Charter Modification JOFOC_Redacted.pdf
PDF 275 KB Posted
- Solicitation number
- 31310023D0004P00012
- Issued by
-
Nuclear Regulatory Commission
About this file
This is a Justification and Approval (J&A) document for a noncompetitive contract modification issued by the U.S. Nuclear Regulatory Commission (NRC).
The NRC is seeking a ceiling increase to an existing Indefinite Delivery Indefinite Quantity (IDIQ) cost-reimbursement contract with Southwest Research Institute (SwRI) for operation of the Center for Nuclear Waste Regulatory Analyses (CNWRA), the NRC's Federally Funded Research and Development Center (FFRDC). The contract modification increases the maximum contract value from $10,618,861 to $18,600,000, representing a $7,981,139 increase. The current performance period runs from March 30, 2023, through March 29, 2028 (inclusive of one remaining one-year option). The contractor is located at 6220 Culebra Road, San Antonio, Texas 78238-5166. CNWRA provides specialized research and technical expertise in eight competency areas including civil and structural engineering, environmental science, geology and geophysics, hydrology, material sciences, health physics, and performance assessment to support the NRC's waste management program, including nuclear fuel cycle activities, storage, transportation, and geologic disposal under the Nuclear Waste Policy Act and the Accelerating Deployment of Versatile, Advanced Nuclear for Clean Energy Act of 2024. The ceiling increase is justified under RFO 6.103-3(b)(2) to maintain essential engineering, research, and development capabilities at an FFRDC. The modification is conducted on a sole-source basis without competitive solicitation, and no pre-solicitation or post-award notices will be published. Cost reasonableness will be determined through comparison to historical pricing, labor rate benchmarking, and verification of Defense Contract Audit Agency-approved indirect rates. The NRC will conduct a comprehensive market research review in Fiscal Year 2027 to determine whether continued sponsorship of CNWRA is warranted, representing a 39-year investment exceeding $260 million.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
NRC JUSTIFICATION AND APPROVAL
This Justification for Other Than Full and Open Competition (JOFOC) supports the issuance of a noncompetitive modification to increase the IDIQ maximum value from $10,618,861 by $7,981,139 to $18,600,000.
2. Contract Type: Cost-Reimbursement
3. Period of Performance & Total Estimated Value of Contract
The estimated total ceiling is revised to $18,600,000.
The effective period of performance is five years.
The current base and exercised ordering periods are 3/30/2023 – 3/29/2027.
There is one remaining one-year option period (3/30/2027 – 3/29/2028).
4. Provide a background and description of the supplies or services required to meet the agency's needs, including the rationale for the estimated value change (if applicable).
CNWRA was established on October 15, 1987. Since then, the Commission has subsequently approved continued sponsorship of the CNWRA every five years, mostly recently in 2022.
CNWRA provides the NRC with access to resources with highly technical and specialized competencies needed to support NRC’s regulatory program related to nuclear fuel cycle activities. This includes, but is not limited to storage, transportation, future geologic disposal, and advanced fuel programs under the Nuclear Waste Policy Act (NWPA) and the Accelerating Deployment of Versatile, Advanced Nuclear for Clean Energy Act of 2024 (ADVANCE Act). The NRC relies on CNWRA’s expertise and specialized capabilities, free of OCOI, to ensure the credibility of the NRC as an independent regulator.
Since the Charter Contract renewal was awarded in 2023, the NRC’s waste management program requirements have exceeded those initially anticipated. A ceiling increase is now necessary to allow the ordering flexibility to award new work for the remaining two years of the ordering period. Moving forward, the NRC envisions the need for continued research and technical assistance under the Charter Contract due to increased interest in advanced reactors and new and advanced fuels, particularly the transportation, storage and disposal of spent advanced reactor fuel. The estimated value change was based on the average annual usage of the contract over the first three years of the ordering period, as well as consideration of planned future work.
5. Authority:
RFO 6.103-3 Industrial mobilization; engineering, developmental, or research capability; or expert services
Specifically, the authorization at RFO 6.103-3(b)(2), “To establish or maintain an essential engineering, research, or development capability to be provided by…a federally funded research and development center.”
6. Supporting Rationale
The following rationale supports the use of the authority cited in Section 5 of this document.
RFO 6.103-3 Rationale
This modification is being issued pursuant to the authorization at RFO 6.103-3(b)(2), “to establish or maintain an essential engineering, research, or development capability to be provided by…a federally funded research and development center.”
CNWRA was established as the NRC’s FFRDC to provide research and technical expertise, within its areas of special competency, to support NRC’s waste management program. CNWRA’s special competencies currently include: (1) Administration, (2) Civil, Structural and Mechanical Engineering; (3) Environmental Science and Environmental Engineering; (4) Geology and Geophysics; (5) Hydrology and Hydrologic Transport; (6) Material Sciences; (7) Health Physics; and (8) Performance Assessment. This need cannot be met as effectively by existing in-house or contractor resources with capabilities similar to CNWRA.
