursuant to 41 CFR 60-4.5) in a Hometown Plan approved by the U.S. Department of Labor in the covered area either individually or through an association, its affirmative action obligations on all work in the Plan area
(including goals and timetables) shall be in accordance with that Plan for those trades which have unions participating in the Plan.
Contractors must be able to demonstrate their participation in and compliance with the provisions of any such Hometown Plan.
Each contractor or subcontractor participating in an approved Plan is individually required to comply with its obligations under the
EEO clause and to make a good faith effort to achieve each goal under the Plan in each trade in which it has employees. The
Madison County Compliance Package- updated May 23, 2012 Page 7 overall good faith performance by other contractors or subcontractors toward a goal in an approved Hometown Plan does not excuse any covered contractor's or subcontractor's failure to make good faith efforts to achieve the Hometown Plan goals and timetables.
4. The contractor shall implement the specific affirmative action standards provided in Paragraphs 7.a. through 7.p. of these specifications. The goals set forth in the solicitation from which this contract resulted are expressed as percentages of the total hours of employment and training of minority and female utilization the contractor should reasonably be able to achieve in each construction trade in which it has employees in the covered area. The contractor is expected to make substantially uniform progress toward its goals in each craft during the period specified.
5. Neither the…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .