This document is the EA Deliverables Table that is an attachment to a Statement of Work (SOW) for a federal contract opportunity. The table outlines the various deliverables the contractor is required to provide, including project management plans, meeting materials, DOPAA development, draft and final EA/FONSI documents, mitigation and monitoring plans, administrative records, noise analyses, airspace support, cultural resource surveys, biological assessments, natural resource surveys, coastal zone management determinations, and wetland delineations. The deliverables have specified frequencies, formats, and distribution to various government points of contact. This attachment provides a comprehensive overview of the contractor's responsibilities and expected deliverables for this environmental assessment project.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Attachment C_Deliverables Table_LMTF.docx | DOCX document | |
| LMTF SOW.pdf | ||
| Combo_LMTF.pdf | ||
| Attach B DAF EIAP Format Guide_08162024_CIE FINAL.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Tasks in this table should align with the tasks outlined in the SOW - ensure task and deliverables numbers are edited for consistency with SOW text. Tasks included fully in red text can be removed if they are not applicable; red text within a task should be revised/updated, or removed as appropriate.
Ensure any applicable POCs (including JAOE, Cooperating Agencies, etc.) are included/added to the “Submit To” column of table, as necessary. Ensure all
POCs listed here are identified in the SOW. It is also acceptable to include a single DAF POC who would then distribute deliverables for review/staffing as necessary.
SOW Attachment C – EA Deliverables Table
Task Deliverable
Deliverable Description Frequency
# of Copies
Format
Submit To
Task 1: Project Management
Task 1.1 - Contractor’s
Progress, Status, and
Management Report
Deliverable
1.1
Project Management Plan (20 pages maximum)
Monthly Contractor’s Progress, Status, and Management Report
• Project Management Plan due 3 weeks after Kick-off.
• First submittal due no later than 30 calendar days after award.
• Subsequent submittals shall be monthly and are due no later than 20 calendar days after the end of the
Contractor's cost accounting period
Electronic
• Contracting Officer’s
Representative (COR)
Task 1.2 –– Project
Schedule
Deliverable
1.2
Initial project schedules and updates that include identification of planned and actual dates.
• Initial project schedules will be presented during the post award/kickoff meeting.
• Updated as needed
Electronic as needed
• COR
• Proponent POC
• Installation POC
• AFCEC/CIE POC
Task 2: Meetings
Task 2.1 - Post-Award
Kickoff / Planning
Meeting
Deliverable
2.1
Virtual kickoff meeting to initiate the contract and obtain project
POCs, and plan for data gap identification/data collection, project coordination meetings, and in-person DOPAA Development
Workshop/data collection visit
• Once
• Agenda items and presentation materials will be provided at least three (3) days prior to kick-off meeting.
1 Virtual
Meeting
Electronic as needed
• COR
• Proponent POC
• Installation POC
• AFCEC/CIE POC
Deliverable
Deliverable Description Frequency
# of Copies
Format
Submit To
Task 2.2 - Data Gap
Identification / Data
Collection
Deliverable
2.2
Identify and collect all relevant data. Upon conclusion of the project site review and data collection effort and if necessary, the Contractor shall submit a list of data gaps needing to be supplied by DAF personnel.
• Once following Post-Award Kickoff /
Planning Meeting
Electronic as needed
• COR
• Proponent POC
• Installation POC
• AFCEC/CIE POC
Task 2.3 - Coordination
Meetings /
Teleconferences
Deliverable
2.3
The Contractor shall prepare the agenda, minutes, and presentation materials for project coordination review meetings / teleconferences twice (2) per month.
• Bi-weekly
• Agenda items and presentation materials will be provided at least two
(2) days prior to meeting
Electronic as needed
• COR
• Proponent POC
• Installation POC
• AFCEC/CIE POC
Task 2.4 – DOPAA
Development Workshop /
On-Site Data Collection
Deliverable
2.4
Up to ## (##) Contractors shall travel to [location] for a three (3) day DOPAA Development
Workshop.
• Once, as scheduled
Site Visit
• COR
• Proponent POC
• Installation POC
• AFCEC/CIE POC
Task 2.5- On-Board
Reviews (OBRs)
Deliverable
2.5
The Contractor shall support
OBRs as Described in Task 2.5
• Once, as required by project schedule
• Proponent POC
• Installation POC
• AFCEC/CIE POC
Task 2.6 – Cooperating
Agencies
Deliverable
2.6
The Contractor shall support coordination with Cooperating
Agencies as described in Task 2.4.
• Once, as required by project schedule
Electronic as needed
• COR
• Proponent POC
• Installation POC
• AFCEC/CIE POC
Task 3: Project Coordination and Consultations
Task 3.1 – Regulatory and Professional Interface
Deliverable
3.1
The Contractor shall assist with oral/written interaction with interested parties related to the project.
• As required Electronic as needed
• COR
• Proponent POC
Deliverable
Deliverable Description Frequency
# of Copies
Format
Submit To
Task 3.2 – Coordination and Consultation POC
List
Deliverable
3.2
The Contractor shall identify key stakeholders and create a project
POC list.
• As needed / required by project schedule
Electronic as needed
• COR
• Proponent POC
• Installation POC
• AFCEC/CIE POC
Task 3.3 – Interagency /
Intergovernmental /
Government-to-
Government
Coordination and
Consultation
Deliverable
3.3
The Contractor shall prepare appropriate coordination and consultation letters and mail letters requiring read receipts.
• As required by SOW and project schedule
Hardcopies for mailing
• COR
• Proponent POC
• Installation POC
• AFCEC/CIE POC
Task 4: DOPAA
Task 4.1 – Preliminary
Draft DOPAA
Deliverable
4.1
The Contractor shall provide a
Preliminary Draft DOPAA for review and comment.
• Once, as required by project schedule Electronic
• COR
• Proponent POC
• Installation POC
• AFCEC/CIE POC
Task 4.2 – Check Draft
DOPAA for SME Review
Deliverable
4.2
The Contractor shall provide a
Check Draft DOPAA for review and comment.
• Once, as required by project schedule Electronic
• COR
• Proponent POC
• Installation POC
• AFCEC/CIE POC
Task 4.3 – Interim Draft
DOPAA for HAF Review
Deliverable
4.3
The Contractor shall provide an
Interim Draft DOPAA for review and comment.
• Once, as required by schedule Electronic
• COR
• Proponent POC
• Installation POC
• AFCEC/CIE POC
Task 4.4 – Interim Draft
DOPAA OBR
Deliverable
4.4
The Contractor shall prepare for and conduct an OBR to resolve
Interim Draft DOPAA comments.
• Once, as required by schedule
• COR
• Proponent POC
Deliverable
Deliverable Description Frequency
# of Copies
Format
Submit To
Task 4.5 – Stabilized
DOPAA
Deliverable
4.5
The Contractor shall provide a
Stabilized DOPAA.
• Once, as required by project schedule Electronic
• COR
• Proponent POC
• Installation POC
• AFCEC/CIE POC
Task 4.6 – Coordination
& Consultation Letters
Deliverable
4.6 As described in SOW Task 3.3 • As described in SOW Task 3.3
• COR
• Proponent POC
• Installation POC
• AFCEC/CIE POC
Task 4.7 – Early Public
Notice Newspapers
Deliverable
4.7
The Contractor shall prepare and publish an Early Public Notice for actions in floodplains and/or wetlands.
• Once, as required by SOW and project schedule
Electronic
Newspapers
• COR
• Proponent POC
• Installation POC
• AFCEC/CIE POC
Task 5: Draft EA / FONSI
Task 5.1 – Preliminary
Draft EA / FONSI
Deliverable
5.1
The Contractor shall provide a
Preliminary Draft EA / FONSI for review and comment.
• Once, as required by project schedule Electronic
• COR
• Proponent POC
• Installation POC
• AFCEC/CIE POC
Task 5.2 – Preliminary
Draft EA / FONSI OBR
Deliverable
5.2
The Contractor shall prepare for and conduct an OBR to resolve
Preliminary Draft EA / FONSI comments.
