CHC20006_SPECS.pdf

PDF 2 MB Posted

Attached to
BIL West Point Spillway Gate Painting and Repair Industry Day
Solicitation number
W9127823R0109
Issued by

About this file

This special notice from the Department of the Army Corps of Engineers Engineering District Mobile announces an industry day for the BIL West Point Spillway Gate Painting and Repair project.

The industry day will provide an opportunity for contractors to learn more about the scope of work, which involves power washing, priming, and painting all metal components of the spillway gates, hoists, and associated equipment at the West Point Dam. The project also includes installing and replacing rubber seals, installing cathodic protection anodes on each gate, and performing weld repairs. The work window for painting the spillway gates and placing/removing stoplogs is October 1 to January 15. The two sets of existing stoplogs may also be painted as part of an optional bid item. The solicitation number for this requirement is W9127823R0109.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

WEST POINT SPILLWAY GATE PAINTING AND REPAIR

WEST POINT DAM, GEORGIA CHC20006

Table of Contents Page 1

TABLE OF CONTENTS

SPECIFICATIONS

DIVISION 01 - GENERAL REQUIREMENTS

01 00 00 ADDITIONAL SPECIAL CONTRACT REQUIREMENTS

01 00 01 GENERAL CONTRACT REQUIREMENTS

01 11 00 SUMMARY OF WORK

01 32 01.00 10 PROJECT SCHEDULE

01 33 00 SUBMITTAL PROCEDURES

SUBMITTAL REGISTER

01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS

01 42 00 SOURCES FOR REFERENCE PUBLICATIONS

01 45 00.00 10 QUALITY CONTROL

01 45 00.15 10 RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE (RMS CM)

01 57 19 TEMPORARY ENVIRONMENTAL CONTROLS

DIVISION 02 - EXISTING CONDITIONS

02 83 00 LEAD REMEDIATION

DIVISION 05 - METALS

05 05 23.16 STRUCTURAL WELDING

DIVISION 09 - FINISHES

09 97 02 PAINTING: HYDRAULIC STRUCTURES

DIVISION 26 - ELECTRICAL

26 42 14.00 10 CATHODIC PROTECTION SYSTEM (SACRIFICIAL ANODE)

DIVISION 32 – EXTERIOR IMPROVEMENTS

32 31 13.53 HIGH SECURITY FENCES (CHAIN LINK) AND GATES

DIVISION 35 – WATERWAY AND MARINE CONSTRUCTION

35 20 14 STOPLOGS

--End of Project Table of Contents--

This page was intentionally left blank for duplex printing.

SECTION 01 00 00

ADDITIONAL SPECIAL CONTRACT REQUIREMENTS

PART 1 GENERAL

1.1 SCOPE OF WORK

Refer to Section 01 11 00 SUMMARY OF WORK for the scope of work, As-builts, Hydraulic Steel Structure Inspection Report.

1.2 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK

The Contractor shall be required to (1) commence work under this contract within 10 calendar days after the date the Contractor receives the notice to proceed, (2) prosecute the work diligently, and (3) complete the entire work ready for use not later than 1,095 calendar days after receipt of notice to proceed. This time stated for completion shall include final cleanup of the premises.

1.3 LIQUIDATED DAMAGES--CONSTRUCTION

(a) If the Contractor fails to complete the work within the time specified in the contract, the Contractor shall pay liquidated damages to the Government in the amount of $731.00 for each calendar day of delay until the work is completed or accepted.

(b) If the Government terminates the Contractor's right to proceed, liquidated damages will continue to accrue until the work is completed.

These liquidated damages are in addition to excess costs of repurchase under the Termination clause.

1.4 SECURITY REQUIREMENTS

(a) All contractor employees, to include sub-contractor employees, requiring access to Army installations, facilities, controlled access areas, or require network access, shall complete AT Level I awareness training within 30 calendar days after contract start date or effective date of incorporation of this requirement into the contract, whichever is applicable. Upon request, the contractor shall submit certificates of completion for each affected contractor employee and subcontractor employee, to the COR or to the contracting officer (if a COR is not assigned), within 5 calendar days after completion of training by all employees and subcontractor personnel. AT Level I awareness training is available at the following website:

http://jko.jten.mil/courses/atl1/launch.html; or it can be provided by the RA ATO in presentation form which will be documented via memorandum.

(b) The contractor and all associated sub-contractors shall brief all employees on the local iWATCH, Corps Watch, or See Something, Say Something program (training standards provided by the requiring activity ATO). This local developed training will be used to inform employees of the types of behavior to watch for and instruct employees to report suspicious activity to the COR. This training shall be completed within 30 calendar days of contract award and within 30 calendar days of new employees commencing performance with the results reported to the COR NLT 5 calendar days after contract award.

SECTION 01 00 00 Page 1

(c) All contract employees, including subcontractor employees who are not in possession of the appropriate security clearance, will be escorted in areas where they may be exposed to classified and/or sensitive materials and/or sensitive or restricted areas.

(d) Contractor and all associated sub-contractors employees shall comply with adjudication standards and procedures using the National Crime Information Center Interstate Identification Index (NCIC-III) and Terrorist Screening Database (TSDB) (Army Directive 2014-05 / AR 190-13), applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative, as NCIC and TSDB are available), or, at OCONUS locations, in accordance with status of forces agreements and other theater regulations.