Maintaining CNWRA’s essential engineering, research, or development capability is necessary to support future work within the scope of contract. Increasing the contract ceiling allows the NRC to maintain mission-critical capabilities and expertise at CNWRA, free of OCOIs. The CNWRA will be critical in ensuring the NRC is positioned to be successful during this period of transformation by providing research and technical assistance related to spent fuel storage, transportation, aging, and disposal; especially for advanced technologies. This support is especially critical as the NRC complies with and responds to the significant reform brought about with implementing Executive Order (EO) 14300, Ordering the Reform of the Nuclear Regulatory Commission. For example, CNWRA is supporting the development of the technical basis for revisions to 10 CFR Part 61.
7. Market Research:
As part of the recent exercise of Option Period Three, the NRC staff conducted a comprehensive review of the use and need of the FFRDC. The NRC staff determined there is a continuing need for a contractor free of OCOI with potential or current applicants or licensees, to provide research and technical support for the NRC’s waste management program.
Beginning in 2027, NRC will perform an analysis including market research to determine whether the NRC should continue to sponsor the CNWRA for up to another five years.
8. A description of efforts made to ensure that offers are solicited from as many potential sources as is practicable, including whether a notice was or will be publicized.
In accordance with RFO 6.103-3, this action is being conducted on a sole-source basis. As a result, offers were not solicited from multiple sources because the NRC has determined that it is necessary to award the modification to SwRI to maintain the essential engineering and research capabilities of the CNWRA.
A pre-solicitation notice for this ceiling increase modification will not be publicized in accordance with the exemption at RFO 5.101(b)(2).
9. A determination by the contracting officer that the anticipated cost to the Government will be fair and reasonable.
The Contracting Officer will determine that the anticipated cost for new work is fair and reasonable as task orders are awarded. To make this determination, the Contracting Officer will consult with the Contracting Officer’s Representative (COR) to confirm the technical validity and reasonableness of the proposed level of effort to ensure that it accurately reflects the work necessary to meet the NRC’s requirements.
To establish cost reasonableness, the Contracting Officer will:
compare cost to historical pricing for similar services, compare CNWRA labor rates with published labor rates for similar professional labor categories in technical fields; and ensure indirect rates are in accordance with the rates approved by the Defense Contract Audit Agency, which are incorporated into the contract.
Additionally, the contract includes language that caps employee compensation at the FFRDC (in accordance with 3 USC 102 for information on the President’s salary and 41 USC 4304(a)(16) as amended by section 702 of The Bipartisan Budget Act of 2013 (Pub. L. 113-67) for the limit set therein).
Upon completion of this review, the Contracting Officer will document the determination that the cost for the task order is fair and reasonable and represents the best value for the Government.
10. Any other facts to support justification.
The NRC deemed certain capabilities essential for its waste management program and spent considerable time, effort, and appropriated funds to develop these capabilities at the CNWRA. If the CNWRA cannot maintain these essential capabilities, the NRC will lose an investment of 39 years and over $260 million dollars. CNWRA is an organization which has continued to be free of OCOI and provides high-quality research and technical support to the NRC. The loss of this independent support would threaten the credibility and continuity of the NRC’s technical program. It would also jeopardize NRC’s ability to be flexible in reacting to the Nation's evolving policy on nuclear waste, advanced reactors and new and advanced fuels.
To retain its high-caliber experts, the CNWRA must maintain a stable, technically challenging work environment.
Consequently, the agency staff has concluded that if the NRC does not maintain continuous staffing at the CNWRA, it would take years to reestablish the required technical expertise with staff functioning at the level required to provide adequate support to the NRC.
All task orders under this IDIQ Contract are Section 508 Compliant as applicable.
11. A listing of the sources, if any, that expressed, in writing, an interest in the acquisition.
Not Applicable
12. A statement of the actions, if any, the agency may take to remove or overcome any barriers to competition before any subsequent acquisition for the supplies or services required.
a. Approximately every five years, the NRC staff reviews the status of and need for continued sponsorship of the FFRDC. Results of the review and evaluation will be used as a basis to provide recommendations to the Commission to determine if an FFRDC is still required and if an open competition is warranted. NRC will begin this review in Fiscal Year 2027.
b. AMD will closely scrutinize future requests for renewal of the CNWRA and will ensure that any restrictions on competition are adequately supported and documented.
13. Publicizing Contract Actions
A pre-solicitation notice for this ceiling increase modification will not be posted to the Governmentwide Point Entry (GPE) in accordance with RFO 5.101(b)(2).
A post award notice for this ceiling increase modification will not be posted to the GPE in accordance with RFO
5.301 as this action does not meet the requirements to do so.
APPROVAL SIGNATURES
Technical/Program Office Personnel Certification
Evidence that any supporting data that is the responsibility of technical or requirements personnel (e.g., verifying the Government's minimum needs or requirements or other rational for restricting competition) and which form a basis for the justification have been certified as complete and accurate by the technical or requirements personnel.
Prepared By:
Contracting Officer’s Representative
The contracting officer's certification that the justification is accurate and complete to the best of the contracting officer's knowledge and belief. The contracting officer certifies that the anticipated cost to the Government will be fair and reasonable.
The signature below represents the contracting officer's certification that the justification is accurate and complete to the best of the contracting officer's knowledge and belief.
Contracting Officer
Advocate for Competition