Chemical Storage Building bid specifications Final3.docx
DOCX document 40 KB Posted
- Attached to
- DNR herbicide storage sheds
- Solicitation number
- 20-422DNR-DIREC-B-13707
- Issued by
- Jefferson County, Niles Village, Illinois
About this file
This document is a Scope of Work and Project Requirements issued by the Illinois Department of Natural Resources (IDNR) for the procurement of two (2) prefabricated chemical storage buildings. One building will be delivered to Prairie Ridge State Natural Area and the other to Ferne Clyffe State Park. The buildings must meet specific size, material, and functional requirements. Bids are to be submitted electronically through the BIDBUY system by the specified due date and time. The contract requires a minimum of 60% of the work to be completed by the prime contractor. No pre-bid meeting is scheduled, and all questions must be directed to BIDBUY. The contract term is through September 30, 2020, with the possibility of an extension if agreed upon by both parties.
The contract is not subject to a small business set-aside. Bidders must provide proof of at least 5 years of experience in the commercial safety storage product industry and documentation of completing at least 5 similar projects. Prevailing wage rates apply, and contractors must maintain an Illinois office as the primary place of employment. The contract may be funded in whole or in part by tax-exempt bonds issued by the State. Award will be made to the compliant low bidder for the total price of all line items.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ILLINOIS DEPARTMENT OF NATURAL RESOURCES
SMALL PURCHASE PROCUREMENT
SCOPE OF WORK & PROJECT REQUIREMENTS
LOCATION: Prairie Ridge State Natural Area and Ferne Clyffe State Park
PROJECT TITLE: Chemical Storage Buildings
PROJECT NARRATIVE:
The Illinois Department of Natural Resources, hereinafter referred to as DNR, is seeking bids to purchase two (2) chemical storage buildings that are prefabricated and delivered fully assembled to two (2) DNR sites. One building will be delivered to Prairie Ridge State Natural Area, located southwest of Newton, Illinois and the other building would be delivered to Ferne Clyffe State Park, located south of Goreville, Illinois.
Prairie Ridge State Natural Area 4295 N 1000th St Newton, IL 624448
Ferne Clyffe State Park 90 Office Drive Goreville, IL 62939
SCOPE OF WORK:
The chemical storage building would need to be new, unused, fully assembled and free from defects at time of delivery. The storage building must meet the following minimum specifications regarding size, interior and exterior finishes and construction components. Delivery costs shall be included in the bids. Off-loading, hook ups and site preparation will be the responsibility of IDNR. Vendor will not off load the buildings or do any site preparations or hook ups.
Dimensions:
· 12’ long x 10’ high x 9’ tall Specifications:
· Non-combustible rated building
· Exterior building material must be steel
· Door(s) with 60” minimum width x 80” standard height
· Sump under floor and integrated into building with minimum 390 gallon capacity
· Door-hold, open fusible link for active leaf only
· Panic exit rim device for door
· Minimum of R10 wall and ceiling insulation
· Minimum of R20 insulation in door(s)
· Interior 20W LED low profile light fixtures with exterior
· Exterior 20W LED light fixture with photocell
· Minimum of 20 feet of 16” deep stainless shelves with standards
· Steel entrance ramp minimum of 48” wide and a minimum of 88” long
· 7.6Kw, 240/208V, 1-Phase, 24,000 BTU/HR Convection Heater
· Exterior low mounted exhaust ventilation with snap type switch
· NEMA 3R distribution or service disconnect switch
· NEMA 3R single phase load center
PROJECT SPECIFICATIONS & REQUIREMENTS:
1) All electrical components must meet and or exceed the minimum requirements set forth by the National Electrical Code, NEC.
2) All components must meet or exceed any requirement specified by the State Fire Marshal’s Office regarding storage or flammable or hazardous chemicals.