(e) The Contractor must pre-screen Candidates using the E-verify Program (http://www.uscis.gov/e-verify) website to meet the established employment eligibility requirements. The Vendor must ensure that the Candidate has two valid forms of Government issued identification prior to enrollment to ensure the correct information is entered into the E-verify system. An initial list of verified/eligible Candidates must be provided to the COR no later than 3 business days after the initial contract award." *When contracts are with individuals, the individuals will be required to complete a Form I-9, Employment Eligibility Verification, with the designated Government representative. This Form will be provided to the Contracting Officer and shall become part of the official contract file.

1.5 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. The following shall be submitted in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

Electronic Mail System Plan; G,CD.

Layout of Temporary facilities including utility connections; G,CD.

Hazard Analysis; G,SO.

Work Sequence Plan; G,CD

SD-07 Certificates

Certificates of Compliance: G,CD.

Request for Interruption of Utility Services; G,CD.

SD-11 Closeout Submittals

Cost or Pricing Data; G,CD

1.6 CONTRACT DRAWINGS, MAPS AND SPECIFICATIONS

a) The Contractor will be furnished one CD-ROM containing a

SECTION 01 00 00 Page 2 reproducible copy of the advertised solicitation, including contract clauses, plans and specifications. The work shall conform to the specifications and the contract drawings listed in the technical provisions.

b) Omissions from the drawings or specifications, the mis-description of details of work which are manifestly necessary to carry out the intent of the drawings and specifications which are customarily performed shall not relieve the Contractor from performing such omitted or mis-described details of the work but they shall be performed as if fully and correctly set forth and described in the drawings and specifications.

c) The Contractor shall check all drawings furnished him immediately upon their receipt and shall promptly notify the Contracting Officer's Representative of any discrepancies. Figures marked on drawings shall in general be followed in preference to scale measurements. Large scale drawings shall in general govern small scale drawings. The Contractor shall compare all drawings and verify the figures before laying out the work and will be responsible for any errors which might have been avoided thereby.

d)The list of drawings and maps provided in the Index Sheet of the Plans for this solicitation are hereby incorporated by reference into these specifications. Any schedules included in the drawings are for the purpose of defining requirements other than quantities.

NOTE: Refer to the folio of drawings for the index of drawings in this solicitation.

1.7 PHYSICAL DATA

Data and information furnished or referred to below is for the Contractor's information. The Government shall not be responsible for any interpretation of or conclusion drawn from the data or information by the Contractor.

a. The indications of physical conditions on the drawings and in the specifications are the result of site investigations by surveys.

b. Weather Conditions. Weather conditions shall be investigated by the Contractor to determine the hazards likely to arise therefrom. Complete weather records and reports may be obtained from the local U.S. Weather Bureau.

c. Transportation facilities. The contractor shall investigate and make arrangements for transporting all materials and equipment to the site of work.

1.8 TIME EXTENSIONS FOR UNUSUALLY SEVERE WEATHER

a. This provision specifies the procedure for determination of time extensions for unusually severe weather in accordance with the contract clause entitled "Fixed Price Construction". In order for the Contracting Officer to award a time extension under this clause, the following conditions must be satisfied:

b. The weather experienced at the project site during the contract period must be found to be unusually severe, that is, more severe than the

SECTION 01 00 00 Page 3 adverse weather anticipated for the project location during any given month.

1. The unusually severe weather must actually cause a delay to the completion of the project. The delay must be beyond the control and without the fault or negligence of the Contractor.

2. The following schedule of monthly anticipated adverse weather delays is based on National Oceanic and Atmospheric Administration (NOAA) or similar data for the project location and will constitute the base line for monthly weather time evaluations. The Contractor's progress schedule must reflect these anticipated adverse weather delays in all weather dependent activities.

MONTHLY ANTI CI PATED ADVERSE WEATHER DELAY

WORK DAYS BASED ON ( 5) DAY WORK WEEK

JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC

3 4 4 3 3 6 8 9 6 3 3 3

Upon acknowledgment of the Notice to Proceed (NTP) and continuing throughout the contract, the Contractor will record on the daily CQC report, the occurrence of adverse weather and resultant impact to normally schedule work. Actual adverse weather delay days must prevent work on critical activities for 50 percent or more of the Contractor's scheduled work day.

c. The number of actual adverse weather delay days shall include days impacted by actual adverse weather (even if adverse weather occurred in previous month), be calculated chronologically from the first to the last day of each month, and be recorded as full days. If the number of actual adverse weather delay days exceeds the number of days anticipated in paragraph 2, above, the Contracting Officer will convert any qualifying delays to calendar days, giving full consideration for equivalent fair weather work days, and issue a modification in accordance with the Contract Clause entitled "Default (Fixed Price Construction)".

1.9 TIME EXTENSIONS

Notwithstanding any other provisions of this contract, it is mutually understood that the time extensions for changes in the work will depend upon the extent, if any, by which the changes cause delay in the completion of the various elements of construction. The change order granting the time extension may provide that the contract completion date will be extended only for those specific elements so delayed and that the remaining contract completion dates for all other portions of the work will not be altered and may further provide for an equitable readjustment of liquidated damages under the new completion schedule.

1.10 CERTIFICATES OF COMPLIANCE

Any certificates required for demonstrating proof of compliance of materials with specification requirements shall be executed in four copies. Each certificate shall be signed by an official authorized to certify on behalf of the manufacturing company and shall contain the name and address of the Contractor, the project name and location, and the quantity and date or dates of shipment or delivery to which the certificates apply. Copies of laboratory test reports submitted with certificates shall contain the address of the testing laboratory and the

SECTION 01 00 00 Page 4 date or dates of the tests to which the report applies. Certification shall not be construed as relieving the Contractor from furnishing satisfactory material, if, after tests are performed on selected samples, the material is found not to meet the specific requirements.