• Once, as required by project schedule
• COR
• Proponent POC
• Installation POC
• AFCEC/CIE POC
Task 5.3 – Check Draft
EA / FONSI for SME
Review
Deliverable
5.3
The Contractor shall provide a
Check Draft EA / FONSI for review and comment.
• Once, as required by project schedule Electronic
• COR
• Proponent POC
• Installation POC
• AFCEC/CIE POC
Task 5.4 – Interim Draft
EA / FONSI for HAF
Review
Deliverable
5.4
The Contractor shall provide a
Interim Draft EA / FONSI for review and comment.
• Once, as required by project schedule Electronic
• COR
• Proponent POC
Deliverable
Deliverable Description Frequency
# of Copies
Format
Submit To
Task 5.5 – Interim Draft
EA / FONSI OBR
Deliverable
5.5
The Contractor shall prepare for and conduct an OBR to resolve
Interim Draft EA / FONSI comments.
• Once, as required by project schedule
• COR
• Proponent POC
• Installation POC
• AFCEC/CIE POC
Task 5.6 – Draft EA /
FONSI for Public
Comment Period
Deliverable
5.6
The Contractor shall provide a
Draft EA / FONSI to be published for public review and comment
• Once, as required by project schedule
Ten (10)
DVD/CDs for libraries
• COR
• Proponent POC
• Installation POC
• AFCEC/CIE POC
Task 5.7 – Draft EA /
FONSI NOA,
Newspapers
Deliverable
5.7
The Contractor shall prepare and publish a Draft EA NOA.
• Once, as required by SOW and project
• COR
• Proponent POC
• Installation POC
• AFCEC/CIE POC
Task 5.8 – Draft EA /
FONSI Coordination &
Consultation Letters
Deliverable
5.8 As described in SOW Task 3.3 • As described in SOW Task 3.3
• Hardcopies
• COR
• Proponent POC
• Installation POC
• AFCEC/CIE POC
Task 6: Final EA / FONSI
Task 6.1 – Preliminary
Final EA / FONSI
Deliverable
6.1
The Contractor shall provide a
Preliminary Final EA / FONSI for review and comment.
• Once, as required by project schedule Electronic
• COR
• Proponent POC
Deliverable
Deliverable Description Frequency
# of Copies
Format
Submit To
Task 6.2 – Preliminary
Final EA / FONSI OBR
Deliverable
6.2
The Contractor shall prepare for and conduct an OBR to resolve
Preliminary Final EA / FONSI comments.
• Once, as required by project schedule
• COR
• Proponent POC
• Installation POC
• AFCEC/CIE POC
Task 6.3 – Check Final
EA / FONSI for SME
Review
Deliverable
6.3
The Contractor shall provide a
Check Final EA / FONSI for review and comment.
• Once, as required by project schedule Electronic
• COR
• Proponent POC
• Installation POC
• AFCEC/CIE POC
Task 6.4 – Interim Final
EA / FONSI for HAF
Review
Deliverable
6.4
The Contractor shall provide a
Interim Final EA / FONSI for review and comment.
• Once, as required by project schedule Electronic
• COR
• Proponent POC
• Installation POC
• AFCEC/CIE POC
Task 6.5 – Interim Final
EA / FONSI OBR
Deliverable
6.5
The Contractor shall prepare for and conduct an OBR to resolve
Interim Final EA / FONSI comments.
• Once, as required by project schedule
• COR
• Proponent POC
• Installation POC
• AFCEC/CIE POC
Task 6.6 – Final EA /
FONSI for Signature
Deliverable
6.6
The Contractor shall provide a
Final EA / FONSI to be staffed for
DAF signature
• Once, as required by project schedule
Ten (10)
DVD/CDs for libraries
• COR
• Proponent POC
• Installation POC
• AFCEC/CIE POC
Task 6.7 – Final EA /
Signed FONSI
Newspapers
Deliverable
6.7
The Contractor shall prepare and publish a Draft EA NOA.