Acceptable Manufacturers: The Manufacturer is required to provide a quality product with superior performance by such entities as Underwriters Laboratories (UL), Applied Research Laboratory (ARL), or consumer-based organizations such as Consumer Reports. They are chosen to describe the standard of quality, performance and characteristics desired and is not intended to limit or restrict competition.
| A. | Project Specifications: |
| 1) | The awarded contractor must have a minimum of 5 years of experience in the commercial safety storage product industry and be able to provide documentation of completion of at least 5 projects similar in size and scope to this one if needed. |
B. Project Instructions and Notes:
1) Work Completed by Prime Contractor:
A minimum of sixty percent (60%) of the work shall be completed by the Prime Contractor or manufacture on this project. Pursuant to (30 ILCS 500/1-15.17) the Contractor is the person having a contract with the Illinois Department of Natural Resources.
| 2) | Coordination of Work Activities: |
| All work activities and entry to the sites must be coordinated with the site superintendent at | each site and or Mr. Roger Jansen, South Region Manager. |
3) Deliverables and Staff Training:
Three (3) sets of operating and maintenance manual and start-up procedures shall be provided to DNR. DNR staff shall receive proper training and instruction on the operation and maintenance of all new equipment.
| 4) | Contractor’s Licensing and/or Certifications: | |
| Contractor shall be responsible for compliance with all applicable contractor and trades person | licensing with the appropriate State agency. |
5) Shop Drawings:
Submit for the approval to Roger Jansen Regional Manager, shop drawings and product data for the Chemical Storage Building(s).
6) Extended Warranty:
Workmanship, materials and equipment subject to seasonal loads will be in conformance with the contract and free from defects for a period of two years, commencing from the goods acceptance date. This includes, but is not limited to, heating, ventilating, temperature control and test and balance work, as specified.
C. Project Requirements:
| 1) | Project Meeting |
| PROJECT MEETING TO BE HELD: YES |_| NO |X| | |
| MANDATORY ATTENDANCE: YES |_| NO |X| | |
| Refer to the BidBuy solicitation for meeting date and time. There will not be a pre-bid meeting | |
| associated with this project. Any and all questions need to be deferred to BidBuy. |
| 2) | Duration |
| Bids shall be good for ninety (90) calendar days after the submittal date, or for an extended | |
| period, if agreed to in writing by the Bidder and DNR. |
| 3) | Prevailing Wage Rates |
| This contract [or agreement] calls for the construction of a “public work,” within the meaning of | |
| the Illinois Prevailing Wage Act, 820 ILCS 130/.01 et seq. (“the Act”). The Act requires | |
| contractors and subcontractors to pay laborers, workers and mechanics performing services on | |
| public works projects no less than the current “prevailing rate of wages” (hourly cash wages | |
| plus, amount for fringe benefits) in the county where the work is performed. The Illinois | |
| Department of Labor (IDOL) publishes the prevailing wage rates on its website at | |
| http://labor.illinois.gov/. IDOL revises the prevailing wage rates and the | |
| contractor/subcontractor has an obligation to check the IDOL’s web site for revisions to | |
| prevailing wage rates. For information regarding current prevailing wage rates, please refer to | |
| IDOL’s website. All contractors and subcontractors rendering services under this contract must | |
| comply with all requirements of the Act, including but not limited to, all wage requirements and | |
| notice and record keeping duties. |
4) Small Business Set-Aside Not Applicable.
5) Illinois Office The bidder must certify that the bidder will maintain an Illinois office as the primary place of employment for persons employed in the construction authorized by the contract.