1.11 EQUIPMENT OWNERSHIP AND OPERATING EXPENSE SCHEDULE

a. This clause does not apply to terminations.

b. Allowable cost for construction and marine plant and equipment in sound workable condition owned or controlled and furnished by a contractor or subcontractor at any tier shall be based on actual cost data for each piece of equipment or groups of similar serial and series for which the Government can determine both ownership and operating costs from the contractor's accounting records. When both ownership and operating costs cannot be determined for any piece of equipment or groups of similar serial or series equipment from the contractor's accounting records, costs for that equipment shall be based upon the applicable provisions of EP 1110-1-8, "Construction Equipment Ownership and Operating Expense Schedule," Region III. Working conditions shall be considered to be average for determining equipment rates using the schedule unless specified otherwise by the contracting officer. For equipment not included in the schedule, rates for comparable pieces of equipment may be used or a rate may be developed using the formula provided in the schedule. For forward pricing, the schedule in effect at the time of negotiations shall apply. For retrospective pricing, the schedule in effect at the time the work was performed shall apply.

c. Equipment rental costs are allowable, subject to the provisions of FAR 31.105(d)(ii) and FAR 31.205-36. Rates for equipment rented from an organization under common control, lease-purchase arrangements, and sale-leaseback arrangements will be determined using the schedule, except that actual rates will be used for equipment leased from an organization under common control that has an established practice of leasing the same or similar equipment to unaffiliated lessees.

d. When actual equipment costs are proposed and the total amount of the pricing action exceeds the small purchase threshold, the contracting officer shall request the contractor to submit either certified cost or pricing data, or partial/limited data, as appropriate. The data shall be submitted on Standard Form 1411, "Contract Pricing Proposal Cover Sheet."

1.12 CONTRACTOR MAINTENANCE

At the end of each working day the Contractor shall police the work area and the area immediately surrounding the work area of all work-related debris. The Contractor shall comply with all applicable safety requirements and shall conduct his operations in a manner to insure an accident-free environment. Contractor shall keep all grassed areas within his work area in a neatly trimmed state during the growing season.

Stacked materials shall not be within 25 feet of an active roadway.

1.13 REQUIREMENTS FOR TEMPORARY CRANES

1.14 SAFETY MARKINGS ON CRANE BOOMS

All cranes shall have a red strobe light and two flags attached to the end of the boom. The flags shall be 46 cm (18-inches) square and international orange in color. The strobe does not need to be flashing

SECTION 01 00 00 Page 5 during daylight hours or when the boom is lowered to the ground at night.

The strobe shall be flashing when operating during weather in which visibility is reduced or when operating at night. The strobe shall remain flashing if the boom remains elevated at night.

1.15 ELECTRONIC MAIL SYSTEM

The Contractor shall provide and maintain for the life of this contract an electronic mail system which shall interface, connect to and be compatible with the existing electronic mail system in the Corps of Engineers Resident Office. The Contractors electronic mail system shall transfer and receive correspondence between the Resident Office without loss or modification of formatting codes or special characters.

The Resident Office is currently utilizing Exchange/MS Outlook for Windows and is Internet accessible. The Corps Internet E-mail gateway accepts binary files in uuencoded format, with a limit of 6Mb per E-mail message. Internet messages may be sent to any Mobile District Corps of Engineers Employee using the form <First Name>.<Middle Initial>.<Last Name>@usace.army.mil without the brackets surrounding the names.

During construction, all Requests For Information (RFIs) including field sketched drawings shall be transmitted to the Corps of Engineers Resident Office in an electronic format. The RFIs shall be saved into a ".pdf" format using Adobe Acrobat 4.0 software.

The Contractor's electronic mail system shall have the capability of sending and receiving text, graphic, and drawing files developed on the following software:

1) Microsoft Word

2) WordPerfect

3) AutoCad

4) Adobe Acrobat

The Contractor shall bear the responsibility to ensure total hardware and software compatibility with the Government's system when transferring and receiving information.

Within 10 days after receipt of NTP, the Contractor shall submit for approval an electronic mail system plan which details the hardware, software, communication paths, processes and procedures for establishing and maintaining the Contractor's electronic mail system.

1.16 SCHEDULED OUTAGES

a. All outages, including but not limited to communication, water, electricity, natural gas, sewage and road closures, shall be of as short in duration as possible and shall be scheduled by the Contractor in writing, as far in advance as possible with the Contracting Officer's representative. In no case shall utility scheduling occur less than ten

(10) days prior to the required outage.

1. The Contractor's outage request shall include the following:

a) Type of utility, access or service to be disrupted.

b) Areas and/or facilities affected.

SECTION 01 00 00 Page 6

c) Expected duration of outage.

d) Date of proposed outage.

e) Names of authorized personnel.

f) Point of contact and telephone numbers.

b. The Contractor shall obtain in writing from the Contracting Officer's representative a statement of schedule, giving the permissible times of outages for particular installations or activities and the maximum time allowed for each outage. Any utility outage expected to exceed one (1) hour in duration shall be scheduled for the weekend (Saturday/Sunday) and shall not exceed six (6) hours in duration. Any utility outage scheduled during the week (Monday through Friday) shall not exceed one (1) hour in duration. Scheduled outages during the week may be required to occur before or after normal business hours. No outage shall occur until written approval is received from the Contracting Officer's representative. The Contractor shall strictly observe such schedules and will be held responsible for any violations. The Contractor shall include with each outage request a list or bill of materials and equipment that will be used during said outage. The Contractor will be solely responsible for ensuring that all materials and equipment will be on hand and ready for use during any scheduled outage.