• Once, as required by SOW and project
• COR
• Proponent POC
• Installation POC
Task 7: Mitigation & Monitoring Plan
Deliverable
Deliverable Description Frequency
# of Copies
Format
Submit To
Task 7.1 – Preliminary
Draft MMP
Deliverable
7.1
The Contractor shall provide a
Preliminary Draft MMP for review and comment
• Once, as required by project schedule Electronic
• COR
• Proponent POC
• Installation POC
• AFCEC/CIE POC
Task 7.2 – Check Draft
MMP for SME Review
Deliverable
7.2
The Contractor shall provide a
Check Draft MMP for review and comment
• Once, as required by project schedule Electronic
• COR
• Proponent POC
• Installation POC
• AFCEC/CIE POC
Task 7.3 – Interim Draft
MMP for HAF Review
Deliverable
7.3
The Contractor shall provide a
Interim Draft MMP for review and comment
• Once, as required by project schedule Electronic
• COR
• Proponent POC
• Installation POC
• AFCEC/CIE POC
Task 7.4 – Interim Draft
MMP OBR
Deliverable
7.4
The Contractor shall prepare for and conduct an OBR to resolve
Interim Draft MMP comments.
• Once, as required by project schedule
• COR
• Proponent POC
• Installation POC
• AFCEC/CIE POC
Task 7.5 – Final MMP Deliverable
7.5
The Contractor shall provide a
Final MMP
• Once, as required by project schedule
• Within 90 days of signed FONSI Electronic
• COR
• Proponent POC
• Installation POC
• AFCEC/CIE POC
Task 8: Administrative Record
Task 8.1 – Draft AR
Outline
Deliverable
8.1
The Contractor shall provide a
Draft AR outline for review and comment.
• Once, as required by project schedule Electronic
• COR
• Proponent POC
• Installation POC
• AFCEC/CIE POC
Task 8.2 – Final AR
Outline
Deliverable
8.2
The Contractor shall provide a
Final AR Outline.
• Once, as required by project schedule Electronic
• COR
• Proponent POC
Deliverable
Deliverable Description Frequency
# of Copies
Format
Submit To
Task 8.3 – Final AR Deliverable
8.3
The Contractor shall prepare a searchable electronic AR on
DVD/CD-ROM.
• Once, within 30 days after FONSI signature
XX (XX)
DVD/CD
• COR
• Proponent POC
• Installation POC
• AFCEC/CIE POC
Task 9: Noise Analysis & Deliverables
Section 7.2.1 – Airfield
Noise Analysis
Deliverables
9.1, 9.2, 9.3, 9.4
The Contractor shall prepare a
Data Validation Package, NMODD, Noise Contours &
Modeling Files, and a Technical
Report Deliverable for all required types of noise analysis for review and comment
• Once, as required by project schedule Electronic
• COR
• Proponent POC
• Installation POC
• AFCEC/CIE POC
Section 7.2.2 – Airspace
Noise Analysis
Deliverables
9.1, 9.3, 9.4
The Contractor shall prepare a
Data Validation Package, Noise
Contours & Modeling Files, and a
Technical Report Deliverable for all required types of noise analysis for review and comment
• Once, as required by project schedule Electronic
• COR
• Proponent POC
• Installation POC
• AFCEC/CIE POC
Section 7.2.3 –
Construction Noise
Analysis
Deliverable
9.4
The Contractor shall prepare
Technical Report Deliverable for all required types of noise analysis for review and comment
• Once, as required by project schedule Electronic
• COR
• Proponent POC
• Installation POC
• AFCEC/CIE POC
Section 7.2.4 – Traffic
Noise Analysis
Deliverable
9.4
The Contractor shall prepare
Technical Report Deliverable for all required types of noise analysis for review and comment
• Once, as required by project schedule Electronic
• COR
• Proponent POC
• Installation POC
• AFCEC/CIE POC
Tasks 10 – 13: Airspace Support Tasks
Task 10 – FAA
Circularization Support
Deliverable
The Contractor shall provide support for FAA’s Circularization
Process as described in SOW
Task 10
• As required by project schedule
Virtual