| 6) | Subcontractors |
| The Contractor shall identify the names of all subcontractors to be utilized by them in the | |
| performance of this contract, together with the anticipated amount of money that each | |
| subcontractor is expected to receive pursuant to this contract. Pursuant to Illinois Procurement | |
| Code (30 ILCS 500/1-15-108), a person or entity is not a “subcontractor” if that person only | |
| Provides goods or supplies that are incidental to the performance of a contract by a person | |
| who has a contract subject to the Code. |
| 7) | Insurance |
| Contractor shall, at all times during the term of this contract and any renewals or extensions, maintain and provide a Certificate of Insurance naming the State as an additionally insured for all required bonds and insurance. Certificates may not be modified or canceled until at least thirty (30) days’ notice has been provided to the State. Contractor shall provide: (a) General Commercial Liability insurance in the amount of $1,000,000 per occurrence (Combined Single Limit Bodily Injury and Property Damage) and $2,000,000 Annual Aggregate; (b) Auto Liability, including Hired Auto and Non-owned Auto (Combined Single Limit Bodily Injury and Property Damage), in amount of $1,000,000 per occurrence; and (c) Worker’s Compensation Insurance in the amount required by law. Insurance shall not limit Contractor’s obligation to indemnify, defend, or settle any claims. |
8) Permits and Licenses Permits and licenses necessary for the execution of the work shall be secured and paid for by the Contractor.
9) Highway Permits The Contractor is responsible for contacting the appropriate County Superintendent(s) of Highways and/or other appropriate local officials concerning the proposed work activities on the project as they may relate to use of the County and local road system. Coordination of any activities of concern to the County or Township shall be the responsibility of the Contractor. Special attention shall be given to load limits and seasonal restrictions.
10) New Products Unless otherwise specifically provided in the contract documents, all materials, equipment and products incorporated in the work under the contract shall be new and of a suitable grade for the purpose intended.
| 11) | Steel Products |
| Any steel product(s) used or supplied in the performance of this contract shall be manufactured or produced in the United States, in accordance with the Steel Products Procurement Act, unless a waiver is granted by IDNR (30 ILCS 565/). |
12) Specified Materials Bids shall be based on providing all products/materials exactly as required by the project specifications. Contractor may select from the list of acceptable manufacturers, offer an “equal” product and provide proof of its capabilities to meet the project specifications or, for products specified only by reference or performance standards, select any product which meets or exceeds the specified standards, by any manufacturer, subject to the approval of DNR.
13) Warranties The Contractor warrants that all work provided under the contract will be in conformance with the contract and free from defects in workmanship, materials, and equipment for a period of one year from the goods acceptance date. See Section B.6. Project Instructions and Notes, for any extended warranties that may apply.
14) Inducement Resolution All or a portion of this project may be paid or reimbursed from the proceeds of tax-exempt bonds subsequently issued by the State.
| 15) | Term of Contract |
| All work shall be completed by September 30, 2020 including delivery unless agreed to by both | |
| The Contractor and DNR, that a time extension is warranted. | |
| 16) | Award |
| Award shall be made to the compliant low bidder for the total price for all line items. |
17) Bid Submittal Bids must be submitted electronically on BidBuy. No paper bids will be accepted.
| 18) | Bid Submittal Date and Time |
| Refer to the BIDBUY solicitation for the bid due date and time. |
19) IDNR Contacts:
| Project Engineer: | Gary W. Iles | ||
| Illinois Department of Natural Resources | |||
| 14694 N. Lost Lake Lane | |||
| Mt. Vernon, Illinois 62864 | |||
| Phone: (618)920-1118 | |||
| E-mail: gary.iles@illinois.gov |
| Natural Heritage Regional Manager: Roger Jansen | ||
| Illinois Department of Natural Resources | ||
| 4295 N. 1000TH Street | ||
| Newton, IL 62448 | ||
| Phone: 618-783-2685 | ||
| E-mail: roger.jansen@illinois.gov |
| Billing: | Roger Jansen | |
| Illinois Department of Natural Resources | ||
| 4295 N. 1000TH Street | ||
| Newton, IL 62448 | ||
| Phone: 618-783-2685 | ||
| E-mail: roger.jansen@illinois.gov |
O:\OcdEng\Engadm\PROCUREMENT\FORMS\SCOPE DOCUMENT 2-28-2019.docx
File details come from the government source that posted it. Updated .