1.17 WORK SEQUENCE PLAN

The Contractor shall submit a Work Sequence Plan to the Contracting Officer's Representative for approval 30 days prior to commencement of construction. The Work Sequence Plan shall identify proposed sequence of performing the work identified in the scope of work. Contractor shall coordinate with powerhouse personnel in developing the construction sequance plan. The work sequence plan shall provide a strategy to bringing the gate operational within seven days for emergency flood control operations. The work sequence plan shall provide a storm plan that shows a step-by-step plan to remove all scaffolding and associated equipment out of the spillway.See scope of work for additional infromation. Significant rainstorms can cause a sudden rise in the upper pool, causing the stoplogs to overtop if they are not removed. In the event of an emergency the government will need two days to remove the stoplogs.

1.18 CONSTRUCTION/SITE MANAGEMENT STANDARDS

a. GENERAL

1) The following standards relate to the appearance of the construction site during the construction cycle, temporary administrative and storage areas, and service facilities needed for execution and completion of the work

2) A visually acceptable site is an important construction standard. A clean, well-kept site will help ensure compliance with the safety and environmental requirements of the contract. The contractor shall maintain the trailers or storage buildings in good condition or they shall be removed. The contractor is responsible for the security of his property and general housekeeping of the area(s).

3) Site Plan. Prior to starting the work, the Contractor shall

SECTION 01 00 00 Page 7 coordinate with the Powerhouse Personnel and Contracting Officer's representative for approval for the layout and details of all temporary facilities used for this contract.

4) At completion of work, the contractor shall remove the facilities and restore the site to its original condition.

A. CONTRACTOR'S TEMPORARY FACILITIES

1) Administrative Field Offices and Material Storage Trailers:

Contractor's administrative field office and storage trailers shall be in like new condition. Storage of materiel's/debris under the trailers is prohibited.

a. Staging Areas - Are indicated on the drawings.

b. Temporary Sanitation Facilities. All temporary sewer and sanitation facilities shall be self contained units with both urinals and stool capabilities. Ventilate the units to control odors and fumes and empty and clean them at least once a week or more often if required by the contracting officer. The doors should be self-closing. The exterior of the unit will match the base standard. Locate the facility behind the construction fence or out of the public view.

1.19 COORDINATION CONFERENCES

Routine coordination conferences will be scheduled by the Contracting Officer's Representative throughout the life of this contract.

Coordination conferences will be held to discuss contract administration, Contractor quality control, phasing, scheduling, and other aspects relating to this construction. The Using Agency, Corps of Engineers and the Contractor will be represented at each of these meetings. Similar information concerning replacement personnel shall be forwarded to the Contracting Officer's Representative, should any replacement be required at any time during the life of this contract. Coordination conferences will be scheduled to occur on a weekly basis. The Contractor shall develop the Meeting Minutes for each Coordination conference. A copy of the meeting minutes shall be provided to the Corps and all attendees via e-mail no later than three (3) working days after each meeting. The Contractor shall develop and maintain a list of action items that arise during construction or at each Coordination Conference. The Action Items list shall describe each Issue/Action Item and state what organization/person is tasked with its resolution. Blanks, or cells, shall be provided for dates when the Issue/Action Item was first raised, the due date for its resolution, and the date of actual resolution.

1.20 REGISTRATION OF PRIVATELY OWNED VEHICLES

All vehicles owned, leased, or operated on the reservation shall be registered as directed by the COR at the pre-construction conference.

Evidence of required insurance must be presented at the time of registration.

1.21 HAZARD ANALYSIS

A Hazard Analysis Plan, as described in Section 1, Article 01.A.05 of the Corps of Engineers Safety and Health Requirements Manual, EM 385-1-1, latest edition, is required for this contract, and shall be submitted

SECTION 01 00 00 Page 8 thirty (30) days after Notice To Proceed (NTP).

1.22 CONSTRUCTION MATERIALS

All construction materials shall remain in the designated staging area until ready for use. Storage of materials in areas other that the designated area will not be allowed unless approved by the COR.

1.23 CONSTRUCTION DEBRIS DISPOSAL

All construction debris shall be disposed of at an approved disposal site off Government controlled lands.

1.24 RADIO TRANSMISSIONS

To avoid conflict with transmission frequencies currently in use, the Contractor shall submit a written request for use of each radio device to be used at the job site. The request shall contain: (1) a list of all radios to be used with serial number, (2) frequencies to be used, (3) power output, and (4) a copy of the FCC license for each device. The Contracting Officer's Representative reserves the right to order the Contractor not to use radios in times of sensitive base operations. The Contractor shall provide to the Contracting Officer's Representative a point of contact to be notified when all radio transmissions must cease due to sensitive base operations and when radio operations can resume.

Radios shall not be used until the Contractor receives written approval from the Contracting Officer's Representative.

1.25 RATES OF WAGES

Wage rates follow at the end of this section.

PART 2 PRODUCTS (NOT APPLICABLE)

PART 3 EXECUTION (NOT APPLICABLE)

-- End of Section --

SECTION 01 00 00 Page 9

SECTION 01 11 00

SUMMARY OF WORK

1 Project Description

The West Point Dam is a concrete gravity type structure with rolled earthen embankments joining the high ground on the east and west sides of the river. The total length of the concrete dam and earth embankments is 7,250 feet. The principal structures that make up the concrete dam are a non-overflow section, an intake-powerhouse structure, a gated spillway located in the main river channel, and concrete gravity abutment walls which supports the left earth embankment. The construction of West Point Dam was completed in June 1974.