• Proponent POC
Deliverable
Deliverable Description Frequency
# of Copies
Format
Submit To
Task 11 – FAA FONSI
Support
Deliverable
The Contractor shall provide support for FAA’s FONSI as described in SOW Task 11
• Proponent POC
• Installation POC
• AFCEC/CIE POC
Task 12 – Radar
Signature Data
Deliverable
The Contractor shall obtain, analyze, and summarize available radar data as described in SOW
Task 12
• Proponent POC
• Installation POC
• AFCEC/CIE POC
Task 13 – Airfield /
Airspace Obstruction or
Encroachment Analysis
Deliverable
The Contractor shall obtain, analyze, and summarize available obstruction/encroachment data as described in SOW Task 13
As required by project schedule Electronic
• COR
• Proponent POC
• Installation POC
• AFCEC/CIE POC
Task 14: Cultural Resources Surveys
Task 14.1 – Draft
Workplan
Deliverable
14.1
The Contractor shall provide a
Draft Workplan for review and comment
• Once, as required by project schedule Electronic
• COR
• Proponent POC
• Installation POC
• AFCEC/CIE POC
Task 14.2 – Final
Workplan
Deliverable
14.2
The Contractor shall provide a
Final Workplan
• Once, as required by project schedule Electronic
• COR
• Proponent POC
• Installation POC
• AFCEC/CIE POC
Task 14.3 – Surveys Deliverable
14.3
Up to three (3) Contractors shall conduct a no more than three (3) day survey at [location]
• Once, as required by project schedule Site Visit
• COR
• Proponent POC
• Installation POC
• AFCEC/CIE POC
Task 14.4 – Preliminary
Draft Survey Report
Deliverable
14.4
The Contractor shall provide a
Preliminary Draft Survey Report for review and comment
• Once, as required by project schedule Electronic
• COR
• Proponent POC
Deliverable
Deliverable Description Frequency
# of Copies
Format
Submit To
Task 14.5 – Check Draft
Survey Report
Deliverable
14.5
The Contractor shall provide a
Check Draft Survey Report for review and comment
• Once, as required by project schedule Electronic
• COR
• Proponent POC
• Installation POC
• AFCEC/CIE POC
Task 14.6 –Draft Survey
Report
Deliverable
14.6
The Contractor shall provide a
Draft Survey Report for review and comment
• Once, as required by project schedule Electronic
• COR
• Proponent POC
• Installation POC
• AFCEC/CIE POC
Task 14.7 – Check Final
Survey Report
Deliverable
14.7
The Contractor shall provide a
Check Final Survey Report for review and comment
• Once, as required by project schedule Electronic
• COR
• Proponent POC
• Installation POC
• AFCEC/CIE POC
Task 14.8 – Final Survey
Report
Deliverable
14.8
The Contractor shall provide a
Final Survey Report
• Once, as required by project schedule Electronic
• COR
• Proponent POC
• Installation POC
• AFCEC/CIE POC
Task 15: Programmatic Agreement / Memorandum of Agreement / Memorandum of Understanding
Task 15.1 – Preliminary
Draft PA / MOA / MOU
Deliverable
15.1
The Contractor shall provide a
Preliminary Draft PA / MOA /
MOU for review and comment
• Once, as required by project schedule Electronic
• COR
• Proponent POC
• Installation POC
• AFCEC/CIE POC
Task 15.2 – Check Draft
PA / MOA / MOU for
SME Review
Deliverable
15.2
The Contractor shall provide a
Check Draft PA / MOA / MOU for review and comment
• Once, as required by project schedule Electronic
• COR
• Proponent POC
• Installation POC
• AFCEC/CIE POC
Task 15.3 – Interim Draft
PA / MOA / MOU for
HAF Review
Deliverable
15.3
The Contractor shall provide an
Interim Draft PA / MOA / MOU for review and comment
• Once, as required by project schedule Electronic
• COR
• Proponent POC
Deliverable
Deliverable Description Frequency
# of Copies
Format
Submit To
Task 15.4 –Draft PA /
MOA / MOU for
Consultation
Deliverable
15.4
The Contractor shall provide a
