About this file

This document is a Construction Cost Estimate Summary for the City of Meriden, Connecticut, specifically for emergency repairs to Bridge No. 04184 located on Oregon Road over the Quinnipiac River, scheduled for July 2025. The project involves several key construction items including construction access, disposal of lead debris, localized paint removal and field painting of existing steel, structural steel work, and traffic management using municipal police officers and uniformed flaggers. The total estimated project scope includes specific quantities for each item, such as 2 barrels of lead debris disposal, 20 square feet of paint removal, and 40 hours of uniformed flagger services.

The total project cost is estimated at $150,000, broken down into a base construction estimate of $104,000 for structural contract items, with additional costs for maintenance and protection of traffic (6.0% or $7,000), mobilization and project closeout (7.0% or $8,000), incidentals (15.0% or $18,000), and contingencies (10.0% or $12,000). The cost estimate includes provisions for potential additional items and reflects a comprehensive approach to bridge repair that accounts for potential complexities such as lead paint removal, structural steel work, and traffic management during the construction period.

View the file

Other files

File Type Posted
Prevailing_Wages_Ordered.pdf PDF
Oregon_Bridge_Project_Info.pdf PDF
Oregon_Rd_Specs.pdf PDF
Oregon_Rd_Plans.pdf PDF
B026-05_Oregon_Rd_Bridge_Repairs.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ITEM No. ITEM DESCRIPTION UNITS TOTAL QTY. UNIT PRICE COST

0100600A CONSTRUCTION ACCESS L.S. 1 75,000$ 75,000$

0603253A DISPOSAL OF LEAD DEBRIS BBL 2 500$ 1,000$

0603729A LOCALIZED PAINT REMOVAL AND FIELD PAINTING OF EXISTING STEEL S.F. 20 200$ 4,000$

0603801 STRUCTURAL STEEL CWT 5 2,000$ 10,000$

0970006 TRAFFICPERSON (MUNICIPAL POLICE OFFICER) EST. 1 10,000$ 10,000$

0970007 TRAFFICPERSON (UNIFORMED FLAGGER) HR. 40 100$ 4,000$

BASE ESTIMATE - STRUCTURAL CONTRACT ITEMS: SUBTOTAL (A) 104,000$

0971001 MAINTENANCE AND PROTECTION OF TRAFFIC L.S. 6.0% $7,000

0975004 MOBILIZATION AND PROJECT CLOSEOUT L.S. 7.0% $8,000

LUMP SUM ITEMS $15,000

CONSTRUCTION COST (Base Estimate with Additive Costs) $120,000

INCIDENTALS 15.0% $18,000

CONTINGENCIES 10.0% $12,000

ADDITIONAL ITEMS $30,000

TOTAL PROJECT COST $150,000

SAY* $150,000

JULY 2025

CONSTRUCTION COST ESTIMATE SUMMARY

MERIDEN, CT

EMERGENCY REPAIRS OF BRIDGE NO. 04184 - OREGON ROAD OVER QUINNIPIAC RIVER