The gated spillway is a 350-foot-long concrete gravity flow structure with six tainter gate. Each gate is 50 feet wide by 41.40 feet high. Access to the spillway is provided by a spillway service bridge that can be accessed from the right side of the dam. The gates are numbered 1 through 6 with the number one gate being closest to the powerhouse. In order to close the spillway for maintenance, stop logs are placed on the upstream face of the spillway gates. The project currently has two sets of stop logs but only one gate can be closed to maintain spillway capacity.

The spillway tainter gates were last painted in the 1990s and in November 2019, structural engineers from the U.S. Army Corps of Engineers performed a hands-on inspection of the critical structural components of the Tainter gates. The Tainter gates were found to be in satisfactory condition. Primary findings and conditions on the downstream side of the gates include isolated deformations along the struts and strut end frame bracing members, complete section loss in girder web stiffeners, moderate to severe surface corrosion, and debris and ponding at the joints. To see the full report, refer to Appendix A.

Figure 1: Spillway Gate nomenclature

SECTION 01 11 00

2 Mobile District Points of Contact

The Mobile District Project Manager (PM) for this work is Scott Ellzey, Phone: (251) 694-3604, Email:

Matthew.S.Ellzey@usace.army.mil

The Mobile District technical point of contact, Technical Lead (TM) for this work is James Defalco, Phone:

(251) 694-4201, Email: James.A.Defalco@usace.army.mil

The Resident Engineer to contact for access to work described in this SOW for West Point is Ron Stuckey, Phone: (706) 643-5391, E-mail: John.R.Stuckey@usace.army.mil, Rick Landeen, Phone: (229) 768-0130, E-mail: Ricker.P.Landeen@usace.army.mil and Jay Jamison, Phone: (706) 645-2937, E-mail:

Jay.L.Jamison@usace.army.mil

3 Project Scope of Work

The objective of this project is for the Contractor to provide all labor, materials, and equipment necessary to power wash, prime and paint all metal components of the spillway gates, hoists, and associated equipment, and existing old stoplogs (bid option). Painting includes power washing and painting of each structure, installing/replacing rubber seals and installing cathodic protection anodes on each gate, and performing weld repairs in accordance with the attached specifications and as indicated below:

a) Spillway Gates 1-6 painting and placing & removing the stoplogs shall take place in the work window of October 1 to January 15 (See Explanation of Bid Items for specific date years). The stoplog bid option (if executed) can start once notice to proceed is issued by Contracting.

Contractor shall have access to the spillway gates during work window stated above 24 hours a day 7 days a week.

b) NOT USED

c) NOT USED

d) Within fifteen (15) calendar days of contract award, the Contractor shall have a pre-construction meeting to bring all affected parties together to get a clear understanding of the work to be performed.

e) During the construction work window (October 1 to January 15) The Government will close Dam Road at the two swing gates. The Government will provide road closure signs for Dam Road and press release for road closure. When delivering and returning stop logs, the government will provide temporary barricades to close dam road to allow access to the storage yard. The contractor is responsible for the overall traffic control during construction. The Government will not be providing personnel for traffic control.

f) The Contractor my use the Storage Yard as a lay down area and park vehicles in the east gated dirt parking area.

g) The Contractor may use the 110v receptacle power available at each gate. West Point Dam does not have access to potable water on the dam.

h) The Government will provide a meeting place for weekly meeting between the Contractor and the Government. The contractor shall furnish their own office space if needed.

i) The Contractor will be allowed to work on one gate at a time. Before moving to another gate, the previous gate shall be fully operable with all equipment, scaffolding, and stoplogs removed.

During construction all other gates will be operating and releasing water. This will cause water particles to be suspended in the air. The contractor shall determine if a portable paint both is required to properly apply the coating system.

j) After power washing and before painting the Government requires an inspection hold point to allow USACE Hydraulic Steel Structure two-man team to inspect the spillway gate.

k) West Point Dam Road Bridge design load is HS-20 Truck loading and 50-ton capacity crane.

l) Old Stoplog/Pickup Beam Weight:

a. Stoplog - 23,465 Lbs

b. Bottom Stoplog - 23,420 Lbs

c. Lifting Beam - 7,880 Lbs

m) The contractor shall provide the following equipment to set the stoplogs for dewatering the gates and remove the stoplogs once the work is complete. The Government will have approximately 5 personnel on site to direct and assist with setting the stoplogs. The government will lead this effort. The contractor shall allow seven days for the government to place and seven days to remove the stoplogs. Equipment associated with setting the stoplogs will need to be on site up to seven days. Gate Painting Schedule and sequence shall be submitted to the COR for approval before commencing work. The work sequence plan shall provide a strategy to bringing the gate operational within seven days for emergency flood control operations. The work sequence plan shall provide a step-by-step plan to remove all scaffolding and associated equipment out of the spillway. Significant rainstorms can cause a sudden rise in the upper pool, causing the stoplogs to overtop if they are not removed. In the event of an emergency the government will need two days to remove the stoplogs.

a. Resources to place the stoplogs:

1. 2 each 80-ton hydraulic truck cranes with 16,000 counterweights (1 at the storage yard and 1 on the dam)

2. 2 each riggers (contractor to supply)