Draft PA / MOA / MOU for DAF to use during Consultations
• Once, as required by project schedule Electronic
• COR
• Proponent POC
• Installation POC
• AFCEC/CIE POC
Task 15.5 – Check Final
PA / MOA / MOU
Deliverable
15.5
The Contractor shall provide a
Check Final PA / MOA / MOU for review and comment
• Once, as required by project schedule Electronic
• COR
• Proponent POC
• Installation POC
• AFCEC/CIE POC
Task 15.6 – Final PA /
MOA / MOU
Deliverable
15.6
The Contractor shall provide a
Final PA / MOA / MOU
• Once, as required by project schedule Electronic
• COR
• Proponent POC
• Installation POC
• AFCEC/CIE POC
Task 16: Biological Assessment / Biological Evaluation
Task 16.1 – Preliminary
Draft BA / BE
Deliverable
16.1
The Contractor shall provide a
Preliminary Draft BA / BE for review and comment
• Once, as required by project schedule Electronic
• COR
• Proponent POC
• Installation POC
• AFCEC/CIE POC
Task 16.2 – Check Draft
BA / BE
Deliverable
16.2
The Contractor shall provide a
Check Draft BA / BE for review and comment
• Once, as required by project schedule Electronic
• COR
• Proponent POC
• Installation POC
• AFCEC/CIE POC
Task 16.3 – Draft BA /
BE for Consultation
Deliverable
16.3
The Contractor shall provide a
Draft BA / BE for DAF to use in
Consultations
• Once, as required by project schedule Electronic
• COR
• Proponent POC
• Installation POC
• AFCEC/CIE POC
Task 16.4 – Check Final
BA / BE
Deliverable
16.4
The Contractor shall provide a
Check Final BA / BE for review and comment
• Once, as required by project schedule Electronic
• COR
• Proponent POC
Deliverable
Deliverable Description Frequency
# of Copies
Format
Submit To
Task 16.5 – Final BA /
BE
Deliverable
16.5
The Contractor shall provide a
Final BA / BE
• Once, as required by project schedule Electronic
• COR
• Proponent POC
• Installation POC
• AFCEC/CIE POC
Task 17: Natural Resource Surveys
Task 17.1 – Draft
Workplan
Deliverable
17.1
The Contractor shall provide a
Draft Workplan for review and comment
• Once, as required by project schedule Electronic
• COR
• Proponent POC
• Installation POC
• AFCEC/CIE POC
Task 17.2 – Final
Workplan
Deliverable
17.2
The Contractor shall provide a
Final Workplan
• Once, as required by project schedule Electronic
• COR
• Proponent POC
• Installation POC
• AFCEC/CIE POC
Task 17.3 – Surveys Deliverable
17.3
Up to three (3) Contractors shall conduct a no more than three (3) day survey at [location]
• Once, as required by project schedule Site Visit
• COR
• Proponent POC
• Installation POC
• AFCEC/CIE POC
Task 17.4 – Preliminary
Draft Survey Report
Deliverable
17.4
The Contractor shall provide a
Preliminary Draft Survey Report for review and comment
• Once, as required by project schedule Electronic
• COR
• Proponent POC
• Installation POC
• AFCEC/CIE POC
Task 17.5 – Check Draft
Survey Report
Deliverable
17.5
The Contractor shall provide a
Check Draft Survey Report for review and comment
• Once, as required by project schedule Electronic
• COR
• Proponent POC
• Installation POC
• AFCEC/CIE POC
Task 17.6 –Draft Survey
Report
Deliverable
17.6
The Contractor shall provide a
Draft Survey Report for review and comment
• Once, as required by project schedule Electronic
• COR
• Proponent POC
Deliverable
Deliverable Description Frequency
# of Copies
Format
Submit To
Task 17.7 – Check Final
Survey Report
Deliverable
17.7
The Contractor shall provide a
Check Final Survey Report for review and comment
• Once, as required by project schedule Electronic
• COR
• Proponent POC
• Installation POC
• AFCEC/CIE POC
Task 17.8 – Final Survey
Report
Deliverable
17.8
The Contractor shall provide a