3. 2 Tractor, with operators, equipped with “high-bed” trailer 47 feet long

(contractor to supply)

4. 1 each flagman to work with tractor / high-bed trailer at the stop log storage area (contractor to supply)

5. 1 each flagman to work with tractor / high-bed trailer at the spillway gate

(Government to supply)

6. Miscellaneous rigging accessories (cables, slings, binders, etc.) (contractor to supply)

7. Lifting beam (Government supplied)

8. Spreader beam (Government supplied)

9. Cribbing (Government Supply)

10. Dive team on retainer (contractor to provide), dive team will be required to assist if a stoplog gets stuck in a stoplog slot.

b. Procedure to place the stop logs

SECTION 01 11 00

1. The stoplogs are stored .6 miles from the spillway on a concrete pad. The lifting beam (used to set stoplogs) and the spreader beam (used to load stoplogs on flatbed trailer) are also stored on the concrete pad. One 80 ton hydraulic craned will be setup at the pad and one on the spillway roadway over the top of the gate to be un-watered. The lifting beam will have to be transported to the spillway via flatbed trailer. The crane at the storage pad will load the bottom log on the trailer using the spreader beam. Cribbing is required as the bottom of this log is not flat. Stoplog shall be level on the cribbing. Once the beam is bound to the trailer it will be transported .6 miles to the spillway. The trailer will have to be backed onto the spillway to allow the crane to pick it up. To pick up the stoplog off the trailer the beam will have to hang off the trailer approximately fifteen feet. The crane on the spillway will pick up the bottom stoplog using the lifting beam and set into the slot.

Figure 2 Stoplog being picked up by pickup beam

2. Once the log is off the trailer the trailer can be sent back to the storage pad to get the next stoplog. The remaining stoplogs are identical and can go in any order. It will be transported to the spillway and set with the crane there.

This process will repeat until all 9 stoplogs are in position.

3. Reverse the process to remove the stoplogs and store them at the storage pad.

n) In the event of a rainstorm, the Contractor shall take the necessary measures to protect the work area, establish adequate protection/coverage of the spillway gate with available materials. A storm plan shall be provided to the Government for review and approval, prior to commencing work that identifies how these measures will be accomplished. The plan shall include a timeline by which the measures required shall take place and shall identify reasonable times to mitigate damage resulting from the ongoing work effort. The contractor's plan shall address responses to minor rain events, severe thunderstorms, tropical storms, and hurricanes.

o) The contractor may take down the downstream fencing to allow access for equipment. The contractor shall only take down two gate bays at a time. If the fencing is removed, the contractor shall provide temporary control access fencing on either end of the top of dam to prevent pedestrians from entering the work area while the fence is down. The contractor shall determine if the fencing is required to be removed for crane access and painting access. The fence has a black wire attached to it by zipped ties. This wire will be removed by government personnel. The fencing shall be re-installed to its original location after the work is complete and the stop logs

Figure 3 Stoplog on trailer with cribbing, hanging approximately 15 feet off the back of the trailer, this allows the crane to reach the stoplog to pick it up. Notice the cribbing must be high enough to clear the crane outriggers

SECTION 01 11 00

have been removed. Any portion of the fencing if damaged beyond that of the existing conditions shall be replaced by the contractor at no additional expense to the Government.

Figure 4 Downstream Fencing

Figure 5 Crane passing through man gate to allow clearance for lifting stoplogs

p) The present paint system on all painted structures includes lead primer. Removal and disposal of any failing paint or primer will be accomplished in compliance with all applicable laws, standards, regulations, and guidelines as published by the EPA, OSHA, USACE, and Georgia EPD. The contractor must provide proof, through an approved Accident Prevention Plan (APP), Site Safety & Health Plan (SSHP), and Lead Compliance Plan (LCP), of all provisions they plan to implement on site to ensure the protection of the personnel required to perform the work and the protection of the environment from any generated Lead waste.

q) Minor repairs to gate seal keeper bars, skin plate, embedded sills, lifting machinery shall be performed as necessary while each gate is dewatered.

r) The Contractor shall remove and replace gate rubber seals

a. Rubber seals of ethylene propylene dimonomer (EPDM) or neoprene (CR) conforming to

ASTM D2240, ASTM D412, ASTM D573, ASTM D471, ASTM D1149, ASTM D395,

ASTM D624 and ASTM D1630. Provide the surfaces of finished splices that are smooth and free of irregularities. Match-drill bolt holes in the rubber seals with the seal support and clamping bars, as applicable; to insure proper fit and spacing between holes of the completed seal assembly. Match finish seal support and clamping bars to conform to the configurations shown on the as-built drawings. Install the seals and blocks after painting has been completed.

b. Physical characteristics of the seals shall meet the following requirements

s) The contractor shall paint hoists and associated equipment. To paint the structural steel on the machinery deck, the contractor will have to remove the grating. Items that are galvanized or aluminum do not require to be painted.

t) The contractor shall remove organics, debris and clean the gate by power washing before painting. Areas that required to be repaired by welding shall be mechanical cleaned to bare metal. Any loose or flaking paint shall be removed before power washing by a vacuum system or other approved methods. The safety and health provisions that the contractor intends to implement on site to prevent personnel exposure to Lead and other Heavy Metals during the performance of this work task must be clearly outlined in an approved APP, SSHP, and/or LCP.

PHYSICAL TEST TEST VALUE TEST METHOD SPECIFICATION

Tensile Strength 2500 psi (min) ASTM D412

Elongation at Break 450 percent (min) ASTM D412

300 percent 900 psi (min) ASTM D412

Durometer Hardness (Shore Type A)

60 to 70 ASTM D2240

*Water Absorption 5 percent by weight (max)

ASTM D471

Compression Set 30 percent (max) ASTM D395

Tensile Strength (after aging 48 hrs)

80 percent of tensile strength (min)

ASTM D572

SECTION 01 11 00

The contractor must clearly outline the provisions that they intend to implement to ensure that no hazardous materials or debris are deposited into any of the surrounding water bodies through the completion of this work task.”

The standards that WILL BE applicable for work tasks (e) and (g) will include, but are not limited to, the following:

- Clean Water Act (40 CFR 117)

- Resource Conservation and Recovery Act (RCRA) (40 CFR 239 through 299)

- OSHA 29 CFR 1910.1200 (Hazard Communication)

- OSHA 29 CFR 1910.1025 (Lead)

- OSHA 29 CFR 1926.62 (Lead in Construction)

- OSHA 29 CFR 1926.1127 (Cadmium)

- OSHA 29CFR 1926.1126 (Hexavalent Chromium)

- USACE EM 385-1-1 (Ensure that the APP, SSHP, and LCP are written IAW Sections

01.A.12/Appendix A, 33.B.02, and 06.C.02, respectively.)

u) The contractor shall remove all debris/vegetation from the spillway gates before power washing.

v) Inadequate drainage exists on the girders and strut end frame joints at M5 and B5 due to undersized or hindered drain holes. Inadequate drainage also exists on the strut end frame joints M1 through M4 and B1 through B4 due to a lack of drain holes. The contractor shall install 1/2” diameter drain hole as directed by the COR. See attached HSS inspection report for additional details. Contractor shall submit proposed method for installing 1/2” dia. drain holes for approval.

w) The contractor shall install sacrificial anode and brackets in accordance with specification 26 42

14.00 10. Cathodic protection will be applied to the skin surface to reduce corrosion activity and prevent damage to the gate. See sheet CP-501 for additional details. The spillway gates currently do not have any cathodic protection.

x) The contractor shall only apply the 3rd and 4th coat of the 3-A-Z system to the existing coating system that is still properly adhered to the gate or stoplogs (bid option). famous

y) The contractor shall apply 2nd, 3rd, and 4th coat of the 3-A-Z system to areas where the lead base primer is exposed. If the primer is not adhered to the surface and is flaking off. The contractor shall remove the primer and install the full system in that area.

z) The contractor shall install the full 3-A-Z system to areas that are mechanical cleaned.

aa) Safety requirements EM 385-1-1 for fall protection? Comply with the requirements set forth in Engineering Manual 385-1-1, Safety and Health Requirements Manual dated 30 Nov 2014, with emphasis on Section 1 Program Management and Section 21 Fall Protection.

bb) The Contractor shall accept direction only from the Mobile District Contracting Officer (KO) or the Authorized Representative of the Contracting Officer (COR). Requests or desires of the users or using agency made direct to the contractor will be immediately brought to the attention of the PM or TM, and KO. Any changes to the project scope or other provisions of the SOW must be authorized in writing by the KO.

Bid Option:

SECTION 01 11 00

a) The project has two sets of stoplogs. The two sets of stoplogs are referred to as the “new” and “old” stop logs. The old stoplogs requires the same cleaning and paint application as the spillway gates and the new stoplogs require a paint stripe on all the copes showing signs of rust. Rust shall be removed before painting. The stop logs can be painted in the storage area

b) Old stoplogs - All seals shall be replaced, and all damaged seal keeper bars shall be replaced.

c) General outline of work:

i. Spot mechanical clean and coat old logs example areas are marked on the old logs

ii. Replace vertical J seals on old set of logs.

iii. Remove pack rust from horizontal J seal keeper bars on the old logs.

iv. Straighten hook on old stop log #6, then check for cracks with MT. Submit plan for approval

v. Straighten vertical J seal support on log #6

d) Spillway tainter gate hoisting ropes with sockets - (2 Wire Cables Per Gate – 1 pair)

I. Reference drawings WP3M-211 and WP3M-209

II. Contractor shall supply two new hoisting rope assemblies with socket ends attached.

III. Flat wire rope dimensions shall be 5/8” x 7” (15/16” x 8 1/8”)

IV. Flat wire ropes shall be constructed of corrosion resisting steel type 302

V. Flat wire ropes shall consist of 4 x 19 weave with type 302 corrosion resisting sewing wires

VI. Flat wire ropes will be prestressed to 20 % of breaking prior to final socketing

VII. The ends of each cable shall be seized and set in zinc filled socket blocks

VIII. Sockets shall be tested to 40% of breaking strength after zincing

IX. Flat wire ropes shall not exceed 80’ 6” plus or minus 1” following the prestressing

X. Attach bottom socket

a. Reference drawing number WP3M-211

b. Cast steel Fed. Spec. QQ-S-681d

c. Class 65-35

XI. Attach Top socket

a. Reference drawing number WP3M-209

b. Cast steel Fed. Spec. QQ-S-681d

c. Class 90-60

XII. Reference drawing number WP3M-211 for hoisting rope connection detail

Spillway Tainter Gate Rope Use Information

The hoisting rope at each end of the spillway gate is a woven flat wire rope. The wire ropes are 5/8” x 7”, 4 x 19 weave, and type 302 corrosion resisting steel. The ends of each rope are seized and set in zinc filled socket blocks. At the hoisting drum, one end of the rope with attached socket block fits into a slot in the drum. The other end of the rope, with its attached socket block, is secured to the gate lifting bracket by eyebolts with spanner nuts.