Final Survey Report
• Once, as required by project schedule Electronic
• COR
• Proponent POC
• Installation POC
• AFCEC/CIE POC
Task 18: Coastal Zone Management Determinations
Task 18.1 – Preliminary
Draft CZM
Determination Package
Deliverable
18.1
The Contractor shall provide a
Preliminary Draft CZM
Determination Package for review and comment
• Once, as required by project schedule Electronic
• COR
• Proponent POC
• Installation POC
• AFCEC/CIE POC
Task 18.2 – Check Draft
CZM Determination
Package
Deliverable
18.2
The Contractor shall provide a
Check Draft CZM Determination
Package for review and comment
• Once, as required by project schedule Electronic
• COR
• Proponent POC
• Installation POC
• AFCEC/CIE POC
Task 18.3 – Draft CZM
Determination Package for Consultation
Deliverable
18.3
The Contractor shall provide a
Draft CZM Determination
Package for DAF to use in
Consultations
• Once, as required by project schedule Electronic
• COR
• Proponent POC
• Installation POC
• AFCEC/CIE POC
Task 18.4 – Check Final
CZM Determination
Package
Deliverable
18.4
The Contractor shall provide a
Check Final CZM Determination
Package for review and comment
• Once, as required by project schedule Electronic
• COR
• Proponent POC
• Installation POC
• AFCEC/CIE POC
Task 18.5 – Final CZM
Determination Package
Deliverable
18.5
The Contractor shall provide a
Final CZM Determination Package
• Once, as required by project schedule Electronic
• COR
• Proponent POC
• Installation POC
Task 19: Wetland Delineations
Deliverable
Deliverable Description Frequency
# of Copies
Format
Submit To
Task 19.1 – Draft
Workplan
Deliverable
19.1
The Contractor shall provide a
Draft Workplan for review and comment
• Once, as required by project schedule Electronic
• COR
• Proponent POC
• Installation POC
• AFCEC/CIE POC
Task 19.2 – Final
Workplan
Deliverable
19.2
The Contractor shall provide a
Final Workplan
• Once, as required by project schedule Electronic
• COR
• Proponent POC
• Installation POC
• AFCEC/CIE POC
Task 19.3 – Delineations Deliverable
19.3
Up to three (3) Contractors shall conduct a no more than three (3) days of delineations at [location]
• Once, as required by project schedule Site Visit
• COR
• Proponent POC
• Installation POC
• AFCEC/CIE POC
Task 19.4 – Preliminary
Draft Delineation Report
Deliverable
19.4
The Contractor shall provide a
Preliminary Draft Delineation
Report for review and comment
• Once, as required by project schedule Electronic
• COR
• Proponent POC
• Installation POC
• AFCEC/CIE POC
Task 19.5 – Check Draft
Delineation Report
Deliverable
19.5
The Contractor shall provide a
Check Draft Delineation Report for review and comment
• Once, as required by project schedule Electronic
• COR
• Proponent POC
• Installation POC
• AFCEC/CIE POC
Task 19.6 –Draft
Delineation Report
Deliverable
19.6
The Contractor shall provide a
Draft Delineation Report for review and comment
• Once, as required by project schedule Electronic
• COR
• Proponent POC
• Installation POC
• AFCEC/CIE POC
Task 19.7 – Check Final
Delineation Report
Deliverable
19.7
The Contractor shall provide a
Check Final Delineation Report for review and comment
• Once, as required by project schedule Electronic
• COR
• Proponent POC
Deliverable
Deliverable Description Frequency
# of Copies
Format
Submit To
Task 19.8 – Final
Delineation Report
Deliverable
19.8
The Contractor shall provide a
Final Delineation Report
• Once, as required by project schedule Electronic
• COR
• Proponent POC
• Installation POC
Note: Days refer to working / business days and exclude Saturdays, Sundays, and Federal holidays unless otherwise authorized by the Contracting Officer.