4 Structural Welding Guidance

Weld Repairs:

Weld repairs shall be performed in accordance with AWS D 1.1 “non-tubular statically loaded structures”, using E7018 electrodes. Repairs shall be done with the gates in place, scaffolding, man baskets or other means of access and related safety equipment shall be provided by the contractor. Typical types of weld repairs are as follows:

a) Under sized welds, mostly due to corrosion and section loss (welds undersized by less than 20% are acceptable) – remove surface contamination by grinding, apply 200 degree pre-heat, then build up with new weld metal. No welding shall be performed if water is weeping or steam is present.

b) Under cutting shall be repaired by grinding or sanding until it is smoothed out or blended in.

c) Poor surface profile shall be repaired by grinding to an acceptable profile according to D 1.1.

d) Cracks shall be MT tested to find the extent of the crack, pre-heat, then gouge or grind out, check with MT fill with new weld metal, slow cool then MT

e) Estimated Quantities per Gate:

a. Under sized welds 70 LF

b. Under cutting 25 LF

c. Surface profile 70 LF

d. Cracks 10 LF

Surface Defect Repairs:

These defects consist of old fit up welds, nicks, gouges, weld spatter, arc strikes, surface laminations, or other defects that may affect the coating performance. These defects shall be repaired by grinding to a smooth profile for proper coating application.

a) Estimated Quantities per Gate: 130 LF

Breaking Edges:

Sharp edges of flanges, stiffeners etc. shall be ground to a slight radius for proper coating application.

a) Estimated Quantities per Gate: 1200LF

Pitting Repairs:

There is widespread pitting on the gates, the most severe is typically on the upstream face of the skin plate. Much of the pitting is in close proximity to the stainless steel cable due to galvanic action. The

SECTION 01 11 00

pitting varies in depth and diameter. An important aspect of the repairs will be to attempt removal of subsurface contamination of the steel due to corrosion that would prematurely cause coating failure. The pitting will be categorized below, with repair procedures:

a) Pits ¼” and greater in depth. Shall be cleaned and smoothed out by grinding or sanding to white metal, approximately 1/32” surface removal, prior to mechanical cleaning to establish a proper profile for coating adhesion.

b) Pits 1/8” to 1/4” in depth. Shall be cleaned by light sanding.

c) Pits less that 1/8” in depth. Shall be cleaned by sanding.

d) Sheet rust on downstream members shall have rust removed. Typically found on framing members and horizontal girder webs.

e) Estimated quantities per gate:

a) Pits greater than ¼” in depth 130 each

b) Pits 1/8 to ¼” in depth 230 each

c) Pits less than 1/8” in depth 205 SF

d) Sheet rust 150 SF

Note:

For first gate only - repair pitting as described above and fill pits in with BELZONA prior to application of vinyl paint. This gate will be a test subject for this type of repair. Contractor shall have USACE Engineer of Record (EOR) inspect before painting.

Other Repairs:

Gusset plates, stiffener plates, and other member sections that have severe section loss will need to be replaced. Replacement material shall be A 572 grade 50, welding shall be performed as outlined in weld repairs noted above.

a) Gusset plate repair – The structural member connecting gusset plates vary in shape and size. A few of them have extreme section loss and thinning of the plate between members. Packed rust and prying action with cracked or deformed welds can also be present, between the gusset plate and connecting member.

b) Stiffener replacement – Numerous stiffeners are located between the vertical ribs in the vicinity of the horizontal girder bearing. They have been difficult to clean and paint in the past, resulting in a large amount of section loss in some of them. If more than 20% section loss is present, they need to be replaced.

c) Vertical rib/web replacement – Where the vertical ribs make contact with the horizontal girders is a typical problem area for thinning of section due to corrosion and difficulty in performing proper cleaning prior to coating application. If over 20% of the section is lost due to corrosion and is over one foot in length, it needs to be replaced.

SECTION 01 11 00

d) Pack rust removal and sealing – These areas are typically located between gusset plates and the connecting members. They are also typically found between the vertical rib flange and the horizontal girder flange. These areas shall be properly cleaned by use of sharp raking tools or small bur grinders. Once these areas are as clean as practical they shall be seal welded where possible.

e) Estimated Quantities per Gate:

a. Gusset plate repair/replacement 6 each

b. Stiffener replacement 15 LF

c. Rib flange replacement 6 LF

d. Pack rust removal 120 each

f) Miscellaneous Plates - ASTM A709 GR 50

HD Bolts, Hex. Nut and Lock Washer – Stainless Steel – A304

Note:

See attached As-built for plate sizes and HSS inspection

SECTION 01 32 01.00 10

PROJECT SCHEDULE

02/15

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

AACE INTERNATIONAL (AACE)

AACE 29R-03 (2011) Forensic Schedule Analysis

AACE 52R-06 (2006) Time Impact Analysis - As Applied in Construction

U.S. ARMY CORPS OF ENGINEERS (USACE)

ER 1-1-11 (1995) Administration -- Progress, Schedules, and Network Analysis Systems

1.2 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

Project Scheduler Qualifications; G

Preliminary Project Schedule; G

Initial Project Schedule; G

Periodic Schedule Update; G

1.3 PROJECT SCHEDULER QUALIFICATIONS

Designate an authorized representative to be responsible for the preparation of the schedule and all required updating and production of…